A method and system for multi-variety mixed production scheduling of computer chassis for flexible production lines

By extracting bending position parameters to calculate changeover costs and grouping and sorting specifications, unnecessary changeover losses and out-of-tolerance part dimensions on flexible production lines are solved, achieving efficient production scheduling.

CN123070523APending Publication Date: 2026-11-10GUANGDONG PINSHENG IND CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611048224.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-07-15
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

On flexible production lines, existing technologies cannot effectively determine whether a model change is necessary, leading to unnecessary downtime for model changeovers and problems with out-of-tolerance parts dimensions, especially when different chassis models within the same specification family or the same model undergo design changes.

Method used

By extracting the bending position parameters of the batches to be produced, calculating the changeover cost, grouping and sorting based on chassis specifications, and generating a production schedule in conjunction with delivery date constraints, the system can automatically determine changeover requirements and optimize the production sequence.

Benefits of technology

It reduces unnecessary changeover losses, avoids part dimensional deviations, improves production efficiency and product quality, and achieves a deep match with the actual adjustment capabilities of the bending machine.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123070523A_ABST
    Figure CN123070523A_ABST
Patent Text Reader

Abstract

This application discloses a method and system for multi-variety mixed production scheduling of computer chassis for flexible production lines, relating to the field of production manufacturing scheduling technology. The method includes: extracting bending position parameters of each batch of products to be scheduled based on the bending control program corresponding to the batch to be scheduled; calculating changeover cost data based on the difference in bending position parameters between adjacent batches; grouping the batches to be scheduled according to chassis specifications; sorting the batches within each specification group based on the changeover cost data to obtain a production sequence within each group; verifying the completeness of the production sequence within each group based on the completeness requirements of parts corresponding to each chassis model; obtaining the completeness verification results; and connecting the production sequences within each specification group across groups, generating a production plan in conjunction with delivery date constraints. This application departs from the coarse-grained approach of judging changeover based on model codes, instead using the actual difference in bending position parameters to accurately quantify changeover costs, while simultaneously minimizing changeover losses and ensuring completeness of parts.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of production scheduling technology, and in particular to a method and system for scheduling multi-variety mixed production of computer chassis for flexible production lines. Background Technology

[0002] Computer chassis consist of various sheet metal parts, including side panels, top panels, bottom panels, front panels, and rear panels. All of these parts must be bent before they can enter the assembly process. On a flexible bending production line, multiple models of chassis sheet metal parts need to be produced continuously on the same line. When switching between different batches, if the bending positions of the parts in the two batches differ significantly, workers need to stop the line to manually readjust the bending machine positioning and change the cutting tools, which can take anywhere from ten minutes to longer. If the difference is small, the bending machine can adjust itself and connect in a few seconds without stopping the line. Therefore, producing batches with similar bending positions as close as possible is key to reducing changeover losses.

[0003] Currently, chassis sheet metal production lines use product model codes as the basis for production change decisions. If the model changes, a change is made; otherwise, no change is assumed. However, different models within the same specification family, such as mid-tower chassis conforming to the ATX standard, have similar bending positions. When switching between front and back bends, the bending machine can adjust automatically without stopping the line. Yet, the existing scheduling system may still trigger a line stop for changeover due to model differences, wasting production capacity. If a chassis of the same model undergoes a design change, even a slight adjustment of a few millimeters to the dimensions of a bending edge will change the bending position. If this exceeds the bending machine's automatic adjustment capability, the line must be stopped. However, current technology does not automatically convert the dimensional information from the design change to the bending parameters, causing the scheduling system to fail to detect this change. Workers continue processing according to the old parameters, resulting in dimensional errors and batch scrap.

[0004] Therefore, how to automatically determine whether a changeover is needed based on the actual difference in bending parameters, and how to reasonably arrange the production sequence of each batch while ensuring that the parts of the same chassis are completed as a set, so as to reduce unnecessary changeover losses, has become an urgent problem to be solved. Summary of the Invention

[0005] In view of the aforementioned problems, this application is hereby filed.

[0006] Therefore, this application provides a method and system for scheduling multi-variety mixed production of computer chassis for flexible production lines, which can solve the problems mentioned in the background art.

[0007] To solve the above-mentioned technical problems, this application provides the following technical solution: In the first aspect, this application provides a method for scheduling multi-variety mixed production of computer chassis for flexible production lines, including: extracting the bending position parameters of each batch of production to be scheduled based on the bending control program corresponding to the batch of production to be scheduled, calculating the changeover cost based on the difference between the bending position parameters of adjacent batches of production to be scheduled, and obtaining changeover cost data. The production batches to be scheduled are grouped by specifications based on chassis specifications, and the production batches to be scheduled are sorted within each specification group according to the changeover cost data to obtain the production scheduling sequence within the group. Based on the complete set requirements of the parts corresponding to each chassis model, the completeness verification of the production sequence within the group is performed to obtain the completeness verification result. Based on the complete set of verification results, the production scheduling sequences within each specification group are linked across groups, and a production scheduling plan is generated in combination with delivery date constraints.

[0008] Preferably, the bending position parameters of each batch to be produced are extracted based on the bending control program corresponding to the batch to be produced, including: The bending control program corresponding to each batch to be scheduled for production is analyzed to obtain the bending step sequence corresponding to each batch to be scheduled for production. Based on the bending step sequence, the X-axis coordinate value and R-axis angle value of the back gauge corresponding to each bending step are extracted to obtain the bending position parameters of each batch to be scheduled for production. In response to the absence of a bending control program for any of the batches to be scheduled for production, standard bending parameters are extracted based on the chassis specifications of the chassis model corresponding to the batch to be scheduled for production. These standard bending parameters are then used as the bending position parameters for the batch to be scheduled for production, and the batch to be scheduled for production is marked as pending confirmation.

[0009] Preferably, the step of calculating the changeover cost based on the difference in bending position parameters between adjacent production batches to be scheduled, and obtaining the changeover cost data, includes: The bending position parameters of adjacent production batches to be scheduled are compared step by step to obtain the X-axis coordinate difference and R-axis angle difference corresponding to each bending step. In response to any bending step where the X-axis coordinate difference exceeds the X-axis automatic adjustment threshold or the R-axis angle difference exceeds the R-axis automatic adjustment threshold, the number of bending steps between adjacent production batches that exceed the X-axis automatic adjustment threshold or the R-axis automatic adjustment threshold is counted, and the number of bending steps is determined as the changeover cost of the corresponding adjacent production batches. If the X-axis coordinate difference of all bending steps does not exceed the X-axis automatic adjustment threshold and the R-axis angle difference does not exceed the R-axis automatic adjustment threshold, the changeover cost of the corresponding adjacent production batch to be scheduled is determined to be zero. The changeover costs of each adjacent production batch to be scheduled are summarized to obtain the changeover cost data.

[0010] As a preferred option, it also includes: Parameter-driven replacement records are obtained by filtering out replacement records from historical replacement records that have different chassis models between batches and have no corresponding manual replacement instruction records. The bending position parameters of each batch corresponding to the previous and next batches in the parameter-driven change record are calculated step by step to obtain the X-axis coordinate difference and R-axis angle difference of each bending step corresponding to each change record. The minimum X-axis coordinate difference that causes line stoppage and line change in each of the aforementioned change records is determined as the X-axis automatic adjustment threshold, and the minimum R-axis angle difference that causes line stoppage and line change in each of the aforementioned change records is determined as the R-axis automatic adjustment threshold.

[0011] Preferably, the specification grouping of the production batches to be scheduled based on chassis specification standards includes: Based on the aforementioned chassis specification standards, extract the standard outer dimension codes of the chassis models corresponding to each of the batches to be produced; Batches of production to be scheduled that have the same standard code for outer dimensions shall be grouped into the same specification group; When the number of production batches to be scheduled in any specification group is lower than a preset batch lower limit, the adjacent specification group with the lowest changeover cost is determined based on the changeover cost data. The specification group is then merged with the adjacent specification group to update the specification group.

[0012] Preferably, the step of sorting the production batches to be scheduled within each specification group based on the changeover cost data to obtain the production scheduling sequence within the group includes: Based on the changeover cost data, construct a changeover cost matrix among the production batches to be scheduled within each specification group; Within each specification group, the production batch with the lowest total changeover cost compared to the other production batches to be scheduled is determined as the starting batch; Based on the current batch, the batch with the lowest changeover cost to the current batch is selected from the changeover cost matrix as the next batch. The production order of all batches to be scheduled within each specification group is determined step by step to obtain the production sequence within the group.

[0013] Preferably, the step of performing a completeness check on the production sequence within the group based on the completeness requirements of the parts corresponding to each chassis model, and obtaining the completeness check result, includes: Based on the component assembly requirements, determine the types of components required for each chassis model and the minimum assembly quantity for each component type; The production batches of each chassis model and each part type in the production scheduling sequence of the group are counted to obtain the production quantity to be scheduled. The quantity to be produced is checked for integer division with the corresponding minimum quantity of complete sets; In response to any part type having a non-zero divisibility margin, the parameter difference is calculated for each bending step of the production batch to be scheduled corresponding to the divisibility margin and the batches of the same chassis model already scheduled in the production sequence within the group. The number of bending steps exceeding the threshold corresponding to each scheduled batch is obtained. The adjacent position of the scheduled batch with the smallest number of bending steps exceeding the threshold is determined as the insertion position. The production batch to be scheduled corresponding to the divisibility margin is inserted into the insertion position and marked as a batch to be supplemented. If the divisibility remainder of all part types is zero, it is determined that the production sequence within the group meets the completeness requirement. The integer division verification results for each part type are summarized to obtain the complete set verification results.

[0014] Preferably, the step of performing cross-group connection of the production scheduling sequence within each specification group based on the complete set verification results includes: The cost of switching between the production batches to be scheduled at the end of each specification group and the production batches to be scheduled at the beginning of the adjacent specification group is used as the cross-group connection cost. Enumerate the arrangement order of each specification group and calculate the total cross-group connection cost corresponding to each arrangement order; Select the order with the lowest total cost of cross-group connection, and then sequentially splice the production scheduling sequences within each specification group according to the given order to obtain the global production scheduling sequence.

[0015] Preferably, the production scheduling plan generated in conjunction with delivery date constraints includes: The difference between the estimated completion time and the corresponding delivery date of each batch to be scheduled in the global production scheduling sequence is calculated to obtain the delivery date margin for each batch to be scheduled. In response to any production batch having a delivery date margin lower than a preset margin threshold, the production batch is identified as a forced advance batch. Within the specification group to which the forced advance batch belongs, the forced advance batch is moved forward to the earliest production scheduling position that satisfies the delivery date constraint of the forced advance batch, thus obtaining a production scheduling plan.

[0016] Secondly, this application also provides a multi-product mixed-layout production scheduling system for computer chassis for flexible production lines, including: The changeover analysis module extracts the bending position parameters of each batch of production to be scheduled based on the bending control program corresponding to the batch to be scheduled, calculates the changeover cost based on the difference in bending position parameters between adjacent batches to be scheduled, and obtains changeover cost data. The group sorting module groups the batches to be produced according to the chassis specification standards, and sorts the batches to be produced within each specification group according to the changeover cost data to obtain the production scheduling sequence within the group. The complete set verification module is used to verify the completeness of the production sequence within the group according to the complete set requirements of the parts corresponding to each chassis model, and to obtain the complete set verification result. The production scheduling module connects the production scheduling sequences within each specification group based on the complete set verification results, and generates a production scheduling plan in combination with delivery date constraints.

[0017] Implementing this application will have the following beneficial effects: 1. This application extracts the bending position parameters of each batch of products to be scheduled based on the bending control program corresponding to the batch to be scheduled. Specifically, it extracts the X-axis coordinate value and R-axis angle value of the back gauge. The number of bending steps between adjacent batches that exceed the automatic adjustment threshold of the equipment is used as the quantitative basis for changeover cost, thus eliminating the crude judgment method of triggering changeover based on differences in product model codes. For different model batches belonging to the same specification family and with similar bending parameters, it can be identified as a zero-cost changeover without line stoppage. For batches of the same model whose bending parameters have subtly shifted due to design changes and exceed the automatic adjustment capability of the equipment, it can be accurately identified as requiring line stoppage for changeover, avoiding workers continuing to process according to the old parameters, which would lead to out-of-tolerance parts and batch scrap. This achieves a deep match between changeover judgment and the actual physical mechanism of the bending machine.

[0018] 2. This application selects parameter-driven changeover records from historical changeover records that have different chassis models between batches and have no corresponding manual changeover instructions. By calculating the difference in bending position parameters of each batch between batches corresponding to each changeover record for each bending step, the minimum X-axis coordinate difference and the minimum R-axis angle difference that would cause a production stoppage for changeover are determined as the automatic adjustment thresholds for the X-axis and R-axis, respectively. The threshold self-calibration can be completed without production stoppage calibration. The judgment benchmark that matches the current equipment status is obtained by back-deriving the existing historical data of the production line, so that the changeover cost quantification always matches the actual adjustment capability of the production line.

[0019] 3. In the completeness verification, this application calculates the parameter difference between the production batch to be scheduled corresponding to the divisibility allowance and the batches of the same chassis model already scheduled in the group's production sequence for each bending step. The adjacent position of the scheduled batch with the smallest number of bending steps exceeding the threshold is used as the insertion position. This allows the two originally opposing production scheduling goals of ensuring completeness and saving changeovers to be unified through the same physical quantity, namely the number of bending steps exceeding the threshold. This enables unified quantitative processing, so that while meeting the constraints of completeness of parts, the additional changeover losses caused by inserting orders are controlled to the lowest level. Attached Figure Description

[0020] To more clearly illustrate the technical solutions in the embodiments of this application or related technologies, the drawings used in the description of the embodiments of this application or related technologies will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.

[0021] Figure 1 This is an overall flowchart of the multi-variety mixed production scheduling method for computer chassis for flexible production lines involved in this application; Figure 2 This is a schematic diagram of the completeness verification process of the multi-variety mixed production scheduling method for computer chassis for flexible production lines involved in this application. Figure 3 This is a schematic diagram of the overall structure of the computer chassis multi-variety mixed production scheduling system for flexible production lines involved in this application; Figure 4 This is a computer equipment diagram of the computer chassis multi-variety mixed production scheduling method for flexible production lines involved in this application. Detailed Implementation

[0022] To make the objectives, technical solutions, and advantages of this application clearer, the following detailed description is provided in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the scope of this application.

[0023] In one exemplary embodiment, such as Figure 1 As shown, a method for multi-variety mixed-product production scheduling of computer chassis for flexible production lines is provided, and this method is applied to... Figure 2 The following steps, S1 to S4, are used as an example to illustrate the application scenario. Wherein: Step S1: Extract the bending position parameters of each production batch based on the bending control program corresponding to the production batch to be scheduled. Calculate the changeover cost based on the difference in bending position parameters between adjacent production batches to be scheduled, and obtain the changeover cost data.

[0024] It should be noted that in the daily scheduling of flexible bending production lines, the conventional practice is to use the chassis model code as the basis for model change judgment. A change in the model code triggers a line stop for model change operation. In multi-product mixed scheduling scenarios, this practice will produce deviations in two situations: First, different models belonging to the tower specification family of the ATX standard have similar bending positions. When switching batches, the bending machine can automatically complete the parameter adjustment within a few seconds without stopping the line. However, judging based on the model code will still trigger a line stop for model change, causing unnecessary production capacity loss. Second, if the chassis of the same model has undergone design changes, and the size of a bending edge is adjusted by a few millimeters, the corresponding bending position will shift accordingly. When the offset exceeds the automatic adjustment capability of the bending machine, the line must be stopped. However, if the model code has not changed, the scheduling system cannot detect this change. Workers continue to process using the old parameters, resulting in parts with out-of-tolerance dimensions and batch scrap. Therefore, in step S1 of this application, the bending control program corresponding to the batch to be scheduled is used as the data source to extract bending position parameters that can directly reflect the positioning status of the bending machine, and the actual difference between the bending position parameters of adjacent batches is used as the calculation basis to quantify the changeover cost, so as to provide a judgment benchmark that matches the physical mechanism of the bending machine for subsequent production scheduling.

[0025] The input received in step S1 is the bending control program for each production batch to be scheduled, as well as the X-axis automatic adjustment threshold and R-axis automatic adjustment threshold corresponding to the automatic adjustment capability of the bending machine. The output of step S1 is changeover cost data, which is the set of changeover cost values ​​between each adjacent combination of production batches to be scheduled. The changeover cost data will serve as the basis for sorting within specification groups in step S2, directly affecting the formation of the production scheduling sequence within the group.

[0026] The "batch to be scheduled" refers to the batches of sheet metal parts that need to be processed in the current production schedule. Each batch corresponds to a type of part for a specific chassis model, such as the side panel or top panel of a certain chassis model. The bending control program is a digital program file stored in the bending machine control system or manufacturing execution system, used to control the parameters of each step of the bending machine. It records parameter information such as the back gauge positioning coordinates and bending angle for each bending step.

[0027] In some embodiments, step S1 includes steps S11 and S12: Step S11: Extract the bending position parameters of each batch to be produced based on the bending control program corresponding to the batch to be produced.

[0028] Understandably, step S11 is used to parse parameters from the bending control program that can quantify the positioning status of the bending machine, providing a parameterized expression for each production batch to be scheduled for the changeover cost calculation in step S12.

[0029] In some embodiments, step S11 includes steps S111 to S113: Step S111: Analyze the bending control program corresponding to each batch to be scheduled for production to obtain the bending process sequence corresponding to each batch to be scheduled for production.

[0030] Understandably, bending control programs are typically stored in a structured format, such as the program files generated by the DA CNC system or DELEM system commonly used in CNC bending machines. These files record parameters such as the back gauge coordinates, bending angle, and bending force for each bending action, arranged sequentially by step. Parsing the bending control program for each batch to be produced involves reading each parameter field step by step according to the program file's format specifications, extracting and organizing each bending action in the program into an ordered list—the bending step sequence. This bending step sequence records the execution order of all bending actions during the processing of that batch of parts and the parameter entries for each step, serving as the direct basis for subsequently extracting bending position parameters. For example, the bending control program for the front panel of a certain model of chassis contains six bending steps. After parsing, a bending step sequence numbered 1 to 6 is obtained, with each step recording the parameter information for its corresponding bending action. By analyzing the bending control program for each production batch, the bending action information in the program file can be converted into a structured sequence of steps, providing a unified processing basis for extracting position parameters step by step.

[0031] Step S112: Based on the sequence of each bending step, extract the X-axis coordinate value and R-axis angle value of the back gauge corresponding to each bending step to obtain the bending position parameters of each batch to be scheduled for production.

[0032] The X-axis coordinate value of the back gauge refers to the coordinate value of the back gauge along the X-axis direction when the bending step is executed. The unit is usually millimeters, and it is used to determine the horizontal positioning position of the sheet metal in the bending die. The R-axis angle value refers to the target angle value of the bending beam of the bending machine in the current bending step. The unit is usually degrees, and it is used to determine the bending forming angle. Together, they describe the positioning state of the bending machine in a specific step. The bending position parameters refer to the set of parameters extracted from the bending step sequence, consisting of the X-axis coordinate value and R-axis angle value of the back gauge corresponding to each bending step. They are recorded in batches to be scheduled for production. For example, the bending position parameters of a certain batch to be scheduled for production can be expressed as a parameter list containing 6 sets of X-axis coordinate values ​​and R-axis angle values, where each set of parameters corresponds to one step in the bending step sequence. By extracting the above two types of values ​​step by step from the bending process sequence, the positioning information in the bending control program can be converted into bending position parameters that can be compared numerically, so that the parameter difference between adjacent batches can be quantified and calculated, providing processing input for step S12.

[0033] Step S113: In response to the missing bending control program for any batch to be scheduled for production, extract standard bending parameters according to the chassis specifications of the chassis model corresponding to the batch to be scheduled for production, use the standard bending parameters as the bending position parameters of the batch to be scheduled for production, and mark the batch to be scheduled for production as pending confirmation.

[0034] It is understandable that in actual production environments, the bending control programs for some batches awaiting production scheduling may be missing due to reasons such as not yet being entered into the system, version update delays, or abnormal file transfers. Skipping these missing batches directly would result in incomplete changeover cost data, affecting the accuracy of subsequent production scheduling. Therefore, step S113 establishes a fallback mechanism for cases where bending control programs are missing: using chassis specification standards as the data source, it extracts the standard bending parameters for the corresponding chassis model and substitutes them as the bending position parameters for the missing batches in subsequent calculations. Here, chassis specification standards refer to reference data established based on industry standards such as ATX and mATX or internal product design specifications, recording the standard bending process parameters for each chassis model; standard bending parameters refer to the reference values ​​of the back gauge X-axis coordinate and R-axis angle for each bending step of the corresponding chassis model under standard conditions, extracted from the chassis specification standards. Meanwhile, step S113 marks the production batches with missing bending control programs as "pending confirmation" to distinguish them from batches whose bending position parameters have been extracted from the actual bending control program. This indicates that subsequent processing steps require manual verification of the actual bending parameters for this batch. For example, if the bending control program for a certain production batch is missing due to incomplete version update synchronization, step S113 extracts six sets of standard bending parameters for the corresponding model from the chassis specification standard as bending position parameters and marks the batch as "pending confirmation" so that it can participate in subsequent changeover cost calculations, while retaining the identification information that requires manual confirmation.

[0035] In the absence of bending control procedures, step S113 uses standard bending parameters as temporary substitutes in subsequent calculations to ensure that missing batches are not removed from the production schedule and to guarantee complete coverage of changeover cost data. The pending confirmation status label enables the production schedule results to clearly identify batches with parameter uncertainties, providing a directional basis for manual review and ensuring that the overall production schedule process can still proceed smoothly even with incomplete data.

[0036] It should be noted that step S11 extracts the X-axis coordinate value and R-axis angle value of the back gauge step by step from the bending control program, converting the bending process information of each batch to be scheduled into bending position parameters that can be compared numerically. For batches missing from the bending control program, standard bending parameters are used as input values, and a pending confirmation status is marked simultaneously, achieving complete coverage extraction of bending position parameters. The set of bending position parameters formed in step S11 serves as the input for step S12, enabling the changeover cost between adjacent batches to be scheduled to be quantified based on the actual step-level parameter differences, avoiding misjudgments caused by coarse-grained judgment of changeover based on model codes.

[0037] Step S12: Calculate the changeover cost based on the difference in bending position parameters between adjacent production batches to be scheduled, and obtain the changeover cost data.

[0038] Understandably, step S12 uses the bending position parameters of each production batch to be scheduled formed in step S11 as input, compares the differences in bending position parameters between adjacent production batches step by step, determines whether the bending machine can complete automatic adjustment without stopping the line, and uses the number of bending steps that require line stoppage as the quantitative result of changeover cost, summarizing the changeover cost data. The changeover cost data is recorded in units of adjacent production batch combinations, and will be used as the basis for calculation of sorting within specification groups and cross-group connection in step S2.

[0039] In some embodiments, step S12 includes steps S121 to S124: Step S121: Compare the bending position parameters of adjacent production batches for each bending step to obtain the X-axis coordinate difference and R-axis angle difference corresponding to each bending step.

[0040] It is understandable that comparing the bending position parameters of adjacent production batches step by step involves subtracting the X-axis coordinate values ​​of the back gauge from those of batch A and batch B under the same step number to obtain the X-axis coordinate difference; and subtracting the R-axis angle values ​​under the same step number to obtain the R-axis angle difference. The comparison is based on the absolute difference value, without distinguishing between positive and negative directions. For example, if the X-axis coordinate value of the back gauge in the second bending step of batch A is 152.0 mm, and the X-axis coordinate value of the back gauge in the second bending step of batch B is 154.5 mm, then the corresponding X-axis coordinate difference is 2.5 mm; if the R-axis angle value in the second bending step of batch A is 90.0°, and that of batch B is 91.2°, then the R-axis angle difference is 1.2°. After the step-by-step comparison is completed, a list of X-axis coordinate differences and a list of R-axis angle differences covering all bending steps are obtained, providing step-by-step quantitative comparison results for the threshold judgment in steps S122 and S123.

[0041] Step S122: In response to any bending step where the X-axis coordinate difference exceeds the X-axis automatic adjustment threshold or the R-axis angle difference exceeds the R-axis automatic adjustment threshold, count the number of bending steps between adjacent production batches that exceed the X-axis automatic adjustment threshold or the R-axis automatic adjustment threshold, and determine the number of bending steps as the changeover cost of the corresponding adjacent production batch.

[0042] The X-axis automatic adjustment threshold and R-axis automatic adjustment threshold represent the maximum X-axis coordinate difference and the maximum R-axis angle difference that the bending machine can automatically adjust parameters without stopping the line, respectively. The specific values ​​of these two thresholds can be obtained from historical data analysis of steps A1 to A3, or set according to the automatic adjustment capability parameters in the bending equipment specification manual. If the X-axis coordinate difference or R-axis angle difference of any bending step exceeds the X-axis automatic adjustment threshold, it indicates that the parameter change corresponding to that bending step has exceeded the automatic adjustment capability of the bending machine, requiring manual adjustment during batch switching. A bending step that meets any of the above conditions is called an over-threshold step. The total number of over-threshold steps between adjacent batches is counted, and this number is determined as the changeover cost between the two batches. The larger the number of bending steps, the more steps require manual intervention during changeover, and the higher the time loss due to line stoppage for changeover. For example, in a total of 6 bending steps in batches A and B, the X-axis coordinate difference of 2 steps exceeds the automatic X-axis adjustment threshold, and the R-axis angle difference of 1 step exceeds the automatic R-axis adjustment threshold, and there is no overlap among them. Then the number of steps exceeding the threshold is 3, and the corresponding changeover cost is 3.

[0043] Step S123: If the X-axis coordinate difference of all bending steps does not exceed the X-axis automatic adjustment threshold and the R-axis angle difference does not exceed the R-axis automatic adjustment threshold, the changeover cost of the corresponding adjacent production batch to be scheduled is determined to be zero.

[0044] Understandably, when the parameter differences of all bending steps are within the automatic adjustment capability of the bending machine, batch switching can be completed autonomously by the bending machine without manual operation during line stoppage, and the corresponding changeover cost is recorded as zero. Steps S122 and S123 cover two cases for calculating the changeover cost of adjacent batches: when there is a step exceeding the threshold, a non-zero changeover cost is recorded; when none of the steps exceed the threshold, a zero changeover cost is recorded. The two cases are mutually exclusive and completely cover all possible results, ensuring that the changeover cost value has a clear quantitative expression for each pair of adjacent batches.

[0045] Step S124: Summarize the changeover costs of each adjacent production batch to be scheduled to obtain changeover cost data.

[0046] Understandably, after steps S122 and S123 calculate the changeover cost values ​​for each pair of adjacent production batches, step S124 summarizes the changeover costs of all adjacent batch combinations to form changeover cost data. This changeover cost data uses the production batch pairs as indexes, recording the changeover cost values ​​between each batch pair. It can be organized in matrix or list form, and can be directly accessed in step S2 when constructing the changeover cost matrix within each specification group.

[0047] It should be noted that step S12 compares the parameter differences of each bending step and uses the number of steps exceeding the automatic adjustment threshold of the bending machine as the quantitative basis for changeover cost. This makes the changeover judgment result directly correspond to the actual adjustment capability of the bending machine, solving two problems: misjudgment and line stoppage between different models with similar parameters in model code changeover judgment, and inability to detect parameter offset after design changes of the same model. This provides an accurate quantitative basis for changeover cost for subsequent production scheduling.

[0048] Preferably, step S1 uses the bending control program as the parameter source to convert the bending processing status of each batch to be scheduled into bending position parameters composed of the back gauge X-axis coordinate value and R-axis angle value. The number of steps between adjacent batches whose bending position parameters exceed the automatic adjustment capability of the bending machine is used as a quantitative expression of the changeover cost, forming changeover cost data covering all batches to be scheduled. This establishes a quantitative input that matches the physical mechanism of the bending machine for specification grouping and intra-group sorting in step S2, avoiding the problem of changeover misjudgment and change blind spot coexisting under the model code judgment method.

[0049] In some embodiments, this application further includes steps A1 to A3: Step A1: Filter out replacement records from the historical replacement records that have different chassis models from previous and subsequent batches and have no corresponding manual replacement instruction records to obtain parameter-driven replacement records.

[0050] Understandably, step A1 is used to extract changeover event samples from historical production line data that reflect the automatic adjustment boundaries of the bending machine. Historical changeover records refer to batch changeover event logs stored in the production execution system, typically containing fields such as the previous batch chassis model, the subsequent batch chassis model, the changeover occurrence time, and whether a manual changeover instruction exists. The filtering criteria include two aspects: first, the chassis models of the previous and subsequent batches are different, ensuring that the bending parameters of the two batches corresponding to the changeover record have actual differences; second, there is no corresponding manual changeover instruction record, excluding changeover events triggered by manual intervention factors such as mold changes or process adjustments, retaining changeover events driven solely by changes in bending parameters. Changeover records that meet both conditions are parameter-driven changeover records, used for threshold calculations in subsequent steps A2 and A3.

[0051] Step A2: Calculate the difference of bending position parameters for each bending step in the parameter-driven changeover record for each batch before and after the changeover record, and obtain the difference of X-axis coordinate and R-axis angle for each bending step corresponding to each changeover record.

[0052] Understandably, step A2 uses the parameter-driven changeover records obtained in step A1 as input, and calculates the step-by-step difference in bending position parameters of the preceding and following batches in each changeover record using the same method as in step S121, to obtain the X-axis coordinate difference and R-axis angle difference for each bending step corresponding to each changeover record. The bending position parameters in each changeover record are extracted from the bending control program of the corresponding batch, using the same extraction method as in steps S111 and S112. By performing difference calculations on each parameter-driven changeover record, step-level difference data corresponding to each parameter-driven changeover event in history can be obtained, providing numerical samples for step A3 to calculate the automatic adjustment threshold of the equipment.

[0053] Step A3: Determine the minimum X-axis coordinate difference that causes line stoppage and line change in each change record as the X-axis automatic adjustment threshold, and determine the minimum R-axis angle difference that causes line stoppage and line change in each change record as the R-axis automatic adjustment threshold.

[0054] It is understandable that among the changeover record difference data obtained in step A2, some changeover records correspond to actual line stoppages for changeovers, while others correspond to automatic adjustments completed by the bending machine during batch switching. Among the changeover records that caused line stoppages for changeovers, the value with the smallest X-axis coordinate difference is the lower limit of X-axis parameter changes that the bending machine cannot automatically process, as reflected in the historical data, and is determined as the X-axis automatic adjustment threshold; similarly, the value with the smallest R-axis angle difference is determined as the R-axis automatic adjustment threshold. In other embodiments, the threshold can also be appropriately adjusted based on factors such as actual equipment status and maintenance cycle.

[0055] It should be noted that steps A1 to A3 involve filtering parameter-driven changeover records from historical changeover records and calculating the difference in bending position parameters between batches one by one. The minimum difference that actually caused the production line to stop for changeover in historical production line data is used to estimate the automatic adjustment thresholds for the X-axis and R-axis. This eliminates the need for special production stoppage calibration of the bending equipment, allowing the threshold calibration to be completed using existing historical data from the production line and to maintain dynamic matching with the actual adjustment capability of the current equipment. This provides an accurate threshold judgment benchmark for the changeover cost calculation in step S12.

[0056] Step S2: Based on the chassis specification standards, the production batches to be scheduled are grouped by specification. According to the changeover cost data, the production batches to be scheduled within each specification group are sorted to obtain the production sequence within the group.

[0057] It should be noted that in multi-product mixed production scheduling, if all batches to be scheduled are optimized globally without distinction, batches with significantly different bending positions may be arranged in adjacent positions due to local optima. This results in the bending machine needing to adjust from one size range to a completely different size range during batch switching, leading to a changeover loss far greater than that between batches with similar specifications. Taking ATX mid-tower and ITX mini chassis as examples, their external dimensions differ significantly, and the absolute difference in bending position parameters is usually large. If these two types of batches are frequently interleaved, each cross-specification switch requires a significant adjustment of the backgauge positioning, increasing both the number of changeovers and the total changeover time. Therefore, in step S2 of this application, the batches to be scheduled are first divided into several specification groups based on chassis specification standards to ensure that batches within the same group are within a similar range in external dimensions. Then, the batches are sorted within each specification group based on changeover cost data to minimize the changeover loss during batch switching within the group, resulting in a production scheduling sequence within the group.

[0058] Step S2 receives the changeover cost data and the list of production batches to be scheduled generated in step S1 as input, and generates the production scheduling sequence within each specification group as output, which is then used by step S3 for completeness verification.

[0059] In some embodiments, step S2 includes steps S21 and S22: Step S21: Group the batches to be produced according to their specifications based on the chassis specifications.

[0060] In some embodiments, step S21 includes steps S211 to S213: Step S211: Extract the standard outer dimension code of the corresponding chassis model for each batch to be produced based on the chassis specification standard.

[0061] Chassis specification standards refer to standard data describing the external dimensions of various chassis models, established based on industry specifications such as ATX, mATX, and ITX, or internal product design specifications of enterprises. These standards are typically recorded using fields such as the specification code corresponding to the model, and standard values ​​for length, width, and height. The external dimension standard code is a coded field in the chassis specification standard used to uniquely identify a type of external dimension specification. For example, ATX-MID-TOWER represents the tower specification in the ATX standard, and ITX-MINI represents the mini specification in the ITX standard. The specific coding system can be set according to enterprise specifications. Extracting the external dimension standard code means finding and retrieving the corresponding external dimension standard code field value from the chassis specification standard based on the chassis model corresponding to each production batch. For example, production batch P1 corresponds to chassis model M-ATX-01, and the external dimension standard code extracted from the chassis specification standard is MATX-MICRO; batch P2 corresponds to model A-ATX-05, and the extracted external dimension standard code is ATX-MID-TOWER. By extracting the standard codes of the outer dimensions in batches, a grouping basis field is provided for the grouping operation in step S212.

[0062] Step S212: Group production batches with the same standard code for outer dimensions into the same specification group.

[0063] Understandably, using the outer dimension standard code as the grouping key, production batches with the same outer dimension standard code are grouped into the same specification group. After grouping, the chassis models corresponding to batches within each specification group belong to the same specification category in terms of outer dimensions, and the overall range of bending position parameters is relatively concentrated. The parameter adjustment range when switching batches within a group is usually smaller than that when switching across specifications, which is conducive to achieving the goal of minimizing changeover costs. For example, batches P2, P5, and P7 with the outer dimension standard code ATX-MID-TOWER are grouped into group G1; batches P1, P3, and P6 with the outer dimension standard code MATX-MICRO are grouped into group G2. If the outer dimension standard code corresponding to a production batch does not exist in the chassis specification standard, it can be placed into a temporary group and marked, and the grouping results will be updated after manual confirmation.

[0064] Step S213: In response to the number of production batches to be scheduled in any specification group being lower than the preset batch lower limit, determine the adjacent specification group with the lowest changeover cost based on the changeover cost data, merge the specification group with the adjacent specification group, and update the specification group.

[0065] Understandably, the preset batch lower limit refers to the minimum number of batches required to maintain the independent existence of a specification group. This can be configured according to the actual production line situation, for example, set to 3 batches. When the number of batches to be scheduled within a specification group is lower than the preset batch lower limit, the efficiency of this group occupying a production time window alone is low. It is suitable to merge it with the adjacent specification group with the lowest changeover cost to reduce the number of cross-group changes. The adjacent specification group with the lowest changeover cost refers to the group with the lowest average changeover cost among batches within the specification group and batches within other specification groups in the changeover cost data. The merging process involves merging the batches to be scheduled from two specification groups into one specification group and updating the outer dimension standard code record. If, after merging, there are still specification groups with batch numbers lower than the preset batch lower limit, step S213 can be repeated until all specification groups meet the batch number requirements, or all batches have been merged into the same group.

[0066] It should be noted that step S21 divides the batches to be scheduled into various specification groups by using the standard code of the outer dimension as the grouping basis, and merges the groups with insufficient batch quantity, forming a specification grouping result in a concentrated distribution of batches with similar specifications and a reasonable and controllable number of groups. This allows the subsequent step S22 to sort the changeover cost within the specification constraints, avoiding the arrangement of batches with huge differences in bending position parameters in adjacent positions, and providing a grouping premise for minimizing changeover losses in the production sequence within the group.

[0067] Step S22: Sort the production batches to be scheduled within each specification group according to the changeover cost data to obtain the production scheduling sequence within the group.

[0068] In some embodiments, step S22 includes steps S221 to S223: Step S221: Construct a changeover cost matrix among production batches to be scheduled within each specification group based on changeover cost data.

[0069] It is understandable that the changeover cost matrix is ​​a square matrix with all batches to be scheduled within a specification group as rows and columns. The value at position (i,j) in the matrix represents the changeover cost between batch i and batch j when batch i is scheduled before batch j. The value comes from the changeover cost data generated in step S1. The changeover cost matrix only includes batches within the same specification group and does not involve batches across groups. For example, group G1 includes batches P2, P5, and P7. A 3×3 changeover cost matrix is ​​constructed. Position (P2,P5) in the matrix records the changeover cost of switching from batch P2 to batch P5, position (P5,P2) records the changeover cost of switching from batch P5 to batch P2, and so on. By constructing the changeover cost matrix, the changeover costs between all batch pairs within a group can be stored and queried in a unified structure, providing a data foundation for fast retrieval of data for the sorting operations in steps S222 and S223.

[0070] Step S222: Within each specification group, the production batch with the lowest total changeover cost with the other production batches to be scheduled is determined as the starting batch.

[0071] Understandably, the starting batch is the first batch in the production sequence within each specification group. The method for determining the starting batch is as follows: for each batch to be scheduled within a group, read its changeover cost from the changeover cost matrix and sum it with the changeover costs of all other batches within the group to obtain the total changeover cost for that batch; the batch with the smallest total changeover cost is determined as the starting batch. The smallest total changeover cost means that the bending position parameters of this batch are most similar to those of other batches within the group, and using it as the starting point ensures a better initial state for the overall changeover loss of subsequent production sequences. If multiple batches have the same and smallest total changeover cost, one can be randomly selected as the starting batch, or it can be further determined based on other auxiliary conditions, such as delivery date priority.

[0072] Step S223: Based on the current batch, select the unscheduled production batch with the smallest changeover cost from the changeover cost matrix as the next batch, and gradually determine the production order of all production batches to be scheduled within each specification group to obtain the production sequence within the group.

[0073] Understandably, step S223 uses the starting batch determined in step S222 as the current batch, retrieves the changeover cost between the current batch and all unscheduled batches from the changeover cost matrix, selects the unscheduled batch with the smallest changeover cost as the next batch immediately following the current batch, updates the next batch to the current batch, and repeats the above process until all unscheduled batches within the group have determined their scheduling positions, forming an intra-group scheduling sequence. If, at a certain step, multiple unscheduled batches have the same and smallest changeover cost as the current batch, the next batch can be further determined by combining auxiliary conditions such as delivery date. The intra-group scheduling sequence records the scheduling order of each batch within the group in the form of an ordered list, serving as the processing input for the completeness verification in step S3. For example, group G1 starts with batch P5. In the first step, the unscheduled batch P2 with the smallest changeover cost to P5 is selected as the next batch. In the second step, P2 is the current batch, and the unscheduled batch P7 with the smallest changeover cost to P2 is selected, resulting in the intra-group scheduling sequence of group G1 as P5, P2, and P7.

[0074] It should be noted that step S22 constructs a changeover cost matrix, starting with the batch with the smallest total changeover cost, and gradually selects the unscheduled batch with the smallest changeover cost to the current batch as the next batch. Within each specification group, a production scheduling sequence within the group that minimizes the total changeover loss within the group is formed. The changeover cost data quantified in step S1 is transformed into a specific batch arrangement order, providing an ordered production scheduling sequence input for the completeness verification in step S3.

[0075] Preferably, in step S2, the production batch to be scheduled is divided into several specification groups based on the standard code of the outer dimension. Then, the production order of the batch is gradually determined within each specification group based on the changeover cost data, forming a production sequence within the group. This decomposes the changeover optimization problem of multiple batches into a two-stage process of first grouping by specification and then sorting within the group. Under the premise of ensuring that batches with similar specifications are produced in a concentrated manner, the changeover loss within the group is minimized, providing a clear structure and controllable changeover cost within the group for the completeness verification in step S3.

[0076] Step S3: Perform a completeness check on the production sequence within the group based on the completeness requirements of the parts corresponding to each chassis model, and obtain the completeness check results.

[0077] It should be noted that on the flexible bending production line for chassis sheet metal parts, different parts of the same chassis, including side panels, top panels, bottom panels, front panels, and rear panels, must all be bent before entering the assembly process. Conventional production scheduling prioritizes minimizing changeover losses, arranging batches according to similar bending parameters. This may result in situations where the batch quantity of some part types for the same chassis model does not meet the set ratio requirements. For example, if four batches of side panels for a certain chassis model have been scheduled, but only three batches of bottom panels have been scheduled, the divisibility margin is 1, leading to a shortage of matching parts during the assembly stage and affecting the overall assembly progress. Therefore, in step S3 of this application, the part set requirements corresponding to each chassis model are used as the verification basis to perform a divisibility check on the production sequence within the group formed in step S2. For part types with divisibility margins, the set gap is eliminated by inserting surplus batches into the already scheduled sequence. This ensures the completion of part sets while maintaining a layout that minimizes changeover losses, resulting in a set verification result.

[0078] Step S3 receives the intra-group production scheduling sequence formed in step S2 and the part set requirements for each chassis model as input, and generates a set verification result as output, which is then used for cross-group connection and production scheduling scheme generation in step S4.

[0079] In some embodiments, the execution flow of step S3 in this application is as follows: Figure 2 As shown, steps S31 to S36 are included: Step S31: Based on the component assembly requirements, determine the types of components required for each chassis model and the minimum assembly quantity for each component type.

[0080] Among them, the component set requirement refers to the minimum batch ratio of various components required for each chassis model to complete a complete machine assembly, which is usually determined by product design specifications or assembly process documents. Component type refers to the category of various sheet metal parts that make up a chassis, such as side panels, top panels, bottom panels, front panels, and rear panels. The component types included in different chassis models may vary. Minimum set quantity refers to the minimum batch quantity base corresponding to the mutual matching of various component types in the component set requirement. For example, if a chassis model requires 2 batches of side panels, 1 batch of top panels, and 1 batch of bottom panels to form the minimum set unit, then the minimum set quantities for each component type are 2, 1, and 1, respectively. Step S31 clarifies the component type list and minimum set quantity for each chassis model, providing a verification benchmark for the production scheduling quantity statistics in step S32 and the integer division verification in step S33.

[0081] Step S32: Count the number of batches to be scheduled for each chassis model and part type in the production scheduling sequence within the group, and obtain the quantity to be scheduled.

[0082] It is understandable that the production quantity to be scheduled refers to the actual number of batches of each part type corresponding to the same chassis model that have been scheduled within the group's production scheduling sequence. Using the group's production scheduling sequence formed in step S2 as the statistical object, the batch quantity is counted one by one according to two dimensions: chassis model and part type, to obtain the production quantity to be scheduled for each part type of each chassis model. For example, if a chassis model M1 contains 4 side panel batches, 2 top panel batches, and 2 bottom panel batches in the group's production scheduling sequence, then the production quantities to be scheduled for each part type of model M1 are 4, 2, and 2, respectively. The production quantity to be scheduled is recorded using the combination of chassis model and part type as an index, for comparison item by item during the integer division verification in step S33.

[0083] Step S33: Perform an integer division check between the quantity to be produced and the corresponding minimum complete set quantity.

[0084] Understandably, the integer division check refers to dividing the production quantity to be scheduled obtained in step S32 by the minimum complete set quantity determined in step S31 for each chassis model and each part type, and checking whether the integer division remainder is zero. A zero integer division remainder indicates that the production batch quantity of the corresponding part type is exactly an integer multiple of the minimum complete set quantity, meeting the completeness requirement; a non-zero integer division remainder indicates that there are batches of the corresponding part type that are less than one complete set unit, requiring order insertion for supplementation. Step S33 performs the integer division check on each part type of all chassis models one by one, obtaining the integer division remainder for each item, providing a basis for judgment in the case-by-case processing of steps S34 and S35.

[0085] Step S34: In response to any part type having a non-zero divisibility allowance, calculate the parameter difference between the production batch to be scheduled corresponding to the divisibility allowance and the batches already scheduled for the same chassis model in the group's production sequence for each bending step, obtain the number of bending steps exceeding the threshold corresponding to each scheduled batch, determine the adjacent position of the scheduled batch with the smallest number of bending steps exceeding the threshold as the insertion position, insert the production batch to be scheduled corresponding to the divisibility allowance into the insertion position, and mark it as a batch to be supplemented.

[0086] It is understandable that the production batch corresponding to the divisibility remainder refers to the batch that cannot be divided evenly after the divisibility verification in step S33. For example, if the production quantity of side panels is 5 and the minimum complete set quantity is 2, then the divisibility remainder is 1, corresponding to one side panel batch as the divisibility remainder batch. The parameter difference between the production batch corresponding to the divisibility remainder and the batches of the same chassis model already scheduled in the production sequence of the group is calculated step by step. The step-by-step difference and threshold comparison method is used as in steps S121 and S122 to calculate the number of bending steps exceeding the threshold between the divisibility remainder batch and each of the scheduled batches of the same chassis model when the divisibility remainder batch is inserted into the adjacent position of each scheduled batch of the same chassis model. The adjacent position of the batch with the smallest number of bending steps exceeding the threshold, i.e., the position immediately before or after it, is determined as the insertion position. The production batch to be scheduled corresponding to the integer division remainder is inserted into the insertion position, and it is marked as a supplementary batch in the production sequence within the group to distinguish it from the original production batch. This indicates that the insertion operation is a supplementary process performed to meet the completeness requirements.

[0087] If multiple scheduled batches correspond to the same minimum number of bending steps exceeding the threshold, the adjacent position of the scheduled batch with the earlier production position can be selected as the insertion position. This allows the batch to be supplemented to complete processing as early as possible, providing more preparation time for the assembly process. Through the above processing, the batch to be supplemented is inserted into the production sequence within the group in a way that minimizes changeover losses. This allows the two objectives of ensuring completeness and minimizing changeover losses to be handled uniformly through the same quantitative indicator (number of bending steps exceeding the threshold).

[0088] Step S35: In response to the fact that the divisibility remainder of all part types is zero, determine that the production sequence within the group meets the completeness requirements.

[0089] It is understandable that when step S33 shows that the integer division remainder is zero for all chassis models and all part types, it means that the production batch quantity of each part type in the group's production sequence meets the complete set ratio requirement. There is no need to perform order insertion processing. It can be directly determined that the group's production sequence meets the complete set requirement, and then proceed to step S36.

[0090] Step S36: Summarize the integer division verification results for each part type to obtain the complete set of verification results.

[0091] Understandably, step S36 summarizes the results of the integer division verification and order insertion processing performed on each chassis model and part type in steps S33 to S35, forming a complete set verification result. The complete set verification result records the integer division verification status, order insertion processing status, and updated intra-group production scheduling sequence for each chassis model and part type, and also marks the insertion position information of the batch to be supplemented, for use in the cross-group connection and production scheduling scheme generation in step S4.

[0092] Preferably, step S3 involves dividing the number of production batches for each chassis model and part type in the production scheduling sequence within the group by integer, identifying the part types that do not meet the complete set ratio requirements, and determining the optimal insertion position of the surplus batch based on the number of bending steps exceeding the threshold. While maintaining the changeover cost arrangement structure formed in step S2, the complete set gap is eliminated, forming a complete set verification result that simultaneously meets the requirements of minimizing changeover loss and completing the complete set of parts, thus providing a complete and usable intra-group production scheduling sequence for the cross-group connection in step S4.

[0093] Step S4: Based on the complete set verification results, perform cross-group connection of the production scheduling sequence within each specification group, and generate a production scheduling plan in combination with delivery date constraints.

[0094] It should be noted that after steps S2 and S3, each specification group has formed an intra-group production scheduling sequence that meets the requirements of minimizing changeover costs and ensuring complete parts sets. However, the order of arrangement between specification groups has not yet been determined. In continuous production on a flexible bending production line, when the last batch of one specification group switches to the first batch of the next specification group, if the bending position parameters of the two are significantly different, the line must be stopped for changeover, resulting in cross-group connection losses. If the arrangement order of each specification group is not optimized, the cross-group connection changeover cost may offset the effect of intra-group scheduling optimization. In addition, in the global production scheduling sequence arranged with the goal of minimizing changeover losses, some batches with tight delivery dates may be placed in later positions, resulting in insufficient delivery date margins. Therefore, in step S4, this application first enumerates and optimizes the arrangement order of each specification group, selects the arrangement order with the minimum total cross-group connection cost to obtain the global production scheduling sequence, and then, combined with delivery date constraints, moves batches with insufficient delivery date margins forward, finally generating a production scheduling plan.

[0095] Step S4 receives the complete set of verification results (including the updated production schedule sequence within each specification group) generated in step S3 as input and the delivery date information of each batch to be scheduled as output to form a production schedule plan.

[0096] In some embodiments, step S4 includes steps S41 and S42: Step S41: Based on the complete set verification results, perform cross-group connection of the production scheduling sequence within each specification group.

[0097] In some embodiments, step S41 includes steps S411 to S413: Step S411: Use the changeover cost between the last batch of production to be scheduled in each specification group and the first batch of production to be scheduled in the adjacent specification group as the cross-group connection cost.

[0098] It is understandable that cross-group connection cost refers to the changeover cost incurred when switching from the last batch of one group to the first batch of the next group when two specification groups are arranged sequentially. The calculation method for cross-group connection cost is the same as that for single-batch changeover cost in step S12, that is, the changeover cost value is the number of bending steps that exceed the automatic adjustment threshold in the bending position parameters of the two batches. The last batch to be scheduled in each specification group is the last batch in the production sequence within the group after the complete set verification in step S3, and the first batch to be scheduled in each specification group is the first batch in the production sequence within the group. Cross-group connection cost is recorded with specification group pairs as indexes and is used for enumeration calculation in step S412.

[0099] Step S412: Enumerate the arrangement order of each specification group and calculate the total cross-group connection cost corresponding to each arrangement order.

[0100] It is understandable that if there are N specification groups, then there are N permutations of the order of these specification groups. Step S412 enumerates all permutations one by one. For each permutation, the cross-group connection cost between adjacent specification groups is accumulated sequentially to obtain the total cross-group connection cost corresponding to that permutation. In practical applications, when the number of specification groups is large, an appropriate enumeration strategy can be selected based on the actual computing power. For example, all permutations can be enumerated within the time constraint, or an approximate enumeration method can be used when the number of groups is large. The specific strategy can be set according to the actual application scenario.

[0101] Step S413: Select the order with the lowest total cost of cross-group connection, and then combine the production sequence within each specification group in the order of arrangement to obtain the global production sequence.

[0102] Understandably, from all the permutation sequences and their corresponding total cross-group connection costs obtained in step S412, the permutation sequence with the smallest total cross-group connection cost is selected. The production scheduling sequences within each specification group are then linked end-to-end according to the selected permutation sequence to form a global production scheduling sequence covering all batches to be scheduled. The global production scheduling sequence records the order of each batch in the overall production scheduling in an ordered list format, serving as the basis for calculating the delivery time leeway in step S42. If multiple permutation sequences have the same and smallest total cross-group connection cost, the final permutation sequence can be further determined by combining auxiliary conditions such as the urgency of the first batch's delivery time within each group.

[0103] It should be noted that step S41 enumerates the arrangement order of each specification group and selects the group with the minimum total cost of cross-group connection as the selection criterion. The production sequence within each specification group is spliced ​​into a global production sequence. On the basis of optimizing the changeover loss within each specification group, the cross-group changeover loss caused by the connection and switching between groups is further reduced. This optimizes the changeover cost of the overall production sequence at both the intra-group and cross-group levels, forming a complete production sequence with better global changeover loss.

[0104] Step S42: Generate a production scheduling plan by combining delivery date constraints.

[0105] In some embodiments, step S42 includes steps S421 and S422: Step S421: Calculate the difference between the estimated completion time and the corresponding delivery date of each batch to be scheduled in the global production scheduling sequence to obtain the delivery date margin for each batch to be scheduled.

[0106] It is understandable that the estimated completion time refers to the estimated completion time of each batch's bending processing, calculated sequentially based on its position in the global production schedule, the standard processing time of each batch, and the estimated completion time of the preceding batch. The estimated completion time can be calculated starting with the batch at the top of the global production schedule and proceeding sequentially. The estimated completion time of each batch equals the estimated completion time of the previous batch plus the changeover time between batches plus the standard processing time of the current batch. The delivery date refers to the latest completion time required by the customer order for the corresponding chassis model for each batch, obtained from the order management system or production planning system. Delivery margin refers to the difference between the delivery date and the estimated completion time for each batch. A positive difference indicates that the estimated completion time is earlier than the delivery date, leaving room for adjustment; a negative difference or a small difference indicates that the estimated completion time is close to or later than the delivery date, posing a delivery risk.

[0107] Step S422: In response to any production batch having a delivery date margin lower than a preset margin threshold, the production batch is identified as a forced advance batch. Within the specification group to which the forced advance batch belongs, the forced advance batch is moved forward to the earliest production scheduling position that meets the delivery date constraint of the forced advance batch, thus obtaining a production scheduling plan.

[0108] The preset margin threshold refers to the critical value of the delivery date margin for determining whether a batch needs to be forcibly moved forward. This value can be set according to the actual production line cycle time and delivery date management requirements. For example, setting it to 8 hours means that batches whose estimated completion time differs from their delivery date by less than 8 hours will trigger a forced move forward. A forced move forward batch refers to a batch whose delivery date margin is lower than the preset margin threshold and needs to be scheduled earlier in the production sequence. Moving the forced move forward within the specification group means adjusting the batch to the earliest position in the production sequence within its specification group that meets the delivery date constraint, without disrupting the overall arrangement structure within the specification group. This avoids adjusting across specification groups, thus maintaining the basic structure of the changeover optimization results within the specification group. The earliest production position that meets the delivery date constraint of the forced move forward batch is the position at the very beginning of the sequence within the specification group where the estimated completion time of the forced move forward batch is no later than its delivery date. After processing all batches with insufficient delivery date margins, the final production schedule is obtained. The production scheduling plan records the final production order of each batch to be scheduled in an ordered list, and marks the batches that are forced to move forward and the batches that need to be supplemented. It can be directly output to the manufacturing execution system to guide production line production.

[0109] It should be noted that step S42 calculates the delivery date margin of each batch to be scheduled in the global production scheduling sequence, identifies batches with insufficient delivery date margin, and moves them forward to the earliest scheduling position that meets the delivery date constraint within their respective specification groups. While maintaining the optimized arrangement structure of the changeover within the specification groups, the expected completion time of each batch meets the delivery date constraint, and integrates delivery date control into the final adjustment step of the production scheduling sequence, forming a production scheduling plan that takes into account both minimizing changeover losses and delivery date constraints.

[0110] Preferably, step S4 obtains the global production scheduling sequence by enumerating the grouping order of each specification and selecting the arrangement scheme with the minimum cross-group connection cost. Then, combined with the delivery date margin of each batch, the urgent batch is processed by moving the specification group forward. The cross-group changeover optimization and delivery date constraint adjustment are integrated into the production scheduling scheme generation process. Finally, the production scheduling scheme that has been comprehensively processed in three dimensions—changeover loss, complete set completion, and delivery date satisfaction—is output, providing a directly executable scheduling basis for the multi-variety mixed production of the flexible bending production line.

[0111] In one exemplary embodiment, such as Figure 3 As shown, this application also provides a multi-product mixed-location production scheduling system for computer chassis for flexible production lines, including a changeover analysis module, an intra-group sorting module, a complete set verification module, and a production scheduling scheme module, wherein: The changeover analysis module extracts the bending position parameters of each production batch based on the bending control program corresponding to the production batch to be scheduled. It calculates the changeover cost based on the difference in bending position parameters between adjacent production batches to be scheduled, and obtains the changeover cost data.

[0112] The group sorting module groups the batches to be produced based on the chassis specification standards, and sorts the batches to be produced within each specification group according to the changeover cost data to obtain the group production sequence.

[0113] The complete set verification module performs complete set verification on the production sequence within the group based on the complete set requirements of the parts corresponding to each chassis model, and obtains the complete set verification results.

[0114] The production scheduling module connects the production scheduling sequences within each specification group based on the complete set verification results, and generates a production scheduling plan in combination with delivery date constraints.

[0115] The modules in the aforementioned computer-based multi-product mixed-layout production scheduling system for flexible production lines can be implemented entirely or partially through software, hardware, or a combination thereof. These modules can be embedded in the processor of the computer device in hardware form or independent of it, or stored in the memory of the computer device in software form, so that the processor can call and execute the corresponding operations of each module.

[0116] In one exemplary embodiment, a computer device is provided, which may be a terminal, and its internal structure diagram may be as follows: Figure 4As shown, the computer device includes a processor, memory, input / output interfaces, a communication interface, a display unit, and an input device. The processor, memory, and input / output interfaces are connected via a system bus, and the communication interface, display unit, and input device are also connected to the system bus via the input / output interfaces. The processor provides computing and control capabilities. The memory includes non-volatile storage media and internal memory. The non-volatile storage media stores the operating system and computer programs. The internal memory provides the environment for the operation of the operating system and computer programs in the non-volatile storage media. The input / output interfaces are used for exchanging information between the processor and external devices. The communication interface is used for wired or wireless communication with external terminals; wireless communication can be achieved through Wi-Fi, mobile cellular networks, Near Field Communication (NFC), or other technologies. When the computer program is executed by the processor, it implements a multi-product mixed-layout production scheduling method for computer chassis in flexible production lines. The display unit is used to form a visually visible image and can be a display screen, a projection device, or a virtual reality imaging device. The display screen can be an LCD screen or an e-ink screen. The input device of the computer device can be a touch layer covering the display screen, or buttons, trackballs, or touchpads set on the casing of the computer device, or external keyboards, touchpads, or mice, etc.

[0117] Those skilled in the art will understand that Figure 4 The structure shown is merely a block diagram of a portion of the structure related to the present application and does not constitute a limitation on the computer device to which the present application is applied. Specific computer devices may include more or fewer components than those shown in the figure, or combine certain components, or have different component arrangements.

[0118] In one embodiment, a computer device is also provided, including a memory and a processor, wherein the memory stores a computer program, and the processor executes the computer program to implement the steps in the above method embodiments.

[0119] In one embodiment, a computer-readable storage medium is provided having a computer program stored thereon that, when executed by a processor, implements the steps in the above method embodiments.

[0120] In one embodiment, a computer program product is provided, including a computer program that, when executed by a processor, implements the steps in the above method embodiments.

[0121] It should be noted that the user information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data used for analysis, data stored, data displayed, etc.) involved in this application are all information and data authorized by the user or fully authorized by all parties, and the collection, use and processing of the relevant data must comply with relevant regulations.

[0122] Those skilled in the art will understand that all or part of the processes in the methods of the above embodiments can be implemented by a computer program instructing related hardware. The computer program can be stored in a non-volatile computer-readable storage medium, and when executed, it can include the processes of the embodiments of the above methods. Any references to memory, databases, or other media used in the embodiments provided in this application can include at least one of non-volatile memory and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. By way of illustration and not limitation, RAM can take many forms, such as Static Random Access Memory (SRAM) or Dynamic Random Access Memory (DRAM). The databases involved in the embodiments provided in this application may include at least one type of relational database and non-relational database. Non-relational databases may include, but are not limited to, blockchain-based distributed databases. The processors involved in the embodiments provided in this application may be general-purpose processors, central processing units, graphics processing units, digital signal processors, programmable logic devices, quantum computing-based data processing logic devices, artificial intelligence (AI) processors, etc., and are not limited to these.

[0123] The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this application.

[0124] The embodiments described above are merely illustrative of several implementation methods of this application, and while the descriptions are specific and detailed, they should not be construed as limiting the scope of this patent application. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of this application, and these all fall within the protection scope of this application. Therefore, the protection scope of this application should be determined by the appended claims.

Claims

1. A method for scheduling multi-variety mixed production of computer chassis for flexible production lines, characterized in that: include: Based on the bending control program corresponding to the production batch to be scheduled, the bending position parameters of each production batch to be scheduled are extracted, and the changeover cost is calculated based on the difference between the bending position parameters of adjacent production batches to be scheduled, so as to obtain the changeover cost data. The production batches to be scheduled are grouped by specifications based on chassis specifications, and the production batches to be scheduled are sorted within each specification group according to the changeover cost data to obtain the production scheduling sequence within the group. Based on the complete set requirements of the parts corresponding to each chassis model, the completeness verification of the production sequence within the group is performed to obtain the completeness verification result. Based on the complete set of verification results, the production scheduling sequences within each specification group are linked across groups, and a production scheduling plan is generated in combination with delivery date constraints.

2. The method for multi-variety mixed production scheduling of computer chassis for flexible production lines as described in claim 1, characterized in that: The bending position parameters for each batch of products to be produced are extracted by the bending control program corresponding to the batch to be produced, including: The bending control program corresponding to each batch to be scheduled for production is analyzed to obtain the bending step sequence corresponding to each batch to be scheduled for production. Based on the bending step sequence, the X-axis coordinate value and R-axis angle value of the back gauge corresponding to each bending step are extracted to obtain the bending position parameters of each batch to be scheduled for production. In response to the absence of a bending control program for any of the batches to be scheduled for production, standard bending parameters are extracted based on the chassis specifications of the chassis model corresponding to the batch to be scheduled for production. These standard bending parameters are then used as the bending position parameters for the batch to be scheduled for production, and the batch to be scheduled for production is marked as pending confirmation.

3. The method for multi-variety mixed production scheduling of computer chassis for flexible production lines as described in claim 2, characterized in that: The calculation of changeover cost based on the difference in bending position parameters between adjacent production batches to be scheduled, resulting in changeover cost data, includes: The bending position parameters of adjacent production batches to be scheduled are compared step by step to obtain the X-axis coordinate difference and R-axis angle difference corresponding to each bending step. In response to any bending step where the X-axis coordinate difference exceeds the X-axis automatic adjustment threshold or the R-axis angle difference exceeds the R-axis automatic adjustment threshold, the number of bending steps between adjacent production batches that exceed the X-axis automatic adjustment threshold or the R-axis automatic adjustment threshold is counted, and the number of bending steps is determined as the changeover cost of the corresponding adjacent production batches. If the X-axis coordinate difference of all bending steps does not exceed the X-axis automatic adjustment threshold and the R-axis angle difference does not exceed the R-axis automatic adjustment threshold, the changeover cost of the corresponding adjacent production batch to be scheduled is determined to be zero. The changeover costs of each adjacent production batch to be scheduled are summarized to obtain the changeover cost data.

4. The method for multi-variety mixed production scheduling of computer chassis for flexible production lines as described in claim 3, characterized in that, Also includes: Parameter-driven replacement records are obtained by filtering out replacement records from historical replacement records that have different chassis models between batches and have no corresponding manual replacement instruction records. The bending position parameters of each batch corresponding to the previous and next batches in the parameter-driven change record are calculated step by step to obtain the X-axis coordinate difference and R-axis angle difference of each bending step corresponding to each change record. The minimum X-axis coordinate difference that causes line stoppage and line change in each of the aforementioned change records is determined as the X-axis automatic adjustment threshold, and the minimum R-axis angle difference that causes line stoppage and line change in each of the aforementioned change records is determined as the R-axis automatic adjustment threshold.

5. The method for multi-variety mixed production scheduling of computer chassis for flexible production lines as described in claim 1, characterized in that: The specification grouping of the batches to be produced based on chassis specification standards includes: Based on the aforementioned chassis specification standards, extract the standard outer dimension codes of the chassis models corresponding to each of the batches to be produced; Batches of production to be scheduled that have the same standard code for outer dimensions shall be grouped into the same specification group; When the number of production batches to be scheduled in any specification group is lower than a preset batch lower limit, the adjacent specification group with the lowest changeover cost is determined based on the changeover cost data. The specification group is then merged with the adjacent specification group to update the specification group.

6. The method for multi-variety mixed production scheduling of computer chassis for flexible production lines as described in claim 5, characterized in that: The step of sorting the production batches to be scheduled within each specification group based on the changeover cost data to obtain the production scheduling sequence within the group includes: Based on the changeover cost data, construct a changeover cost matrix among the production batches to be scheduled within each specification group; Within each specification group, the production batch with the lowest total changeover cost compared to the other production batches to be scheduled is determined as the starting batch; Based on the current batch, the batch with the lowest changeover cost to the current batch is selected from the changeover cost matrix as the next batch. The production order of all batches to be scheduled within each specification group is determined step by step to obtain the production sequence within the group.

7. The method for multi-variety mixed production scheduling of computer chassis for flexible production lines as described in claim 1, characterized in that: The completeness verification of the production sequence within the group is performed based on the completeness requirements of the parts sets corresponding to each chassis model, and the completeness verification results are obtained, including: Based on the component assembly requirements, determine the types of components required for each chassis model and the minimum assembly quantity for each component type; The production batches of each chassis model and each part type in the production scheduling sequence of the group are counted to obtain the production quantity to be scheduled. The quantity to be produced is checked for integer division with the corresponding minimum quantity of complete sets; In response to any part type having a non-zero divisibility margin, the parameter difference is calculated for each bending step of the production batch to be scheduled corresponding to the divisibility margin and the batches of the same chassis model already scheduled in the production sequence within the group. The number of bending steps exceeding the threshold corresponding to each scheduled batch is obtained. The adjacent position of the scheduled batch with the smallest number of bending steps exceeding the threshold is determined as the insertion position. The production batch to be scheduled corresponding to the divisibility margin is inserted into the insertion position and marked as a batch to be supplemented. If the divisibility remainder of all part types is zero, it is determined that the production sequence within the group meets the completeness requirement. The integer division verification results for each part type are summarized to obtain the complete set verification results.

8. The method for multi-variety mixed production scheduling of computer chassis for flexible production lines as described in claim 7, characterized in that: The step of linking the production scheduling sequences within each specification group based on the complete set verification results across groups includes: The cost of switching between the production batches to be scheduled at the end of each specification group and the production batches to be scheduled at the beginning of the adjacent specification group is used as the cross-group connection cost. Enumerate the arrangement order of each specification group and calculate the total cross-group connection cost corresponding to each arrangement order; Select the order with the lowest total cost of cross-group connection, and then sequentially splice the production scheduling sequences within each specification group according to the given order to obtain the global production scheduling sequence.

9. The method for multi-variety mixed production scheduling of computer chassis for flexible production lines as described in claim 8, characterized in that, The process of generating a production scheduling plan by combining delivery date constraints includes: The difference between the estimated completion time and the corresponding delivery date of each batch to be scheduled in the global production scheduling sequence is calculated to obtain the delivery date margin for each batch to be scheduled. In response to any production batch having a delivery date margin lower than a preset margin threshold, the production batch is identified as a forced advance batch. Within the specification group to which the forced advance batch belongs, the forced advance batch is moved forward to the earliest production scheduling position that satisfies the delivery date constraint of the forced advance batch, thus obtaining a production scheduling plan.

10. A multi-product mixed-layout production scheduling system for computer chassis for flexible production lines, employing the multi-product mixed-layout production scheduling method for computer chassis for flexible production lines as described in any one of claims 1 to 9, characterized in that, include: The changeover analysis module extracts the bending position parameters of each batch of production to be scheduled based on the bending control program corresponding to the batch to be scheduled, calculates the changeover cost based on the difference in bending position parameters between adjacent batches to be scheduled, and obtains changeover cost data. The group sorting module groups the batches to be produced according to the chassis specification standards, and sorts the batches to be produced within each specification group according to the changeover cost data to obtain the production scheduling sequence within the group. The complete set verification module is used to verify the completeness of the production sequence within the group according to the complete set requirements of the parts corresponding to each chassis model, and to obtain the complete set verification result. The production scheduling module connects the production scheduling sequences within each specification group based on the complete set verification results, and generates a production scheduling plan in combination with delivery date constraints.