Non-kerf floor and construction method thereof

By setting angle steel and steel mesh at the floor junction and adding steel fibers to the concrete, the problems of prone to cracking and uneven floor settlement of traditional floor silo materials are solved, and a seamless floor design with high structural strength and safe use is achieved.

CN119664074APending Publication Date: 2025-03-21CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202510069117.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-16
Publication Date
2025-03-21

AI Technical Summary

Technical Problem

When the traditional factory building is constructed with ultra-long and ultra-wide floor, the materials of the warehouse are prone to cracking, causing bumps in the forklifts to walk, and the uneven floor settlement causes a difference in height, affecting the safety of use.

Method used

The design of the floor is adopted. By setting angle steel and upper and lower layers of steel mesh at the junction of the floor, combined with steel fibers added to the concrete, a floor with high structural strength and seamless structure is formed.

Benefits of technology

The structural strength of the floor is improved, and the local collapse problem caused by uneven stress in the later stage of the floor is avoided. At the same time, the strength of the concrete is enhanced to ensure the safe walking of the forklift.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119664074A_ABST
    Figure CN119664074A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building construction, in particular to a kerf-free terrace and a construction method thereof. Comprising the steps that concrete is sequentially poured in a designed position zone to form a terrace; the angle steel is arranged between the two adjacent terraces in a vertical height adjustable mode, the angle steel is arranged along the junction of the two adjacent terraces in a full-length mode, and the angle steel is buried in the terraces; and the two layers of reinforcing meshes are formed below the angle steel and are distributed up and down, and the two layers of reinforcing meshes are embedded in the terrace. The floor has the advantages that the structural strength of the floor is improved by arranging the angle steel, the upper reinforcing mesh and the lower reinforcing mesh at the junction of each floor, and meanwhile, the problem of local collapse caused by uneven stress of the floor in the later period is avoided due to the seamless design of the floor.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, in particular to a seamless floor and a construction method thereof. Background Art

[0002] In the traditional factory building super-long and super-wide floor construction, the skipping method is mainly used. One warehouse is about 1200-1500 square meters. The warehouses are divided by armored seams or templates. After pouring, the seams are cut every 6m in each warehouse (the cutting area is preferably not more than 30 square meters) to ensure the release of stress and avoid cracking of the floor in the later stage, which will cause the following problems:

[0003] (1) Traditional concrete floors use armored seams or formwork as compartment materials, which may cause concrete shrinkage and cause the armored seams to open, causing forklifts to travel bumpy and unable to meet usage requirements.

[0004] (2) As a storage warehouse, the logistics warehouse will store a large number of heavy-loaded equipment for a long time. The use of conventional concrete flooring may cause uneven settlement of the ground after cutting, resulting in floor height differences, which will also affect subsequent use and forklifts cannot move safely.

[0005] Therefore, the present invention provides a seamless floor and a construction method thereof. Summary of the invention

[0006] The purpose of the present invention is to overcome the defects of the prior art, provide a seamless floor and a construction method thereof, and solve the problems that the existing floor compartment materials are easy to crack and cause forklifts to run bumpy.

[0007] The technical solution to achieve the above purpose is:

[0008] The present invention provides a seamless floor, comprising:

[0009] The floor is formed by pouring concrete in the designed location and in different areas in sequence;

[0010] An angle steel is arranged between two adjacent floors with adjustable heights, the angle steel is arranged along the entire length of the junction of the two adjacent floors, and the angle steel is buried in the floors;

[0011] Two layers of steel mesh distributed up and down are formed under the angle steel, and the two layers of steel mesh are buried in the floor.

[0012] Furthermore, it also includes:

[0013] Crushed stone, the crushed stone is horizontally laid on the ground at the designed position of the floor;

[0014] A concrete cushion layer is cast on top of the crushed stone, and the floor is cast on top of the concrete cushion layer.

[0015] Furthermore, it also includes a plurality of vertical bolts for supporting the angle steel and nuts arranged on the vertical bolts, the lower end of the vertical bolts is vertically buried in the gravel and the concrete cushion layer, the angle steel is located above the nut and is movably arranged on the vertical bolts up and down, and the height and inclination of the angle steel are adjusted by turning the nut to move it up or down.

[0016] Furthermore, it also includes a metal mesh arranged below the angle steel, the metal mesh is arranged along the length direction of the angle steel and is fixedly connected to the corresponding vertical pole bolts, the lower end of the metal mesh is vertically buried in the gravel and the concrete cushion layer, and the upper end is fixedly connected to the angle steel.

[0017] Furthermore, a plurality of cement pads are formed by pouring at intervals on the concrete cushion layer, and the steel mesh of the lower layer is horizontally fixed on the cement pads;

[0018] A plurality of supporting saddle bars are fixedly arranged at intervals on the concrete cushion layer, and the steel mesh of the upper layer is fixedly arranged horizontally on the upper ends of the supporting saddle bars.

[0019] Furthermore, steel fibers for enhancing the structural strength of the floor are mixed into the concrete used for casting the floor, and hook portions are formed at both ends of the steel fibers.

[0020] The present invention also provides a construction method for a seamless floor, which specifically comprises the following steps:

[0021] Laying two layers of upper and lower steel mesh at the designed position of the floor;

[0022] Angle steel is arranged above the upper and lower layers of the steel mesh, and the angle steel is located at the junction of two adjacent floors;

[0023] Concrete is poured in turn at the designed position of each floor, and the difference in pouring time between two adjacent floors does not exceed 36 hours.

[0024] Furthermore, before laying the steel mesh, a pole bolt and a metal mesh are provided, the pole bolt is vertically fixed on the ground and the metal mesh is fixed on the pole bolt;

[0025] Providing crushed stones, and laying the crushed stones horizontally at the designed position of the floor;

[0026] Then, a concrete cushion layer is cast on the top of the crushed stones, so that the lower ends of the upright bolts and the metal mesh are buried in the crushed stones and the concrete cushion layer.

[0027] Furthermore, before installing the angle steel, a nut is provided and installed on the vertical pole bolt, and then the angle steel is installed on the vertical pole bolt so that the nut supports the angle steel, and the height of the nut is adjusted by screwing the nut, thereby adjusting the height and inclination of the angle steel.

[0028] Furthermore, before pouring the floor, steel fibers are provided and evenly mixed into the concrete.

[0029] Compared with the prior art, the present invention has the following beneficial effects:

[0030] By installing angle steel and upper and lower layers of steel mesh at the junction of each floor, the structural strength of the floor is improved. At the same time, the seamless design of the floor avoids the problem of local collapse caused by uneven force in the later stage of the floor.

[0031] By adding steel fibers to concrete, the structural strength of concrete is greatly improved, thereby further improving the structural strength of the floor. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 It is a side sectional view of the seamless floor of the present invention.

[0033] Figure 2 A cross-sectional view of the seamless floor of the present invention

[0034] Legend: 1. Angle steel; 2. Vertical bolt; 3. Nut; 4. Metal mesh; 5. Steel mesh; 6. Anti-cracking steel bar; 7. Supporting horse stool bar; 8. Partition; 9. Cement pad; 10. Floor; 11. Concrete cushion; 12. Gravel. DETAILED DESCRIPTION

[0035] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0036] See also Figure 1 The present invention provides a seamless floor and a construction method thereof, which solves the problems that the existing floor compartment materials are easy to crack, causing forklifts to bump. By setting angle steel and upper and lower layers of steel mesh at the junction of each floor, the structural strength of the floor is improved. At the same time, the seamless design of the floor avoids the problem of partial collapse of the floor due to uneven force in the later stage.

[0037] By adding steel fibers to concrete, the structural strength of concrete is greatly improved, thereby further improving the structural strength of the floor.

[0038] The following describes a seamless floor and a construction method thereof according to the present invention in conjunction with the accompanying drawings.

[0039] See also Figure 1 , showing a side cross-sectional view of the seamless floor of the present invention. Figure 2 , showing a cross-sectional view of the seamless floor of the present invention. Figure 1 and Figure 2 , a seamless floor and a construction method thereof are described in the present invention.

[0040] like Figure 1 and Figure 2 As shown, a seamless floor of the present invention comprises:

[0041] The concrete is poured in the designed location in order to form a floor 10;

[0042] An angle steel 1 is arranged between two adjacent floors 10 with adjustable heights, the angle steel 1 is arranged along the entire length of the junction of the two adjacent floors 10, and the angle steel 1 is buried in the floors 10;

[0043] Two layers of steel mesh 5 distributed vertically are formed below the angle steel 1 , and the two layers of steel mesh 5 are buried in the floor 10 .

[0044] In a specific embodiment, the angle steel 1 has a height of 50 mm, a width of 30 mm, and a thickness of 2 mm. The height of the floor 10 formed by casting is 0.02 m higher than the height of the angle steel 1 .

[0045] In a specific embodiment, the thickness of the poured floor 10 is 250 mm.

[0046] In a specific embodiment, the steel mesh 5 is composed of a plurality of HRB400E steel bars fixed in a horizontal and vertical staggered manner, and the spacing between two adjacent HRB400E steel bars is 150 mm, and the diameter is 10 mm.

[0047] In a specific embodiment, it also includes:

[0048] Crushed stone 12, the crushed stone 12 is horizontally laid on the ground at the designed position of the floor 10;

[0049] A concrete cushion layer 11 is cast on the top of the crushed stone 12 , and the floor 10 is cast on the top of the concrete cushion layer 11 .

[0050] In a specific embodiment, it also includes a plurality of vertical bolts 2 for supporting the angle steel 1 and nuts 3 arranged on the vertical bolts 2. The lower end of the vertical bolts 2 is vertically buried in the gravel 12 and the concrete cushion layer 1. The angle steel 1 is located above the nuts 3 and is movably arranged on the vertical bolts 2. The nut 3 is screwed to move it up or down, so that the height and inclination of the angle steel 1 are adjusted, and after the adjustment is completed, the angle steel 1 and the nuts 3 are welded and fixed.

[0051] In a specific embodiment, the distance between two adjacent upright bolts 2 is 1 m.

[0052] In a specific embodiment, it also includes a metal mesh 4 arranged below the angle steel 1, the metal mesh 4 is arranged along the length direction of the angle steel 1 and is fixedly connected to the corresponding upright bolt 2, the lower end of the metal mesh 4 is vertically buried in the gravel 12 and the concrete cushion layer 11, and the upper end is fixedly connected to the angle steel 1.

[0053] In a specific embodiment, the metal mesh 4 is fixed to the pole bolts 2 by means of a wire tie, and the mesh gaps on the metal mesh 4 are smaller than the maximum aggregate particle size of the concrete.

[0054] In a specific embodiment, a plurality of anti-cracking steel bars 6 are horizontally fixed on the angle steel 1, and the anti-cracking steel bars 6 are distributed at intervals.

[0055] In a specific embodiment, a plurality of cement pads 9 are cast at intervals on the concrete cushion layer 11, and the steel mesh 5 of the lower layer is horizontally fixed on the cement pads 9;

[0056] A plurality of supporting saddle bars 7 are fixedly arranged at intervals on the concrete cushion layer 11 , and the steel mesh 5 of the upper layer is horizontally fixedly arranged on the upper ends of the supporting saddle bars 7 .

[0057] In a specific embodiment, the cement pad 9 has a thickness of 40 mm, the spacing between two adjacent supporting saddle bars 7 is 700 mm, and the spacing between the upper and lower layers of the steel mesh 5 is 50 mm.

[0058] In a specific embodiment, steel fibers for enhancing the structural strength of the floor 10 are mixed into the concrete used for casting the floor 10, and hook portions are formed at both ends of the steel fibers.

[0059] In a specific embodiment, the length of the steel fiber is 60 mm, the diameter is ≤ 1 mm, the tensile strength is ≥ 1500 MPa, and the amount of steel fiber is not less than 35 kg / m 3 .

[0060] In a specific embodiment, the water-cement ratio of the concrete for pouring the floor 10 is ≤0.5, the maximum particle size of the coarse aggregate is 25 mm, the grading is continuous, the content of silicate cement in the cement does not exceed 10%, and granulated blast furnace slag cannot be used as an admixture.

[0061] In a specific embodiment, reinforcing ribs are also provided between the floor 10 and the walls and columns.

[0062] In a specific embodiment, it also includes a partition 8 arranged between the floor 10 and the central column and the side column. The partition 8 has a thickness of 9 mm, a height of 250 mm, and a width consistent with the side width of the corresponding central column and the side column.

[0063] Specifically, the partition 8 between the floor 10 and the center column is a PE foam board, and the partition 8 between the floor 10 and the side column is a high-extruded board.

[0064] The present invention also provides a construction method for a seamless floor, which specifically comprises the following steps:

[0065] Lay two layers of steel mesh 5 at the designed position of the floor 10;

[0066] Angle steel 1 is arranged above the upper and lower layers of the steel mesh 5, and the angle steel 1 is located at the junction of two adjacent floors 10;

[0067] Concrete is poured in turn at the designed position of each floor 10, and the difference in pouring time between two adjacent floors 10 does not exceed 36 hours to ensure that the poured floors 10 form a whole.

[0068] In a specific embodiment, before laying the steel mesh 5, a pole bolt 2 and a metal mesh 4 are provided, the pole bolt 2 is vertically fixed on the ground and the metal mesh 4 is fixed on the pole bolt 2;

[0069] Providing gravel 12, and laying the gravel 12 horizontally at the designed position of the floor 10;

[0070] Then, a concrete cushion layer 11 is cast on the top of the crushed stone 12 , so that the lower ends of the upright bolts 2 and the metal mesh 4 are buried in the crushed stone 12 and the concrete cushion layer 11 .

[0071] In a specific embodiment, before installing the angle steel 1, a nut 3 is provided and installed on the vertical bolt 2, and then the angle steel 1 is installed on the vertical bolt 2 so that the nut 3 supports the angle steel 1, and the height of the nut 3 is adjusted by screwing the nut 3, thereby adjusting the height and inclination of the angle steel 3.

[0072] In a specific embodiment, before pouring the floor 10, steel fibers are provided and uniformly mixed into concrete.

[0073] In a specific embodiment, when installing the angle steel 1, an electronic level is provided to monitor the height and inclination of the angle steel 1, and the height and inclination of the angle steel 1 are adjusted to reach the designed position.

[0074] The construction process of a seamless floor according to the present invention is described in detail below.

[0075] First, vertically arrange the pole bolts 2 at the designated position, and vertically weld the metal mesh 4 on the pole bolts 2, then lay a layer of crushed stone 12 at the designed position of the floor 10, and then pour on the crushed stone 12 to form a concrete cushion layer 11, so that the lower ends of the pole bolts 2 and the metal mesh 4 are buried in the crushed stone 12 and the concrete cushion layer 11.

[0076] Then, support saddle bars 7 and cement pads 9 are arranged at intervals on the concrete cushion layer 11 , and a steel mesh 5 is laid on the cement pads 9 and the support saddle bars 7 , and the steel mesh 5 is fixed.

[0077] Install the nut 3 and the angle steel 1 on the pole bolt 2, and make the angle steel 1 be located above the nut 3. Use an electronic level to detect the height and inclination of the angle steel 1, and adjust the height and inclination of the angle steel 1 by turning the nut 3.

[0078] A plurality of anti-cracking steel bars 6 are fixed on the angle steel 1 at intervals horizontally.

[0079] The partition plates 8 are laid on the outer surfaces of the walls and columns.

[0080] Steel fibers are added to the concrete and mixed evenly, and the concrete is poured at the designed position of the floor 10, and the pouring height is higher than the height of the angle steel 1.

[0081] The present invention is described in detail above in conjunction with the embodiments of the accompanying drawings. A person skilled in the art can make various variations of the present invention according to the above description. Therefore, certain details in the embodiments should not constitute a limitation of the present invention, and the scope of protection of the present invention shall be defined by the scope of the attached claims.

Claims

1. A seamless floor, characterized by: include: Concrete is poured in sequence in the designed locations to form a floor (10); An angle steel (1) is arranged between two adjacent floors (10) with adjustable heights, the angle steel (1) is arranged along the entire length of the junction of the two adjacent floors (10), and the angle steel (1) is buried in the floors (10); Two layers of steel mesh (5) distributed vertically are formed below the angle steel (1), and the two layers of steel mesh (5) are buried in the floor (10).

2. A seamless floor according to claim 1, characterized in that: Also includes: Crushed stone (12), the crushed stone (12) is horizontally laid on the ground at the designed position of the floor (10); A concrete cushion layer (11), the concrete cushion layer (11) is cast and formed on the top of the crushed stone (12), and the floor (10) is cast and formed on the top of the concrete cushion layer (11).

3. The seamless floor according to claim 2, characterized in that: It also includes a plurality of vertical bolts (2) for supporting the angle steel (1) and nuts (3) arranged on the vertical bolts (2); the lower end of the vertical bolts (2) is vertically buried in the gravel (12) and the concrete cushion layer (1); the angle steel (1) is located above the nuts (3) and is arranged on the vertical bolts (2) so as to be movable up and down; by screwing the nuts (3) to move them up or down, the height and inclination of the angle steel (1) can be adjusted.

4. The seamless floor according to claim 3, characterized in that: It also includes a metal mesh (4) arranged below the angle steel (1), the metal mesh (4) is arranged along the length direction of the angle steel (1) and is fixedly connected to the corresponding upright bolt (2), the lower end of the metal mesh (4) is vertically buried in the gravel (12) and the concrete cushion layer (11), and the upper end is fixedly connected to the angle steel (1).

5. The seamless floor according to claim 2, characterized in that: A plurality of cement pads (9) are cast at intervals on the concrete cushion layer (11), and the steel mesh (5) at the lower layer is horizontally fixed on the cement pads (9); A plurality of supporting saddle bars (7) are fixedly arranged at intervals on the concrete cushion layer (11), and the steel mesh (5) of the upper layer is fixedly arranged horizontally on the upper ends of the supporting saddle bars (7).

6. The seamless floor according to claim 1, characterized in that: Steel fibers for enhancing the structural strength of the floor (10) are mixed into the concrete used for casting the floor (10), and hook portions are formed at both ends of the steel fibers.

7. A construction method for a seamless floor according to claim 1, characterized in that: The specific steps include: Laying upper and lower layers of steel mesh (5) at the designed position of the floor (10); Angle steel (1) is arranged above the upper and lower layers of the steel mesh (5), and the angle steel (1) is located at the junction of two adjacent floors (10); Concrete is poured in turn at the designed position of each floor (10), and the difference in pouring time between two adjacent floors (10) does not exceed 36 hours.

8. The construction method of the seamless floor according to claim 7 is characterized in that: Before laying the steel mesh (5), providing a pole bolt (2) and a metal mesh (4), vertically fixing the pole bolt (2) on the ground and fixing the metal mesh (4) on the pole bolt (2); Providing crushed stones (12), and laying the crushed stones (12) horizontally at the designed position of the floor (10); Then, a concrete cushion layer (11) is cast on top of the crushed stone (12), so that the lower ends of the upright bolts (2) and the metal mesh (4) are buried in the crushed stone (12) and the concrete cushion layer (11).

9. The construction method of the seamless floor according to claim 8 is characterized in that: Before installing the angle steel (1), a nut (3) is provided and installed on the vertical pole bolt (2), and then the angle steel (1) is installed on the vertical pole bolt (2) so that the nut (3) supports the angle steel (1), and the height of the nut (3) is adjusted by screwing the nut (3), thereby adjusting the height and inclination of the angle steel (3).

10. The construction method of the seamless floor according to claim 7, characterized in that: Before pouring the floor (10), steel fibers are provided and evenly mixed into concrete.

Citation Information

Patent Citations

  • Construction method for connecting joint structure of foundation of stamping equipment and floor

    CN111663559A

  • Ultra-large-area ultra-high-precision one-time forming terrace seamless connection construction method

    CN112696024A

  • High-precision floor construction equipment based on guide rail adjustable support

    CN117005649A

  • Simple and easy vertical dual -purpose regulator of level

    CN206737445U