An auxiliary device and method for installing the external suspension cables of a high-low four-main-cable suspension bridge

By setting up temporary cable clamps and hangers on the high and low four-main-cable suspension bridge, and combining continuous jacks and steel strands, the outer main cable was actively pulled down, which solved the problems of insufficient clearance for the installation of the outer slings and asynchronous deformation of the inner and outer main cables, thus achieving efficient and safe installation of the outer slings.

CN123109060APending Publication Date: 2026-11-17CCCC SECOND HARBOR ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611287967.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-24
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In the construction of a high-low four-main-cable suspension bridge, insufficient clearance for the installation of the outer suspenders and asynchronous deformation of the inner and outer main cables make conventional solutions unable to guarantee installation accuracy and safety, leading to construction difficulties.

Method used

A pull-down system consisting of multiple temporary cable clamps and hangers is used. Through the cooperation of continuous jacks and steel strands, the outer main cable is actively pulled down to provide sufficient pull force, so that the outer slings gradually approach the stiffening beam, ensuring that the installation clearance meets the requirements, and precise installation is achieved through a synchronous control unit.

Benefits of technology

It solves the bottleneck of the inability to install external suspenders, improves construction efficiency, ensures installation accuracy and safety, and is suitable for four-main-cable suspension bridges with different bridge type parameters.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109060A_ABST
    Figure CN123109060A_ABST
Patent Text Reader

Abstract

This invention discloses an auxiliary device and method for installing external suspenders on a four-main-cable suspension bridge with varying elevations. The device includes multiple temporary cable clamps arranged parallel to the external main cables, with two temporary cable clamps per group. A hanger is hinged to the lower part of each temporary cable clamp, and the hanger is connected to a lower anchor beam via steel strands. The top of the lower anchor beam rests against the bottom of a corbel on the underside of a stiffening beam. This solution significantly improves the efficiency and accuracy of external suspender installation while ensuring safe construction, thus guaranteeing the quality of the construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of engineering construction technology, and in particular to an auxiliary device and method for installing the external suspension cables of a high-low four-main-cable suspension bridge. Background Technology

[0002] The high-low four-main-cable suspension bridge is a new type of suspension bridge structure developed in recent years to adapt to ultra-long spans and complex terrain conditions. Its core feature is the arrangement of two main cables with different sags on the same side. During the construction of a certain bridge, because its main span exceeded 1.5km, the sag-to-span ratio of the inner main cable exceeded 1 / 10, and the sag-to-span ratio of the outer main cable also exceeded 1 / 10. At the same time, in the completed bridge state, the elevation of the outer main cable was lower than the top surface of the stiffening girder for several hundred meters in the middle of the span, forming a "cable-girder intersection zone" (defined as a continuous section where the elevation of the outer main cable is lower than the top surface of the stiffening girder). The stiffening girder was hoisted using a cable-mounted crane supported on the inner main cable, with the cables arranged alternately inside and outside. However, the following technical difficulties arose during the hoisting of the middle-span segment: (1) Insufficient clearance for sling installation: The minimum length of the inner sling is limited. After the cable crane lifts the stiffening beam to the limit height, there is still a certain distance between the lower end of the outer sling and the outer lifting point at the corbel of the stiffening beam, making it impossible to complete the pin connection. (2) The problem cannot be solved by optimizing the lifting equipment alone: ​​conventional solutions (such as reducing the height of the lifting equipment and modifying the lifting mechanism) have been used to their limit. Further lifting will cause the lifting equipment to collide with the main structure of the cable crane, resulting in greater safety risks. Therefore, it is impossible to further increase the installation space. (3) Asynchronous deformation of inner and outer main cables: Due to the different stiffness of the inner and outer main cables, the inner main cable has a small stiffness and is affected by the load of the cable-mounted crane, resulting in large deformation, while the outer main cable has a large stiffness and small deformation. During the hoisting of the stiffening beam, the height difference between the inner and outer cables changes dynamically, resulting in a very short window period for the installation of the outer slings. Conventional processes cannot guarantee the installation accuracy and safety. Summary of the Invention

[0003] This invention provides an auxiliary device and method for installing external suspension cables of a high-low four-main-cable suspension bridge, which solves the construction technology problems mentioned in the background art.

[0004] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is: an auxiliary device and method for installing the outer suspension cables of a high and low four-main-cable suspension bridge, including multiple temporary cable clamps arranged in parallel on the outer main cables, with two temporary cable clamps per group, and a hanger hinged to the lower part of the temporary cable clamps. The hanger is connected to the lower anchor beam through steel strands, and the top of the lower anchor beam abuts against the bottom of the corbel on the lower side of the stiffening beam.

[0005] In the preferred embodiment, a continuous jack is installed on the inner side of the hanger. The upper side of the steel strand is threaded through the continuous jack, and the lower side of the steel strand is threaded through the lower anchor beam via a clamp. Multiple external slings are also installed between the two temporary cable clamps. The external slings are connected to the brackets via pins, and the pins are threaded through the external slings and the brackets.

[0006] In the preferred embodiment, the temporary cable clamp includes two opposing semi-ring plates, with ear plates on both sides of each semi-ring plate. The two ear plates are connected by screws and nuts, and the two ear plates on the lower side are hinged to the hanger via a first shaft.

[0007] In the preferred embodiment, a first through hole and a second through hole are provided through the ear plate, a screw is inserted through the first through hole, a lifting lug is provided at the top of the hanger, a first shaft is inserted through the lifting lug and the second through hole, and two adjacent temporary cable clamps are connected by a positioning frame.

[0008] In the preferred embodiment, an arc-shaped plate and a notch are respectively provided on both sides of the semi-ring plate. A first locking tooth and a second locking tooth are respectively provided on one side of the arc-shaped plate and the notch. The first locking tooth on the two adjacent semi-ring plates engages with 4070. The positioning frame includes a support plate and locking plates provided on both sides of the support plate. The first shaft passes through the locking plate and the second through hole.

[0009] In the preferred embodiment, multiple grooves are arranged parallel to each other along the circumference on the inner side of the semi-ring plate. Ball bearings are installed in the grooves. The length of the groove is greater than the outer diameter of the ball bearings. The top surface of the ball bearings is slightly higher than the top surface of the groove. The ball bearings are attached to the outer side of the outer main cable.

[0010] In the preferred embodiment, two adjustment components are arranged opposite each other on the upper part of the lower anchor beam. The adjustment components are connected by a guide frame and a steel strand. The guide frame includes a C-shaped plate, and the C-shaped plate is hinged to pulleys by two parallel insert rods. The steel strand is passed between the two pulleys, and the position and state of the steel strand are adjusted by the steel strand.

[0011] In the preferred embodiment, the adjustment component includes an L-shaped plate, which is connected to the lower anchor beam by screws. A hydraulic cylinder is installed on one side of the L-shaped plate, and a telescopic rod is installed inside the hydraulic cylinder. One side of the C-shaped plate is connected to the telescopic rod. An arc groove is provided on the outside of the pulley. The arc grooves of two adjacent pulleys cooperate to form a locking space, and the steel strand is threaded through the locking space.

[0012] In the preferred embodiment, one side of the L-shaped plate abuts against the outer wall of the bracket, and multiple threaded holes are provided on both sides of the bracket. The L-shaped plate is connected to the bracket by screws, with the screws passing through the L-shaped plate and the threaded holes.

[0013] In a preferred embodiment, an installation method for an auxiliary device for installing the outer suspension cables of a four-main-cable suspension bridge with varying elevations includes the following steps: S1. Segment identification and pull-down demand calculation: Based on bridge design parameters and construction simulation, identify segments that require pull-down assistance. S2. First, install temporary cable clamps on the outside of the main cable, then install the hanger, then place the continuous jacks inside the hanger, and finally connect the hanger to the temporary cable clamps through the first shaft. S3. After the stiffening beam is gradually lifted close to the lower part of the inner main cable by the cable-mounted crane to the limit height, the lower anchor beam is installed on the corbel on the lower side of the stiffening beam. S4. Pass the upper side of the steel strand through the continuous jack, and pass the lower side of the steel strand through the lower anchor beam and fix it through the clamp and the lower anchor beam; S5. Install displacement and pressure sensors and connect them to the synchronous control console; S6. Collaborate to complete the pulling down of the external main cable and the locking installation of the external slings to the bracket; S7. After the previous stiffening beam is fixed, remove all components and repeat S1~S6 to complete the installation of all mid-span segments.

[0014] The beneficial effects of this invention are as follows: by setting up temporary cable clamps, and in conjunction with hangers, traction mechanisms, flexible force transmission components (such as steel strands), anchor beams (including anchorages), and synchronous control units, a pull-down system is formed. Through the active force application of the pull-down system, sufficient and effective pull-down force is provided to the external main cable, thereby gradually bringing the external suspenders originally suspended on the stiffening beam closer to the stiffening beam until they are within the installation standard range. The overall control response effect is good, the operation is simple, the installation efficiency is greatly improved, and there are good economic benefits.

[0015] 1. Solving installation challenges under extreme working conditions: Addressing the bottleneck of the inability to install external slings in the cable-beam intersection area, the external cable is actively pulled down to increase the installation clearance between the lower end of the external sling and the external suspension point of the stiffening beam from a negative value (i.e., the lower end of the external sling is lower than the suspension point) to a positive operating space of ≥0.2m, ensuring smooth connection of the sling and filling a technological gap in this field; 2. Improved construction efficiency: The device has a simple structure and is easy to operate, allowing for rapid installation and transportation; 3. High versatility: The pull-down force and displacement can be flexibly adjusted according to different bridge type parameters (main cable stiffness, mid-span height difference, suspension cable length), and it is suitable for various four-main-cable suspension bridges. Attached Figure Description

[0016] The present invention will be further described below with reference to the accompanying drawings and embodiments: Figure 1 This is a process diagram of the present invention. Figure 1 ; Figure 2 This is a process diagram of the present invention. Figure 2 ; Figure 3 This is a process diagram of the present invention. Figure 3 ; Figure 4 This is a process diagram of the present invention. Figure 4 ; Figure 5 This is a process diagram of the present invention. Figure 5 ; Figure 6 This is a flowchart illustrating the present invention; Figure 7 This is a schematic diagram of the temporary cable clip installation of the present invention. Figure 1 ; Figure 8 yes Figure 7 A frontal view diagram; Figure 9 yes Figure 7 A left-view diagram; Figure 10 yes Figure 7 A top-down view; Figure 11 This is a schematic diagram of the temporary cable clip installation of the present invention. Figure 2 ; Figure 12 yes Figure 7 A schematic diagram of the exploded structure; Figure 13 This is a schematic diagram of the temporary cable clip installation of the present invention. Figure 3 ; Figure 14 This is a schematic diagram of the temporary cable clip installation of the present invention. Figure 4 ; Figure 15 This is a schematic diagram of the steel strand for the hanger installation of the present invention. Figure 1 ; Figure 16 This is a schematic diagram of the steel strand for the hanger installation of the present invention. Figure 2 ; Figure 17 This is a schematic diagram of the overall structure of the temporary cable clamp of the present invention; Figure 18 yes Figure 17 Explosion structure diagram Figure 1 ; Figure 19 yes Figure 17 Explosion structure diagram Figure 2 ; In the diagram: 1. Cable-mounted crane; 2. Inner main cable; 3. Outer main cable; 4. Temporary cable clamp; 401. Semi-ring plate; 402. Ear plate; 403. First through hole; 404. Arc plate; 405. Notch; 406. First locking tooth; 407. Second locking tooth; 408. Slot; 409. Second through hole; 410. Hanger; 5. Lifting lug; 501. Outer sling; 6. Continuous jack; 7. Steel strand; 8. Lower anchor beam; 9. Bracket; 10. Threaded hole; 100. 1; Jacket 11; Pin 12; Screw 13; Nut 14; Positioning frame 15; Support plate 1501; Clamping plate 1502; First shaft 16; Adjustment assembly 17; L-shaped plate 1701; Hydraulic cylinder 1702; Telescopic rod 1703; Guide frame 18; C-shaped plate 1801; Insert rod 1802; Pulley 1803; Arc groove 1804; Locking space 1805; First shaft 19; Stiffening beam 20. Detailed Implementation

[0017] Example 1 like Figure 1-5 As shown, an auxiliary device and method for installing the outer suspension cables of a high-low four-main-cable suspension bridge includes multiple temporary cable clamps 4 arranged in parallel on the outer main cable 3. Each pair of temporary cable clamps 4 forms a group, constituting a single group of downward force-bearing units. The lower part of the temporary cable clamp 4 is hinged to a hanger 5. The hanger 5 is connected to the lower anchor beam 9 through steel strands 8. The top of the lower anchor beam 9 abuts against the bottom of the corbel 10 on the lower side of the stiffening beam 20.

[0018] During the construction of a Yangtze River Bridge, with a main span of 1860m, ​​the inner main cable sag-to-span ratio was 1 / 13.058 and the outer main cable sag-to-span ratio was 1 / 12.130. During the hoisting of mid-span segments (such as JD33~JD36), a "cable-beam intersection zone" was formed, leading to the problem described in the background technology. Originally, the minimum length of the inner suspender cable was only 4.45m. After the cable-mounted crane lifted the stiffening beam to its maximum height, there was still a distance of 0.04~1.9m between the lower end of the outer suspender cable and the outer suspension point at the corbel of the stiffening beam, making it impossible to complete the pin connection and causing inconvenience in construction. The adoption of this device solved the problem and improved the overall construction efficiency. This solution has been successfully applied in the project.

[0019] The auxiliary device of this application uses the outer main cable as the upper temporary anchoring foundation and the stiffening beam corbel as the lower reaction foundation to form a closed self-balancing force system. By actively pulling down the outer main cable, the installation clearance is created, which fundamentally breaks through the physical limits of the conventional "lifting beam to adapt to sling" process.

[0020] The temporary cable clamp is tensioned and held tightly to the main cable by a screw, relying on the friction of the contact surface to prevent slippage. The required friction force is calculated based on the maximum pulling force, and the screw preload is determined (with a safety factor of 3) to ensure that the temporary cable clamp does not slip during the pulling process, and that the overall force is more fully and stably distributed.

[0021] The temporary cable clamps fully cover the main cable, thereby generating a stable downward driving force for the cable. Through the cooperation of continuous jacks and steel strands, the stiffening beam is lifted, thus enabling the installation of the external slings. This solves the problem that when the stiffening beam reaches its top limit position in the initial state, there is still a certain distance between the lower end of the external sling and the external lifting point at the stiffening beam bracket, making it impossible to complete the pin connection.

[0022] In the preferred embodiment, a continuous jack 7 is provided on the inner side of the hanger 5, the upper side of the steel strand 8 is passed through the continuous jack 7, and the lower side of the steel strand 8 is passed through the lower anchor beam 9 through the clamp 11; multiple external slings 6 are also provided between the two temporary cable clamps 4, and the external slings 6 are connected to the bracket 10 through the pin 12, with the pin 12 passing through the external slings 6 and the bracket 10.

[0023] Among them, the continuous jack 7 adopts a through-type continuous tensioning jack, which is a mature equipment in the field of bridge construction. It relies on two sets of clamps to alternately clamp the steel strands and the hydraulic cylinder to reciprocate to achieve continuous winding and unwinding of the steel strands. It has the characteristics of unlimited stroke, stepless load adjustment, and support for multi-machine synchronous control, and is suitable for the large displacement downward pulling conditions in this scenario. The steel strand 8 adopts low relaxation prestressed steel strands with a nominal strength of not less than 1860MPa. Each set of pulling units is equipped with 4 to 8 steel strands, with a safety factor of not less than 2.5, which meets the requirements of bridge construction safety specifications. The jacket 11 is a wedge-type working anchor with an anchoring efficiency coefficient of not less than 0.95, which can achieve reliable anchoring of the lower end of the steel strand to the lower anchor beam.

[0024] like Figure 17-19 As shown, in the preferred embodiment, the temporary cable clamp 4 includes two semi-ring plates 401 arranged opposite to each other. Ear plates 402 are respectively provided on both sides of the semi-ring plates 401. The two ear plates 402 are connected by screws 13 and nuts 14. The two ear plates 402 located on the lower side are hinged to the first shaft 19 and the hanger 5.

[0025] The inner diameter of the semi-ring plate 401 is adapted to the outer diameter of the outer main cable 3, and the inner side is attached to the PE protective layer of the main cable. The positive pressure generated by the bolt pre-tightening force provides anti-slip friction. The hanger and the cable clamp are connected by a hinge, which allows the hanger to rotate slightly around the shaft, adapting to the angle change of the steel strand during the pull-down process, avoiding the cable clamp from bearing additional bending moment, ensuring that the main cable mainly bears the vertical load, which is in line with the stress characteristics of the suspension structure.

[0026] In the preferred embodiment, the ear plate 402 is provided with a first through hole 403 and a second through hole 410, the screw 13 is inserted into the first through hole 403, the top of the hanger 5 is provided with a lifting lug 501, the first shaft 19 is inserted into the lifting lug 501 and the second through hole 410, and two adjacent temporary cable clamps 4 are connected by a positioning frame 15.

[0027] The first through hole 403 is the mounting hole for the cable clamping bolts, and the second through hole 410 is a shared hinge hole, which can simultaneously accommodate the hinged connection of the hanger and the positioning frame, reducing the number of holes for the cable clamps and minimizing structural weakening. The positioning frame 15 is used to constrain the longitudinal spacing of the two temporary cable clamps in the same group, so that the downward load is evenly distributed on the two main cable sections, avoiding local linear distortion of the main cable caused by concentrated load from a single cable clamp, and improving the overall lateral stability of the device, preventing the hanger and jack from swaying sideways. The cooperation of the two first through holes 403 ensures the installation accuracy of the two opposing semi-ring plates 401.

[0028] like Figure 7-14 As shown, in the preferred embodiment, arc-shaped plates 404 and notches 405 are respectively provided on both sides of the semi-annular plate 401. A first locking tooth 406 and a second locking tooth 407 are respectively provided on one side of the arc-shaped plate 404 and the notch 405. The first locking tooth 406 and the second locking tooth 407 on two adjacent semi-annular plates 401 mesh with each other. The positioning frame 15 includes a support plate 1501 and locking plates 1502 provided on both sides of the support plate 1501. The second shaft 16 passes through the locking plate 1502 and the second through hole 410.

[0029] During assembly, the arc-shaped plate 404 is embedded into the notch 405 for radial positioning. Lateral insertion is used for alignment and installation. The first locking tooth 406 and the second locking tooth 407 mesh to achieve circumferential positioning. This ensures precise alignment of the two semi-ring plates without misalignment and converts the lateral shear force borne by the bolts into surface contact bearing pressure of the locking teeth, preventing bolt breakage under shear. This significantly improves the overall shear resistance and clamping reliability of the cable clamp, ensuring no relative displacement of the cable clamps under heavy tonnage loads. The positioning frame's locking plate engages with the inner side of the cable clamp's ear plate, achieving a rigid connection via the second shaft, ensuring constant spacing and synchronized force distribution among cable clamps in the same group.

[0030] In the preferred embodiment, a plurality of grooves 408 are arranged parallel to each other along the circumference on the inner side of the semi-ring plate 401. Ball bearings 409 are arranged in the grooves 408. The length of the grooves 408 is greater than the outer diameter of the ball bearings 409. The top surface of the ball bearings 409 is slightly higher than the top surface of the grooves 408. The ball bearings 409 are attached to the outer side of the outer main cable 3.

[0031] The combination of the trough 408 and the ball bearings 409 in this scheme balances anti-slip bearing capacity and turnover efficiency: when the cable clamp bolts are finally tightened to the design torque, the inner main surface of the semi-ring plate 401 presses against the surface of the outer main cable 3, relying on static friction to provide anti-slip bearing capacity, and the ball bearings 409 are partially pressed into the trough 408 and do not participate in the main force; when it is necessary to move and rotate along the longitudinal direction of the main cable, the bolts are loosened to the semi-ring plate in a slightly open state. At this time, the ball bearings 409 contact the surface of the main cable to form rolling friction, and the operators can directly push the entire cable clamp device to move along the outer main cable without completely disassembling the cable clamps and hangers, which greatly improves the construction efficiency of multi-segment cyclic operations. Because the steel strand 8 is manufactured in an axial spiral upward pattern, this design ensures stronger overall load-bearing capacity. Therefore, when the half-clamp 401 is installed on the steel strand 8 at different positions, the contact point of the half-clamp 401 relative to the steel strand 8 is different. The ball bearing 409 can move within a certain range of the arc groove of the groove 408, thereby adapting to the angle changes of different single bundles on the steel strand 8 and better fitting into the gap between adjacent steel strands 8, thus ensuring the overall locking accuracy. At the same time, through the adaptive adjustment of the ball bearing 409, it is ensured that the half-clamp 401 at different positions can be in a vertically downward state after installation.

[0032] like Figure 15-16 As shown, in the preferred embodiment, two adjustment components 17 are arranged opposite each other on the upper part of the lower anchor beam 9. The adjustment components 17 are connected to the steel strand 8 through the guide frame 18. The guide frame 18 includes a C-shaped plate 1801. The C-shaped plate 1801 is hinged to pulleys 1803 through two parallel insert rods 1802. The steel strand 8 is passed between the two pulleys 1803. The position and state of the steel strand 8 are adjusted by adjusting the adjustment components 17.

[0033] The lower anchor beam 9 adopts a box-section steel structure, serving as the lower reaction support of the pull-down system. It cleverly utilizes the self-weight of the stiffening beam to balance the pull-down load, eliminating the need for additional counterweights or reaction frames and significantly simplifying on-site construction equipment. The pulley structure of the guide frame converts the sliding friction of the steel strands into rolling friction, reducing frictional resistance loss during the pull-down process and limiting the lateral displacement of the steel strands, ensuring straight force distribution. Furthermore, when the continuous jacks 7 on different hangers 5 are not perfectly synchronized, the position of the steel strands 8 can be finely adjusted via the guide frame 18, ensuring that both sides of the lower anchor beam 9 are coplanar. This results in high overall adjustment accuracy and excellent performance.

[0034] In the preferred embodiment, the adjustment assembly 17 includes an L-shaped plate 1701, which is connected to the lower anchor beam 9 by screws 13. A hydraulic cylinder 1702 is provided on one side of the L-shaped plate 1701, and a telescopic rod 1703 is provided inside the hydraulic cylinder 1702. One side of the C-shaped plate 1801 is connected to the telescopic rod 1703. An arc groove 1804 is provided on the outer side of the pulley 1803. The arc grooves 1804 of two adjacent pulleys 1803 cooperate to form a locking space 1805, and the steel strand 8 is passed through the locking space 1805.

[0035] The guide frame can be moved laterally by the extension and retraction of the hydraulic cylinder, which can adjust the spatial position of the steel strand in real time, compensate for the uneven load on the steel strand caused by installation errors, ensure that the steel strand is always under vertical force, and avoid cable clamp torsion and local shear damage to the bracket caused by uneven load. The circumferential arc groove of the pulley is adapted to the outer diameter of the steel strand, and the locking space formed by the pulleys on both sides can form a lateral constraint on the steel strand, preventing the steel strand from derailing and swaying during the pull-down process, and improving the stability of operation.

[0036] In the preferred embodiment, one side of the L-shaped plate 1701 abuts against the outer wall of the bracket 10, and multiple threaded holes 1001 are provided on both sides of the bracket 10. The L-shaped plate 1701 is connected to the bracket 10 by screws 13, and the screws 13 are inserted into the L-shaped plate 1701 and the threaded holes 1001.

[0037] This design forms a dual constraint system of "bottom bearing + side anchoring": the top surface of the lower anchor beam bears the vertical reaction force of the bracket, and the side wall of the L-shaped plate is horizontally anchored to the bracket by screws, which can effectively prevent the lower anchor beam from shifting, slipping or overturning during the pulling process, significantly improving the operational safety under extreme loads. The bracket 10 forms a stable reaction seat, ensuring the stable operation of the hydraulic cylinder 1702. At the same time, the overall rigidity formed by the lower anchor beam 9 is strong, and the overall force distribution is more balanced.

[0038] like Figure 6 As shown, in a preferred embodiment, an installation method for an auxiliary device for installing the outer suspension cables of a four-main-cable suspension bridge with varying elevations includes the following steps: S1. Span segment identification and pull-down demand calculation: Based on bridge design parameters and construction simulation, identify segments requiring pull-down assistance. Dynamic force determination method: Calculate the pull-down force based on the vertical stiffness of the outer cable and the required pull-down displacement, with a safety factor of 1.5 (considering dynamic load factor, non-uniformity factor, and material variation factor). In practice, a segmented catenary method is used to establish a finite element model of the entire bridge construction stage. Parameters such as the cross-sectional area of ​​the inner and outer main cables, the modulus of elasticity, the design sag-to-span ratio, the weight of the stiffening girder segment, and the working load of the cable-mounted crane are input to simulate the structural deformation when the stiffening girder is lifted to its limit height. The vertical deviation between the lower end of the outer suspender cable of each segment and the pin hole of the corbel suspension point is calculated. When the vertical deviation is greater than the allowable clearance for pin installation (usually 50mm), it is determined to be a construction segment that requires downward pulling assistance, and a work list for the cable-girder intersection area is formed.

[0039] Simultaneously, based on the required operating clearance for the installation of the external slings (with a safety margin of 100~200mm), the target pull-down displacement of the external main cable is determined; based on the deformation theory of suspension structures, the single pull-down load required to achieve this displacement is calculated, and indicators such as the anti-slip safety factor of the temporary cable clamp (required ≥2.0), the local stress of the main cable, the local bearing strength of the corbel, and the safety factor of the steel strand are verified to ensure the structural safety of the entire process.

[0040] The equivalent vertical stiffness of a suspension cable is inversely proportional to the square of its sag; the larger the sag-to-span ratio, the smaller the equivalent stiffness. In this scenario, the inner cable has a larger sag-to-span ratio and its equivalent stiffness is significantly smaller than that of the outer cable. Therefore, it deforms more under the load of the cable-mounted crane, which is the core mechanical reason for the asynchronous deformation of the inner and outer cables.

[0041] S2. First, install temporary cable clamps 4 on the outside of the main cable 3, then install the hanger 5, then place the continuous jacks 7 inside the hanger 5, and finally connect the hanger 5 to the temporary cable clamps 4 through the first shaft 19.

[0042] In practice, using a cable-mounted crane platform or a main cable maintenance vehicle, the cable clamps are assembled at the preset mileage position of the outer main cable: two semi-ring plates are wrapped around the outside of the outer main cable, and the connecting bolts are pre-tightened after the interlocking teeth are engaged; the cable clamps are adjusted to the design mileage position, and after confirming that there are no errors, the bolts are finally tightened to the design pre-tightening force with a torque wrench to ensure that the anti-slip bearing capacity of the cable clamps meets the requirements; then the hanger hinge is completed and the jack is fixed, and the upper anchoring system is assembled.

[0043] S3. After the stiffening beam 20 is gradually lifted close to the lower part of the inner main cable 2 by the cable-mounted crane 1 to the limit height, the lower anchor beam 9 is installed on the corbel 10 on the lower side of the stiffening beam 20.

[0044] The maximum lifting height refers to the minimum safe clearance between the lifting device and the main body of the cable-mounted crane. This is the physical lifting limit of the existing cable-mounted crane, and conventional processes cannot further increase it. After lifting into position, the inner slings and stiffening beams are connected first to achieve the initial suspension and positioning of the stiffening beams. Then, the lower anchor beam is installed at the bottom of the corresponding bracket, and the lower anchor beam is fitted against the lower flange of the bracket. The L-shaped plate is then fastened to the threaded hole on the side wall of the bracket with screws to complete the fixation of the lower reaction seat.

[0045] Conventional suspension bridge cable installation processes are based on the core idea of ​​"lifting the beam to a height where the cables can be connected". However, in the area where the cable and beam intersect, the beam lifting height has reached its limit due to the physical limitations of the cable-mounted crane structure height and the minimum length of the lifting equipment, which cannot meet the clearance for the installation of the external cables. This is the core motivation for the reverse downward pulling approach adopted in this invention.

[0046] S4. Pass the upper side of the steel strand 8 through the continuous jack 7, and pass the lower side of the steel strand 8 through the lower anchor beam 9 and fix it through the sleeve 11 and the lower anchor beam 9.

[0047] After the cable is threaded, the steel strands are pre-tightened in stages, and the initial stress is controlled at 10% to 15% of the design pull-down load to ensure that the steel strands in the same group are subjected to uniform force and the cable force deviation is no more than 5%, so as to avoid the risk of single steel strands breaking due to overload during the pull-down process.

[0048] S5. Install displacement and pressure sensors and connect them to the synchronization control console.

[0049] Specifically, two types of monitoring sensors, displacement and load, are deployed, all connected to a PLC synchronous control console to construct a closed-loop control system. Displacement monitoring: High-precision displacement sensors (accuracy ±1mm) are installed at temporary cable clamps to collect the downward displacement of the outer main cable in real time; displacement sensors are installed at the corresponding positions of the stiffening beam to monitor the vertical deformation of the beam; at the same time, the relative height difference between the inner and outer main cables is monitored.

[0050] Load monitoring: Pressure sensors are installed in the hydraulic circuit of the continuous jack to collect the total load pulling down in real time; cable force sensors are installed at the anchor of the steel strand to monitor the stress state of a single steel strand.

[0051] The synchronous control console has functions such as multi-machine synchronous drive, displacement closed-loop control, load overload protection, and automatic alarm for abnormalities. It is the core hardware foundation for solving the problem of asynchronous deformation of internal and external main cables.

[0052] S6. Collaborate to complete the pull-down of the external main cable 3 and the locking installation of the external sling 6 to the bracket 10.

[0053] The operation is performed using a control strategy of "graded loading, displacement control, load verification, and dynamic adaptation". Staged loading: The synchronous control console drives the continuous jacks on both sides to pull down synchronously. Each stage of loading is 20% of the design load. After each stage of loading, the load is held for 2-3 minutes to monitor data such as cable clamp slippage, main cable deformation, and steel strand tension. If there are no abnormalities, the next stage of loading is started.

[0054] Dynamically adapting to deformation differences: During the pull-down process, the system collects the relative height difference data of the inner and outer main cables in real time. Due to the small equivalent stiffness of the inner main cable and the large deformation caused by the load of the cable-mounted crane, the stiffening beam is prone to slight sinking; at this time, the system automatically accelerates the pull-down speed of the outer main cable, dynamically compensating for the height difference changes caused by the deformation of the inner main cable, so that the lower end of the outer sling and the bracket lifting point are always within the tolerance range for pin installation, transforming the extremely short natural installation window period under conventional processes into a controllable load-bearing installation time.

[0055] Precise installation: After the outer main cable is pulled down to the target displacement, the system automatically holds the load and stabilizes the voltage. At this time, the pin hole at the lower end of the outer sling is completely aligned with the lifting point hole of the bracket. The operator inserts the pin and installs the anti-loosening baffle to complete the permanent connection of the outer sling.

[0056] Staged unloading: After the slings are installed, the jacks are used to unload the load in stages, so that the outer slings gradually bear the load and avoid impact loads from damaging the main cable and slings; after the steel strands are unloaded and loosened, the lower end anchor is removed.

[0057] S7. After the previous stiffening beam 20 is fixed, remove all components and repeat S1~S6 to complete the installation of all mid-span segments.

[0058] Example 2 The present invention relates to an auxiliary device and method for installing external suspenders in the mid-span cable-beam intersection area of ​​a high-low four-main-cable suspension bridge. The process involves "calculation and judgment—device installation—coordinated pull-down—external suspender installation—recycling," and the overall workflow is as follows: Figure 6 As shown, the specific implementation details are as follows: Step 1: Segment identification and pull-down demand calculation Based on bridge design parameters and construction simulation, identify the segments requiring pull-down assistance (e.g., Yanji Bridge JD33~JD37). For each segment requiring pull-down assistance, calculate the required pull-down displacement S and pull-down force F: Collected parameters: stiffness K of the outer cable in the empty state, height difference Δh between the inner and outer cables, minimum safe lifting distance dmin of the cable-mounted crane (a fixed value, determined by the height of the cable-mounted crane and lifting gear), height of the lower lifting lug of the stiffening beam from the top of the beam (a fixed value, determined by the height of the stiffening beam), design length Ldesign of the outer sling, and installation and operation space Δoper (taken as 0.2m).

[0059] (2) Calculate the required additional displacement: S = (dmin + hear + Δoper) - (Δh + Ldesign) (When S > 0, you need to pull down).

[0060] (3) Calculate the pulling force: F=k·K·S, where k is the safety factor, which is taken as 1.5. The method for determining k is: k=k1·k2·k3, where k1 is the dynamic load factor (1.1~1.2), k2 is the non-uniformity factor (1.1~1.3), and k3 is the material variation factor (1.05~1.1), which is taken as 1.5.

[0061] (4) Determine the jack model: Select the appropriate through-hole jack (such as 60t class) according to the calculated pull-down force.

[0062] K (kN / m): Stiffness of the outer cable in its unloaded state Δh (m): Difference in elevation between inner and outer cables dmin (m): Minimum safe lifting distance for cable-mounted cranes (a fixed value determined by the height of the cable-mounted crane and the lifting gear). hear (m): Height of the lower lifting lug of the stiffening beam from the top of the beam (a fixed value, determined by the height of the stiffening beam). Ldesign (m): Design length of external sling Δoper (m): Installation and operating space (taken as 0.2m) Step 2: Install the pull-down device (1) Install temporary clamps on both sides of the permanent clamp on the outer main cable and install temporary clamps on the outer main cable. The temporary clamps are tensioned and hold the main cable by screws, relying on the friction of the contact surface to resist slippage. Calculate the required anti-slip friction force based on the maximum pull force, determine the screw preload (safety factor of 3), and use a torque wrench or tensioning equipment to tension the screw to the design preload to ensure that the temporary clamps do not slip during the pull-down process. The temporary clamps can be installed on both sides of the permanent clamps, but there is no need to rely on the permanent clamps for axial restraint.

[0063] (2) Install the hanger, install the continuous jack in the hanger in advance, and then connect the hanger and the temporary cable clamp with the pin.

[0064] (3) After the cable crane lifts the stiffening beam to its limit height, it installs the lower anchor beam at the bottom of the stiffening beam bracket; at the same time, it completes the initial connection of the inner slings (the pin is inserted but not tightened) to prevent the stiffening beam from falling.

[0065] (4) Pass the steel strand through the jack and anchor it to the anchorage of the lower anchor beam to form a pull-down system; install displacement sensors and pressure sensors and connect them to the synchronous control console. For the two outer main cables on the same side, use a synchronous control system to ensure that the difference in pull-down displacement between the two sides does not exceed 5mm.

[0066] Step 3: Coordinated pull-down and sling installation (1) The cable crane unloads in stages of 10%, and holds the load for 5 minutes after each stage of unloading to monitor the tension of the inner slings and the attitude of the stiffening beam. After stabilization, the next stage of unloading is carried out to transfer part of the load to the installed inner slings and stabilize the attitude of the stiffening beam.

[0067] (2) Start the pull-down jack and slowly pull down the outer cable at a speed of 0.5 cm / min, while monitoring the pull-down force and the displacement of the outer cable. Stop when the calculated displacement S is reached. The difference in pull-down displacement between the two outer main cables on the same side should be controlled within 5 mm.

[0068] (3) At this point, the clearance between the lower end of the external sling and the external lifting point of the stiffening beam reaches the operating space (≥0.2m). Install the external sling pin to complete the connection. 7 (4) After the external slings are connected, the cable-stayed crane continues to unload in stages until 100% is achieved, and the load on the beam segment is completely transferred to the internal and external sling systems. (5) Remove the pull-down device and prepare for the next section.

[0069] Step 4: Device cyclical reversal When multiple segments are hoisted in sequence, the pull-down device can be reused: after completing one segment, remove the temporary cable clamps, scaffolds, and lower anchor beams, and move them to the corresponding position of the next segment for installation, repeating steps 2 to 4.

[0070] During the turnover operation, loosen the connecting bolts of the temporary cable clamps, and use the ball bearing structure on the inner side of the semi-ring plate to push the entire upper device along the outer main cable to the next section to be installed. There is no need to completely disassemble the cable clamps and hangers, which can significantly improve the efficiency of the cycle operation. Repeat the above process until the installation of the outer slings of all sections in the cable beam intersection area is completed.

[0071] The above embodiments are merely preferred technical solutions of the present invention and should not be considered as limitations on the present invention. The scope of protection of the present invention should be limited to the technical solutions described in the claims, including equivalent substitutions of the technical features described in the claims. That is, equivalent substitutions and improvements within this scope are also within the scope of protection of the present invention.

Claims

1. An auxiliary device for installing the external suspenders of a four-main-cable suspension bridge with varying elevations, characterized in that: It includes multiple temporary cable clamps (4) arranged in parallel on the outer main cable (3), with two temporary cable clamps (4) forming a group. The lower part of the temporary cable clamp (4) is hinged to a hanger (5), which is connected to the lower anchor beam (9) via steel strand (8). The top of the lower anchor beam (9) abuts against the bottom of the corbel (10) on the underside of the stiffening beam (20).

2. The auxiliary device for installing the outer suspension cables of a four-main-cable suspension bridge with varying elevations according to claim 1, characterized in that: A continuous jack (7) is installed inside the hanger (5). The upper side of the steel strand (8) is inserted into the continuous jack (7), and the lower side of the steel strand (8) is inserted into the lower anchor beam (9) through the clamp (11). Multiple external slings (6) are also installed between the two temporary cable clamps (4). The external slings (6) are connected to the bracket (10) through the pin (12). The pin (12) is inserted into the external slings (6) and the bracket (10).

3. The auxiliary device for installing the outer suspension cables of a four-main-cable suspension bridge with varying elevations according to claim 1, characterized in that: The temporary cable clamp (4) includes two semi-ring plates (401) arranged opposite to each other. Ear plates (402) are respectively provided on both sides of the semi-ring plates (401). The two ear plates (402) are connected by screws (13) and nuts (14). The two ear plates (402) located on the lower side are hinged by the first shaft (19) and the hanger (5).

4. The auxiliary device for installing the outer suspension cables of a high-low four-main-cable suspension bridge according to claim 3, characterized in that: The ear plate (402) has a first through hole (403) and a second through hole (410) through it. The screw (13) passes through the first through hole (403). The top of the hanger (5) has a lifting lug (501). The first shaft (19) passes through the lifting lug (501) and the second through hole (410). The two adjacent temporary cable clamps (4) are connected by a positioning frame (15).

5. The auxiliary device for installing the outer suspension cables of a high-low four-main-cable suspension bridge according to claim 4, characterized in that: The two sides of the semi-ring plate (401) are respectively provided with an arc plate (404) and a notch (405). The arc plate (404) and the notch (405) are respectively provided with a first locking tooth (406) and a second locking tooth (407) on one side. The first locking teeth (406) and 407 on two adjacent semi-ring plates (401) mesh. The positioning frame (15) includes a support plate (1501) and a locking plate (1502) provided on both sides of the support plate (1501). The first shaft (16) passes through the locking plate (1502) and the second through hole (410).

6. The auxiliary device for installing the outer suspension cables of a high-low four-main-cable suspension bridge according to claim 3, characterized in that: Multiple grooves (408) are arranged parallel to each other along the circumference on the inner side of the semi-ring plate (401). Balls (409) are arranged in the grooves (408). The length of the groove (408) is greater than the outer diameter of the ball (409). The top surface of the ball (409) is slightly higher than the top surface of the groove (408). The ball (409) is attached to the outer side of the outer main cable (3).

7. The auxiliary device for installing external suspenders of a four-main-cable suspension bridge with varying elevations according to claim 4, characterized in that: Two adjustment components (17) are arranged opposite each other on the upper part of the lower anchor beam (9). The adjustment components (17) are connected to the steel strand (8) through the guide frame (18). The guide frame (18) includes a C-shaped plate (1801). The C-shaped plate (1801) is hinged to a pulley (1803) through two parallel insert rods (1802). The steel strand (8) is passed between the two pulleys (1803). The position and state of the steel strand (8) are adjusted by the steel strand (8).

8. The auxiliary device for installing the outer suspension cables of a four-main-cable suspension bridge with varying elevations according to claim 1, characterized in that: The adjustment assembly (17) includes an L-shaped plate (1701), which is connected to the lower anchor beam (9) by screws (13). A hydraulic cylinder (1702) is provided on one side of the L-shaped plate (1701), and a telescopic rod (1703) is provided inside the hydraulic cylinder (1702). A C-shaped plate (1801) is connected to the telescopic rod (1703) on one side. An arc groove (1804) is provided on the outside of the pulley (1803). The arc grooves (1804) of two adjacent pulleys (1803) cooperate to form a locking space (1805). The steel strand (8) is threaded through the locking space (1805).

9. The auxiliary device for installing the outer suspension cables of a four-main-cable suspension bridge with varying elevations according to claim 8, characterized in that: The L-shaped plate (1701) abuts against the outer wall of the bracket (10) on one side. The bracket (10) has multiple threaded holes (1001) on both sides. The L-shaped plate (1701) is connected to the bracket (10) by screws (13). The screws (13) are inserted into the L-shaped plate (1701) and the threaded holes (1001).

10. The installation method of the auxiliary device for installing the outer suspension cables of a high-low four-main-cable suspension bridge according to any one of claims 1 to 9, characterized in that: Includes the following steps: S1. Segment identification and pull-down demand calculation: Based on bridge design parameters and construction simulation, identify segments that require pull-down assistance. S2. First, install temporary cable clamps (4) on the outside of the main cable (3), then install the hanger (5), then place the continuous jack (7) inside the hanger (5), and finally connect the hanger (5) to the temporary cable clamps (4) through the first shaft (19). S3. After the stiffening beam (20) is lifted by the cable crane (1) and gradually approaches the lower part of the inner main cable (2) to the limit height, the lower anchor beam (9) is installed on the corbel (10) on the lower side of the stiffening beam (20). S4. Pass the upper side of the steel strand (8) through the continuous jack (7), and pass the lower side of the steel strand (8) through the lower anchor beam (9) and fix it through the sleeve (11) and the lower anchor beam (9); S5. Install displacement and pressure sensors and connect them to the synchronous control console; S6. Collaborate to complete the pull-down of the external main cable (3) and the locking installation of the external sling (6) onto the corbel (10); S7. After the previous stiffening beam (20) is fixed, remove all components and repeat S1~S6 to complete the installation of all mid-span segments.