Gravity wharf structure and construction method
By assembling gravity wharf structures using modular prefabricated components, the problem of high dependence on large equipment in traditional construction has been solved, enabling efficient and low-cost construction in underdeveloped areas and island environments, and improving the integrity and stability of the structure.
Patent Information
- Application Number
- CN202611476762.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-21
- Publication Date
- 2026-11-17
AI Technical Summary
In underdeveloped regions and island environments, traditional gravity-type wharf construction relies heavily on large caisson prefabrication sites and specialized transportation equipment, resulting in high construction costs, long cycles, and difficulty in ensuring underwater installation accuracy and joint treatment. In particular, construction risks are high in narrow waters and complex water flow conditions.
Modular prefabricated components, including raft slabs, prefabricated pipe piles, interlocking piles, bottom sealing concrete, and backfill, are used. These components are transported to the site by conventional ships for assembly. The cofferdam and internal backfill are used to form a gravity-type wharf structure, reducing dependence on site and equipment and improving construction efficiency and overall integrity.
It reduced construction costs and site requirements, improved the flexibility and efficiency of construction organization, enhanced the overall integrity of the structure and its anti-seepage and anti-sliding stability, and shortened the construction period.
Smart Images

Figure CN123109094A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of wharf engineering. More specifically, this invention relates to a gravity-type wharf structure and its construction method. Background Technology
[0002] Gravity quays are an important structural form in port engineering, relying primarily on their own weight to resist horizontal loads and maintain overall stability. In traditional construction, large caisson gravity quays are the most common application. The construction process typically requires first building a large, water-adjacent caisson prefabrication yard on shore, equipped with dedicated prefabrication platforms, curing areas, and transport slipways. After the caissons are cast in the prefabrication yard, they are launched into the water via slipways, floating docks, or semi-submersible barges, and then towed to the installation area by high-powered tugboats or specialized caisson transport vessels. Upon arrival at the site, a positioning system is used to precisely place the caissons onto a pre-leveled underwater foundation. Sand or stones are then filled inside the caissons to increase gravity, and finally, the superstructure and ancillary facilities are constructed. This technology is relatively mature overall, but it places high demands on the prefabrication yard, transport channels, and large-scale marine machinery and equipment.
[0003] Another common structural form is the precast block gravity wharf. This scheme breaks down the wharf wall into several smaller precast concrete blocks, each typically weighing between tens and hundreds of tons. These blocks are prefabricated on shore and then hoisted one by one onto an underwater foundation using conventional lifting equipment. They are then stacked according to the design, relying on the interlocking and staggered joints between the blocks, as well as the structure's own weight, to form a gravity retaining wall. Compared to large caissons, the precast block scheme reduces the requirements for prefabrication sites and transport vessels, eliminating the need for large transport slipways or semi-submersible barges, and offering greater flexibility in construction organization. However, this scheme involves a large number of blocks, requires high underwater installation precision necessitating diving operations, has numerous joints between blocks resulting in weaker overall integrity and watertightness, lower construction efficiency, and a significant impact on the long-term durability of the structure due to the quality of the joints. In areas with poor wave and current conditions, the hoisting and placement of small blocks is challenging, and wave resistance stability is difficult to guarantee.
[0004] In overseas port projects, island wharves, and projects in remote areas, site conditions often fail to meet the requirements of the two traditional solutions mentioned above. Many project locations lack large caisson prefabrication sites and the conditions for constructing deep-water transport wharves or slipways. Local areas typically lack key construction equipment such as semi-submersible barges, large crane vessels, and specialized tugboats, and it is even difficult to rent vessels that meet the towing requirements. While the equipment requirements are reduced for the prefabricated block solution, underwater installation accuracy and joint treatment rely heavily on strong construction organization capabilities and diving resources, which are also difficult to guarantee in some underdeveloped areas. Furthermore, some port waterways are narrow and shallow, making the towing or hoisting of large components significantly affected by wind, waves, and currents. This results in high construction risks, long construction periods, and a substantial increase in preparation time and construction costs, sometimes even making implementation impossible due to a lack of basic conditions.
[0005] Therefore, for regions with limited construction conditions, there is an urgent need for a gravity-type wharf structure and construction method that does not rely on large caisson prefabrication and specialized transportation and installation equipment. This structure should be able to utilize modular prefabricated components, be transported by conventional vessels, and be assembled on-site with relatively simple equipment. Simultaneously, it should utilize cofferdams and internal backfilling to form an integral structure that meets the load-bearing requirements of a gravity-type wharf. This would reduce dependence on site, ship and machinery equipment, and local construction capabilities, shorten the construction period, and improve the feasibility of the solution in underdeveloped regions and island environments. Summary of the Invention
[0006] One objective of this invention is to provide a gravity-type wharf structure that can be constructed using modular prefabricated components, transported by conventional vessels, and assembled on-site with relatively simple equipment. It can also utilize cofferdams and internal backfilling to form an overall structure that meets the stress requirements of a gravity-type wharf, thereby reducing dependence on site, ship and machinery equipment, and local construction capabilities, shortening the construction period, and improving the feasibility of the solution in underdeveloped areas and island environments.
[0007] To achieve these and other advantages according to the invention, in a first aspect, the invention provides a gravity-type wharf structure comprising a plurality of gravity units arranged side by side, the gravity units being situated on an underwater foundation, the upper parts of the gravity units being connected to a wharf surface layer, the gravity units comprising: a raft slab, horizontally arranged on the underwater foundation; a cofferdam body, disposed at the upper surface edge of the raft slab, the cofferdam body being composed of a plurality of precast pipe piles spaced apart and interlocking piles disposed between two adjacent precast pipe piles, the two sides of the interlocking piles respectively abutting the outer walls of two adjacent precast pipe piles, all the precast pipe piles and interlocking piles forming a continuous cofferdam body; bottom sealing concrete, poured into the cofferdam body and covering the upper surface of the raft slab; backfill, filling and compacting the cofferdam body above the bottom sealing concrete; and an internal support frame, arranged in multiple layers spaced apart along the height direction within the cofferdam body and embedded in the backfill.
[0008] Preferably, the upper surface edge of the raft slab is provided with upwardly protruding conical guide blocks at intervals, each conical guide block corresponding to a precast pipe pile. The outer diameter of the conical guide block gradually decreases from bottom to top, and its root outer diameter is adapted to the inner diameter of the precast pipe pile. The lower end of the precast pipe pile is sleeved on the conical guide block, and the bottom surface of the precast pipe pile rests on the raft slab. The inner cavity of the precast pipe pile is filled with pile core concrete, which covers the conical guide block and fixes the precast pipe pile to the raft slab.
[0009] Preferably, the interlocking pile is I-shaped and inserted between two adjacent precast pipe piles. The interlocking pile includes two parallel side plates and a steel web connecting the two side plates. The side plates extend along the axial direction of the precast pipe pile and have a length equal to that of the precast pipe pile. The two sides of the side plates are respectively attached to the outer walls of the two adjacent precast pipe piles. The two side plates and the outer walls of the two adjacent precast pipe piles (2) together form a casting cavity, in which interlocking concrete is cast.
[0010] Preferably, the upper surface of the raft slab is provided with an upwardly protruding upturned lattice beam on the inner side of the cofferdam body, and the top surface of the bottom sealing concrete is higher than the top surface of the upturned lattice beam.
[0011] Preferably, the backfill body comprises, from bottom to top, a gravel drainage layer, a sand filter layer, and several sand filling layers. The sand filter layer and the sand filling layers are flat and compacted. The internal support frame is a concrete structure. Each layer of the internal support frame is cast on the upper surface of the flat and compacted sand filter layer or sand filling layer and is covered by the backfill body above.
[0012] Preferably, the internal support frame includes multiple prefabricated lattice frames, which are arranged in a matrix and placed on the upper surface of a leveled and compacted sand filter layer or sand fill layer. Each prefabricated lattice frame is a closed frame, and a casting space is formed between adjacent prefabricated lattice frames and between the prefabricated lattice frames and the inner wall of the cofferdam. An internal support steel cage is placed in the casting space, and the internal support frame is formed by pouring concrete in the casting space.
[0013] Preferably, a waterstop is provided at the joint between the cofferdam bodies of two adjacent gravity units. The waterstop is provided along the height direction of the cofferdam body to seal the gap between the adjacent cofferdam bodies.
[0014] Secondly, the present invention provides a construction method for a gravity-type wharf, applicable to the aforementioned gravity-type wharf, comprising the following steps: S1. Prefabricate raft slabs and prefabricated pipe piles, and level the underwater foundation bed at the construction site to complete the foundation bed construction; S2. Hoist the raft deck into the underwater foundation and position and level it. S3. Around the edge of the raft slab, the precast pipe piles are vertically positioned and lowered onto the raft slab in sequence, and temporarily fixed. S4. Construct interlocking piles between adjacent precast pipe piles so that all the precast pipe piles are connected by the interlocking piles to form a continuous wall, forming a watertight cofferdam. S5. Underwater concrete is poured at the bottom inner side of the cofferdam to form bottom sealing concrete. S6. After the bottom sealing concrete has solidified, drain the water inside the cofferdam to create a dry working environment. S7. Fill and compact the soil in layers within the cofferdam. After each layer of soil is filled and compacted, construct an inner support frame on the surface of the soil layer. Once the strength of the inner support frame meets the standard, continue the construction of the upper soil and the inner support frame. Continue this alternating construction layer by layer until the soil fills the cofferdam and forms a complete gravity unit. S8. After all gravity units are completed, the construction of the upper wharf surface layer is completed.
[0015] Preferably, in step S7, a gravel drainage layer is first laid at the bottom of the cofferdam, and drainage pipes are buried in the gravel drainage layer; during the subsequent layered filling of the backfill and construction of the internal support frame, drainage is continuously carried out through the drainage pipes so that the water level in the cofferdam is not higher than the upper surface of the gravel drainage layer.
[0016] Preferably, after step S7 is completed, the grouting pipe is lowered from above the backfill body so that the opening of the grouting pipe extends into the crushed stone drainage layer, and grout is injected into the crushed stone drainage layer (6) through the grouting pipe to seal the crushed stone drainage layer.
[0017] The present invention has at least the following beneficial effects: First, compared with large caisson gravity wharves, this invention breaks down the gravity unit into modular components such as raft slabs, precast pipe piles, interlocking piles, bottom sealing concrete, backfill, and internal support frames. Each component can be prefabricated in advance and transported to the construction site by conventional ships. On-site, only assembly, pouring, and filling are required in sequence. There is no need to set up a large caisson prefabrication yard and special transportation and towing equipment, which greatly reduces construction costs and site requirements, and makes construction organization more flexible and convenient.
[0018] Secondly, compared with the precast block gravity wharf, the present invention forms a continuous closed cofferdam wall by bonding precast pipe piles and interlocking piles, and forms an integral load-bearing structure together with bottom sealing concrete and internal backfill. The structural integrity and water-stopping performance are significantly improved, avoiding a large number of precast blocks for underwater hoisting and joint treatment, resulting in higher construction efficiency and better anti-seepage and anti-sliding stability.
[0019] Other advantages, objectives and features of the present invention will become apparent in part from the following description, and in part from those skilled in the art through study and practice of the invention. Attached Figure Description
[0020] Figure 1 This is a schematic diagram of a gravity unit according to the present invention; Figure 2 This is a schematic diagram of the interior of the cofferdam body in one technical solution of the present invention; Figure 3 This is a schematic diagram of the cross-section of the cofferdam body in one technical solution of the present invention; Figure 4 This is a schematic diagram of the interlocking post in one technical solution of the present invention; Figure 5 This is a schematic diagram of the construction process of the cofferdam in one technical solution of the present invention; Figure 6 This is a schematic diagram of the installation of precast pipe piles in one technical solution of the present invention; Figure 7 This is a schematic diagram of the construction of the internal support frame in one technical solution of the present invention; Figure 8 This is a schematic diagram of the layered backfill in one technical solution of the present invention.
[0021] Attached reference numerals: 1-raft slab, 11-upward lattice beam, 12-reserved reinforcement, 13-conical guide block, 2-precast pipe pile, 21-pile core concrete, 3-interlocking pile, 31-side plate, 32-steel web, 33-interlocking concrete, 4-internal support frame, 41-precast lattice frame, 42-internal support steel cage, 5-bottom sealing concrete, 6-gravel drainage layer, 7-sand filter layer, 8-sand filling layer, 9-grouting pipe. Detailed Implementation
[0022] The present invention will now be described in further detail with reference to the accompanying drawings and specific embodiments, so that those skilled in the art can implement it based on the description.
[0023] It should be understood that terms such as “having,” “comprising,” and “including” as used herein do not exclude the presence or addition of one or more other elements or combinations thereof.
[0024] It should be noted that, unless otherwise specified, the experimental methods described in the following embodiments are conventional methods, and the structures and components described are commercially available. In the description of this invention, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "setting" should be interpreted broadly. For example, they can refer to fixed connection or setting, detachable connection or setting, or integral connection or setting. Those skilled in the art can understand the specific meaning of the above terms in this invention based on the specific circumstances. The terms "lateral," "longitudinal," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this invention and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this invention.
[0025] like Figures 1-8 As shown, the present invention provides a gravity-type wharf structure, comprising several gravity units arranged side by side, the gravity units being seated on an underwater foundation, and the upper part of the gravity units being connected to a wharf surface layer. Each gravity unit includes: A raft 1 is horizontally placed on an underwater foundation. A cofferdam is located at the upper edge of the raft 1. The cofferdam consists of several precast pipe piles 2 spaced apart and interlocking piles 3 placed between two adjacent precast pipe piles 2. The two sides of the interlocking piles 3 are respectively attached to the outer walls of the two adjacent precast pipe piles 2. All the precast pipe piles and interlocking piles form a continuous cofferdam. A bottom sealing concrete 5 is poured into the cofferdam and covers the upper surface of the raft 1. Backfill is filled and compacted in the cofferdam above the bottom sealing concrete 5. An internal support frame 4 is arranged in multiple layers along the height direction in the cofferdam and buried in the backfill.
[0026] Raft slab 1 is horizontally positioned on the underwater foundation, serving as the bottom load-bearing structure of the entire gravity unit. Raft slab 1 can be precast with reinforced concrete, and its planar shape is determined according to the wharf's segmentation and stress requirements; it can be rectangular or polygonal. The bottom surface of raft slab 1 is in direct contact with the underwater foundation, which is pre-leveled and compacted to ensure uniform stress distribution on raft slab 1. The thickness and reinforcement of raft slab 1 are determined based on the design load, generally ranging from 0.8 meters to 2.0 meters. Lifting components and connectors can be pre-embedded within raft slab 1 to facilitate lifting on the water and connection to the superstructure.
[0027] The cofferdam is located at the upper edge of the raft foundation 1, arranged around its perimeter to form a closed or nearly closed water-retaining wall. The cofferdam consists of several precast pipe piles 2 spaced apart and interlocking piles 3 positioned between adjacent precast pipe piles 2. The precast pipe piles 2 can be steel pipe piles, prestressed concrete pipe piles, or steel-concrete composite pipe piles, with a circular outer contour. The pile diameter and wall thickness are determined based on the lateral water pressure and fill height. The precast pipe piles 2 are vertically positioned, with their bottoms resting on the raft foundation 1. Positioning and connection can be achieved by pre-reserving positioning grooves, inserting reinforcing bars, or embedding steel plates on the raft foundation 1. A water-stopping structure can be installed between the bottom of the precast pipe piles 2 and the raft foundation 1, such as laying water-swellable water-stopping strips or injecting sealing material at the contact surface to prevent bottom leakage. The spacing between adjacent precast pipe piles 2 is determined based on the width of the interlocking piles 3 and the water-stopping requirements, generally controlled between 0.5 meters and 1.5 meters. The precast pipe piles 2 are processed and formed in the factory, transported to the site, and then hoisted into place by lifting equipment.
[0028] Interlocking piles 3 are installed between two adjacent precast pipe piles 2, with their sides respectively abutting the outer walls of the two adjacent precast pipe piles 2 to form a continuous cofferdam wall. Interlocking piles 3 can be formed by combining steel components with cast-in-place concrete, or by assembling precast concrete components. In one embodiment, the interlocking pile 3 uses steel side plates 31 and steel web plates 32 to form an I-shaped frame. The side plates 31 abut the outer walls of the precast pipe piles 2, and the steel web plates 32 are located in the middle to provide tension. Then, concrete is poured into the casting cavity formed by the two side plates 31 and the outer walls of the adjacent precast pipe piles 2, connecting the adjacent precast pipe piles 2 into a whole. The length of the interlocking pile 3 is equal to the length of the precast pipe pile 2 to ensure continuous closure throughout the entire height of the cofferdam. Sealing strips or waterproofing materials can be applied to the mating surfaces between the interlocking pile 3 and the precast pipe pile 2 to improve the watertightness of the cofferdam. By alternating the arrangement of precast pipe piles 2 and interlocking piles 3, the cofferdam body forms a continuous vertical wall that can withstand the water and soil pressure from the outside and prevent external water from entering the interior of the cofferdam body.
[0029] The bottom sealing concrete 5 is poured at the bottom of the cofferdam body, covering the upper surface of the raft slab 1 and connecting to the inner wall of the cofferdam body. The bottom sealing concrete 5 is constructed using underwater casting technology after the cofferdam body is formed. The thickness of the bottom sealing concrete 5 can be controlled between 0.5 and 1.5 meters, specifically determined based on the head difference and the stress on the bottom slab. At the contact surfaces of the bottom sealing concrete 5 with the raft slab 1, precast pipe piles 2, and interlocking piles 3, the connection strength can be improved by setting shear keys, pre-embedded reinforcement, or roughening the surface. The function of the bottom sealing concrete 5 is to seal the bottom of the cofferdam body, preventing external water from flowing in from the bottom, and connecting the bottom of the cofferdam body to the raft slab 1 as a whole, providing dry working conditions for subsequent drainage and backfilling construction. The top surface of the bottom sealing concrete 5 should be higher than any possible leakage channels at the bottom of the cofferdam body, forming a smooth construction surface.
[0030] The backfill material is filled and compacted within the cofferdam body above the bottom sealing concrete 5. The backfill material serves as the ballast material for the entire gravity wharf structure, providing anti-sliding and anti-overturning capabilities based on its own weight. The backfill material can be sandy soil, crushed stone, graded gravel, or quarried stone, depending on local material availability and design requirements. The backfill material must be filled and compacted in layers, with each layer controlled to a thickness of 0.3–1.5 meters. Compaction is performed using a small vibratory roller, plate compactor, or frog-type rammer, ensuring the compaction degree meets design requirements, typically not less than 90%. After the backfill material is filled, a dense soil mass forms inside the cofferdam body, which, together with the cofferdam body, bottom sealing concrete, and raft foundation, constitutes the gravity structure.
[0031] The internal support frame 4 is arranged in multiple layers along the height direction within the cofferdam body and embedded in the backfill. The main function of the internal support frame 4 is to constrain the deformation of the cofferdam body under the lateral pressure of the backfill, thereby improving the overall rigidity of the cofferdam body. The internal support frame 4 can be a reinforced concrete beam, a steel frame, or a steel-concrete composite structure, and its planar shape is adapted to the internal space of the cofferdam body. In this embodiment, the internal support frame 4 adopts a cast-in-place reinforced concrete structure. Each layer of the internal support frame 4 is poured after the backfill surface at the corresponding elevation has been compacted. During concrete pouring, it adheres to the inner wall of the cofferdam body, forming a horizontal support relationship between the internal support frame 4 and the cofferdam body. The spacing between the layers of the internal support frame 4 is determined based on the backfill height and the stress calculation of the cofferdam body, and can be controlled between 2 and 6 meters. The cross-sectional dimensions and reinforcement of the internal support frame 4 are determined based on the horizontal load, and the width can be controlled between 0.3 meters and 0.8 meters. Through the combined action of the multi-layered internal support frame 4 and the backfill, the cofferdam can remain stable under the action of backfill and external water pressure, and the entire gravity unit forms a structure with sufficient rigidity and load-bearing capacity.
[0032] Multiple gravity units are arranged side by side, with the cofferdam bodies of adjacent gravity units connected together. Waterstops or sealing materials can be installed at the joints to prevent seawater from seeping in between the units. The upper part of each gravity unit is connected to a wharf surface layer, which can be paved with cast-in-place reinforced concrete slabs or precast slabs, upon which mooring bollards, fenders, and other wharf ancillary facilities are installed. The wharf surface layer connects the gravity units into a whole, coordinating deformation between the units and ensuring the overall structural integrity of the wharf. Through this structure, the present invention utilizes modular precast raft slabs, precast pipe piles, and interlocking piles to form a cofferdam body. Then, through the combined action of bottom sealing concrete, backfill, and internal support frames, an integral structure with the structural integrity of a gravity-type wharf is formed, eliminating the need for large caissons and reducing construction equipment and site requirements.
[0033] In another technical solution, conical guide blocks 13 with upward protrusions are provided at intervals on the upper surface edge of the raft slab 1. Each conical guide block 13 corresponds to a precast pipe pile 2. The outer diameter of the conical guide block 13 gradually decreases from bottom to top, and its root outer diameter is adapted to the inner diameter of the precast pipe pile 2. The lower end of the precast pipe pile 2 is sleeved on the conical guide block 13, and the bottom surface of the precast pipe pile 2 rests on the raft slab 1. The inner cavity of the precast pipe pile 2 is filled with pile core concrete 21, which covers the conical guide block 13 and fixes the precast pipe pile 2 to the raft slab 1.
[0034] The conical guide block 13 consists of a lower columnar end and an upper conical end. The columnar end connects to the raft slab 1 and extends upwards, while the conical end is located above the columnar end. Its outer diameter gradually decreases from bottom to top, and the outer diameter at the root matches the inner diameter of the precast pipe pile 2. During the prefabrication stage of casting the raft slab 1 on land, pre-embedded reinforcing bars 12 extending upwards are first embedded at corresponding positions. Due to the positioning error of the formwork, the actual position of the pre-embedded reinforcing bars 12 may deviate. Therefore, after the raft slab 1 is cast and before it is installed in the water, the upper surface of the raft slab 1 is precisely laid out on land. Using the pre-embedded reinforcing bars 12 as the connecting foundation, a custom conical template is erected, and concrete is poured a second time to form the conical guide block 13. The secondary pouring on land can eliminate the influence of the positional deviation of the pre-embedded reinforcing bars 12, ensuring that the conical guide block 13 corresponds precisely to the precast pipe pile 2.
[0035] The function of the conical guide block 13 is to provide installation positioning and temporary fixation for the precast pipe pile 2. When the precast pipe pile 2 is hoisted into position in the water, it is difficult to make precise horizontal adjustments to the lower end of the precast pipe pile 2 due to the buoyancy of the water, the action of water flow, and the swaying of the lifting equipment. The conical guide block 13, with its tapered end being smaller at the top and larger at the bottom, has a guiding function. When the precast pipe pile 2 is lowered, its lower end is roughly aligned with the upper part of the conical guide block 13, and the inner wall of the precast pipe pile 2 can slide along the outer surface of the conical end and be centered, reducing the difficulty of positioning in the water. After the lower end of the precast pipe pile 2 is fitted onto the cylindrical end of the conical guide block 13, the bottom surface of the precast pipe pile 2 sits on the raft slab 1. The cylindrical end restricts the horizontal displacement of the pipe pile, so that the precast pipe pile 2 obtains temporary stability before the core concrete 21 is poured, without the need for additional complex underwater temporary fixing devices. Subsequently, core concrete 21 is poured into the inner cavity of the precast pipe pile 2. The core concrete 21 fills the inner cavity of the pipe pile and covers the conical guide block 13, thus fixing the precast pipe pile 2 and the raft slab 1 into a whole. This avoids the construction difficulties of post-installing reinforcement on the raft slab 1 and ensures the installation accuracy and connection reliability of the pipe pile.
[0036] In another technical solution, the interlocking pile 3 is I-shaped and inserted between two adjacent precast pipe piles 2. The interlocking pile 3 includes two parallel side plates 31 and a steel web 32 connected between the two side plates 31. The side plates 31 extend along the axial direction of the precast pipe pile 2 and have the same length as the precast pipe pile 2. The two sides of the side plates 31 are respectively attached to the outer walls of the two adjacent precast pipe piles 2. The two side plates 31 and the outer walls of the two adjacent precast pipe piles 2 together form a casting cavity. The interlocking concrete 33 is cast into the casting cavity.
[0037] The interlocking pile 3 is I-shaped and inserted between two adjacent precast pipe piles 2 to seal the gap between adjacent pipe piles and transmit horizontal force. The interlocking pile 3 includes two parallel side plates 31 and a steel web 32 connecting the two side plates 31. The steel web 32 is arranged along the longitudinal length of the interlocking pile 3, and its two sides are welded to the inner surfaces of the two side plates 31 or fixed by connectors, so that the two side plates 31 remain parallel and form an I-shaped cross section with the steel web 32. Multiple through holes are opened on the steel web 32, which can be arranged at intervals along the vertical and longitudinal directions of the steel web 32. The hole diameter and hole spacing are determined according to the stress and concrete flow requirements. After the through hole is opened, the steel web 32 can still provide tension to the two side plates 31, ensuring the overall shape stability of the interlocking pile 3 during hoisting, transportation and installation, and preventing the side plates 31 from deforming outward or inward. On the other hand, when pouring the interlocking concrete 33, the concrete can pass through the through hole, so that the concrete on both sides of the steel web 32 is connected to each other and forms a whole. At the same time, the steel web 32 is embedded in the concrete, which is equivalent to increasing the steel ratio of the interlocking concrete 33 and improving the bending and shear bearing capacity of the interlocking pile 3.
[0038] Side plate 31 extends axially along the precast pipe pile 2, with a length equal to that of the precast pipe pile 2. Side plate 31 can be made directly from steel plates as the load-bearing skeleton, or it can be formed by pouring concrete into both sides of the steel web plate 32 using formwork to create a reinforced concrete side plate 31. In the latter case, the edges of the steel web plate 32 are embedded in the concrete of the side plate 31, making the steel web plate 32 and the side plate 31 an integral unit. The entire interlocking pile 3 can be transported to the site as a precast component, reducing underwater operations. The two sides of side plate 31 are respectively fitted to the outer walls of two adjacent precast pipe piles 2. To enhance the water-stopping effect of the fitting surface, rubber waterstop strips can be pre-installed on the sides of side plate 31, extending along the length of side plate 31. When the interlocking pile 3 is inserted between two adjacent precast pipe piles 2, the rubber waterstop strips are compressed and deformed, filling the tiny gaps between the side plate 31 and the outer walls of the precast pipe piles 2, improving the watertightness of the cofferdam.
[0039] The two side plates 31, together with the outer walls of the two adjacent precast pipe piles 2, form a casting cavity, into which interlocking concrete 33 is poured. The interlocking concrete 33 is made of micro-expansion concrete, utilizing its micro-expansion during hardening to compensate for concrete shrinkage. This ensures that the interlocking concrete 33 is in close contact with the outer wall of the precast pipe pile 2, the side plates 31, and the steel web 32, preventing gaps caused by shrinkage and improving the connection strength and water-stopping effect between the interlocking pile 3 and the precast pipe pile 2. During pouring, the concrete can be poured from the top of the casting cavity, using underwater pouring or non-drainage pouring techniques to ensure that the interlocking concrete 33 fills the entire cavity and forms a dense structure. Through this construction, the interlocking pile 3 and the precast pipe pile 2 together form a continuous, closed cofferdam wall with good load-bearing and water-stopping properties.
[0040] In another technical solution, the upper surface of the raft slab 1 is provided with an upwardly protruding upward grid beam 11 on the inner side of the cofferdam body, and the top surface of the bottom sealing concrete 5 is higher than the top surface of the upward grid beam 11.
[0041] The upward-turning lattice beams 11 are integrally cast with the raft slab 1 during the prefabrication stage, or they can be formed through secondary casting after the raft slab 1 is cast. The upward-turning lattice beams 11 are arranged longitudinally and transversely along the bottom perimeter and interior of the cofferdam body, forming a lattice-like load-bearing skeleton. After dewatering within the cofferdam body, the bottom surface of the raft slab 1 bears the subgrade reaction force, while the top surface bears the water pressure, backfill load, and vertical force transmitted from the superstructure. The slab is under bending and punching shear stress. The upward-turning lattice beams 11 improve the cross-sectional stiffness and bending resistance of the raft slab 1 in the inner region of the cofferdam body, distributing local loads over a wider area, preventing cracking of the raft slab 1 due to excessive stress during dewatering and subsequent backfilling, and strengthening the connection between the bottom sealing concrete 5 and the raft slab 1. The bottom sealing concrete 5 is constructed using an underwater casting process. During casting, concrete is transported to the bottom of the cofferdam body using a duct or pump pipe, and the concrete fills the inner bottom space of the cofferdam body through its flow and self-weight. Underwater concrete should possess good fluidity and anti-dispersion properties. Underwater non-dispersible concrete or anti-dispersion agents can be used to ensure no significant segregation occurs during underwater pouring. Pouring should be continuous, with controlled pouring speed. The concrete's pushing action should displace accumulated water and laitance at the bottom, ensuring close contact between the bottom sealing concrete 5 and the upper surface of the raft slab 1, the upward-turning lattice beam 11, and the inner wall of the cofferdam, forming a dense, void-free sealing layer. Due to underwater pouring limitations, the upper surface of the bottom sealing concrete 5 does not require complete flatness; some height difference and local unevenness are permissible, but the lowest point must still be higher than the top surface of the upward-turning lattice beam 11, ensuring complete coverage of the beam. After the bottom sealing concrete 5 has cured to its design strength, its surface can be simply leveled or used directly as the base for backfilling. Through this structure, the upward-turning lattice beam 11 and the bottom sealing concrete 5 work together to improve the overall stiffness and crack resistance of the bottom area of the cofferdam, providing a reliable foundation for subsequent drainage and backfilling construction.
[0042] In another technical solution, the backfill body includes, from bottom to top, a gravel drainage layer 6, a sand filter layer 7, and several sand filling layers 8. The sand filter layer 7 and the sand filling layers 8 are both flat and compacted. The internal support frame 4 is a concrete structure. Each layer of the internal support frame 4 is poured on the upper surface of the flat and compacted sand filter layer 7 or sand filling layer 8 and is covered by the backfill body above.
[0043] The crushed stone drainage layer 6 is laid on top of the bottom sealing concrete 5. It uses graded crushed stone or pebbles with a particle size range of 20 mm to 80 mm and a mud content preferably controlled below 5% to ensure smooth drainage. The thickness of the crushed stone drainage layer 6 is determined according to drainage requirements and seepage during construction, and can be 30 to 50 cm. During construction, the crushed stone drainage layer 6 collects and drains water accumulated in the cofferdam body due to seepage from the bottom sealing concrete 5 or water content in the backfill, ensuring that the upper backfill construction is always in a dry working state.
[0044] A sand filter layer 7 is laid on top of the gravel drainage layer 6, using coarse sand, gravelly sand, or a mixture of sand and gravel. The function of the sand filter layer 7 is to prevent fine particles from the sand filling layer 8 above from entering the gravel drainage layer 6 under the action of water flow, avoiding piping or loss of fine particles, while ensuring that seepage water can smoothly pass through the filter layer and drain into the gravel drainage layer 6. The thickness of the sand filter layer 7 can be 30-50 cm. After laying, it needs to be leveled and compacted to form a flat and dense working surface.
[0045] The sand fill layer 8 is located above the sand filter layer 7 and is laid in several layers according to the depth of the cofferdam. The sand fill layer 8 can be made of sandy soil, graded gravel, or crushed stone, with a maximum particle size not exceeding 100 mm and a mud content controlled within a certain range to ensure compaction. The sand fill layer 8 is compacted using a small vibratory roller, plate rammer, or frog-type rammer, and the compaction degree should meet the design requirements. After each sand fill layer 8 is compacted, the surface needs to be leveled to facilitate the subsequent construction of the internal support frame 4.
[0046] The inner support frame 4 is a concrete structure, with each layer of inner support frame 4 cast on the upper surface of the leveled and compacted sand filter layer 7 or sand fill layer 8. The bottom surface of the inner support frame 4 contacts the upper surface of the soil layer below, relying on the soil layer to provide uniform support, and laterally adheres to the inner wall of the cofferdam, forming a horizontal support system. After the inner support frame 4 is cast, its top surface is covered by the upper fill, so that the inner support frame 4 is embedded in the fill and works together with the fill. Through the above-mentioned bottom-up layered construction of the fill, the interior of the cofferdam not only meets the drainage requirements during construction, but also ensures the compactness and filter performance of the fill, providing a flat and stable working surface for the layered construction of the inner support frame 4, and also making the entire gravity unit form a stable overall load-bearing structure.
[0047] In another technical solution, the internal support frame 4 includes multiple prefabricated lattice frames 41, which are arranged in a matrix and placed on the upper surface of the leveled and compacted sand filter layer 7 or sand filling layer 8. Each prefabricated lattice frame 41 is a closed frame on all four sides. A casting space is formed between adjacent prefabricated lattice frames 41 and between the prefabricated lattice frames 41 and the inner wall of the cofferdam. An internal support steel cage 42 is placed in the casting space, and the internal support frame 4 is formed by pouring concrete in the casting space.
[0048] The precast lattice frame 41 is a closed frame structure that can be prefabricated using reinforced concrete or steel-concrete composite in a land-based prefabrication yard or factory, and then transported to the construction site by conventional ships or land transport. The planar dimensions of the precast lattice frame 41 are determined based on the internal space of the cofferdam and the grid division of the inner support frame 4. Typically, the side length of each precast lattice frame 41 can be controlled between 1 and 3 meters, and the height matches the thickness of a single layer of inner support frame 4 to facilitate hoisting and installation. The wall thickness and reinforcement of the precast lattice frame 41 should meet the rigidity and strength requirements during transportation, hoisting, and as a formwork for concrete pouring.
[0049] After the precast lattice frame 41 is hoisted into the cofferdam body, it is placed piece by piece on the upper surface of the leveled and compacted sand filter layer 7 or sand fill layer 8. Since the sand filter layer 7 and sand fill layer 8 have been compacted and leveled, their surfaces are relatively flat and dense, providing stable support for the precast lattice frame 41. To prevent grout from leaking between the bottom of the precast lattice frame 41 and the soil layer during subsequent concrete pouring, cement mortar can be applied along the junction of the bottom edge of the precast lattice frame 41 and the soil surface after it is placed in position to seal the bottom of the pouring space. For areas with uneven bottoms, a thin layer of sand or mortar can be laid first to level the surface before placing the precast lattice frame 41, ensuring close contact between the bottom of the frame and the soil layer.
[0050] After multiple precast lattice frames 41 are arranged in a matrix, strip-shaped casting spaces are formed between adjacent precast lattice frames 41, while a continuous casting space is also formed between the outermost precast lattice frame 41 and the inner wall of the cofferdam. These casting spaces are interconnected, forming the planar lattice shape of the inner support frame 4. The spacing between the precast lattice frames 41 can be determined according to the beam width requirements of the inner support frame 4. The spacing between the precast lattice frames 41 and the inner wall of the cofferdam can be appropriately increased to ensure that a ring structure that fits tightly with the cofferdam body can be formed after the concrete is poured. The casting space is laterally enclosed by the frame walls of the precast lattice frames 41 or the inner wall of the cofferdam, and is open at the top to facilitate the placement of the reinforcing cage and the pouring of concrete.
[0051] An internal support steel cage 42 is placed within the pouring space. The internal support steel cage 42 is constructed by binding or welding longitudinal steel bars and stirrups, and its length and cross-sectional dimensions are adapted to the pouring space. The internal support steel cage 42 can be pre-assembled on land and hoisted into the pouring space as a whole, or it can be bound on-site within the pouring space. The diameter and spacing of the steel bars in the internal support steel cage 42 are determined based on the stress calculations of the internal support frame 4. After the internal support steel cage 42 is placed, concrete is poured into the pouring space. Ordinary C25 to C40 concrete can be used. After compaction, the internal support frame 4 is formed. Since the frame walls of the precast lattice frame 41 can also serve as concrete formwork, no additional formwork is required, simplifying construction. Furthermore, after the concrete hardens, it integrates seamlessly with the precast lattice frame 41.
[0052] The inner support frame 4, in plan view, comprises an outer ring structure connected to the inner wall of the cofferdam, and internally interwoven frame beams. The outer ring structure is cast along the entire length of the inner wall of the cofferdam, tightly fitting the inner walls of the precast pipe piles 2 and interlocking piles 3, forming a closed horizontal support ring that can evenly transfer the lateral forces on the cofferdam to the internal frame beams. The internal frame beams are composed of cast-in-place concrete beams between adjacent precast lattice frames 41, forming a whole with the outer ring structure, creating a lattice-like force system. In this way, the inner support frame 4 not only acts as a horizontal support to constrain the deformation of the cofferdam, but also divides the backfill into several blocks through the frame beams, improving the interlocking effect between the backfill and the inner support frame 4, allowing the inner support frame 4 and the backfill to work together, enhancing the integrity and stiffness of the entire gravity unit.
[0053] In another technical solution, a waterstop is installed at the joint between the cofferdam bodies of two adjacent gravity units. The waterstop runs the entire length of the cofferdam body along its height to seal the gap between adjacent cofferdam bodies. The installation method of this waterstop can refer to the water-stopping method between adjacent caissons in a caisson-type gravity wharf. Specifically, the waterstop can be made of rubber, water-swellable strips, or composite waterstop materials, and is pre-fixed at the joint position of the two adjacent gravity units during the prefabrication or on-site installation stage of the cofferdam body. The waterstop extends vertically from the bottom to the top of the cofferdam body, forming a continuous sealing path. Relying on the mutual compression of the cofferdam bodies after installation or the pressure of subsequent sealing materials, the waterstop adheres tightly to the outer wall of the cofferdam body, preventing external water from seeping into the wharf structure through the gap between the units. Crushed stone or sealing materials can also be filled outside the waterstop between adjacent gravity units as needed to further improve the watertightness and overall stability of the joint.
[0054] In another technical solution, a construction method for a gravity wharf structure is provided, which is applied to the aforementioned gravity wharf structure; S1. Prefabricate raft slab 1 and prefabricated pipe piles 2, and level the underwater foundation bed on site to complete the foundation bed construction. Raft slab 1 can be integrally cast with reinforced concrete. Formwork is made according to the design dimensions and reinforcement requirements. After tying the reinforcing bars, concrete is poured and cured to the design strength before demolding. Prefabricated pipe piles 2 can be formed using centrifugal casting or vertical casting methods. The pile body should ensure that the roundness and verticality meet the design requirements. Underwater foundation bed leveling can be done by paving with rubble or crushed stone, followed by work by divers or a leveling vessel. The elevation and flatness of the foundation bed surface should meet the installation requirements of raft slab 1, and the height difference should be controlled within the allowable range specified in the code to ensure uniform stress on raft slab 1. After the foundation bed construction is completed, surveyors will verify the elevation and planar position of the top surface of the foundation bed.
[0055] S2. Raft slab 1 is hoisted and lowered onto the underwater foundation bed, and its positioning and leveling are performed. After the strength acceptance test of raft slab 1 is completed at the prefabrication yard, it is hoisted into the water by a crane vessel or a large crawler crane in conjunction with a barge. Before hoisting, hoisting points are set on raft slab 1, and the positions of the hoisting points are determined according to the dimensions and center of gravity of raft slab 1. During the lowering process, the levelness of raft slab 1 is controlled to avoid one side touching the bottom first and causing deviation. After raft slab 1 is placed on the foundation bed, divers check the contact between the bottom surface and the foundation bed. If there are gaps in some areas, they can be treated by grouting or filling with sand and gravel. During positioning and leveling, the pre-embedded measuring marks on raft slab 1 can be used to verify its planar position and elevation by surveyors. If necessary, fine adjustments can be made by adjusting the local elevation of the foundation bed or adding a thin layer of sand and gravel to make raft slab 1 reach the design position.
[0056] S3. Around the edge of the raft slab 1, vertically position and lower the precast pipe piles 2 onto the raft slab 1, and temporarily fix them. The precast pipe piles 2 are hoisted using lifting equipment on a crane barge or gantry. Before hoisting, a lifting device is set on the upper end of the pipe pile to keep it vertical. During hoisting, proceed sequentially according to the positions marked on the raft slab 1. First, lower the precast pipe piles 2 to the edge of the upper surface of the raft slab 1, so that the lower end of the pipe pile aligns with the corresponding position on the raft slab 1. If the raft slab 1 is equipped with a conical guide block 13, then the lower end of the precast pipe pile 2 is fitted onto the conical guide block 13. The guiding action of the conical guide block 13 achieves automatic centering, and the bottom surface of the pipe pile sits on the raft slab 1, thus achieving initial positioning. For cases where the conical guide block 13 is not provided, a positioning ring or temporary guide frame can be preset on the raft slab 1 to assist in positioning. The temporary fixing measures should ensure that the horizontal and vertical deviations of the pipe pile meet the design requirements.
[0057] S4. Construct interlocking piles 3 between adjacent precast pipe piles 2, connecting all precast pipe piles 2 into a continuous wall through the interlocking piles 3, forming a watertight cofferdam. Specifically, after the precast pipe piles 2 are temporarily fixed on the raft slab 1, pour core concrete 21 into the inner cavity of each precast pipe pile 2. The core concrete 21 uses ordinary concrete or micro-expansion concrete of grade C30 or higher, and is poured from the top of the pipe pile through a guide pipe or bucket. The pouring speed is controlled during the pouring process, utilizing the concrete's own weight to fill the inner cavity of the pipe pile. If necessary, a vibrator is used to compact the concrete. The core concrete 21 fills the inner cavity of the pipe pile and covers the conical guide block 13, fixing the precast pipe pile 2 and the raft slab 1 into a whole, transforming the precast pipe pile 2 from a temporarily fixed state to a permanently connected state, providing a stable foundation for the subsequent insertion of the interlocking piles 3.
[0058] After the core concrete 21 has initially set, construction of the interlocking piles 3 begins. The interlocking piles 3 have been prefabricated on land, with two parallel side plates 31 and a steel web 32 connecting them, forming an I-shape. The length of the side plates 31 is equal to that of the prefabricated pipe piles 2, and the two sides of each side plate 31 extend along their length. During construction, the interlocking piles 3 are vertically inserted through the upper opening between two adjacent prefabricated pipe piles 2, so that the two side plates 31 are located on either side of the gap, with the sides of the side plates 31 fitting against the outer walls of the two prefabricated pipe piles 2. During lowering, a guiding device can be used to control the verticality and planar position of the interlocking piles 3. The rubber waterstop strips pre-installed on the edges of the side plates 31 deform under pressure when in contact with the outer wall of the pipe pile, filling the tiny gaps at the contact surface. After the interlocking pile 3 is lowered to the design elevation, its bottom surface can contact or maintain a slight gap with the upper surface of the raft slab 1. The two side plates 31 and the outer walls of the two adjacent precast pipe piles 2 together form a casting cavity. Then, micro-expansion concrete is poured into the casting cavity to form the interlocking concrete 33. The concrete is poured using the tremie pipe method or pumping method, with material being discharged from the top of the cavity. The pouring process is continuous, allowing the concrete to fill the entire cavity and pass through the through holes on the steel web 32, connecting the concrete on both sides of the steel web 32 into a whole. After the interlocking concrete 33 solidifies, the interlocking pile 3 and the two precast pipe piles 2 on both sides become a whole. After the construction of all the interlocking piles 3 is completed in sequence, the precast pipe piles 2 and the interlocking piles 3 are alternately connected to form a continuous closed cofferdam wall, which has the function of water and soil retention.
[0059] S5. Underwater concrete is poured at the bottom inner side of the cofferdam to form bottom sealing concrete 5. After the cofferdam is closed, the water on the outside is blocked, but leakage channels may still exist between the bottom and the raft slab 1. To seal the bottom, underwater non-dispersible concrete is used for bottom sealing. Before pouring, divers clean the bottom of the cofferdam, removing accumulated mud and debris. Concrete is transported to the bottom of the cofferdam through a pipe or pump pipe, with the pipe opening embedded in the poured concrete. The flow and displacement of the concrete are used to drain the water at the bottom. The pouring process is continuous, proceeding sequentially from one end to the other, ensuring that the bottom sealing concrete 5 covers the entire bottom area and is in close contact with the upper surface of the raft slab 1 and the inner wall of the cofferdam. The thickness of the bottom sealing concrete 5 should ensure that the lowest point is still higher than the design bottom sealing elevation. After pouring, it is cured to the design strength, and disturbance should be avoided during this period.
[0060] S6. After the bottom sealing concrete 5 has solidified, drain the water from the cofferdam body to create a dry working environment. Once the bottom sealing concrete 5 has reached its design strength, install a drainage pump inside the cofferdam to drain the internal water. During the drainage process, observe the deformation and leakage of the cofferdam body. If any abnormality is found, immediately stop the drainage and take appropriate measures. After drainage is completed, a dry working space is formed inside the cofferdam body, providing conditions for subsequent backfilling and internal support frame construction. Since the underwater-cast bottom sealing concrete 5 may experience localized leakage, a gravel drainage layer 6 can be laid at the bottom and continuously drained using drainage pipes to ensure that the internal water level remains below the upper surface of the gravel drainage layer 6 during construction.
[0061] S7. The fill soil is filled and compacted in layers within the cofferdam body. After each layer of fill soil is completed and compacted, an inner support frame 4 is constructed on the surface of the fill soil layer. After the strength of the inner support frame reaches the standard, the construction of the upper fill soil and the inner support frame 4 continues. The construction is carried out alternately layer by layer until the fill soil fills the cofferdam body and forms a complete gravity unit.
[0062] First, a crushed stone drainage layer 6 is laid on the bottom sealing concrete 5. The crushed stone drainage layer 6 uses graded crushed stone and is leveled after laying. Drainage pipes are embedded in the crushed stone drainage layer 6, and seepage water is continuously pumped out during construction to ensure that the internal water level does not exceed the upper surface of the crushed stone drainage layer 6. Then, a sand filter layer 7 is laid on top of the crushed stone drainage layer 6 and leveled and compacted. After the sand filter layer 7 is constructed, precast lattice frames 41 are placed on its upper surface in a matrix arrangement. The precast lattice frames 41 are closed frames on all four sides, and a pouring space is formed between adjacent precast lattice frames 41 and between the precast lattice frames 41 and the inner wall of the cofferdam. The inner support steel cage 42 is placed in the pouring space, and concrete is poured to form the first inner support frame 4. After the first inner support frame 4 has cured to a strength suitable for human habitation, a sand filling layer 8 is continued to be filled on top of it, and compacted using a small vibratory roller or plate tamper, with a compaction degree of not less than 90%. After each layer of sand fill 8 is completed, leveled, and compacted, the next internal support frame 4 is constructed on the surface of that layer, using the same construction method as the first internal support frame 4. This process of alternating construction of fill and internal support frames 4 continues upwards, until the fill reaches the designed top elevation of the cofferdam. The final internal support frame 4 is located within the uppermost layer of fill. After the fill construction is completed, the interior of the cofferdam is filled with dense fill and multiple layers of internal support frames 4, forming a complete gravity unit.
[0063] S8. After all gravity units are completed, the construction of the upper wharf surface layer is finished. The gravity units are arranged side-by-side with adjacent cofferdam bodies. After the construction of all gravity units is completed, the wharf surface layer is constructed on top of the cofferdam bodies and the top surface of the backfill. The wharf surface layer can be a cast-in-place reinforced concrete structure. First, the surface layer steel mesh is tied, then the concrete is poured and cured. The wharf surface layer connects the gravity units into a whole, coordinating the deformation between the units, and installing mooring bollards, fenders, and other wharf ancillary facilities on it. At this point, the construction of the gravity wharf structure is complete.
[0064] In another technical solution, in step S7, a gravel drainage layer 6 is first laid at the bottom of the cofferdam, and a drainage pipe is buried in the gravel drainage layer 6; during the subsequent layered filling of the backfill and construction of the internal support frame 4, drainage is continuously carried out through the drainage pipe so that the water level in the cofferdam is not higher than the upper surface of the gravel drainage layer 6.
[0065] During construction, after the bottom sealing concrete 5 reaches its design strength and drainage is completed, a crushed stone drainage layer 6 is laid on the upper surface of the bottom sealing concrete 5. The crushed stone drainage layer 6 uses well-graded crushed stone or pebbles, and its thickness is determined according to the seepage volume and drainage requirements. It is laid mechanically or manually and properly leveled to ensure a relatively flat surface for the subsequent laying of the sand filter layer 7. The crushed stone drainage layer 6 should cover the entire bottom area inside the cofferdam, with a certain gap between the edges and the inner wall of the cofferdam to prevent the crushed stone from directly pressing against the cofferdam body and causing localized stress concentration.
[0066] Simultaneously with or after the laying of the crushed stone drainage layer 6, drainage pipes are buried within it. The drainage pipes can be PVC, HDPE, or steel pipes, with the diameter determined based on the seepage volume and drainage capacity. The drainage pipes are arranged in a serpentine or ring-shaped pattern along the bottom of the cofferdam, with permeable holes spaced at intervals. These holes are typically 5 to 10 millimeters in diameter and covered with geotextile or a filter screen to prevent clogging by gravel or fine particles. One or more ends of the drainage pipes are led to an external or internal sump pit outside the cofferdam and connected to pumping equipment. If the internal space of the cofferdam is large, a sump pit can be installed, and the drainage pipes will flow into the sump pit before being pumped out to the outside of the cofferdam by a submersible pump or centrifugal pump.
[0067] After the initial laying is completed, the drainage system should be kept running continuously during the subsequent layered filling and construction of the internal support frame 4. Seepage water within the cofferdam should be continuously removed through drainage pipes. Pumping equipment should be selected based on the seepage volume and can be equipped with an automatic start / stop device. When the water level in the sump reaches a set height, drainage will automatically begin, ensuring that the water level within the cofferdam never exceeds the upper surface of the gravel drainage layer 6. During construction, the drainage pipes should be checked regularly for patency; any blockages should be cleared or replaced promptly to ensure the drainage system functions effectively. Continuous drainage keeps the sand filter layer 7 and sand filling layer 8 above the gravel drainage layer 6 in an unsaturated state, providing a dry working environment for layered filling and compaction and the concrete pouring of the internal support frame 4, preventing the quality of soil compaction and concrete construction from being affected by rising water levels.
[0068] In another technical solution, after step S7 is completed, the grouting pipe 9 is lowered from above the backfill body so that the opening of the grouting pipe 9 extends into the crushed stone drainage layer 6, and grout is injected into the crushed stone drainage layer 6 through the grouting pipe 9 to seal the crushed stone drainage layer 6.
[0069] During construction, the grouting pipe 9 can be pre-installed during the backfilling process, or it can be lowered into the backfill after drilling from the top of the backfill. When pre-installing the grouting pipe 9, it should be placed vertically or inclined at the predetermined position before the backfill reaches the gravel drainage layer 6. The bottom of the pipe should extend into the gravel drainage layer 6, and the upper end should be led above the surface of the backfill and protected with a temporary cover to prevent clogging of the pipe opening during backfilling and compaction. When using the post-drilling method, the borehole diameter should be slightly larger than the outer diameter of the grouting pipe 9. Verticality must be controlled during drilling to avoid damaging the already constructed internal support frame 4 and the backfill structure. The grouting pipe 9 can be made of steel, PVC, or composite pipe, with a diameter generally between 25 mm and 50 mm. Grout outlet holes are opened in the pipe wall, located within the section of the pipe extending into the gravel drainage layer 6. The pipe is protected with a filter screen or tape to prevent clogging by gravel during lowering.
[0070] The grouting material can be selected from cement grout, cement mortar, or grout mixed with admixtures such as bentonite and fly ash, depending on the sealing requirements. The water-cement ratio of cement grout is generally controlled between 0.6 and 1.0. The fineness modulus of sand in cement mortar should not be too high to ensure good fluidity and injectability of the grout, allowing it to penetrate the pores of the crushed stone drainage layer 6. If the pores of the crushed stone drainage layer 6 are large or the seepage is significant, an appropriate amount of quick-setting agent or expanding agent can be added to the grout to shorten the setting time, compensate for shrinkage, and improve the sealing effect. A grouting pump is used for grouting. The grouting pressure is determined based on the thickness of the fill and the permeability of the crushed stone drainage layer 6, generally controlled between 0.1 MPa and 0.5 MPa. During grouting, the pressure should be increased slowly to avoid excessive pressure causing the fill to lift, split, or the grout to leak out along the inner wall of the cofferdam.
[0071] The grouting sequence should proceed from one side of the gravel drainage layer 6 to the other, or from the lower to the higher points, allowing the grout to gradually fill the pores and drain accumulated water. During grouting, observe the changes in grouting pressure and volume. When the grouting pressure continuously increases, the grouting volume significantly decreases, or grout overflows from adjacent grouting pipe openings or at the junction of the gravel drainage layer 6 and the inner wall of the cofferdam, it indicates that the gravel drainage layer 6 in that area has been basically filled with grout, and grouting can be stopped for that pipe. For multiple grouting pipes 9, grouting should be done intermittently to avoid localized pressure concentration. After grouting is completed, clean the grouting pipes promptly, and seal or cut the upper opening of the grouting pipe 9 below the surface of the backfill. The pipe openings can be covered by the subsequent construction of the wharf surface layer. Through grouting sealing, the gravel drainage layer 6 transforms from a permeable layer into a low-permeability sealing layer, eliminating long-term leakage channels at the bottom of the cofferdam during its service life and restoring the overall seepage prevention performance of the structure.
[0072] It should be noted that although the steps are described in a specific order above, this does not mean that they must be performed in that order. In fact, some of these steps can be executed concurrently, or even in a different order, as long as the required functionality is achieved. The number of devices and processing scale described herein are for simplification of the invention; applications, modifications, and variations of this invention will be readily apparent to those skilled in the art.
[0073] Although embodiments of the present invention have been disclosed above, they are not limited to the applications listed in the specification and embodiments. They can be applied to various fields suitable for the present invention. For those skilled in the art, other modifications can be easily made. Therefore, without departing from the general concept defined by the claims and their equivalents, the present invention is not limited to the specific details and illustrations shown and described herein.
Claims
1. A gravity-type wharf structure, characterized in that, It includes several gravity units arranged side by side, the gravity units are placed on an underwater foundation, and the upper part of the gravity units are connected to the dock surface layer. The gravity unit includes: Raft (1) is horizontally placed on the underwater foundation; The cofferdam body is set at the upper surface edge of the raft (1). The cofferdam body is composed of a number of precast pipe piles (2) spaced apart and interlocking piles (3) set between two adjacent precast pipe piles (2). The two sides of the interlocking piles (3) are respectively attached to the outer walls of two adjacent precast pipe piles (2). All the precast pipe piles (2) and interlocking piles (3) form a continuous cofferdam body. Sealing concrete (5) is poured into the cofferdam body and covers the upper surface of the raft slab (1); The backfill material is filled and compacted within the cofferdam body above the bottom sealing concrete (5); The internal support frame (4) is arranged in multiple layers along the height direction within the cofferdam body and buried within the backfill.
2. The gravity-type wharf structure as described in claim 1, characterized in that, The upper surface edge of the raft slab (1) is provided with conical guide blocks (13) that protrude upwards at intervals. Each conical guide block (13) corresponds to a precast pipe pile (2). The outer diameter of the conical guide block (13) gradually decreases from bottom to top. The outer diameter of its root is adapted to the inner diameter of the precast pipe pile (2). The lower end of the precast pipe pile (2) is sleeved on the conical guide block (13), and the bottom surface of the precast pipe pile (2) sits on the raft slab (1). The inner cavity of the precast pipe pile (2) is filled with pile core concrete (21). The pile core concrete (21) covers the conical guide block (13) and fixes the precast pipe pile (2) to the raft slab (1).
3. The gravity-type wharf structure as described in claim 1, characterized in that, The interlocking pile (3) is I-shaped and inserted between two adjacent precast pipe piles (2). The interlocking pile (3) includes two parallel side plates (31) and a steel web plate (32) connecting the two side plates (31). The length of the side plate (31) is equal to that of the precast pipe pile (2). The two sides of the side plate (31) are respectively attached to the outer walls of the two adjacent precast pipe piles (2). The two side plates (31) and the outer walls of the two adjacent precast pipe piles (2) together form a casting cavity. The interlocking concrete (33) is cast in the casting cavity.
4. The gravity-type wharf structure as described in claim 1, characterized in that, The upper surface of the raft slab (1) is provided with an upwardly protruding upward grid beam (11) on the inner side of the cofferdam body, and the top surface of the bottom sealing concrete (5) is higher than the top surface of the upward grid beam (11).
5. The gravity-type wharf structure as described in claim 4, characterized in that, The backfill consists of a gravel drainage layer (6), a sand filter layer (7), and several sand filling layers (8) from bottom to top. The sand filter layer (7) and the sand filling layer (8) are flat and compacted. The inner support frame (4) is a concrete structure. Each layer of the inner support frame (4) is poured on the upper surface of the flat and compacted sand filter layer (7) or sand filling layer (8) and is covered by the backfill above.
6. The gravity-type wharf structure as described in claim 5, characterized in that, The internal support frame (4) includes multiple prefabricated lattice frames (41). The multiple prefabricated lattice frames (41) are arranged in a matrix and placed on the upper surface of the leveled and compacted sand filter layer (7) or sand filling layer (8). The prefabricated lattice frames (41) are enclosed frames on all four sides. A casting space is formed between adjacent prefabricated lattice frames (41) and between the prefabricated lattice frames (41) and the inner wall of the cofferdam. An internal support steel cage (42) is placed in the casting space. The internal support frame (4) is formed by pouring concrete in the casting space.
7. The gravity-type wharf structure as described in claim 1, characterized in that, A waterstop is provided at the joint between two adjacent cofferdam bodies. The waterstop is provided along the height of the cofferdam body to seal the gap between the adjacent cofferdam bodies.
8. A construction method for a gravity-type wharf structure, applicable to the gravity-type wharf structure as described in any one of claims 1 to 7; S1. Prefabricate raft slabs (1) and prefabricate pipe piles (2), and level the underwater foundation bed at the construction site to complete the foundation bed construction; S2. Hoist the raft (1) down onto the underwater foundation and position and level it. S3. Around the edge of the raft slab (1), the precast pipe piles (2) are vertically positioned and lowered onto the raft slab (1) in sequence, and temporarily fixed. S4. Construct interlocking piles (3) between adjacent precast pipe piles (2) so that all the precast pipe piles (2) are connected into a continuous wall through the interlocking piles (3) to form a watertight cofferdam. S5. Underwater concrete is poured at the bottom inner side of the cofferdam to form bottom sealing concrete (5); S6. After the bottom sealing concrete (5) has solidified, drain the water inside the cofferdam to form a dry working environment. S7. Fill and compact the soil in layers within the cofferdam. After each layer of soil is filled and compacted, construct an inner support frame (4) on the surface of the soil layer. After the strength of the inner support frame (4) reaches the standard, continue the construction of the upper soil and the inner support frame (4). Continue the construction layer by layer until the soil fills the cofferdam and forms a complete gravity unit. S8. After all gravity units are completed, the construction of the upper wharf surface layer is completed.
9. The construction method for a gravity-type wharf structure as described in claim 8, characterized in that, In step S7, a gravel drainage layer (6) is first laid at the bottom of the cofferdam, and a drainage pipe is buried in the gravel drainage layer (6). During the subsequent layered filling of the backfill and construction of the internal support frame (4), the water level in the cofferdam is continuously drained through the drainage pipe so that the water level in the cofferdam is not higher than the upper surface of the gravel drainage layer (6).
10. The construction method of the gravity-type wharf structure as described in claim 9, characterized in that, After step S7 is completed, the grouting pipe (9) is lowered from above the backfill body so that the opening of the grouting pipe (9) extends into the crushed stone drainage layer (6) and grout is injected into the crushed stone drainage layer (6) through the grouting pipe (9) to seal the crushed stone drainage layer (6).