Fault monitoring method and system based on low-voltage power distribution system

Through the fault monitoring method based on the low-voltage distribution system, the power consumption information of the electrolytic cell is obtained in real time and compared with historical data, the problem of insufficient real-time monitoring of the electrolytic cell is solved, and faster and more accurate fault detection and response are achieved.

CN119667326APending Publication Date: 2025-03-21SHENGHUI NEW ENERGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411780073.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-05
Publication Date
2025-03-21

AI Technical Summary

Technical Problem

In the prior art, the fault monitoring of electrolytic cells is poor in real-time, which makes it difficult to identify and respond to faults in a timely manner, which may lead to failure deterioration.

Method used

The fault monitoring method based on the low-voltage distribution system is adopted, and the current cumulative power consumption information and hydrogen preparation information of the target electrolytic cell are obtained by responding to the hydrogen preparation end instruction. Combined with the historical database, the target cumulative power consumption information is quickly obtained and the fault detection result information is generated in real time.

Benefits of technology

It improves the real-time nature of fault monitoring, timely identify and respond to faults, avoids fault deterioration, and significantly improves the monitoring effect of electrolytic cells.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119667326A_ABST
    Figure CN119667326A_ABST
Patent Text Reader

Abstract

The invention is suitable for the technical field of fault monitoring, and provides a fault monitoring method and system based on a low-voltage power distribution system, and the method comprises the steps: obtaining the current accumulated power consumption information and hydrogen preparation amount information of a target electrolytic cell in response to a hydrogen preparation ending instruction, and then retrieving a historical database according to the hydrogen preparation amount information, target accumulated power consumption information of the target electrolytic cell is rapidly obtained, and finally fault detection result information is generated in real time according to the current accumulated power consumption information and the target accumulated power consumption information. According to the method, after the hydrogen preparation task is completed, fault detection and treatment can be rapidly carried out on the target electrolytic cell, the real-time performance of fault monitoring is greatly improved, and by optimizing the fault monitoring mechanism of the electrolytic cell, the efficiency and sustainability of alkaline water hydrogen production can be improved, implementation of a dual-carbon target is supported, and carbon emission and energy consumption are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of fault monitoring, and in particular to a fault monitoring method and system based on a low voltage power distribution system. Background Art

[0002] Electrolyzer is one of the commonly used equipment in hydrogen production by electrolysis of water. Electrolyzer can generate hydrogen and oxygen by electrolyzing water. Since no harmful by-products are produced in the process of electrolyzing water, it meets environmental protection requirements and can produce high-purity hydrogen and oxygen, so electrolyzer has been more widely used.

[0003] At present, the monitoring of electrolytic cells mainly relies on regular inspections, which makes it difficult to identify and respond to faults in a timely manner when they occur. This has a certain lag and may even cause the fault to continue to deteriorate. The real-time performance is poor and needs further improvement. Summary of the invention

[0004] Based on this, an embodiment of the present application provides a fault monitoring method and system based on a low-voltage power distribution system to solve the problem of poor real-time performance in the prior art.

[0005] In a first aspect, an embodiment of the present application provides a fault monitoring method based on a low voltage power distribution system, the method comprising:

[0006] In response to the hydrogen production end instruction, obtaining current cumulative power consumption information and hydrogen production amount information of the target electrolytic cell;

[0007] According to the hydrogen production amount information and a preset historical database, obtaining the target cumulative power consumption information of the target electrolyzer;

[0008] Fault detection result information is generated according to the current cumulative power consumption information and the target cumulative power consumption information.

[0009] Compared with the prior art, the beneficial effect is that in the fault monitoring method based on the low-voltage power distribution system provided in the embodiment of the present application, the terminal device can first respond to the hydrogen preparation end instruction, quickly obtain the current cumulative power consumption information and hydrogen preparation information of the target electrolyzer, and then search the historical database according to the hydrogen preparation information, and efficiently obtain the target cumulative power consumption information of the target electrolyzer, and finally generate fault detection result information in real time according to the current cumulative power consumption information and the target cumulative power consumption information, so as to realize timely fault detection and processing of the target electrolyzer after the hydrogen preparation task is completed, effectively improve the real-time performance of fault monitoring, and to a certain extent solve the current problem of poor real-time performance.

[0010] In a second aspect, an embodiment of the present application provides a fault monitoring system based on a low voltage power distribution system, the system comprising:

[0011] Current accumulated power consumption information acquisition module: used to obtain the current accumulated power consumption information and hydrogen production amount information of the target electrolyzer in response to the hydrogen production end instruction;

[0012] Target cumulative power consumption information acquisition module: used to acquire the target cumulative power consumption information of the target electrolyzer according to the hydrogen production amount information and a preset historical database;

[0013] Fault detection result information generating module: used for generating fault detection result information according to the current accumulated power consumption information and the target accumulated power consumption information.

[0014] In a third aspect, an embodiment of the present application provides a terminal device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the method of the first aspect described above when executing the computer program.

[0015] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the method of the first aspect described above are implemented.

[0016] It can be understood that the beneficial effects of the second to fourth aspects mentioned above can be found in the relevant description of the first aspect mentioned above, and will not be repeated here. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments or the description of the prior art are briefly introduced below.

[0018] Figure 1 is a flowchart of a fault monitoring method provided by an embodiment of the present application;

[0019] Figure 2 is a flow chart of step S200 in the fault monitoring method provided in one embodiment of the present application;

[0020] Figure 3 is a flowchart of step S300 in the fault monitoring method provided in one embodiment of the present application;

[0021] Figure 4 It is a flowchart after step S300 in the fault monitoring method provided in one embodiment of the present application;

[0022] Figure 5It is a flowchart after step S410 in the fault monitoring method provided in one embodiment of the present application;

[0023] Figure 6 is a module block diagram of a fault monitoring system provided by an embodiment of the present application;

[0024] Figure 7 It is a schematic diagram of a terminal device provided in one embodiment of the present application. DETAILED DESCRIPTION

[0025] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present application. However, it should be clear to those skilled in the art that the present application may also be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present application.

[0026] In the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.

[0027] References to "one embodiment" or "some embodiments" etc. described in the specification of this application mean that one or more embodiments of the present application include specific features, structures or characteristics described in conjunction with the embodiment. Therefore, the statements "in one embodiment", "in some embodiments", "in some other embodiments", "in some other embodiments", etc. that appear in different places in this specification do not necessarily refer to the same embodiment, but mean "one or more but not all embodiments", unless otherwise specifically emphasized in other ways. The terms "including", "comprising", "having" and their variations all mean "including but not limited to", unless otherwise specifically emphasized in other ways.

[0028] In order to illustrate the technical solution described in this application, a specific embodiment is provided below for illustration.

[0029] See also Figure 1 , Figure 11 is a flow chart of a fault monitoring method based on a low-voltage power distribution system provided in an embodiment of the present application. In this embodiment, the execution subject of the fault monitoring method is a terminal device. It is understandable that the types of terminal devices include but are not limited to mobile phones, tablet computers, laptop computers, ultra-mobile personal computers (Ultra-Mobile Personal Computer, UMPC), netbooks, personal digital assistants (Personal Digital Assistant, PDA), etc., and the embodiments of the present application do not impose any restrictions on the specific types of terminal devices.

[0030] See also Figure 1 The fault monitoring method provided in the embodiment of the present application includes but is not limited to the following steps:

[0031] In S100, in response to the hydrogen production end instruction, the current cumulative power consumption information and hydrogen production amount information of the target electrolytic cell are obtained.

[0032] Specifically, the terminal device can first respond to the hydrogen preparation end instruction, obtain the hydrogen preparation amount information of the target electrolyzer based on the preset gas flow meter, and at the same time obtain the current cumulative power consumption information of the target electrolyzer based on the low-voltage power distribution system connected to the target electrolyzer, wherein the hydrogen preparation end instruction is used to describe the feedback instruction generated by the target electrolyzer to end the hydrogen preparation task; the target electrolyzer is used to describe the PEM electrolyzer or alkaline electrolyzer monitored in real time; the current cumulative power consumption information is used to describe the power consumption of the target electrolyzer in this hydrogen preparation task; and the hydrogen preparation amount information is used to describe the amount of hydrogen prepared by the target electrolyzer in this hydrogen preparation task.

[0033] In S200, target cumulative power consumption information of the target electrolytic cell is obtained based on the hydrogen production amount information and a preset historical database.

[0034] Specifically, after the terminal device obtains the current cumulative power consumption information and hydrogen production information, the terminal device can quickly obtain the target cumulative power consumption information of the target electrolyzer based on the hydrogen production information and a preset historical database.

[0035] In some possible implementations, in order to quickly obtain the target cumulative power consumption information of the target electrolytic cell, please refer to Figure 2 Step S200 includes but is not limited to the following steps:

[0036] In S210, the historical database is searched based on the hydrogen production amount information to obtain the preliminary power consumption information.

[0037] Specifically, the terminal device can first search the historical database based on the hydrogen preparation quantity information, and obtain the preliminary power consumption information from the historical database, wherein the historical database stores multiple historical preparation quantity information, and the historical database also stores the historical cumulative power consumption information corresponding to each historical preparation quantity information; the preliminary power consumption information is used to describe the historical cumulative power consumption information corresponding to the historical preparation quantity information that is equal to the current cumulative power consumption information.

[0038] Exemplarily, the terminal device may first determine the historical preparation quantity information in the historical database that is equal to the current cumulative power consumption information, and then determine the historical cumulative power consumption information corresponding to the historical preparation quantity information.

[0039] It should be noted that, when there is no historical preparation quantity information equal to the current cumulative power consumption information in the historical database, the terminal device can determine the historical preparation quantity information whose value is closest to the current cumulative power consumption information as the determination object.

[0040] In S220 , it is determined whether the number of the initially selected power consumption information is plural.

[0041] Specifically, after the terminal device obtains the preliminary selected power consumption information, the terminal device may determine whether the number of the preliminary selected power consumption information is multiple.

[0042] In S230 , if there are multiple pieces of preliminary selected power consumption information, the preliminary selected power consumption information with the shortest difference time is determined as the target cumulative power consumption information; otherwise, the preliminary selected power consumption information is determined as the target cumulative power consumption information.

[0043] Specifically, if there are multiple preliminary power consumption information, the terminal device can determine the preliminary power consumption information with the shortest gap time as the target cumulative power consumption information, where the gap time is used to describe the interval time between the preliminary power consumption information and the response time of the hydrogen preparation end instruction.

[0044] Without loss of generality, if the number of the preliminary selected power consumption information is only one, the terminal device can directly determine the preliminary selected power consumption information as the target cumulative power consumption information.

[0045] In S300 , fault detection result information is generated based on the current cumulative power consumption information and the target cumulative power consumption information.

[0046] Specifically, after the terminal device determines the target cumulative power consumption information of the target electrolyzer, the terminal device can promptly generate fault detection result information based on the current cumulative power consumption information and the target cumulative power consumption information, thereby achieving timely fault detection and processing after the target electrolyzer completes the hydrogen preparation task, thereby improving the real-time performance of fault monitoring.

[0047] In some possible implementations, in order to generate effective fault detection result information, please refer to Figure 3 Step S300 includes but is not limited to the following steps:

[0048] In S310, power consumption abnormal increase value information is generated based on the difference between the current cumulative power consumption information and the target cumulative power consumption information.

[0049] Without loss of generality, as the use time of the target electrolytic cell increases, the components inside the target electrolytic cell may experience excessive aging and other faults, resulting in an abnormal increase in power consumption.

[0050] Specifically, the terminal device can generate abnormal power consumption growth value information based on the difference between the current cumulative power consumption information and the target cumulative power consumption information, wherein the abnormal power consumption growth value information is the difference between the current cumulative power consumption information and the target cumulative power consumption information.

[0051] In S320, the abnormal growth value information of power consumption is compared with the preset reasonable growth value information.

[0052] Specifically, after the terminal device generates abnormal power consumption growth value information, the terminal device can compare the abnormal power consumption growth value information with the preset reasonable growth value information, wherein the reasonable growth value information is used to describe the power consumption growth value of the target electrolytic cell that meets the production requirements as the usage time increases. The reasonable growth value information can be customized by production personnel according to production requirements.

[0053] In S330, if the abnormal increase value information of power consumption is greater than the reasonable increase value information, the increase difference information is generated according to the difference between the abnormal increase value information of power consumption and the reasonable increase value information.

[0054] Specifically, if the abnormal growth value information of power consumption is greater than the reasonable growth value information, the terminal device can generate growth difference information based on the difference between the abnormal growth value information of power consumption and the reasonable growth value information, wherein the growth difference information is the difference between the abnormal growth value information of power consumption and the reasonable growth value information.

[0055] In S340, the growth difference information is compared with the preset difference threshold information.

[0056] Specifically, after the terminal device generates the growth difference information, the terminal device may compare the growth difference information with the preset difference threshold information, wherein the difference threshold information may be customized by the production personnel according to the production requirements.

[0057] In S350, if the growth difference information is greater than the difference threshold information, severe fault information is generated, otherwise, mild fault information is generated.

[0058] Specifically, the fault detection result information includes minor fault information or major fault information. The minor fault information is used to describe the existence of a minor fault in the target electrolytic cell, and the major fault information is used to describe the existence of a major fault in the target electrolytic cell. If the growth difference information is greater than the difference threshold information, the terminal device can generate major fault information. If the growth difference information is less than or equal to the difference threshold information, the terminal device can generate minor fault information, thereby achieving real-time and accurate monitoring of the target electrolytic cell on the premise of measuring the actual working condition of the target electrolytic cell.

[0059] In some possible implementations, in order to facilitate iterative fault monitoring of the target electrolyzer in combination with big data, please refer to Figure 4 If the fault detection result information is severe fault information, then after step S300, the method further includes but is not limited to the following steps:

[0060] In S400, the current maximum current information, the maximum electrolyte concentration information and the current maximum operating temperature information of the target electrolytic cell are obtained.

[0061] Specifically, the terminal device can first obtain the current maximum current information of the target electrolyzer based on the low-voltage power distribution system connected to the target electrolyzer, and obtain the maximum electrolyte concentration information of the target electrolyzer based on a preset concentration sensor, and at the same time obtain the current maximum operating temperature information of the target electrolyzer based on a preset temperature sensor, wherein the current maximum current information is used to describe the maximum current of the target electrolyzer in this hydrogen preparation task; the maximum electrolyte concentration information is used to describe the maximum electrolyte concentration of the target electrolyzer in this hydrogen preparation task; and the current maximum operating temperature information is used to describe the highest operating temperature of the target electrolyzer in this hydrogen preparation task.

[0062] In S410, warning parameter set information is generated according to the current maximum current information, the maximum electrolyte concentration information and the current maximum operating temperature information.

[0063] Specifically, after the terminal device obtains the current maximum current information, the maximum electrolyte concentration information and the current maximum operating temperature information, the terminal device can comprehensively generate the warning parameter set information based on the current maximum current information, the maximum electrolyte concentration information and the current maximum operating temperature information, thereby classifying the current maximum current information, the maximum electrolyte concentration information and the current maximum operating temperature information into a warning parameter set, so as to facilitate the automatic generation of warning information when the corresponding parameters reach the current maximum current information, the maximum electrolyte concentration information and the current maximum operating temperature information again.

[0064] In some possible implementations, in order to facilitate production personnel to intuitively know the maintenance effect, please refer to Figure 5After step S410, the method further includes but is not limited to the following steps:

[0065] In S420, in response to the fault repair completion instruction, the hydrogen production end instruction is executed again to obtain the current cumulative power consumption information and hydrogen production information of the target electrolytic cell until the fault detection result information is generated based on the current cumulative power consumption information and the target cumulative power consumption information.

[0066] Specifically, the terminal device may execute the above steps S100 to S300 again in response to a fault repair completion instruction, wherein the fault repair completion instruction is used to describe the production personnel completing the fault repair task for the target electrolytic cell.

[0067] In S430, if the fault detection result information is light fault information or heavy fault information, fault repair failure information is generated.

[0068] Specifically, if the fault detection result information is again a minor fault information or a severe fault information, it indicates that the maintenance effect is not as expected, and the terminal device can generate fault repair failure information, where the fault repair failure information is used to describe the failure of the fault repair process for the target electrolytic cell and requires repair again.

[0069] The implementation principle of the fault monitoring method based on the low-voltage power distribution system in the embodiment of the present application is as follows: the terminal device can first respond to the hydrogen preparation end instruction, obtain the current cumulative power consumption information and hydrogen production information of the target electrolyzer, and then search the historical database according to the hydrogen production information to quickly obtain the target cumulative power consumption information of the target electrolyzer, and finally generate fault detection result information in real time according to the current cumulative power consumption information and the target cumulative power consumption information, so as to realize timely fault detection and processing of the target electrolyzer after the hydrogen preparation task is completed, thereby effectively improving the real-time performance of fault monitoring.

[0070] It should be noted that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.

[0071] The embodiment of the present application also provides a fault monitoring system based on a low voltage power distribution system. For ease of description, only the parts related to the present application are shown, such as Figure 6 As shown, the system 60 includes:

[0072] Current accumulated power consumption information acquisition module 61: used to obtain current accumulated power consumption information and hydrogen production amount information of the target electrolyzer in response to the hydrogen production end instruction;

[0073] Target cumulative power consumption information acquisition module 62: used to acquire target cumulative power consumption information of a target electrolyzer according to hydrogen production amount information and a preset historical database;

[0074] The fault detection result information generating module 63 is used to generate fault detection result information according to the current cumulative power consumption information and the target cumulative power consumption information.

[0075] Optionally, the target cumulative power consumption information acquisition module 62 includes:

[0076] A submodule for obtaining preliminary power consumption information: used to retrieve a historical database based on hydrogen preparation amount information to obtain preliminary power consumption information, wherein the historical database stores a plurality of historical preparation amount information and historical cumulative power consumption information corresponding to each historical preparation amount information, and the preliminary power consumption information is used to describe the historical cumulative power consumption information corresponding to the historical preparation amount information equal to the current cumulative power consumption information;

[0077] Quantity judgment submodule: used to judge whether the quantity of the primary selected power consumption information is multiple;

[0078] Target cumulative power consumption information determination submodule: used to determine the preliminary power consumption information with the shortest gap time as the target cumulative power consumption information if there are multiple preliminary power consumption information; otherwise, determine the preliminary power consumption information as the target cumulative power consumption information, wherein the gap time is used to describe the interval between the preliminary power consumption information and the response time of the hydrogen preparation end instruction.

[0079] Optionally, the fault detection result information generating module 63 includes:

[0080] The power consumption abnormal growth value information generating submodule is used to generate the power consumption abnormal growth value information according to the difference between the current cumulative power consumption information and the target cumulative power consumption information;

[0081] The power consumption abnormal growth value information comparison submodule is used to compare the power consumption abnormal growth value information with the preset reasonable growth value information;

[0082] Growth difference information generation submodule: used for generating growth difference information according to the difference between the abnormal growth value information of power consumption and the reasonable growth value information if the abnormal growth value information of power consumption is greater than the reasonable growth value information;

[0083] Growth difference information comparison submodule: used to compare growth difference information with preset difference threshold information;

[0084] Severe fault information generation submodule: used to generate severe fault information if the growth difference information is greater than the difference threshold information, otherwise generate mild fault information, wherein the fault detection result information includes mild fault information or severe fault information.

[0085] Optionally, if the fault detection result information is severe fault information, the system 60 further includes:

[0086] Current maximum current information acquisition module: used to obtain the current maximum current information, electrolyte maximum concentration information and current maximum operating temperature information of the target electrolytic cell;

[0087] Warning parameter set information generation module: used to generate warning parameter set information according to current maximum current information, maximum electrolyte concentration information and current maximum operating temperature information.

[0088] Optionally, the system 60 further includes:

[0089] Fault repair completion instruction response module: used to respond to the fault repair completion instruction, execute again in response to the hydrogen preparation end instruction, obtain the current cumulative power consumption information and hydrogen preparation amount information of the target electrolyzer, and generate fault detection result information according to the current cumulative power consumption information and the target cumulative power consumption information;

[0090] Fault repair failure information generation module: used to generate fault repair failure information if the fault detection result information is mild fault information or severe fault information.

[0091] It should be noted that the information interaction, execution process and other contents between the above-mentioned modules are based on the same concept as the method embodiment of the present application. Their specific functions and technical effects can be found in the method embodiment part and will not be repeated here.

[0092] The present application also provides a terminal device, such as Figure 7 As shown, the terminal device 70 of this embodiment includes: a processor 71, a memory 72, and a computer program 73 stored in the memory 72 and executable on the processor 71. When the processor 71 executes the computer program 73, the steps in the above-mentioned fault monitoring method embodiment are implemented, for example Figure 1 Steps S100 to S300 shown; or, when the processor 71 executes the computer program 73, the functions of each module in the above device are realized, for example Figure 6 The functions of modules 61 to 63 are shown.

[0093] The terminal device 70 may be a computing device such as a desktop computer, a notebook, a PDA, or a cloud server, and the terminal device 70 includes but is not limited to a processor 71 and a memory 72. Those skilled in the art will appreciate that Figure 7It is only an example of the terminal device 70 and does not constitute a limitation of the terminal device 70. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, the terminal device 70 may also include input and output devices, network access devices, buses, etc.

[0094] Among them, the processor 71 can be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc.; the general-purpose processor can be a microprocessor or the processor can also be any conventional processor, etc.

[0095] The memory 72 may be an internal storage unit of the terminal device 70, such as a hard disk or memory of the terminal device 70, or the memory 72 may be an external storage device of the terminal device 70, such as a plug-in hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (Secure Digital, SD) card, a flash card (Flash Card), etc. equipped on the terminal device 70; further, the memory 72 may also include both an internal storage unit and an external storage device of the terminal device 70, and the memory 72 may also store a computer program 73 and other programs and data required by the terminal device 70, and the memory 72 may also be used to temporarily store data that has been output or is to be output.

[0096] One embodiment of the present application also provides a computer-readable storage medium, which stores a computer program, and when the computer program is executed by a processor, the steps of each of the above method embodiments can be implemented. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form, etc.; the computer-readable medium may include: any entity or device that can carry computer program code, recording medium, USB flash drive, mobile hard disk, magnetic disk, optical disk, computer memory, read-only memory (ROM), random access memory (RAM), electric carrier signal, telecommunication signal and software distribution medium, etc.

[0097] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, all equivalent changes made according to the methods, principles, and structures of the present application should be included in the protection scope of the present application.

Claims

1. A fault monitoring method based on a low voltage power distribution system, characterized in that: The method comprises: In response to the hydrogen production end instruction, obtaining current cumulative power consumption information and hydrogen production amount information of the target electrolytic cell; According to the hydrogen production amount information and a preset historical database, obtaining the target cumulative power consumption information of the target electrolyzer; Fault detection result information is generated according to the current cumulative power consumption information and the target cumulative power consumption information.

2. The method according to claim 1, characterized in that The step of obtaining target cumulative power consumption information of the target electrolyzer according to the hydrogen production amount information and a preset historical database includes: Based on the hydrogen production amount information, the historical database is searched to obtain preliminary power consumption information, wherein the historical database stores a plurality of historical production amount information and historical cumulative power consumption information corresponding to each of the historical production amount information, and the preliminary power consumption information is used to describe the historical cumulative power consumption information corresponding to the historical production amount information equal to the current cumulative power consumption information; Determining whether the number of the preliminary selected power consumption information is multiple; If there are multiple preliminary power consumption information, the preliminary power consumption information with the shortest gap time is determined as the target cumulative power consumption information, otherwise the preliminary power consumption information is determined as the target cumulative power consumption information, wherein the gap time is used to describe the interval between the preliminary power consumption information and the response time of the hydrogen preparation end instruction.

3. The method according to claim 2, characterized in that The generating fault detection result information according to the current cumulative power consumption information and the target cumulative power consumption information includes: Generate abnormal power consumption growth value information according to the difference between the current cumulative power consumption information and the target cumulative power consumption information; Comparing the abnormal growth value information of power consumption with the preset reasonable growth value information; If the abnormal growth value information of power consumption is greater than the reasonable growth value information, generating growth difference information according to the difference between the abnormal growth value information of power consumption and the reasonable growth value information; Comparing the growth difference information with preset difference threshold information; If the growth difference information is greater than the difference threshold information, severe fault information is generated, otherwise mild fault information is generated, wherein the fault detection result information includes the mild fault information or the severe fault information.

4. The method according to claim 3, characterized in that If the fault detection result information is the severe fault information, then after generating the fault detection result information according to the current cumulative power consumption information and the target cumulative power consumption information, the method further includes: Obtaining current maximum current information, electrolyte maximum concentration information, and current maximum operating temperature information of the target electrolytic cell; The warning parameter set information is generated according to the current maximum current information, the maximum electrolyte concentration information and the current maximum operating temperature information.

5. The method according to claim 4, characterized in that After generating the warning parameter set information according to the current maximum current information, the electrolyte maximum concentration information and the current maximum operating temperature information, the method further includes: In response to the fault repair completion instruction, the instruction in response to the hydrogen production end instruction is executed again, and the current cumulative power consumption information and the hydrogen production amount information of the target electrolyzer are obtained until the fault detection result information is generated according to the current cumulative power consumption information and the target cumulative power consumption information; If the fault detection result information is the minor fault information or the major fault information, fault repair failure information is generated.

6. A fault monitoring system based on a low voltage power distribution system, characterized in that: The system comprises: Current accumulated power consumption information acquisition module: used to obtain the current accumulated power consumption information and hydrogen production amount information of the target electrolyzer in response to the hydrogen production end instruction; Target cumulative power consumption information acquisition module: used to acquire the target cumulative power consumption information of the target electrolyzer according to the hydrogen production amount information and a preset historical database; Fault detection result information generating module: used for generating fault detection result information according to the current accumulated power consumption information and the target accumulated power consumption information.

7. The system according to claim 6, characterized in that The target cumulative power consumption information acquisition module includes: A preliminary power consumption information acquisition submodule: used to retrieve the historical database based on the hydrogen production amount information to obtain preliminary power consumption information, wherein the historical database stores a plurality of historical production amount information and historical cumulative power consumption information corresponding to each of the historical production amount information, and the preliminary power consumption information is used to describe the historical cumulative power consumption information corresponding to the historical production amount information equal to the current cumulative power consumption information; Quantity determination submodule: used to determine whether the quantity of the primary selected power consumption information is multiple; Target cumulative power consumption information determination submodule: used to determine the preliminary power consumption information with the shortest gap time as the target cumulative power consumption information if there are multiple preliminary power consumption information; otherwise, determine the preliminary power consumption information as the target cumulative power consumption information, wherein the gap time is used to describe the interval between the preliminary power consumption information and the response time of the hydrogen preparation end instruction.

8. A terminal device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 5 are implemented.

9. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 5 are implemented.