Prefabricated assembly construction method for large-span hydraulic aqueducts
By using prefabrication and assembly construction methods, the construction of the aqueduct body is completed in the prefabrication yard using gantry cranes and three-way hydraulic fine adjustment mechanisms. Combined with the joint structure of embedded waterstops and shear keys, the problem of low efficiency in high-altitude construction of traditional large-span hydraulic aqueducts is solved, and a highly efficient and safe construction process and quality control are achieved.
Patent Information
- Application Number
- CN202611554710.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-09
- Publication Date
- 2026-11-17
AI Technical Summary
In traditional construction methods for large-span hydraulic aqueducts, the construction of the aqueduct body needs to be completed at high altitudes, resulting in low construction efficiency, long construction period, and high safety risks associated with working at heights.
The prefabricated assembly construction method is adopted, and the construction of the trench body is transferred to the prefabrication yard. The gantry crane and the three-way hydraulic fine adjustment mechanism are used for segment hoisting and precise positioning. Combined with the embedded waterstop, connecting steel bars and shear keys, a joint structure that combines seepage prevention and force transmission is formed. Deformation and settlement during the construction process are monitored simultaneously.
It shortened the construction cycle, improved construction efficiency and component quality, ensured construction safety and installation accuracy, prevented leakage at joints, and effectively transferred structural internal forces.
Smart Images

Figure CN123109072A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the technical field of engineering construction, and in particular to a prefabricated assembly construction method for large-span hydraulic aqueducts. Background Technology
[0002] Long-span aqueducts are key water conveyance structures in inter-basin water transfer projects, with single spans typically reaching tens of meters, large pier heights, and extended lengths along the route. Traditional construction methods employ a full-span scaffolding and cast-in-place process: a high-altitude formwork scaffold is erected between the piers, extending from the ground to the top of the aqueduct. The formwork for the aqueduct body is then supported on the scaffold, reinforcing steel is tied, and concrete is poured on-site. Once the concrete reaches its design strength, the scaffold and formwork are dismantled section by section.
[0003] The fundamental problem with this method is that all construction work on the aqueduct is carried out at high altitude. Because the aqueduct piers are tens of meters high, formwork supports are erected continuously from the ground to the top of the aqueduct, steel reinforcement cages are tied one by one at high altitude, and concrete is poured and cured on the high-altitude work surface. All processes are carried out layer by layer at high altitude. The high-altitude work surface is narrow, materials and tools must be vertically hoisted to the work level, resulting in low construction efficiency, long construction cycles for a single span, and a significantly extended cumulative construction period due to the aqueduct's dozens of spans. Summary of the Invention
[0004] This application aims to at least partially address one of the technical problems in the related art.
[0005] Therefore, one objective of this application is to provide a prefabricated assembly construction method for large-span hydraulic aqueducts, which transfers the construction of the aqueduct body to a prefabrication yard and replaces high-altitude pouring with hoisting and assembly on site, which helps to shorten the construction cycle and stabilize the quality of components; a three-way hydraulic fine adjustment mechanism is used for segment positioning, resulting in high installation accuracy; at the joints, a joint structure combining seepage prevention and force transmission is formed by embedded waterstops, connecting steel bars and shear keys, which helps to prevent leakage at the joints and transmit structural internal forces; during the construction process, the deformation of the aqueduct body, concrete strain, settlement of the aqueduct piers and support reaction force are monitored simultaneously, ensuring controllable construction safety.
[0006] To achieve the above objectives, the first aspect of this application proposes a prefabricated assembly construction method for a long-span hydraulic aqueduct, the aqueduct comprising piers and foundations, including the following steps: S1. Prefabricate multiple precast trough sections in the precast yard; S2. Lay a gantry crane track along the longitudinal direction of the aqueduct on the foundation, and install a gantry crane on the gantry crane track. The gantry crane includes a main beam and two outriggers on both sides. S3. The gantry crane lifts the precast trough section using a lifting device, travels along the gantry crane track to the top of the installation span, and places it on a temporary support; S4. The precast trough section is precisely aligned in the longitudinal, transverse and elevation directions using a three-way hydraulic jack mounted on the temporary support. S5. After fine-tuning the alignment of two adjacent precast trough sections, an embedded rubber waterstop is installed between the end faces of the two adjacent precast trough sections. The connecting steel bars extending from the end faces of the two adjacent precast trough sections are connected by butt joints. A cast-in-place node is poured between the two adjacent precast trough sections. A shear key is formed on the end face of the precast trough section, and the shear key engages with the cast-in-place node. S6. After the cast-in-place node reaches the design strength, longitudinal prestressing tension is applied to the node to make the two adjacent precast trough sections form a whole.
[0007] The prefabricated assembly construction method for large-span hydraulic aqueducts in this application transfers the construction of the aqueduct body to the prefabrication yard, replacing high-altitude pouring with hoisting and assembly on site, which helps to shorten the construction cycle and stabilize the quality of components; a three-way hydraulic fine-tuning mechanism is used for segment positioning, resulting in high installation accuracy; at the joints, embedded waterstops, connecting steel bars, and shear keys form a joint structure that combines seepage prevention and force transmission, which helps to prevent leakage at the joints and transmit structural internal forces; during the construction process, the deformation of the aqueduct body, concrete strain, settlement of the aqueduct piers, and support reaction force are monitored simultaneously, ensuring controllable construction safety.
[0008] In addition, the prefabricated assembly construction method for large-span hydraulic aqueducts proposed in this application may also have the following additional technical features: In one embodiment of this application, in step S3, after the gantry crane hooks up, it first performs a trial lift, lifting the precast trough section 20cm off the ground and pausing for 5 minutes to check the brakes, the lifting device, the rigging and the stability of the section. After confirming that everything is normal, it travels along the gantry crane track to the top of the installation span and falls to a point 50cm above the design elevation and stops.
[0009] In one embodiment of this application, in step S4, the positional deviation of the precast trough section is monitored in real time by a total station and a laser positioning system. The control system automatically calculates the adjustment amount of the three-way hydraulic jack based on the deviation. The longitudinal, lateral and vertical directions of the three-way hydraulic jack are independently controlled and linked for adjustment, thereby completing the longitudinal, lateral and elevation fine-tuning in sequence.
[0010] In one embodiment of this application, the lifting device is a steel truss structure, which is connected to the pre-embedded lifting points on the top surface of the precast trough section. A balance beam is provided on the lifting device to ensure that the force on each lifting point is uniform. During lifting, the lifting center of gravity of the lifting device coincides with the center of gravity of the precast trough section.
[0011] In one embodiment of this application, the temporary support includes a steel pipe column, a Bailey beam supported on the top of the steel pipe column, and a reinforced concrete foundation located at the bottom of the steel pipe column. The three-way hydraulic jack is installed on the top of the Bailey beam, and one temporary support is respectively provided at the bottom of both ends of each precast trough section.
[0012] In one embodiment of this application, the steel pipe column is fixedly connected to the trough pier by a clamp.
[0013] In one embodiment of this application, in step S5, before pouring the cast-in-place node, the end face joint surface of the precast trough section (1) is roughened to form a rough surface, and after removing laitance and debris, it is moistened with water. Before pouring, cement slurry or interface agent is applied to the joint surface.
[0014] In one embodiment of this application, in step S5, the embedded rubber waterstop is installed in the center, with its center line aligned with the center line of the cast-in-place node. The joint of the embedded rubber waterstop is heat-welded, and the area around the embedded rubber waterstop is carefully vibrated and compacted during concrete pouring.
[0015] In one embodiment of this application, in step S6, the longitudinal prestressing tensioning is carried out in a symmetrical, batch, and graded order. The tensioning is mainly controlled by the tension force and supplemented by the elongation check. The deviation between the actual elongation and the theoretical elongation is controlled within ±6%. Grouting of the duct is carried out in a timely manner after the tensioning is completed.
[0016] In one embodiment of this application, a construction monitoring step is also included: deflection measuring points and concrete strain gauges are arranged on the precast trench section, trench pier settlement measuring points are arranged on the trench pier, and support axial force gauges are arranged on the temporary support. Each measuring point is connected to a data acquisition instrument, which transmits the monitoring data to the monitoring center in real time. The monitoring center displays the data of each measuring point in real time and sets multi-level early warnings.
[0017] Additional aspects and advantages of this application will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of this application. Attached Figure Description
[0018] The above and / or additional aspects and advantages of this application will become apparent and readily understood from the following description of the embodiments taken in conjunction with the accompanying drawings, wherein: Figure 1 This is a schematic diagram of the overall elevation of the aqueduct according to the prefabricated assembly construction method for large-span hydraulic aqueducts in accordance with this application. Figure 2 This is a cross-sectional view of the channel section of the prefabricated assembly construction method for large-span hydraulic aqueducts according to this application; Figure 3This is a schematic diagram of a gantry crane lifting a large-span aqueduct according to this application; Figure 4 This is a schematic diagram of the adjustable temporary support system for a large-span hydraulic aqueduct according to this application; Figure 5 This is a cross-sectional view of the node connection structure of the large-span hydraulic aqueduct according to this application; Figure 6 This is a layout diagram of the real-time monitoring system for a large-span hydraulic aqueduct according to this application. Figure 7 This is a flowchart of the method for constructing a large-span hydraulic aqueduct according to this application.
[0019] As shown in the figure: 1. Precast trough section; 2. Cast-in-place joint; 3. Trench pier; 4. Foundation; 5. Gantry crane track; 6. Side wall; 7. Base slab; 8. Top walkway slab; 9. Prestressed steel strand bundle; 10. Prestressed tendon; 11. Gantry crane main beam; 12. Outrigger; 13. Lifting device; 14. Temporary support; 15. Three-way hydraulic jack; 16. Bailey beam crossbeam; 17. Steel pipe column; 18. Reinforced concrete foundation; 19. Hoop; 20. Embedded rubber waterstop; 21. Connecting reinforcement; 22. Shear key; 23. Deflection measuring point; 24. Concrete strain gauge; 25. Settlement measuring point of trench pier; 26. Support axial force gauge; 27. Data acquisition instrument; 28. Monitoring center. Detailed Implementation
[0020] Embodiments of this application are described in detail below, examples of which are illustrated in the accompanying drawings, wherein the same or similar reference numerals denote the same or similar elements or elements having the same or similar functions throughout. The embodiments described below with reference to the accompanying drawings are exemplary and intended to explain this application, and should not be construed as limiting this application. Rather, embodiments of this application include all variations, modifications, and equivalents falling within the spirit and scope of the appended claims.
[0021] The following is in conjunction with the appendix Figure 1-7 This application describes a prefabricated assembly construction method for a large-span hydraulic aqueduct, comprising piers 3 and foundations 4, and includes the following steps: S1. Prefabricate multiple precast trough sections 1 in the precast yard; S2. Lay the gantry crane track 5 on the foundation 4 along the longitudinal direction of the aqueduct, and install the gantry crane on the gantry crane track 5. The gantry crane includes the main beam 11 and the legs 12 on both sides. S3. The gantry crane lifts the precast trough section 1 using the lifting device 13, travels along the gantry crane track 5 to the top of the installation span, and places it on the temporary support 14; S4. The precast trough section 1 is precisely aligned in the longitudinal, transverse and elevation directions by using the three-way hydraulic jacks 15 set on the temporary support 14. S5. After fine-tuning the alignment of two adjacent precast trough sections 1, an embedded rubber waterstop 20 is installed between the end faces of the two adjacent precast trough sections 1. The connecting steel bars 21 extending from the end faces of the two adjacent precast trough sections 1 are connected by butt joint. A cast-in-place node 2 is poured between the two adjacent precast trough sections 1. A shear key 22 is formed on the end face of the precast trough section 1. The shear key 22 engages with the cast-in-place node 2. S6. After the cast-in-place node 2 reaches the design strength, longitudinal prestressing tension is applied to the node to make the two adjacent precast trough sections 1 form a whole.
[0022] S1 prefabricates multiple precast trough sections at the prefabrication yard. In actual construction, the superstructure of the aqueduct is not cast on site, but prefabricated in standard segments at a prefabrication yard. The aqueduct sections are reinforced concrete rectangular cross-section members, which are formed, reinforced, poured, and cured on fixed pedestals before being transported to the site. The purpose of segmented prefabrication is to transfer the high-altitude work on site to the ground factory, shortening the on-site work time. The ends of each section are reserved for the reinforcement and structural surfaces required for subsequent connections.
[0023] S2 lays gantry crane rails 5 on foundation 4 along the longitudinal direction of the aqueduct, and installs the gantry crane, main beam 11 + legs 12. Because the aqueduct is a long, linear structure, hoisting equipment cannot be moved one piece at a time as in conventional engineering projects. Instead, a traveling track is laid along the longitudinal direction of the aqueduct, and the gantry crane moves span by span on the track. The gantry crane spans both sides of the aqueduct, with the main beam crossing over the piers and the outriggers resting on the track. This allows the gantry crane to be advanced from one end of the aqueduct to the other, one span at a time. Foundation 4 is the load-bearing foundation for the gantry crane track, and the bearing capacity of the foundation must meet the operating load of the gantry crane.
[0024] The S3 gantry crane uses lifting device 13 to lift the precast trough section 1, moves it along the track to the top of the installation span, and places it on the temporary support 14. After the precast trough segments are transported to the site, the gantry crane hook lifts them, carrying the segments along the track to the top of the span to be installed, and then lowers them. The segments do not fall directly onto the trough piers, but first onto temporary supports 14—because the cast-in-place joints have not yet been poured, and the segments have not yet formed an integral structure, temporary supports are necessary to bear the self-weight of the segments and the construction load, while also providing an adjustable support surface for subsequent fine-tuning.
[0025] S4 uses the three-way hydraulic jacks 15 on the temporary support 14 to finely adjust and align the precast trough section 1 in the longitudinal, transverse, and elevation directions. After the segments are placed on temporary supports, their positions are rough and require precise adjustment. The three-way hydraulic jacks have adjustment capabilities in three directions: longitudinally, adjusting segment spacing and alignment along the aqueduct axis; and laterally, adjusting offset and elevation perpendicular to the aqueduct axis. Each of the three directions is controlled by an independent jack, with real-time deviation readings from measuring instruments directing the jacks for fine-tuning until the segment's axis, elevation, and misalignment with adjacent segments all meet the accuracy requirements. This step is crucial for achieving millimeter-level installation accuracy.
[0026] After fine-tuning the alignment of adjacent segments of S5, install the embedded rubber waterstop 20, connect the butt-joint steel bars 21, and pour the cast-in-place node 2. A shear key 22 is installed on the end face to engage with the cast-in-place node. After the position is adjusted, a cast-in-place space is left between the end faces of two adjacent segments. Within this space: a ring of embedded rubber waterstop 20 is buried around the perimeter of the trench in the middle to prevent water leakage from the joint; the connecting steel bars 21 extending from the end faces of the two segments are joined together, allowing the post-cast concrete to transfer force with the precast segments on both sides; toothed shear keys 22 are pre-made on the end faces of the segments, and the post-cast concrete fills the toothed grooves and interlocks, transferring shear force and enhancing overall integrity; finally, formwork is erected and concrete is poured to connect the two segments into one. The waterstop for seepage prevention, the steel bar for force transfer, and the shear keys for shear resistance work together to ensure that the joint is both watertight and able to transfer structural internal forces.
[0027] After the S6 cast-in-place node 2 reaches its design strength, longitudinal prestressing is applied to the node to make the two adjacent segments form a whole. After the cast-in-place concrete reaches its design strength, longitudinal prestressed steel strands are threaded and tensioned at the joints to compress adjacent segments axially. Prestressing keeps the joint surface under pre-compression, improving both the joint's crack resistance and seepage prevention reliability, and ensuring that multiple precast segments form a continuous, integral bending member in the longitudinal direction. After tensioning is complete, this segment pair can proceed to the next span for installation, repeating the process from S3 to S6 segment by segment.
[0028] In one embodiment of this application, in step S3, after the gantry crane hooks up, it first performs a trial lift, lifting the precast trough section 1 20cm off the ground and then pausing for 5 minutes to check the brakes, lifting device 13, rigging and section stability. After confirming that everything is normal, it travels along the gantry crane track 5 to the top of the installation span and then falls to a point 50cm from the design elevation and stops.
[0029] Specifically, why should we perform a trial lift first, instead of simply lifting it up and moving it? The weight of a single precast trough section can reach 300 tons, classifying it as a heavy-duty component to be lifted. Before the actual lifting, it is not hoisted directly to a high altitude, but rather lifted approximately 20cm off the ground and stopped for 5 minutes. During these 5 minutes, several things are done: Check the braking system: ensure the gantry crane's hoisting mechanism brake is reliable and that there is no slippage. If the brake fails to stop after lifting a heavy load, operation cannot continue.
[0030] Check the lifting equipment and rigging: whether the connection between the lifting equipment 13 and the pre-embedded lifting point of the segment is in place, and whether the shackles and wire ropes are subjected to uneven stress, abnormal deformation or slippage.
[0031] Check the segment posture: After the tank section is lifted, check whether it remains level and whether one end is higher than the other due to a tilted center of gravity. If it is not level, it indicates uneven stress on the lifting points, and adjustments need to be made before lifting.
[0032] This step is a safety inspection. If a 300-ton object has a problem at high altitude, the consequences will be serious. Therefore, we first verify all stress points at low altitude to confirm that there are no problems before continuing.
[0033] The gantry crane carries the segments along the gantry crane track 5. Because the track is laid longitudinally along the aqueduct, the gantry crane can only travel in a straight line in this direction and cannot move laterally. From the segment lifting point, usually near the prefabrication yard or storage area, it moves along the track directly above the span to be installed. During the movement, the segment is kept at a certain height off the ground to avoid collisions with existing structures or temporary supports on the ground.
[0034] After the gantry crane reaches above the installation span, it begins to descend, but not directly to the design elevation—it stops about 50cm below the design elevation. This is the rough positioning process: At this point, the segment is close to the top of the temporary support 14, but it has not been placed yet. The operator can observe whether the segment's planar position is aligned with the predetermined position of the temporary support. The 50cm height allows space for people on the ground or side to observe, direct, and fine-tune the position using measuring instruments. If the position is off, the position of the gantry crane trolley can be readjusted. After stopping at this height, the three-way hydraulic jack 15 is then used to precisely align the section on the support, instead of relying on the gantry crane to directly and accurately place the section—the gantry crane itself cannot achieve millimeter-level positioning accuracy, so after coarse positioning to 50cm, the fine-tuning mechanism takes over.
[0035] The logic of the entire process is: The process involves a 20cm test lift with a 5-minute pause for low-altitude safety verification, followed by movement along the track to the installation span, a long-distance movement, and a drop to 50cm for rough positioning and handover. Subsequent fine-tuning with three-way jacks achieves millimeter-level positioning. The first half uses a gantry crane to move the heavy object to its approximate location, while the second half uses jacks on temporary supports for precise placement, clearly defining the division of labor between the two sections.
[0036] In one embodiment of this application, in step S4, the position deviation of the precast trough section 1 is monitored in real time by a total station and a laser positioning system. The control system automatically calculates the adjustment amount of the three-way hydraulic jack 15 according to the deviation amount. The three-way hydraulic jack 15 is independently controlled and linked to adjust in the longitudinal, lateral and vertical directions to complete the longitudinal, lateral and elevation fine adjustment in sequence.
[0037] Specifically, in step S4, after the precast trough section 1 is placed on the temporary support 14, the surveyor first sets up a total station on the observation mark preset on the top surface of the section to determine the current plane coordinates and elevation of the section, and compares them with the design coordinates to obtain the longitudinal deviation, lateral deviation and elevation deviation; at the same time, the laser positioning system continuously tracks the reflective target along the longitudinal and lateral directions of the section and sends the deviation amount to the control system in real time.
[0038] The control system converts the difference between the measured position and the design position into the required stroke of the three-way hydraulic jack 15 in each direction: longitudinal deviation corresponds to the extension and retraction of the longitudinal cylinder, lateral deviation corresponds to the extension and retraction of the lateral cylinder, and elevation deviation corresponds to the lifting or lowering of the vertical cylinder. The three sets of cylinders of the three-way hydraulic jack 15 are independently supplied with oil and independently controlled, without linkage between them.
[0039] The adjustment is performed sequentially in the order of longitudinal → lateral → elevation: First, operate the longitudinal cylinder to push the segment near the designed longitudinal axis, and remeasure the deviation after the segment comes to rest; then operate the lateral cylinder to adjust the lateral position and remeasure; finally, operate the vertical cylinder to adjust the elevation. After each direction of adjustment is completed, the deviation is re-read, and the adjustment is only performed in the next direction after confirming that the deviation in that direction has converged. This process is repeated several times until the longitudinal axis deviation, lateral deviation, elevation deviation, and misalignment of adjacent segments all fall within the allowable range. During the adjustment process, the segments are simultaneously observed for any abnormal tilting or localized stress concentration.
[0040] Once the deviation is within acceptable limits, the hydraulic circuit of the three-way hydraulic jack 15 is locked, the temporary support 14 supports the weight of the segment, the gantry crane releases its hook and disengages, and the lifting and positioning of the segment is completed.
[0041] In one embodiment of this application, the lifting device 13 is a steel truss structure, which is connected to the pre-embedded lifting points on the top surface of the precast trough section 1. A balance beam is set on the lifting device 13 to make the force on each lifting point uniform. During lifting, the lifting center of gravity of the lifting device 13 coincides with the center of gravity of the precast trough section 1.
[0042] Specifically, when the precast trough section 1 is poured in the prefabrication yard, lifting points, lifting rings, or anchor plates are pre-embedded on its top surface according to the design positions. Before hoisting, the hook of the gantry crane is connected to the upper end of the lifting device 13 via a wire rope, and each lifting point at the lower end of the lifting device 13 is respectively connected to the pre-embedded lifting points on the top surface of the section and locked with shackles.
[0043] The main body of the lifting device 13 is a steel truss structure, with transverse and longitudinal members forming a lattice frame. It is relatively lightweight while possessing sufficient overall rigidity, resulting in minimal deformation during lifting and preventing uneven stress on various lifting points due to device deflection. A balance beam is installed at the upper suspension point of the lifting device 13. This balance beam is connected to the hook via a pin and can rotate freely within a small range, allowing the lifting device 13 to automatically level itself during lifting. When a segment is subjected to stress from multiple lifting points, the balance beam absorbs uneven deformation between these points, preventing overloading of individual lifting points.
[0044] Before lifting, the arrangement of each lifting point of the lifting equipment 13 is determined by calculation to ensure that the center of gravity of the overall lifting is aligned with the center of gravity of the precast trough section 1 in the vertical line. During the trial lifting, the section is kept horizontal and does not tilt to one end. If the section is found to be tilted during the trial lifting, it is corrected by adjusting the length of the wire rope at each lifting point or by adding adjusting shims at the lifting points until the section remains stable after being lifted horizontally.
[0045] During the formal hoisting process, the lifting device 13 moves, falls, and aligns along the gantry crane track 5 with the segment, always maintaining the segment's horizontal support and preventing additional torsional or eccentric moments. After the segment is in place and the temporary support 14 is locked, the shackles between the lifting device 13 and the pre-embedded lifting points are removed, and the gantry crane returns to the next hoisting position with the lifting device 13.
[0046] In one embodiment of this application, the temporary support 14 includes a steel pipe column 17, a Bailey beam 16 supported on the top of the steel pipe column 17, and a reinforced concrete foundation 18 located at the bottom of the steel pipe column 17. A three-way hydraulic jack 15 is installed on the top of the Bailey beam 16, and a temporary support 14 is respectively set at the bottom of both ends of each precast trough section 1.
[0047] Furthermore, the steel pipe column 17 is fixedly connected to the trough pier 3 by the clamp 19.
[0048] Specifically, temporary supports 14 are arranged longitudinally along the aqueduct on the foundations on both sides of the pier 3. The bottom is a reinforced concrete foundation 18, made of C30 concrete, with dimensions determined by the support reaction calculation. The foundation rests on a stratum with sufficient bearing capacity; soft foundations are first replaced. A steel plate is embedded in the top surface of the foundation 18 for connection with the bottom flange of the steel pipe column 17.
[0049] The steel pipe columns 17 are vertically installed on the embedded steel plates and arranged in rows along the longitudinal direction of the aqueduct. The spacing between adjacent columns is determined by calculation based on the span of the Bailey beam 16 and the load on the aqueduct section. The Bailey beam 16 is erected on top of the steel pipe columns 17 and is arranged transversely along the aqueduct, with both ends supported at the top of adjacent steel pipe columns 17. The Bailey beam 16 is assembled from standard Bailey panels and is reinforced with single or multiple layers depending on the segment lifting load requirements.
[0050] The three-way hydraulic jack 15 is installed on the top surface of the Bailey beam crossbeam 16, corresponding to the designed support point position at the bottom of the precast trough section 1. Each precast trough section 1 has a temporary support 14 at each end and on the left and right sides of its bottom surface, resulting in a total of four support points per section, which together bear the section's weight. After the section is placed onto the temporary support 14, the vertical cylinder of the three-way hydraulic jack 15 presses against the bottom surface of the section's base plate, while the longitudinal and transverse cylinders press against the side walls or bottom guides of the section in their respective directions, providing three-way adjustment capability.
[0051] The steel pipe column 17 is connected to the pier 3 adjacent to it via a clamp 19. The clamp 19 is a two-part steel sleeve that is tightened onto the concrete outer wall of the pier 3. A steel bracket or connector is installed between the clamp 19 and the steel pipe column 17 to transfer force. The clamp 19 connects the temporary support 14 to the constructed pier 3 as a whole, reducing the longitudinal deformation and lateral displacement of the support system during hoisting and joint pouring, and improving overall stability. A rubber pad or mortar leveling layer is installed between the clamp 19 and the contact surface of the pier 3 to ensure a tight fit between the clamp 19 and the concrete surface without damaging the concrete of the pier 3.
[0052] In one embodiment of this application, in step S5, before pouring the cast-in-place node 2, the end face joint surface of the precast trough section 1 is roughened to form a rough surface, and after removing laitance and debris, it is moistened with water. Before pouring, cement slurry or interface agent is applied to the joint surface.
[0053] Specifically, after the precast trough segment 1 is demolded at the precast yard, its end face, which is the joint surface that will subsequently connect with the cast-in-place node 2, is roughened during precasting. This is done using a roughened template or by having workers manually roughen each surface with a chisel during the segment's storage. The roughening depth is controlled to expose fresh aggregate, with a surface unevenness of not less than 6mm, so that the subsequently poured concrete can embed into the grooves to form a mechanical interlock.
[0054] Before the segments are hoisted into place, the joint surfaces are cleaned with a high-pressure water gun or wire brush to remove any laitance, dust, oil, and debris accumulated during prefabrication. After cleaning, the joint surfaces are moistened with water, ensuring even and thorough application to saturate the concrete surface. However, water accumulation is not allowed—it will alter the local water-cement ratio of the subsequent concrete pour, affecting the bonding strength.
[0055] After the reinforcement bars at the joint are connected, the formwork is erected, and before pouring the cast-in-place joint 2, apply a layer of neat cement slurry or a special interface agent evenly to the joint surface. The water-cement ratio of the neat cement slurry should be prepared according to the construction mix ratio, and the coating thickness should be controlled to be thin and uniform, without any omissions or accumulations. Immediately after application, begin pouring the joint concrete, with the interval not exceeding the setting time of the neat cement slurry, to ensure a good bond between the old and new concrete at the interface.
[0056] In one embodiment of this application, in step S5, the embedded rubber waterstop 20 is installed in the center, with its center line aligned with the center line of the cast-in-place node 2. The joint of the embedded rubber waterstop 20 is heat-welded, and the area around the embedded rubber waterstop 20 is carefully vibrated and compacted during concrete pouring.
[0057] Specifically, the embedded rubber waterstop 20 is arranged around the perimeter of the end face of the precast trench section 1 and installed after fine-tuning the alignment of adjacent sections. During installation, the waterstop is first unfolded along the cross-sectional direction of the trench, with its central ring aligned with the center line of the cast-in-place node 2. The two flanges of the waterstop are respectively embedded in the reserved grooves on the end faces of the precast trench sections 1 on both sides. During installation, a steel ruler is used to measure the distance from the central ring to the end face of the section at multiple points around the perimeter of the waterstop to confirm that the embedment depth on both sides is consistent and that the waterstop is not skewed or twisted.
[0058] When waterstops need to be extended, the joints should be heat-welded: the ends of the two waterstop sections are cut flat, placed in a special heat-welding mold, and heated and pressurized to vulcanize and bond the rubber together. Heat-welded joints must not be overlapped or lapped, and the tensile strength at the joint must not be less than 80% of the strength of the waterstop base material. The number and location of joints for each waterstop should be controlled according to design requirements, and joints should be avoided as much as possible from stress concentration areas such as corners of the channel.
[0059] After the waterstop is in place, it is temporarily fixed to the joint reinforcement cage using steel clamps or special fasteners to prevent the waterstop from shifting, floating, or flipping during concrete pouring. The fixing points are evenly distributed around the perimeter of the waterstop, with a spacing of no more than 50cm.
[0060] When pouring the concrete for the cast-in-place node 2, the area below and on both sides of the waterstop 20 is the most challenging for compaction. The waterstop obscures the lower concrete, making it prone to creating voids underneath. During pouring, first lay a layer of mortar with the same mix proportion below the waterstop, then pour the concrete in layers. Use a small-diameter immersion vibrator to symmetrically vibrate from both sides of the waterstop, avoiding direct contact between the vibrator and the waterstop. The concrete below the waterstop will self-compact through vibration from both sides and the pressure of the pouring. During the pouring process, continuously observe the waterstop for any deviation and correct it immediately if any is detected.
[0061] In one embodiment of this application, in step S6, the longitudinal prestressing tensioning is carried out in a symmetrical, batch, and graded order. The tensioning is mainly controlled by the tension force and supplemented by the elongation check. The deviation between the actual elongation and the theoretical elongation is controlled within ±6%. Grouting of the duct is carried out in a timely manner after the tensioning is completed.
[0062] After the cast-in-place concrete at node 2 reaches its design strength, longitudinal prestressing tensioning of the node begins. Before tensioning, the concrete test block strength report is checked to confirm that the design tensioning strength has been reached. The surface of the end anchor plate is then cleaned, and the working anchor plate and wedges are installed.
[0063] The tensioning sequence is symmetrical, phased, and graded. Multiple prestressed steel strands are arranged within the cross-section of the channel section. Tensioning is carried out symmetrically along the centerline of the cross-section, first tensioning the strands closest to the sidewalls, then tensioning the strands in the middle section, ensuring symmetrical stress distribution within the segment during tensioning and preventing torsion. Within each batch, the strands are tensioned sequentially from the middle outwards, with each strand tensioned symmetrically from both ends. The tension force of each strand is applied in several stages, not all at once to the design tonnage, to allow for observation of structural response and stress transfer.
[0064] Tensioning employs a dual-control system. The tension force is controlled by the hydraulic pressure gauge reading, and the actual elongation is used as a checksum: at each tonnage level, the actual elongation of the steel strand is measured and compared with the theoretically calculated elongation. The deviation between the actual and theoretical elongation is controlled within ±6%; if this range is exceeded, tensioning is stopped, and the duct friction, the elastic modulus of the steel strand, and the theoretically calculated value are checked. Tensioning can only continue after the cause has been identified.
[0065] After tensioning is completed and confirmed by the supervisor, grouting of the ducts should be carried out promptly. Before grouting, the ducts should be flushed with pressurized water and then blown out any accumulated water with compressed air. Cement grout should be used for grouting, with the water-cement ratio prepared according to the design mix proportion. It should be injected from one end of the duct, and after thick grout emerges from the other end, the grout outlet should be sealed and pressure maintained for a certain period of time to ensure that the grout in the duct is full and dense. After grouting is completed, excess length of exposed steel strands should be cut off and the anchorages should be sealed.
[0066] In one embodiment of this application, a construction monitoring step is also included: deflection measuring points 23 and concrete strain gauges 24 are arranged on the precast trough section 1, trough pier settlement measuring points 25 are arranged on the trough pier 3, and support axial force gauges 26 are arranged on the temporary support 14. Each measuring point is connected to a data acquisition instrument 27, which transmits the monitoring data to the monitoring center 28 in real time. The monitoring center 28 displays the data of each measuring point in real time and sets multi-level early warnings.
[0067] Specifically, construction monitoring is set up as soon as the segments are hoisted, and it continues throughout the entire process of node pouring, tensioning, and support removal.
[0068] Deflection measuring points 23 are arranged at the mid-span and support positions of each precast trough section 1. Surface displacement gauges or settlement observation points are used to measure the vertical deflection changes of the trough body at each stage of construction. No less than 3 measuring points are arranged in each span: one at the mid-span and one at each of the two end supports.
[0069] Concrete strain gauges 24 are embedded in the sidewalls 6 and bottom slab 7 of the precast trench section 1, pre-embedded at the designed positions along the longitudinal and transverse directions of the trench, to measure the strain changes of concrete under conditions such as hoisting, joint pouring, and prestressing tensioning. The strain gauges are pre-embedded in place when the segment concrete is poured at the precast yard, and the lead wires are led out from the end face of the segment and connected to the acquisition system on site.
[0070] Settlement measuring points 25 are arranged on the top and side of each pier 3, using precise leveling points to measure the settlement and uneven settlement of the pier 3 under the action of temporary support and superstructure load.
[0071] The axial force gauge 26 is installed on the top of the steel pipe column 17 of the temporary support 14 or between the three-way hydraulic jack 15 and the Bailey beam 16 to measure the actual axial reaction force borne by each support point. This is used to determine whether the force on each support point is uniform and the change of support reaction force during the node pouring and tensioning process.
[0072] All the aforementioned measuring points are connected to the data acquisition unit 27 via signal cables. The data acquisition unit 27 is a multi-channel automatic acquisition device. The sampling frequency is set according to the monitoring items; dynamic quantities such as strain and axial force are measured at higher frequencies, while static quantities such as settlement and deflection are collected at fixed time intervals. The data acquisition unit 27 transmits the data from each measuring point to the monitoring center 28 in real time via wired or wireless network.
[0073] Monitoring Center 28 is equipped with a large monitoring screen that displays real-time values and time-history curves for each measuring point. Based on design calculations, Monitoring Center 28 sets three levels of early warning thresholds: Level 1 is a warning threshold, prompting attention when data approaches it; Level 2 is an alarm threshold, triggering an audible and visual alarm and notifying the site to suspend work when data reaches the threshold; Level 3 is a danger threshold, immediately initiating an emergency response upon exceeding the limit. Data from each measuring point is automatically stored in a database for construction process analysis and as-built documentation archiving.
[0074] This application discloses an aqueduct, the upper structure of which is a prestressed concrete rectangular section, which is formed by splicing multiple precast trough sections 1 along the longitudinal direction and is supported on the trough piers 3 and foundations 4 of the lower structure.
[0075] The precast trough section 1 has a trough-shaped cross-section, with side walls 6 on both sides and a bottom plate 7 at the bottom. The thickness of the side walls 6 is determined according to hydraulic conditions and structural stress, while the thickness of the bottom plate 7 is determined based on the mid-span bending moment and crack resistance requirements. The side walls 6 and the bottom plate 7 are cast integrally, with chamfers at the corners to improve stress concentration. The net width and net height of the trough cross-section are determined according to the design water flow rate, and the inner wall surface is smooth to meet the water flow requirements.
[0076] The precast trough section 1 adopts a three-dimensional prestressed structure. Longitudinal prestressed steel strand bundles 9 are arranged and tensioned along the longitudinal ducts in the bottom slab 7 and the lower part of the sidewall 6, creating longitudinal prestress in the section. Transverse prestressing tendons 10 are arranged to apply transverse prestress to the sidewall 6 and withstand the circumferential tensile force generated by the water pressure within the trough. Vertical prestressing tendons 10 are arranged along the height of the sidewall 6 to control vertical cracks in the sidewall 6 during construction and operation. The prestressing ducts in all three directions are pre-embedded and positioned according to the design location during the casting of the section concrete in the precast yard.
[0077] A top walkway 8 is installed on the upper end of each of the two side walls 6 at the top of the trough section. The walkway 8 is arranged along the longitudinal length of the trough for operation and maintenance personnel to walk on. The top surface of the walkway 8 is higher than the top surface of the side wall 6, and a guardrail is installed on the outer side (not shown in the figure).
[0078] A cast-in-place node 2 is left between the end faces of two adjacent precast trough sections 1. Shear keys 22 are provided on the end faces of the sections, which interlock with the cast-in-place concrete of node 2 to transfer force. An embedded rubber waterstop 20 is installed in the middle of node 2, and the connecting steel bars 21 extending from the end faces on both sides are connected inside node 2. After the concrete of node 2 reaches the design strength, longitudinal prestressing is performed to compress the adjacent sections axially, forming a continuous integral structure.
[0079] The pier 3 is a reinforced concrete column, with its top supporting the end of the precast trench section 1 or the bottom of the temporary support 14, and its bottom integrally connected to the foundation 4. The foundation 4 adopts either an enlarged foundation or a pile foundation, which is determined according to the geological conditions and the reaction force of the pier.
[0080] Specifically, the superstructure of the aqueduct is a prestressed concrete rectangular section, constructed by longitudinally splicing multiple precast aqueduct segments 1, supported by the aqueduct piers 3 and foundations 4 of the substructure. The precast aqueduct segment 1 has a trough-shaped cross-section, with side walls 6 on both sides and a bottom slab 7. The side walls 6 and bottom slab 7 are integrally cast, with chamfered corners. The precast aqueduct segment 1 employs a three-dimensional prestressed structure, with prestressed steel strand bundles 9 arranged longitudinally and prestressed tendons 10 arranged laterally and vertically. A top pedestrian walkway slab 8 is installed at the top of each of the two side walls 6 on the top of the aqueduct segment, extending longitudinally along the entire length of the aqueduct.
[0081] During construction, the precast channel segments 1 are first precast in the prefabrication yard according to standard sections. The channel segments are then formed, reinforced, poured, and cured on fixed pedestals. The three-way prestressed ducts are pre-embedded and positioned according to the design location during concrete pouring. Connecting steel bars 21 and structural surfaces for subsequent connections are reserved at both ends of each segment. After the segments reach their design strength, they are hoisted to the storage area and then transported to the hoisting site along the construction access road using a special beam transport vehicle.
[0082] A gantry crane track 5 is laid on the foundation 4 along the longitudinal direction of the aqueduct, and the gantry crane is installed on the track. The gantry crane includes a main beam 11 and two side legs 12. The main beam spans across the aqueduct piers, and the two side legs rest on the track, allowing it to move longitudinally along the aqueduct, span by span.
[0083] After the precast trough section 1 is delivered to the site, the gantry crane hook is connected to the pre-embedded lifting points on the top surface of the section via the lifting device 13. The lifting device 13 is a steel truss structure with a balance beam at the upper suspension point to ensure even force distribution at each lifting point, and that the lifting center of gravity coincides with the center of gravity of the section during lifting. After hooking, a trial lift is performed, raising the precast trough section 1 about 20cm off the ground and pausing for 5 minutes to check the lifting brake, lifting device 13, rigging, and the horizontal posture of the section. After confirming that there are no abnormalities, the section moves along the gantry crane track 5 to the top of the installation span. During movement, the section is kept at a certain height off the ground to avoid collisions with the already installed structure. After reaching the top of the installation span, it is slowly lowered to a stop about 50cm from the design elevation, where surveyors direct the gantry crane trolley for rough horizontal positioning.
[0084] After the segment falls above the temporary support 14, it rests on top of the temporary support 14. The temporary supports 14 are arranged longitudinally along the aqueduct on both sides of the pier 3, with a reinforced concrete foundation 18 at the bottom. The top surface of the foundation 18 has a steel plate pre-embedded to connect to the bottom of the steel pipe column 17. A Bailey beam 16 is erected on top of the steel pipe column 17, and a three-way hydraulic jack 15 is installed on the top surface of the Bailey beam 16. Each precast trough segment 1 has one temporary support 14 at each end and on the bottom surface of each end on the left and right sides, for a total of 4 support points to support the segment. The steel pipe column 17 is connected to the pier 3 at the position adjacent to the pier 3 by a clamp 19, so that the support system is integrated with the substructure.
[0085] After the segment is placed on temporary support 14, fine-tuning and alignment begin. Surveyors set up a total station on a pre-set observation point on the top surface of the segment to determine its current plane coordinates and elevation. These are compared with the design coordinates to determine the longitudinal, lateral, and elevation deviations. Simultaneously, a laser positioning system continuously tracks the segment's reflective target, sending the deviation measurements to the control system in real time. The control system automatically calculates the required stroke of the three-way hydraulic jack 15 in each direction based on the deviation. The longitudinal, lateral, and vertical cylinders of the three-way hydraulic jack 15 are independently controlled and supplied with oil. Adjustments are made sequentially in the order of longitudinal → lateral → elevation. After each direction is adjusted, the deviation is remeasured. This process is repeated several times until the longitudinal axis deviation, lateral deviation, elevation deviation, and misalignment between adjacent segments all fall within the allowable range. Once the deviations are within acceptable limits, the jack's oil circuit is locked, and the gantry crane hook is released.
[0086] After fine-tuning the alignment of two adjacent segments, construction of cast-in-place node 2 begins. Before pouring, the joint surface of the precast trough segment 1 is roughened to expose fresh aggregate, with a surface unevenness of not less than 6mm. A high-pressure water gun is used to remove laitance and debris, and the concrete surface is moistened until it is saturated but not waterlogged. Before pouring, cement slurry or interface agent is evenly applied to the joint surface. Embedded rubber waterstops 20 are installed around the trough between the end faces of adjacent segments, with the central ring aligned with the center line of cast-in-place node 2, and the two flanges embedded in the pre-reserved grooves on the end faces of the two segments. The waterstop joints are heat-welded, without overlapping or lapping, and the joint strength is not less than 80% of the parent material. After the waterstop is in place, it is fixed to the node's reinforcing steel frame using steel clamps. The connecting steel bars 21 extending from the end faces of the adjacent segments are butt-connected, the node formwork is erected, and micro-expansion concrete is poured. The pre-formed toothed shear keys 22 on the end faces of the segments interlock with the cast-in-place node 2 concrete to transfer force. During pouring, use a small-diameter vibrator to symmetrically vibrate from both sides of the waterstop, and carefully vibrate to compact the area below the waterstop.
[0087] After the cast-in-place concrete at node 2 reaches its design strength, longitudinal prestressing tensioning is performed. Tensioning is carried out symmetrically along the centerline of the cross-section, first tensioning the strands near the sidewalls, then the middle sections. Each strand is tensioned symmetrically at both ends, with the tension force applied in several stages. Tensioning is primarily controlled by tension force, supplemented by elongation verification; the deviation between actual and theoretical elongation is controlled within ±6%. Grouting is performed promptly after tensioning. Grout is injected from one end of the duct and thick grout exits from the other end, maintaining pressure to ensure the duct is full and dense.
[0088] Structural monitoring was conducted simultaneously throughout the entire construction process. Deflection measuring points 23 and concrete strain gauges 24 were installed on the precast trough section 1, settlement measuring points 25 were installed on the trough pier 3, and axial force gauges 26 were installed on the temporary support 14. Each measuring point was connected to a data acquisition device 27, which transmitted the data to the monitoring center 28 in real time via wired or wireless network. The monitoring center 28 displayed the values and time history curves of each measuring point in real time and set three-level early warning thresholds according to the design calculation values. When the data reached the corresponding threshold, a level-specific alarm was triggered.
[0089] After the prestressing of the nodes is completed and the structural deformation is stable, the temporary supports 14 are removed according to the principles of symmetry, uniformity, and step-by-step removal: the hydraulic pressure of the three-way hydraulic jacks 15 is reduced synchronously and symmetrically in stages. After each stage of load reduction, the segment deformation and support reaction force are monitored. After confirming that there are no abnormalities, the load reduction continues until the jacks have completely fallen back and the segment is detached from the support. Then, the temporary supports 14 are removed in the order of first the crossbeams and then the columns, from top to bottom. After completion, the gantry crane carries the segment to the next span, and the above procedures of hoisting, fine-tuning, node pouring, tensioning, monitoring, and support removal are repeated, advancing span by span until the aqueduct is fully connected.
[0090] In summary, the prefabrication and assembly construction method for the large-span hydraulic aqueduct in this application transfers the construction of the aqueduct body to the prefabrication yard, and replaces high-altitude pouring with hoisting and assembly on site, which helps to shorten the construction cycle and stabilize the quality of components; the use of a three-way hydraulic fine adjustment mechanism for segment positioning results in high installation accuracy; at the joints, a joint structure combining seepage prevention and force transmission is formed by embedded waterstops, connecting steel bars and shear keys, which helps to prevent leakage at the joints and transmit structural internal forces; during the construction process, the deformation of the aqueduct body, concrete strain, settlement of the aqueduct piers and support reaction force are monitored simultaneously, and the construction safety is controllable.
[0091] In the description of this specification, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one of that feature. In the description of this application, "multiple" means at least two, such as two, three, etc., unless otherwise explicitly specified.
[0092] In the description of this specification, the references to terms such as "one embodiment," "some embodiments," "example," "specific example," or "some examples," etc., refer to specific features, structures, materials, or characteristics described in connection with that embodiment or example, which are included in at least one embodiment or example of this application. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples. Moreover, without contradiction, those skilled in the art can combine and integrate the different embodiments or examples described in this specification, as well as the features of different embodiments or examples.
[0093] Although embodiments of this application have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting this application. Those skilled in the art can make changes, modifications, substitutions and variations to the above embodiments within the scope of this application.
Claims
1. A prefabricated assembly construction method for a long-span hydraulic aqueduct, the aqueduct comprising piers (3) and foundations (4), characterized in that, Includes the following steps: S1. Prefabricate multiple precast trough sections in the prefabrication yard (1). S2. Lay a gantry crane track (5) on the foundation (4) along the longitudinal direction of the aqueduct, and install a gantry crane on the gantry crane track (5). The gantry crane includes a gantry crane main beam (11) and two side legs (12). S3. The gantry crane lifts the precast trough section (1) using the lifting device (13), travels along the gantry crane track (5) to the top of the installation span, and places it on the temporary support (14); S4. The precast trough section (1) is precisely aligned in the longitudinal, transverse and elevation directions by using a three-way hydraulic jack (15) set on the temporary support (14); S5. After fine-tuning the alignment of the two adjacent precast trench sections (1), install the embedded rubber waterstop (20) between the end faces of the two adjacent precast trench sections (1), connect the connecting steel bars (21) extending from the end faces of the two adjacent precast trench sections (1), and cast-in-place nodes (2) are poured between the two adjacent precast trench sections (1). Shear keys (22) are formed on the end faces of the precast trench sections (1), and the shear keys (22) engage with the cast-in-place nodes (2). S6. After the cast-in-place node (2) reaches the design strength, the node is subjected to longitudinal prestressing tension so that the two adjacent precast trough sections (1) form a whole.
2. The prefabrication and assembly construction method for large-span hydraulic aqueducts according to claim 1, characterized in that, In step S3, after the gantry crane hooks up, it first performs a trial lift, lifting the precast trough section (1) 20cm off the ground and then stopping for 5 minutes to check the brake, the lifting tool (13), the rigging and the stability of the section. After confirming that everything is normal, it moves along the gantry crane track (5) to the top of the installation span and falls to a point 50cm from the design elevation.
3. The prefabrication and assembly construction method for large-span hydraulic aqueducts according to claim 1, characterized in that, In step S4, the position deviation of the precast trough section (1) is monitored in real time by a total station and a laser positioning system. The control system automatically calculates the adjustment amount of the three-way hydraulic jack (15) based on the deviation. The three-way hydraulic jack (15) is independently controlled and linked to adjust in the longitudinal, transverse and vertical directions, and longitudinal, transverse and elevation fine-tuning is completed in sequence.
4. The prefabrication and assembly construction method for large-span hydraulic aqueducts according to claim 1, characterized in that, The lifting device (13) is a steel truss structure and is connected to the pre-embedded lifting point on the top surface of the precast trough section (1). A balance beam is set on the lifting device (13) to make the force on each lifting point uniform. During the lifting, the lifting center of gravity of the lifting device (13) coincides with the center of gravity of the precast trough section (1).
5. The prefabrication and assembly construction method for large-span hydraulic aqueducts according to claim 1, characterized in that, The temporary support (14) includes a steel pipe column (17), a Bailey beam (16) supported on the top of the steel pipe column (17), and a reinforced concrete foundation (18) located at the bottom of the steel pipe column (17). The three-way hydraulic jack (15) is installed on the top of the Bailey beam (16). One temporary support (14) is set at the bottom of both ends of each precast trough section (1).
6. The prefabrication and assembly construction method for large-span hydraulic aqueducts according to claim 5, characterized in that, The steel pipe column (17) is fixedly connected to the trough block (3) by a clamp (19).
7. The prefabrication and assembly construction method for large-span hydraulic aqueducts according to claim 1, characterized in that, In step S5, before pouring the cast-in-place node (2), the end face joint surface of the precast trough section (1) is roughened to form a rough surface. After removing the laitance and debris, water is sprinkled to moisten it. Before pouring, cement slurry or interface agent is applied to the joint surface.
8. The prefabrication and assembly construction method for large-span hydraulic aqueducts according to claim 1, characterized in that, In step S5, the embedded rubber waterstop (20) is installed in the center, with its center line aligned with the center line of the cast-in-place node (2). The joint of the embedded rubber waterstop (20) is heat-welded. When pouring concrete, the area around the embedded rubber waterstop (20) is carefully vibrated and compacted.
9. The prefabrication and assembly construction method for large-span hydraulic aqueducts according to claim 1, characterized in that, In step S6, the longitudinal prestressing tensioning is carried out in a symmetrical, batch, and graded manner. The tensioning is mainly controlled by the tension force and supplemented by the elongation check. The deviation between the actual elongation and the theoretical elongation is controlled within ±6%. Grouting of the duct is carried out in a timely manner after the tensioning is completed.
10. The prefabrication and assembly construction method for large-span hydraulic aqueducts according to claim 1, characterized in that, It also includes construction monitoring steps: deflection measuring points (23) and concrete strain gauges (24) are arranged on the precast trough section (1), trough pier settlement measuring points (25) are arranged on the trough pier (3), and support axial force gauges (26) are arranged on the temporary support (14). Each measuring point is connected to a data acquisition instrument (27). The data acquisition instrument (27) transmits the monitoring data to the monitoring center (28) in real time. The monitoring center (28) displays the data of each measuring point in real time and sets up multi-level early warnings.