Preloading construction method for steel pipe supports and construction method for steel box girders
By pre-stressing the steel pipe support system, the problems of complex rework and reinforcement of the steel pipe support system and waiting time for steel box girder construction were solved, thus achieving an efficient and safe construction process.
Patent Information
- Application Number
- CN202611336411.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-31
- Publication Date
- 2026-11-17
AI Technical Summary
In the existing technology, the prestressing of steel pipe supports has problems such as complicated rework and reinforcement processes and labor-intensive construction nodes. In addition, the construction of steel box girders can only be carried out after the steel pipe supports have been erected.
By preloading on the installation basis of steel pipe supports, the sequence of support structure erection and preloading operation is decoupled. Foundation preloading operation is carried out on the ground, and the installation foundation is directly reinforced when the preloading does not meet the threshold, while the construction of steel box girders is carried out simultaneously.
It reduced the difficulty and cost of rework and reinforcement, improved construction efficiency and safety, avoided waiting time for steel box girder construction, and enabled multi-equipment collaborative operation.
Smart Images

Figure CN123109064A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of bridge construction technology, and more specifically, to a pre-stressing construction method for steel pipe supports and a construction method for steel box girders. Background Technology
[0002] During the construction of steel box girders for bridges, steel pipe supports are the key structures that bear the loads of the concrete, formwork, and construction loads. The stability and deformation control of the steel pipe supports are crucial to the alignment and structural safety of the girder. Therefore, effective preloading of the steel pipe supports is a critical step in the bridge construction process.
[0003] In existing technologies, preloading of steel pipe supports typically involves laying the bottom formwork and applying the preload after the steel pipe supports are erected. This is used to eliminate uneven settlement of the foundation and the inelastic deformation of the steel pipe supports. However, once the steel pipe supports are erected, the foundation rectification and reinforcement process becomes complex when the foundation settlement does not meet design requirements. Furthermore, the construction of the steel box girder can only proceed after the steel pipe supports are fully erected and pre-qualified, resulting in delays at key construction points. Therefore, the existing technology for preloading steel pipe supports suffers from complex rework and reinforcement processes and labor-intensive construction milestones. Summary of the Invention
[0004] This application addresses the shortcomings of existing methods by proposing a pre-stressing construction method for steel pipe supports, which solves at least one technical problem in related technologies, namely, the complexity of rework and reinforcement processes and the high labor costs at construction nodes.
[0005] In the first aspect, embodiments of this application provide a pre-stressing construction method for steel pipe supports, comprising: Based on the condition of the foundation, construct the foundation and the installation base for the steel pipe support; The installation foundation is preloaded according to the preset load of the steel pipe support; When the preload of the installation foundation meets the preset threshold of the foundation, the support structure of the steel pipe bracket is erected.
[0006] Specifically, the main technical concept of this application is to perform preloading through the installation foundation of the steel pipe support, breaking the limitation of the prior art where preloading is performed after the overall construction of the steel pipe support is completed. This allows for rework and reinforcement when the foundation settlement does not meet the construction requirements of the steel box girder, without being limited by the overall steel pipe support, reducing the difficulty of rework and reinforcement during the preloading process, facilitating construction correction, and thus reducing rework costs. Simultaneously, the separation of the steel pipe support construction steps allows the preloading process to be transferred to the installation foundation. The installation of the steel box girder does not need to be completed after the support structure is erected, eliminating waiting time and effectively reducing equipment idleness. Furthermore, changing the preloading operation from high-altitude work on the steel pipe support platform to ground work improves the safety of preloading construction. Therefore, the preloading construction method for steel pipe supports provided in this application has at least the advantages of simple rework and reinforcement, low equipment and labor consumption, and high construction safety.
[0007] Furthermore, when the preload of the installation foundation does not meet the preset threshold, the installation foundation is reinforced.
[0008] Furthermore, after erecting the steel pipe support, the following steps are also included: The steel pipe support is preloaded a second time according to the preset load.
[0009] Furthermore, the pre-stressing construction method for steel pipe supports provided in this application embodiment also includes: According to the construction sequence of the steel box girder, at least one set of periodic construction areas shall be configured; the periodic construction area includes: a first working face and a second working face for cyclical construction; While the foundation and installation base are being constructed on the first working face, the supporting structure is being erected simultaneously on the second working face. Alternatively, when the second working face is constructing the foundation and the installation foundation, the first working face is simultaneously erecting the support structure.
[0010] Specifically, another technical concept of this application embodiment is to use the preloading of the installation foundation as a construction splitting node, so as to realize the synchronous operation of the preloading of the installation foundation, the erection of the steel pipe support and the subsequent installation of the steel box girder, thereby improving the overall efficiency of bridge construction.
[0011] Furthermore, the operational procedures of the first and second working faces can be balanced according to the construction time, or a third working face can be added.
[0012] In some alternative embodiments, constructing the foundation and the installation base for the steel pipe support includes: filling and compacting the foundation, and pouring concrete for the ground and the installation base for the steel pipe support.
[0013] Furthermore, the pre-stressing construction method for steel pipe supports provided in this application embodiment also includes: A temporary passageway was constructed on the concrete surface. At least two adjacent foundations and installation bases shall be constructed simultaneously according to the temporary passage.
[0014] In some alternative implementations, preloading the mounting base includes: A foundation preloading platform is set up through the load-bearing beam of the steel pipe support; The preload material of the basic preload platform is configured according to the gradually increasing proportion of the preset load; The settlement deformation value of the installation foundation is detected one by one; When all the settlement deformation values are less than the preset threshold of the foundation, the installation foundation is determined to meet the requirements of pre-compression settlement.
[0015] Furthermore, the preset load ratio gradient is configured as follows: 60%, 80%, and 110%.
[0016] Secondly, embodiments of this application provide a construction method for a steel box girder, including a pre-stressing process for steel pipe supports. The pre-stressing process employs the pre-stressing construction method for steel pipe supports provided according to any optional embodiment of the first aspect. It is understood that the beneficial effects provided by any optional embodiment of the second aspect can be understood with reference to the beneficial effects provided by any optional embodiment of the first aspect.
[0017] The beneficial technical effects of the technical solutions provided in this application include: This embodiment of the application performs preloading on the installation foundation of the steel pipe support, eliminating the need for preloading only after the overall construction of the steel pipe support is completed. This decouples the sequence of steel pipe support structure erection and preloading operation, allowing for direct ground preloading on the ground and reducing construction risks. Furthermore, if the preloading result does not meet the preset threshold, the installation foundation can be directly reinforced, avoiding the technical difficulties of rework and reinforcement of the installation foundation after the steel pipe support structure is erected. In addition, the installation of the steel box girder can be carried out directly after the steel pipe support is erected, without waiting, improving the work efficiency of multi-equipment collaborative operations. Therefore, this embodiment of the application has at least the advantages of simple steel pipe support rework and reinforcement process, no labor-intensive waiting time for steel box girder construction, and safe preloading operation process.
[0018] Additional aspects and advantages of this application will be set forth in part in the description which follows, and will become apparent from the description or may be learned by practice of this application. Attached Figure Description
[0019] The above and / or additional aspects and advantages of this application will become apparent and readily understood from the following description of the embodiments taken in conjunction with the accompanying drawings, wherein: Figure 1 A schematic flowchart of a pre-stressing construction method for a steel pipe support provided in this application embodiment; Figure 2 Construction schematic diagram of steel pipe support preloading provided for related technologies; Figure 3 A construction diagram of the foundation and the installation base of the steel pipe support provided in the embodiments of this application; Figure 4 This is a construction diagram of the preloading of the installation foundation provided in the embodiments of this application; Figure 5 A construction diagram of the steel pipe support provided in the embodiments of this application; Figure 6 This is a schematic diagram illustrating the settlement deformation values provided in the embodiments of this application; Figure 7 This is a construction diagram of the steel box girder construction provided in the embodiments of this application; Figure label: 1. Steel pipe support; 2. Prestressing material; 3. Foundation; 4. Steel box girder; 11. Installation foundation; 12. Support structure; 121. Support platform. Detailed Implementation
[0020] The embodiments of this application are described below with reference to the accompanying drawings. It should be understood that the embodiments described below with reference to the accompanying drawings are exemplary descriptions for explaining the technical solutions of the embodiments of this application, and do not constitute a limitation on the technical solutions of the embodiments of this application.
[0021] Those skilled in the art will understand that, unless specifically stated otherwise, the terms "described" and "the" as used herein may also include plural forms. It should be further understood that the term "comprising" as used in the specification of this application means the presence of the stated features, integers, steps, operations, elements, and / or components, but does not exclude other features, information, data, steps, operations, elements, components, and / or combinations thereof supported by the art. The term "and / or" as used herein refers to at least one of the items defined by the term; for example, "A and / or B" can be implemented as "A," or as "B," or as "A and B."
[0022] To make the objectives, technical solutions, and advantages of this application clearer, the embodiments of this application will be described in further detail below with reference to the accompanying drawings.
[0023] In related technologies, the steel pipe support 1 serves as a key load-bearing structure in the construction of the steel box girder 4. The stability and deformation control of the steel pipe support 1 are crucial to the linearity and structural safety of the steel box girder 4. Please refer to [reference needed]. Figure 2This is a construction diagram illustrating the pre-stressing of the steel pipe support 1, provided for related technologies. In these technologies, after the steel pipe support 1 is erected, before the steel box girder 4 is supported by it during construction, the deformation of the steel pipe support 1 during the support of the steel box girder 4 needs to be pre-compressed to confirm the elastic deformation between the steel pipes and eliminate inelastic deformation. Elastic deformation mainly originates from the compressive deformation of the steel pipe support 1, while inelastic deformation mainly originates from the settlement of the foundation 3. Therefore, in these technologies, after the steel pipe support 1 is erected, a pre-stressing element 2 (marked with dashed lines) is first set on the steel pipe support 1 to simulate the construction load of the steel box girder 4, thereby measuring the elastic deformation of the steel pipe support 1 and eliminating inelastic deformation, thus controlling the alignment of the subsequent construction of the steel box girder 4. In related technologies, the inelastic deformation of the steel pipe support 1 can be estimated based on the soil conditions of the foundation 3 and past construction experience. Therefore, the amount of rework required during the erection of the steel pipe support 1 is not large. However, situations where the inelastic deformation of the steel pipe support 1 does not meet expectations are still inevitable, necessitating reinforcement of the installation foundation 11. However, due to the spatial structure of the steel pipe support 1, the rework of the installation foundation 11 presents time-consuming and labor-intensive technical problems. Furthermore, in related technologies, the construction of the steel box girder 4 requires the pre-stressing of the steel pipe support 1 to proceed. This means that the construction of the steel box girder 4 cannot be carried out directly after the steel pipe support 1 is erected, resulting in a construction waiting period. In other words, the related technologies present technical problems such as difficulties in reworking and reinforcing the installation foundation 11 during the pre-stressing construction of the steel pipe support 1 and the construction waiting period for the steel box girder 4.
[0024] The research and development concept of this application includes: decoupling the support structure 12 of the steel pipe support 1 from the installation foundation 11, and eliminating the inelastic deformation of the foundation 3 through preloading of the installation foundation 11. This solves the technical problem of the inelastic deformation of the steel pipe support 1 affecting the linear change of the steel box girder 4, reduces the difficulty of rework and reinforcement of the installation foundation 11, and improves the erection efficiency of the steel pipe support 1. Simultaneously, the preloading of the installation foundation 11 allows the construction of the steel box girder 4 to proceed immediately after the steel pipe support 1 is erected, optimizing the workflow of the preloading construction of the steel pipe support 1 and reducing the waiting time for the construction of the steel box girder 4. In other words, the embodiment of this application has the advantages of balancing preloading effect, simple rework and reinforcement, and no waiting time for the construction of the steel box girder 4. Therefore, the preloading construction method for the steel pipe support 1 and the construction method for the steel box girder 4 provided by this application aim to solve the above-mentioned technical problems in related technologies.
[0025] The technical solution of this application and how it solves the above-mentioned technical problems are described in detail below with specific embodiments. It should be noted that the following embodiments can be referenced, borrowed, or combined with each other, and the same terms, similar features, and similar implementation steps in different embodiments will not be described again.
[0026] In some optional embodiments, the pre-stressing construction method of the steel pipe support 1 provided in this application embodiment can be found in [reference needed]. Figure 1 A flowchart illustrating a pre-stressing construction method for a steel pipe support 1 provided in this application embodiment includes: Step S10: Based on the condition of the foundation 3, construct the foundation 3 and the installation foundation 11 of the steel pipe support 1, including: The soil condition of the area where the steel pipe support 1 is to be erected is tested to confirm the stability parameters and settlement parameters of the foundation 3. Based on the condition of the foundation 3 in the area where the steel pipe support 1 is to be erected, the foundation 3 is treated, including: filling and compacting the foundation 3. Especially for soft soil foundation 3 or foundation 3 with uneven softness and hardness, compaction can also be carried out by road roller. If necessary, dynamic compaction can be carried out. Then, concrete pavement is poured to expand the concrete foundation and pour the installation foundation 11. Please refer to Figure 3 This is a construction diagram of the foundation 3 and the installation foundation 11 of the steel pipe support 1 provided in the embodiments of this application. Figure 3 Foundation 3 has been treated; please refer to the actual situation. Figure 6 This is a schematic diagram illustrating the settlement deformation values provided in the embodiments of this application. The foundation 3 is surrounded by the soil structure of the construction area itself. That is, the treatment of the foundation 3 includes: filling and compacting the soil layer of the construction area and pouring concrete floor, thereby pouring the installation foundation 11 on the concrete floor, for example: the installation foundation 11 is configured as a concrete base.
[0027] Step S20: Preload the foundation 11 according to the preset load of the steel pipe support 1, including: After completing the construction of foundation 3 and installation foundation 11, preloading work is carried out on installation foundation 11. Please refer to [the relevant documentation]. Figure 4 A construction diagram illustrating the preloading of the installation foundation 11 provided in this embodiment of the application. According to... Figure 4 In this embodiment, the load-bearing beam (not shown in the figure) supporting the steel box girder 4 is set on the installation foundation 11 by the steel pipe support 1. Then, a support platform 121 is set through the load-bearing beam, so that pre-stressing materials 2 can be set on the support surface to achieve pre-stressing of the installation foundation 11. It can be understood that the pre-stressing materials 2 include concrete blocks, sandbags, steel reinforcement materials, etc., and the pre-stressing materials 2 are arranged and stacked according to the mass distribution of the steel box girder 4, for example: Figure 4 Example of a five-layer stacked structure.
[0028] Furthermore, the preloading of the installation foundation 11 is carried out based on the preset load of the steel pipe support 1. It can be understood that the preset load refers to the overall quality of the support structure of the steel pipe support 1 and the steel box girder 4. Compared to the related technologies that provide an overall preloading solution for the steel pipe support 1, the preset load in this embodiment also includes the quality of the support structure.
[0029] Furthermore, the preload on the foundation preloading platform is configured with the preload gradually increasing proportionally during the preloading process. For example, the proportional gradient of the preload is configured as 60%, 80%, and 110%. Then, the settlement deformation value of the installation foundation 11 is detected successively. When each settlement deformation value is less than the foundation's preset threshold, the installation foundation 11 is determined to meet the preloading settlement requirements. It can be understood that in this embodiment, the installation foundation 11 is first preloaded with a 60% preset load, and then the settlement deformation value of the installation foundation 11 under the 60% preset load is detected; then the preset load is increased to 80% for preloading, and the settlement deformation value of the installation foundation 11 is detected again; then, the preset load is increased to 110%, and the settlement deformation value of the installation foundation 11 is detected again. Finally, verify that the settlement deformation values under 60%, 80%, and 110% preset loads are all less than the preset threshold for the foundation. If so, the installation foundation 11 is deemed to meet the pre-loading settlement requirements, and preparations are made for the erection of the support structure 12 of the steel pipe support 1. If not, the installation foundation 11 is reworked and reinforced. Meanwhile, the settlement deformation value refers to the decrease in the top surface of the installation foundation 11 after pre-loading compared to before pre-loading. Please refer to [reference needed]. Figure 6 .
[0030] Optionally, the foundation preloading platform provided in this embodiment consists of a load-bearing beam and a support platform 121 configured within the support structure 12 of the steel pipe support 1. Simultaneously, the preloading material 2 can be configured as a prefabricated installation foundation 11 or a prefabricated concrete block for a bridge structure. That is, preloading in this embodiment can be achieved using existing materials through the installation foundation 11, without requiring additional materials or costs, thereby reducing the construction cost of this embodiment.
[0031] Step S30: When the preload of the installation foundation 11 meets the preset threshold of the foundation, the support structure 12 of the steel pipe support 1 is erected, including: On the installation foundation 11, construct the columns, diagonal braces, and horizontal bracing of the steel pipe support 1, for example, by welding the diagonal braces and horizontal bracing together. Then, erect the load-bearing beams and support platform 121 at the top of the columns for construction support of the steel box girder 4. Please refer to... Figure 5 This is a construction diagram of the steel pipe support 1 provided in the embodiments of this application.
[0032] Optionally, in this embodiment, high-rigidity materials can be used to suppress the elastic deformation of the steel pipe support 1, further reducing the linear impact of the elastic deformation of the steel pipe support 1 on the construction of the steel box girder 4, so that in this embodiment, the construction of the steel box girder 4 can be carried out directly after the support structure 12 is installed.
[0033] Optionally, the embodiments of this application can also perform random checks on the elastic deformation of the steel pipe support 1. According to the preset load, the steel pipe support 1 is preloaded twice to check whether the installation foundation 11 settles again and the elastic deformation of the support mechanism, thereby improving the reliability of the embodiments of this application.
[0034] Furthermore, after the pre-compressed material 2 is unloaded, the embodiments of this application will gradually unload the pre-compressed material 2 in a manner that gradually decreases in proportion. For example, if the pre-compressing proportion is 60%, 80%, and 110%, then the uncompressing proportion is 110%, 80%, and 60%.
[0035] Optionally, in this embodiment, a temporary passage is also provided on the concrete ground. At least two adjacent foundations 3 and installation foundations 11 are constructed simultaneously according to the temporary passage. Please refer to [reference needed]. Figure 7 A construction diagram of the steel box girder 4 provided in the embodiments of this application. Figure 7 The X-axis direction is defined as the longitudinal direction of the bridge, and the Y-axis direction is defined as the transverse direction of the bridge. For example, in this embodiment of the application, if construction is carried out along the X-axis direction, after the construction of the second foundation 3 on the left and the installation foundation 11 is completed, a temporary passage can be erected on the second foundation 3 on the left or the installation foundation 11. The construction of the first foundation 3 on the left and the second foundation 11 on the right can then proceed through the temporary passage. It is understood that the temporary passage is used as a construction passage for workers and equipment, allowing this embodiment of the application to open up multiple work surfaces and improve the construction efficiency of the preloading of the steel pipe support 1 through multi-shift operations.
[0036] Optionally, in this embodiment of the application, at least one set of periodic construction areas is configured according to the construction sequence of the steel box girder 4; the periodic construction area includes: a first working face and a second working face for cyclical construction; when the foundation 3 and installation foundation 11 are being constructed on the first working face, the supporting structure 12 is being erected simultaneously on the second working face; or, when the foundation 3 and installation foundation 11 are being constructed on the second working face, the supporting structure 12 is being erected simultaneously on the first working face. For example: Please refer to Figure 7In this embodiment, multiple different construction procedures exist along the X-axis. The first and second blocks on the left and the first block on the right are constructing the foundation 3 and the installation foundation 11; the second block on the right and the third block on the left are preloading the installation foundation 11; the third block on the right is erecting the support structure 12; and the fourth blocks on the left and the fourth block on the right are constructing the steel box girder 4. That is, the construction of the foundation 3 and the installation foundation 11, the preloading of the installation foundation 11, the erection of the support structure 12, and the construction of the steel box girder 4 in this embodiment do not interfere with each other. During the preloading of the installation foundation 11, workers can proceed with the construction of the foundation 3 and the installation foundation 11, the erection of the support structure 12, and the construction of the steel box girder 4 as needed. Similarly, workers can perform other construction operations while the foundation 3 and the installation foundation 11 are being cured, or while the steel box girder 4 is being poured and cured. Therefore, this application, through its cyclical construction area, enables continuous construction of each process, eliminating the waiting time associated with the pre-stressing of the steel pipe support 1 and the construction of the steel box girder 4, thereby further improving the construction efficiency of both processes. It is understandable that... Figure 7 The third pre-compression material 2 on the left is configured as a three-layer stacked structure, and the second pre-compression material 2 on the right is configured as a five-layer stacked structure. In this embodiment, the preset load ratio can be increased or decreased by increasing or decreasing the number of stacked layers.
[0037] Optionally, embodiments of this application balance the operational procedures of the first and second working faces based on construction time, or add a third working face. It is understood that the curing of the foundation 3 and installation foundation 11, the preloading of the installation foundation 11, and the curing of the concrete pouring for the steel box girder 4 all involve waiting time. Embodiments of this application can schedule the project's construction nodes by combining the waiting time with the construction time of each construction procedure, thereby balancing the construction time of each procedure, reducing the waiting time for workers and equipment, and thus improving construction efficiency.
[0038] Based on the same inventive concept, this application also provides a construction method for a steel box girder 4, including a pre-stressing process for a steel pipe support 1, wherein the pre-stressing process adopts the pre-stressing construction method for the steel pipe support 1 provided in the above-mentioned optional embodiments.
[0039] Therefore, the working principle of this embodiment is as follows: First, the foundation 3 and the installation foundation 11 of the steel pipe support 1 are constructed. After the filling, compaction and concrete pouring of the foundation 3 are completed, the installation foundation 11 is poured on the concrete ground. Then, the load-bearing beam and support platform 121 of the steel pipe support 1 are set on the installation foundation 11 to build a foundation preloading platform. The preloading material 2 with a preset load is set on the foundation preloading platform to detect the settlement deformation value of the installation foundation 11, so that the inelastic settlement of the foundation 3 meets the construction requirements of the steel box girder 4. Since the preloading of the steel pipe support 1 provided in this embodiment does not require the construction of the support structure 12, the difficulty of rework and reinforcement of the installation foundation 11 can be reduced, and the construction efficiency of the preloading of the steel pipe support 1 can be improved. Meanwhile, in this embodiment, the inelastic deformation of the steel pipe support 1 is eliminated by preloading the foundation 11. The elastic deformation of the steel pipe support 1 can be suppressed by high-stiffness materials, thus allowing the construction of the steel box girder 4 to proceed directly after the support structure 12 is completed, thereby improving the construction efficiency of the steel box girder 4. Furthermore, this embodiment also opens up multiple working surfaces through temporary passages and periodic construction areas, further improving the efficiency of preloading the steel pipe support 1 and the construction of the steel box girder 4.
[0040] Therefore, by applying the embodiments of this application, at least the following beneficial effects can be achieved: This embodiment of the application performs a preloading operation on the installation foundation 11 of the steel pipe support 1. This eliminates the need for preloading after the overall construction of the steel pipe support 1 is completed, decoupling the sequence of the erection of the support structure 12 of the steel pipe support 1 and the preloading operation. This allows the foundation 3 to be preloaded directly on the ground, reducing construction risks. Furthermore, if the preloading result does not meet the preset threshold, the installation foundation 11 can be directly reinforced, avoiding the technical problem of rework and reinforcement difficulties associated with the installation foundation 11 after the support structure 12 of the steel pipe support 1 has been erected. In addition, the installation of the steel box girder 4 can be carried out directly after the steel pipe support 1 is erected, without waiting, improving the work efficiency of multi-equipment collaborative operations. Therefore, this embodiment of the application has at least the advantages of a simple rework and reinforcement process for the steel pipe support 1, no need for labor-intensive waiting during the construction of the steel box girder 4, and a safe preloading operation process.
[0041] In the description of this application, the terms "center," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," and "outer," etc., indicate directions or positional relationships based on the exemplary directions or positional relationships shown in the accompanying drawings. They are used to facilitate the description or simplification of the embodiments of this application and are not intended to indicate or imply that the device or component referred to must have a specific orientation or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application.
[0042] The terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this application, unless otherwise stated, "a plurality of" means two or more.
[0043] In the description of this specification, specific features, structures, materials, or characteristics may be combined in any suitable manner in one or more embodiments or examples.
[0044] The above description is only a partial implementation of this application. It should be noted that for those skilled in the art, other similar implementation methods based on the technical concept of this application, without departing from the technical concept of this application, also fall within the protection scope of the embodiments of this application.
Claims
1. A preloading construction method of a steel pipe support characterized by, include: Based on the condition of the foundation, construct the foundation and the installation base for the steel pipe support; The installation foundation is preloaded according to the preset load of the steel pipe support; When the preload of the installation foundation meets the preset threshold of the foundation, the support structure of the steel pipe bracket is erected.
2. The preloading construction method of a steel pipe support according to claim 1, characterized by include: When the preload of the installation foundation does not meet the preset threshold, the installation foundation is reinforced.
3. The preloading construction method of a steel pipe support according to claim 1 or 2, characterized in that, After the steel pipe support is erected, the following is also included: The steel pipe support is preloaded a second time according to the preset load.
4. The preloading construction method of a steel pipe support according to claim 3, characterized in that, Also includes: According to the construction sequence of the steel box girder, at least one set of periodic construction areas shall be configured; the periodic construction area includes: a first working face and a second working face for cyclical construction; While the foundation and installation base are being constructed on the first working face, the supporting structure is being erected simultaneously on the second working face. Alternatively, when the second working face is constructing the foundation and the installation foundation, the first working face is simultaneously erecting the support structure.
5. The preloading construction method of a steel pipe support according to claim 4, characterized in that, The operation procedures of the first and second working faces can be balanced according to the construction time, or a third working face can be added.
6. The preloading construction method of a steel pipe support according to claim 1, characterized in that, The construction of the foundation and the installation base for the steel pipe support includes: filling and compacting the foundation, and pouring concrete for the concrete floor and the installation base for the steel pipe support.
7. The pre-stressing construction method for steel pipe supports according to claim 6, characterized in that, Also includes: A temporary passageway was constructed on the concrete surface. At least two adjacent foundations and installation bases shall be constructed simultaneously according to the temporary passage.
8. The preloading construction method of a steel pipe support according to claim 1, characterized in that, The preloaded mounting base includes: A foundation preloading platform is set up through the load-bearing beam of the steel pipe support; The preload material of the basic preload platform is configured according to the gradually increasing proportion of the preset load; The settlement deformation value of the installation foundation is detected one by one; When all the settlement deformation values are less than the preset threshold of the foundation, the installation foundation is determined to meet the requirements of pre-compression settlement.
9. The pre-stressing construction method for steel pipe supports according to claim 8, characterized in that, The preset load ratio gradient is configured as follows: 60%, 80%, and 110%.
10. A construction method for a steel box girder, comprising a pre-stressing process for steel pipe supports, characterized in that, The pre-compression process adopts the pre-compression construction method for steel pipe supports provided in any optional embodiment according to claims 1-9.