A seepage-proof component and construction method for vertical construction joints of rockfill dam panels.
By using a combination of pre-embedded waterstops, O-ring hollow elastic seals, and elastic rubber sheets at the top of the vertical construction joints of the rockfill dam panel, a three-level seepage prevention system is formed, which solves the problems of poor adaptability and high leakage risk of traditional waterstops, and achieves efficient seepage prevention and low-cost operation and maintenance.
Patent Information
- Application Number
- CN202611137136.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-29
- Publication Date
- 2026-11-17
AI Technical Summary
Traditional rockfill dam panels have poor adaptability to vertical construction joint top waterproofing, insufficient seepage prevention effect, great difficulty in seepage treatment, and high leakage risk, especially in high dam projects with high operation and maintenance costs and safety risks.
A three-level seepage prevention system is formed by combining pre-embedded water-stop components, O-type hollow elastic seals, and elastic rubber plates. The sealing performance and adaptability are enhanced by mechanical compression and adhesive fixing. Combined with the connection components of threaded fasteners and water-stop pressure plates, multiple water-stopping methods are achieved.
It improves the sealing reliability and durability of the concrete top of the panel, reduces the risk of leakage, adapts to joint deformation caused by dam settlement and temperature changes, reduces operation and maintenance costs and safety risks, and is suitable for high-pressure seepage prevention scenarios of high dams and large reservoirs.
Smart Images

Figure CN123109102A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of dam bodies in water conservancy engineering, and specifically relates to a seepage prevention component and construction method suitable for vertical construction joints of rockfill dam panels. Background Technology
[0002] Due to their high safety, adaptability, and economical cost, rockfill dams with concrete panels have become the mainstream dam type in global water conservancy and hydropower projects. A single dam typically has 50 to 120 vertical construction joints in its concrete panel, which are the core weak points in the dam's seepage prevention system, and their seepage prevention performance directly determines the overall operational safety of the dam.
[0003] In concrete-faced rockfill dam projects, the vertical construction joints of the face are susceptible to opening, misalignment, and cracking due to multiple factors such as dam settlement deformation, temperature contraction, and alternating water pressure, leading to leakage. In engineering practice, the construction joint sealing system is usually divided into two levels: bottom embedded sealing and top surface sealing. Bottom sealing often uses copper or PVC waterstops, relying on concrete pouring to achieve a seal. However, due to the quality of pouring and joint misalignment, bottom sealing is prone to defects such as tearing and voids, and the defects are hidden and difficult to detect and repair. Top sealing, as the first line of defense against seepage, directly determines the overall seepage prevention capacity of the construction joint.
[0004] Currently, the top of vertical construction joints in rockfill dam panels generally uses a single water-stop structure, which typically employs SR caps, fillers, or rubber strips for water sealing. Corrugated waterstops are often directly sealed to the concrete surface, presenting the following technical problems:
[0005] 1. Due to limitations in the pouring process, the top of the concrete panel has poor surface flatness and a lot of laitance. When the sealant is directly bonded to the concrete surface, the bonding strength and adhesion are difficult to guarantee. After long-term operation, it is easy to debond, crack, and form leakage channels.
[0006] 2. Traditional solid water-stopping materials have limited deformation capacity and poor adaptability to joint misalignment caused by dam settlement and joint opening and closing caused by temperature changes. Under large deformation, they are prone to permanent deformation or tearing, and lose their water-stopping ability.
[0007] 3. Most top water-stop solutions rely solely on adhesive bonding or mechanical tightening without sealant, making the bolt holes prone to water leakage. Under long-term water pressure changes and material aging, the sealing performance deteriorates rapidly, and it is difficult to repair and restore the sealing performance underwater.
[0008] 4. Traditional top water-stopping standards are too low, resulting in a high risk of leakage in high dam projects. Once leakage occurs, underwater plugging operations are required, and the construction cost can be 5 to 10 times that of onshore repairs. In addition, the operation and maintenance safety risks are high.
[0009] Therefore, based on this, the technical solution of the present invention is proposed. Summary of the Invention
[0010] To address the problems of poor adaptability, insufficient seepage prevention effect, and difficulty in treating seepage at the top of vertical construction joints in traditional rockfill dam panels, this invention provides a seepage prevention component and construction method suitable for vertical construction joints in rockfill dam panels. The seepage prevention component utilizes pre-embedded waterstops, "O-ring" hollow elastic seals, and elastic rubber plates for coordinated waterstopping, improving deformation adaptability and the reliability and durability of seepage prevention. The seepage prevention component includes: Water-stop embedded parts; the water-stop embedded parts are set at the top corner of the vertical construction joint of the concrete panel of the dam body, and are used to level the surface of the concrete panel for water-stopping. "O-type" hollow elastic seal; the "O-type" hollow elastic seal is set on the upper part of the water-stop embedded part, and uses the combined action of the fixed elastic rubber plate and the water pressure of the reservoir to seal the top gap of the vertical construction joint. Elastic rubber sheet; the elastic rubber sheet is disposed on the upper part of the “O-type” hollow elastic seal and the water-stop embedded part, for covering and pressing to form the first seal, and also for pressing the “O-type” hollow elastic seal and the water-stop embedded part to maintain the water-stop seal of the vertical construction joint.
[0011] Preferably, the seepage-proof component suitable for the top of the vertical construction joint of the rockfill dam panel further includes a connecting component; wherein: The connecting assembly includes threaded fasteners and a water-stop pressure plate; The threaded fasteners sequentially pass through and connect the water-stop pressure plate, the elastic rubber plate, and the water-stop embedded parts.
[0012] Preferably, the number of the water-stop embedded parts is two, and the two water-stop embedded parts are symmetrically arranged with respect to the vertical construction joint; wherein: The water-stop embedded component includes a first embedded section and a second embedded section; The top end of the vertical construction joint is chamfered. The first embedded section is adapted to fit the chamfer, and the second embedded section is adapted to fit the concrete panel, so that the first embedded section and the second embedded section are set at an angle. The first embedded section and the second embedded section together form an "L"-shaped water-stop embedded part.
[0013] Preferably, the elastic rubber sheet comprises a straight elastic rubber segment and a curved elastic rubber segment; wherein: The straight elastic rubber segment is pressed tightly against the water-stop embedded part; The curved elastic rubber segment and the "O-type" hollow elastic seal are press-fitted together to achieve a pressing and wrapping effect.
[0014] Preferably, the "O-type" hollow elastic seal is an "O-type" hollow rubber seal.
[0015] Based on the same technical concept, the present invention further provides a construction method, which uses the aforementioned anti-seepage component suitable for vertical construction joints of rockfill dam panels. The anti-seepage construction method includes the following steps: (1) Constructing the base: Cement mortar pad, elastic pad and "W" type waterstop are laid in sequence to obtain the base; (2) Pre-embedded installation: A steel mesh is erected on the laying base, and the water-stop pre-embedded parts are fixedly connected to the steel mesh, and then the panel concrete is poured; (3) Sealing installation: After the concrete of the panel has cured, the water-stop embedded part forms a "V" groove at the top port of the vertical construction joint, and then the "O" hollow elastic seal is installed in the "V" groove. (4) Pressing and installation: Apply waterproof adhesive to the upper surface of the water-stop embedded part, then lay the elastic rubber plate and press the water-stop embedded part and the “O-type” hollow elastic seal to complete the seepage prevention construction.
[0016] Preferably, the seepage prevention construction method further includes: (5) Reinforcement installation: Install the water-stop pressure plate above the elastic rubber plate, and then connect the threaded fasteners through the water-stop pressure plate, the elastic rubber plate and the water-stop embedded parts in sequence to complete the installation of the connection components.
[0017] Preferably, the seepage prevention construction method further includes: (6) Inspection and acceptance: Check the fit between the “O-type” hollow elastic seal and the elastic rubber plate and the tightness of the threaded fasteners to ensure the sealing of the anti-seepage component.
[0018] The beneficial effects of this invention are as follows: 1. This invention replaces the traditional method of directly using the concrete surface as the sealing base by pre-embedding metal water-stopping components on the top of the concrete panel. This effectively solves the problem of poor bonding caused by poor flatness and excessive laitance on the top surface of the concrete panel. It provides a flat and high-strength sealing bonding surface for the "O-type" hollow elastic seal and the elastic rubber plate, thereby improving the reliability of the interface seal.
[0019] 2. This invention constructs a three-level seepage prevention system consisting of a top elastic rubber sheet seal, a middle "O-type" hollow elastic seal, and a bottom W-type waterstop embedded seal. The elastic rubber sheet and the waterstop embedded part form the first surface seal, blocking most of the surface water flow; the "O-type" hollow elastic seal and the waterstop embedded part form the second elastic seal, receiving the seepage water flow; the bottom W-type waterstop serves as the third embedded waterstop, forming the final seepage prevention line. In other words, this invention uses multiple waterstop methods, which can significantly reduce the risk of leakage.
[0020] 3. This invention adopts a combination structure of "O-type" hollow elastic seal and elastic rubber plate, which has high elasticity and strong adaptability. It can adapt to the joint misalignment caused by dam settlement and the joint opening and closing deformation caused by temperature changes, avoiding the problems of rigid waterstops being easily torn and detached. At the same time, the "O-type" hollow elastic seal can form a self-sealing characteristic together with the surface of the waterstop embedded part under the action of reservoir water. The higher the water pressure on the outside of the joint, the more fully the "O-type" hollow elastic seal is squeezed and deformed, the greater the contact sealing pressure with the waterstop embedded part, and the seepage prevention performance increases synchronously with the increase of water pressure, making it suitable for high-pressure seepage prevention scenarios of high dams and large reservoirs.
[0021] 4. The present invention is equipped with a connecting component consisting of threaded fasteners and a water-stop pressure plate, which is fixed by mechanical clamping force and bonding, effectively avoiding the sealing failure caused by the aging of waterproof adhesive and water seepage in bolt holes; at the same time, the mechanical connection structure is detachable, and the aged elastic seal can be directly replaced in the later maintenance, which is fast and greatly reduces the safety maintenance cost and safety risk.
[0022] 5. The seepage prevention components of the present invention adopt a construction mode of factory prefabrication and on-site assembly. The water-stop embedded parts and steel mesh are fixed and poured simultaneously, which makes it easy to ensure construction accuracy, and the process is clear and controllable, and is compatible with the existing construction process of panel rockfill dams. Attached Figure Description
[0023] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0024] Figure 1 This is a schematic diagram of the anti-seepage component described in this invention.
[0025] Figure 2 This is a schematic diagram of the overall structure after the seepage prevention components are installed at the top of the vertical construction joint of the rockfill dam.
[0026] Figure 3This is a construction diagram of steps 2-7 of the seepage prevention construction method in Example 6.
[0027] Figure 4 yes Figure 3 An enlarged schematic diagram of step 2.
[0028] Figure 5 yes Figure 3 An enlarged schematic diagram of step 3.
[0029] Figure 6 yes Figure 3 An enlarged schematic diagram of step 4.
[0030] Figure 7 yes Figure 3 An enlarged schematic diagram of step 5.
[0031] Figure 8 yes Figure 3 An enlarged schematic diagram of step 6.
[0032] Figure 9 yes Figure 3 An enlarged schematic diagram of step 7.
[0033] The attached figures are labeled as follows: 1-Waterstop embedded part; 11-First embedded section; 12-Second embedded section; 13-Welded positioning part; 2- "O-type" hollow elastic seal; 3-Elastic rubber sheet; 31-Straight elastic rubber segment; 32-Curved elastic rubber segment; 4-Connecting components; 41-Threaded fasteners; 42-Water-stop pressure plate; 5- Cement mortar cushion layer; 6-Elastic padding layer; 7-"W-shaped" water stop sheet; 8-Panel concrete; 9-Vertical construction joint; 10 - "V" groove. Detailed Implementation
[0034] To make the objectives, technical solutions, and advantages of this invention clearer, the technical solutions of this invention will be described in detail below. Obviously, the described embodiments are merely some embodiments of this invention, and not all embodiments. Based on the embodiments of this invention, all other implementation methods obtained by those skilled in the art without creative effort are within the scope of protection of this invention.
[0035] Example 1 refer to Figure 1 , Figure 2This embodiment provides a seepage-proof component suitable for vertical construction joints of rockfill dam panels, comprising: Water-stop embedded part 1; The water-stop embedded part 1 is set at the upper apex of the vertical construction joint 9 of the concrete panel 8 of the dam body, and is used to level the water-stopping surface of the concrete panel 8. The water-stop embedded part 1 is prefabricated with water-corrosion resistant metal material, and its surface flatness is much higher than that of cast-in-place concrete. It can eliminate defects such as laitance, pitting, and misalignment on the concrete surface, and provide a uniform bonding base for the upper sealing structure. It solves the technical problem of poor adhesion and easy leakage channels when the sealing part is directly bonded to the concrete surface in the traditional solution.
[0036] The "O-type" hollow elastic seal 2 is installed on the upper part of the water-stop embedded part 1. Utilizing the combined action of the fixed elastic rubber plate 3 and the reservoir water pressure, it seals the top gap of the vertical construction joint 9. The "O-type" hollow elastic seal 2 is made of highly elastic rubber, capable of filling the port gap at the top of the vertical construction joint 9, forming the main water-stop structure, and blocking the inward flow of water along the vertical construction joint 9.
[0037] Elastic rubber plate 3; the elastic rubber plate 3 is disposed on the upper part of the "O-type" hollow elastic seal 2 and the water-stop embedded part 1, and is used to cover and compress to form the first seal. It is also used to compress the "O-type" hollow elastic seal 2 and the water-stop embedded part 1 to maintain the water-stop seal of the vertical construction joint 9. The elastic rubber plate 3 covers the top surface of the water-stop embedded part 1 to form the first surface seal and prevent surface water from contacting the elastic seal. On the other hand, it applies a pre-compression force to the "O-type" hollow elastic seal 2 to ensure that there is always sufficient sealing pressure between the elastic rubber plate 3 and the water-stop embedded part 1, and to avoid the formation of sealing gaps when the joint opens.
[0038] Example 2 As an optional implementation method, refer to Figure 1 , Figure 2 The seepage prevention component suitable for vertical construction joints of rockfill dam panels further includes a connecting component 4; wherein: The connecting component 4 includes a threaded fastener 41 and a water-stop pressure plate 42; The threaded fastener 41 sequentially connects the water-stop pressure plate 42, the elastic rubber plate 3, and the water-stop embedded part 1.
[0039] This embodiment adds a mechanical connection reinforcement structure to the existing embodiment 1. Its function is as follows: (i) The water-stop pressure plate 42 is a rigid pressure plate, which can evenly distribute the concentrated tightening force of the threaded fastener 41 to the entire surface of the elastic rubber plate 3, avoid excessive local stress from damaging the elastic material, and at the same time ensure that the circumferential clamping force of the "O-type" hollow elastic seal 2 is uniform, eliminating weak points in the seal. (ii) The threaded fastener 41 can provide continuous and controllable mechanical clamping force, which strengthens the fixing method of waterproof adhesive bonding. It is not affected by the aging of waterproof adhesive or water environment corrosion. It can maintain stable clamping force under long-term operation and the sealing performance decays slowly. (iii) The connecting component 4 is a detachable structure. During the later operation and maintenance process, the creep relaxation of the elastic material can be compensated by tightening the threaded fastener 41 to restore the sealing pressure. When the “O-type” hollow elastic seal 2 or the elastic rubber plate 3 ages and fails, it can be directly disassembled and replaced without damaging the concrete structure, which greatly reduces the operation and maintenance cost and difficulty.
[0040] Example 3 As an optional implementation method, refer to Figure 1 , Figure 2 The water-stop embedded part 1 consists of two parts, and the two water-stop embedded parts 1 are symmetrically arranged with respect to the vertical construction joint 9; wherein: The water-stop embedded component 1 includes a first embedded section 11 and a second embedded section 12; The top end of the vertical construction joint 9 is chamfered. The first embedded section 11 is adapted to fit the chamfer, and the second embedded section 12 is adapted to fit the panel concrete 8, so that the first embedded section 11 and the second embedded section 12 are set at an angle. The first embedded section 11 and the second embedded section 12 together form an "L"-shaped water-stop embedded part.
[0041] This embodiment optimizes the structure of the water-stopping embedded part 1, the function of which is: (i) The symmetrical arrangement makes the sealing structure on both sides of the vertical construction joint 9 uniformly stressed. When the vertical construction joint 9 undergoes displacement deformation on both sides, the water-stop embedded parts 1 on both sides can deform together to avoid excessive stress on one side leading to failure of the sealing structure. (ii) The first embedded section 11 is arranged at an angle along the top of the vertical construction joint 9, forming an angle with the horizontal second embedded section 12. On the one hand, the inclined first embedded section 11 increases the sealing contact area, extends the seepage path, and improves the seepage prevention effect; on the other hand, the inclined surface can guide and limit the “O-type” hollow elastic seal 2, making it easy to position during installation and restricting the displacement of the “O-type” hollow elastic seal 2 into the vertical construction joint 9 when under pressure, thus ensuring stable sealing pressure. (iii) The water-stop embedded part 1 is embedded into the concrete panel 8 by a welded positioning part 13. The welded positioning part 13 has sufficient anchoring length to ensure the bonding strength between the water-stop embedded part 1 and the concrete, preventing the embedded part from lifting or shifting under the action of clamping force and water pressure, and ensuring the overall stability of the sealing structure. In addition, the welded positioning part 13 and the water-stop embedded part 1 are manufactured as a whole in the factory.
[0042] Example 4 As an optional implementation method, refer to Figure 1 , Figure 2 The elastic rubber sheet 3 includes a straight elastic rubber segment 31 and a curved elastic rubber segment 32; wherein: The straight elastic rubber segment 31 is pressed tightly against the water-stop embedded part 1; in use, this setting forms the first layer of waterproofing effect.
[0043] The curved elastic rubber segment 32 and the "O-type" hollow elastic seal 2 are press-fitted together to achieve a pressing and wrapping effect.
[0044] This embodiment incorporates an adaptability design for the structure of the elastic rubber plate 3, the purpose of which is: (i) The flat elastic rubber section 31 is completely attached to the horizontal top surface of the water-stop embedded part 1, and a surface seal is formed by bonding with waterproof adhesive and mechanical pressing. As the first line of seepage prevention, it directly blocks the surface water in front of the dam from entering the vertical construction joint 9 port, greatly reducing the water pressure and seepage flow borne by the elastic seal. (ii) The inner contour of the curved elastic rubber segment 32 is adapted to the outer contour of the "O-type" hollow elastic seal 2, and can wrap around the upper part of the "O-type" hollow elastic seal 2. On the one hand, it applies a uniform pre-compression force to the "O-type" hollow elastic seal 2 to ensure the initial sealing performance; on the other hand, it can limit the lateral expansion deformation of the "O-type" hollow elastic seal 2 when it is under pressure, so that the deformation of the "O-type" hollow elastic seal 2 is concentrated on the contact surface with the water-stop embedded part 1, further increasing the sealing specific pressure and strengthening the water-stopping effect. (iii) The segmented structure enables the elastic rubber sheet 3 to simultaneously perform the dual functions of surface sealing and compression limiting, eliminating the need for additional limiting components. The structure is simple, easy to install, and the sealing levels are clear, forming a graded seepage prevention system of "surface sealing and plugging - line sealing and pressure bearing".
[0045] Example 5 As an optional implementation method, refer to Figure 1 , Figure 2 The “O-type” hollow elastic seal 2 is an “O-type” hollow rubber seal.
[0046] This embodiment uses a rubber "O-ring" hollow elastic seal 2, the function of which is: (i) The hollow structure provides sufficient deformation space for the seal. When the construction joint opens due to temperature drop or moves due to dam settlement, the "O-type" hollow elastic seal 2 can compensate for the joint deformation through its own elastic deformation, and always maintain a tight fit with the water-stop embedded part 1, avoiding the problem of seal detachment caused by insufficient deformation of the solid seal. (ii) When the outside of the construction joint is subjected to water pressure, the water pressure acts on the exposed side of the “O-type” hollow elastic seal 2, squeezing the hollow structure to flatten it and deform it. The contact area between the seal and the water-stop embedded parts 1 on both sides increases and the contact specific pressure increases. The greater the water pressure, the stronger the sealing and tightening force, forming a self-reinforcing effect of “the higher the water pressure, the stronger the seal”, which is particularly suitable for the high-pressure seepage prevention conditions of high dam projects. (iii) The hollow structure can buffer the impact stress caused by joint deformation, avoid fatigue cracking of solid seals under repeated deformation, extend the service life of seals, and reduce the frequency of maintenance and replacement.
[0047] Example 6 refer to Figures 3-8 This embodiment provides a construction method that uses the aforementioned anti-seepage component suitable for the top of the vertical construction joint of a rockfill dam. The anti-seepage construction method includes the following steps: (1) Construction preparation: Fabricate materials such as water-stop embedded parts 1, "O-type" hollow elastic seals 2, elastic rubber sheets 3, threaded fasteners 41, water-stop pressure plates 42, elastic pads 6, and "W-type" water-stop sheets 7 according to the design dimensions. Inspect the dimensions, appearance, and material properties of all components upon arrival to ensure they meet the design requirements; among which: Water-stop embedded part 1: The material is selected from 304 stainless steel or copper. In this embodiment, 304 stainless steel is selected. "O-type" hollow elastic seal 2: The hollow cross-section size is adapted to the design gap width and has the properties of aging resistance and water erosion resistance; Elastic rubber sheet 3: The cross section includes a straight elastic rubber section 31 and a curved elastic rubber section 32, which are adapted to the contours of the water-stop embedded part 1 and the "O-type" hollow elastic seal 2. Threaded fasteners 41: Stainless steel bolts and nuts are selected, along with matching flat washers and spring washers. The specifications are selected according to the design clamping force. Waterstop pressure plate 42: Made of stainless steel with a smooth surface and through holes at the corresponding bolt positions; "W-type" waterstop 7: Made of copper, the waveform dimensions after molding meet the design requirements.
[0048] This step ensures the precision of component processing through factory prefabrication and controls material quality through on-site inspection, providing qualified finished components for on-site construction.
[0049] (2) Constructing the base: On the foundation surface at the bottom of the vertical construction joint 9, lay cement mortar cushion 5, elastic cushion 6 and “W-shaped” waterstop 7 in sequence to obtain the base; among them, cement mortar cushion 5 is used to level the base; elastic cushion 6 is used as a buffer; “W-shaped” waterstop 7 is arranged in the middle of the construction joint and extends into the concrete on both sides to meet the anchorage length requirements.
[0050] The purpose of this step is to construct the basic seepage prevention system at the bottom of the vertical construction joint 9. The "W-shaped" waterstop 7 serves as the third embedded waterstop, forming a deep seepage prevention line. The elastic pad 6 fills the gap of the construction joint, providing deformation buffer for concrete pouring, while protecting the "W-shaped" waterstop 7 from damage caused by the pouring impact.
[0051] (3) Pre-installation: The steel mesh of the panel concrete 8 is erected on the laying base. The water-stop pre-embedded parts 1 are welded and fixed to the steel mesh by welding positioning parts 13. The welding positioning parts 13 are arranged at appropriate intervals along the length of the construction joint. The elevation and level of the water-stop pre-embedded parts 1 are adjusted to ensure that the water-stop pre-embedded parts 1 on both sides are symmetrically arranged and the top surface is flush.
[0052] This step is a crucial positioning process before pouring. By welding the positioning component 13, the water-stop embedded component 1 is rigidly connected to the steel mesh, which can effectively prevent the embedded component from shifting, floating, or rotating during the concrete pouring process. At the same time, the symmetry and top elevation of the embedded components on both sides are strictly controlled to ensure that the contact surface of the subsequent "O-type" hollow elastic seal 2 is flat and the force is uniform, providing a precise installation benchmark for the entire seepage prevention system.
[0053] (4) Pouring concrete: After acceptance, pour concrete 8 for the panel to prevent the water-stop embedded parts 1 from shifting.
[0054] This step integrates the water-stop embedded part 1 with the concrete panel 8, ensuring the anchoring strength and positional accuracy of the embedded part. The embedded part is fixed by welding steel mesh to prevent it from shifting or floating during the pouring process, thus ensuring the accuracy of the installation benchmark for the subsequent sealing structure.
[0055] (5) Sealing installation: After the concrete 8 of the panel has cured to the design strength, clean the laitance and debris on the top surface of the water-stop embedded part 1, wipe it clean, and place the “O-type” hollow elastic seal 2 along the length of the construction joint to the upper part of the water-stop embedded part 1, corresponding to the chamfer position of the construction joint port (in the “V-type” groove 10), to ensure that the “O-type” hollow elastic seal 2 is continuous, without twisting or breakage.
[0056] This step completes the installation and positioning of the main water-stopping component, ensuring the continuity and integrity of the "O-type" hollow elastic seal 2, forming the second line of defense against seepage; cleaning the base surface ensures that there are no impurities blocking the "O-type" hollow elastic seal 2 and the water-stopping embedded part 1, ensuring a tight fit.
[0057] (6) Pressing and installation: Apply waterproof adhesive evenly to the upper surface of the water-stop embedded part 1, with an appropriate thickness, without any omissions or accumulation; then lay the elastic rubber plate 3 along the construction joint direction, so that the straight elastic rubber section 31 fits against the top surface of the water-stop embedded part 1 and the curved elastic rubber section 32 is fastened to the upper part of the "O-type" hollow elastic seal 2. Use a special roller to roll and vent the air to ensure tight adhesion and no air bubbles.
[0058] This step uses waterproof adhesive to bond and seal the elastic rubber sheet 3 to the water-stop embedded part 1, forming the first line of surface seepage prevention; at the same time, the elastic rubber sheet 3 applies a pre-compression force to the "O-type" hollow elastic seal 2 to ensure the initial sealing performance.
[0059] (7) Reinforcement installation: Place the water-stop pressure plate 42 above the elastic rubber plate 3, align the bolt holes, and then pass the threaded fasteners 41 through the reserved holes of the water-stop pressure plate 42, the elastic rubber plate 3 and the water-stop embedded part 1 in sequence. After adding spring washers, tighten the nuts and use a torque wrench to control the tightening torque to ensure uniform clamping force.
[0060] This step applies continuous and stable clamping force through a mechanical fastening structure, compensating for the long-term performance degradation of adhesive fixation and enhancing sealing reliability; the spring gasket can compensate for the creep relaxation of the elastic material, maintaining stable clamping force over a long period of time.
[0061] (8) Inspection and acceptance: Check the fit of the “O-type” hollow elastic seal 2 and the elastic rubber plate 3 along the entire length of the construction joint to ensure that there is no detachment, no curling, and no damage; check the tightness of the threaded fasteners 41 to ensure that there is no looseness or missing parts; conduct a segmented water filling test on the top of the construction joint, and it is considered qualified if there is no leakage.
[0062] This step involves a final inspection of the construction quality, identifying installation defects, and ensuring that the sealing performance of the waterproof components meets design requirements.
[0063] (9) Operation and maintenance: After the reservoir is filled with water, the water pressure will be used to press the elastic rubber plate 3 down further. The "O-type" hollow elastic seal 2 will be deformed under pressure to further seal the vertical construction joint. When the panel settles and deforms, or when the construction joint is deformed due to seasonal and diurnal temperature changes, the elastic component can adapt to the deformation to maintain the water-stopping effect. The top of the construction joint will be inspected regularly. If the seal is found to be aging or the fasteners are loose, it will be dealt with in time to ensure the long-term seepage prevention effect.
[0064] This step utilizes the self-reinforcing properties of the structure to improve the seepage prevention performance during operation, and eliminates potential hazards in a timely manner through regular operation and maintenance, thereby extending the service life of the seepage prevention system.
[0065] The above description is merely a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the technical scope disclosed in the present invention should be included within the scope of protection of the present invention. Therefore, the scope of protection of the present invention should be determined by the scope of the claims.
Claims
1. A seepage-proof component suitable for vertical construction joints of rockfill dam panels, characterized in that, include: Water-stop embedded parts; the water-stop embedded parts are set at the top corner of the vertical construction joint of the concrete panel of the dam body, and are used to level the surface of the concrete panel for water-stopping. "O-type" hollow elastic seal; the "O-type" hollow elastic seal is set on the upper part of the water-stop embedded part, and uses the combined action of the fixed elastic rubber plate and the water pressure of the reservoir to seal the top gap of the vertical construction joint. Elastic rubber sheet; the elastic rubber sheet is disposed on the upper part of the "O-type" hollow elastic seal and the water-stop embedded part, for covering and pressing to form the first seal, and also for pressing the "O-type" hollow elastic seal and the water-stop embedded part to maintain the water-stop seal of the vertical construction joint.
2. The seepage prevention component for vertical construction joints of rockfill dam panels according to claim 1, characterized in that, It also includes connection components; wherein: The connecting assembly includes threaded fasteners and a water-stop pressure plate; The threaded fasteners sequentially pass through and connect the water-stop pressure plate, the elastic rubber plate, and the water-stop embedded parts.
3. The seepage prevention component for vertical construction joints of rockfill dam panels according to claim 1, characterized in that, The number of the water-stop embedded parts is two, and the two water-stop embedded parts are symmetrically arranged with respect to the vertical construction joint; wherein: The water-stop embedded component includes a first embedded section and a second embedded section; The top end of the vertical construction joint is chamfered. The first embedded section is adapted to fit the chamfer, and the second embedded section is adapted to fit the concrete panel, so that the first embedded section and the second embedded section are set at an angle. The first embedded section and the second embedded section together form an "L"-shaped water-stop embedded part.
4. The seepage prevention component for vertical construction joints of rockfill dam panels according to claim 1, characterized in that, The elastic rubber sheet includes a straight elastic rubber segment and a curved elastic rubber segment; wherein: The straight elastic rubber segment is pressed tightly against the water-stop embedded part; The curved elastic rubber segment and the "O-type" hollow elastic seal are press-fitted together to achieve a pressing and wrapping effect.
5. The seepage prevention component for vertical construction joints of rockfill dam panels according to claim 1, characterized in that, The "O-type" hollow elastic seal is an "O-type" hollow rubber seal.
6. A construction method, characterized in that, The construction method using the seepage prevention component for vertical construction joints of rockfill dam panels as described in claim 1 includes the following steps: (1) Constructing the base: Cement mortar pad, elastic pad and "W" type waterstop are laid in sequence to obtain the base; (2) Pre-embedded installation: A steel mesh is erected on the laying base, and the water-stop pre-embedded parts are fixedly connected to the steel mesh, and then the panel concrete is poured; (3) Sealing installation: After the concrete of the panel has cured, the water-stop embedded part forms a "V" groove at the top port of the vertical construction joint, and then the "O" hollow elastic seal is installed in the "V" groove; (4) Pressing and installation: Apply waterproof adhesive to the upper surface of the water-stop embedded part, then lay the elastic rubber plate and press the water-stop embedded part and the "O-type" hollow elastic seal to complete the seepage prevention construction.
7. The construction method according to claim 6, characterized in that, Also includes: (5) Reinforcement installation: Install the water-stop pressure plate above the elastic rubber plate, and then connect the threaded fasteners through the water-stop pressure plate, the elastic rubber plate and the water-stop embedded parts in sequence to complete the installation of the connection components.
8. The construction method according to claim 7, characterized in that, Also includes: (6) Inspection and acceptance: Check the fit between the "O-type" hollow elastic seal and the elastic rubber plate and the tightness of the threaded fasteners to ensure the sealing of the anti-seepage component.