Construction method of filling anti-freezing concrete between pre-supporting platform and piles in high-cold reservoir area

By adopting the method of first constructing the abutment and then filling the gaps between piles with antifreeze concrete during bridge construction in cold reservoir areas, combined with composite functional layers and real-time monitoring technology, the problems of long construction period and cold bridge effect were solved, and the effects of shortening the construction period and stabilizing the temperature were achieved.

CN123109164APending Publication Date: 2026-11-17CHINA RAILWAY 11TH BUREAU GRP CORP LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611236822.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-14
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In bridge construction in high-altitude reservoir areas, existing technologies suffer from problems such as long construction periods, a sharp drop in the temperature of the filling concrete, and a cold bridging effect caused by the heat conduction of the steel cofferdam walls, resulting in a high risk of frost heave.

Method used

The construction method of first constructing the foundation and then filling the gaps between the piles with antifreeze concrete was adopted. By setting a composite functional layer (insulation layer, buffer isolation layer and antifreeze adhesive layer) on the inner side of the cofferdam wall, and by monitoring the construction status in real time, the construction sequence was optimized to reduce the cold bridge effect and the risk of frost heave.

Benefits of technology

It significantly shortens the construction cycle, stabilizes the temperature of the filling material, reduces the risk of frost heave, and achieves efficient collaboration and precise control in the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109164A_ABST
    Figure CN123109164A_ABST
Patent Text Reader

Abstract

This invention provides a construction method for filling the pile gaps with frost-resistant concrete after the foundation is constructed in a high-altitude reservoir area. Specifically, after the pile foundation construction is completed, a foundation construction platform is erected for foundation construction. After the foundation construction is completed, the upper pier body and the 0# block are constructed. After the 0# block is completed, the 1# block construction and cofferdam lowering are carried out simultaneously, with composite functional panels fixedly attached to the inner wall of the cofferdam. After the cofferdam is lowered to the designed position, a layered pouring process is used to fill the pile gaps with concrete, with each layer having a pouring height ≤ 2.0m and a pouring rate ≤ 0.5m / h. During pouring, the vibrator is kept at least 100mm away from the surface of the composite functional panel. The cofferdam is removed after the pile gap filling concrete reaches the required strength. This invention achieves the dual goals of shortening the construction period and improving the frost resistance of the pile gap filling concrete by optimizing the construction sequence and using a composite functional layer between the inner side of the cofferdam wall panel and the pile gap filling concrete to isolate the cold bridge effect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of bridge engineering construction technology, specifically to a construction method suitable for high-altitude and cold reservoir areas, which involves first constructing the abutment and then filling the gaps between piles with antifreeze concrete. Background Technology

[0002] In bridge construction in the cold regions of Northeast my country, the frost resistance of pile foundations is crucial. Generally, during bridge foundation construction, frost-resistant concrete is filled between the piles to protect them. The current construction sequence for filling the pile foundation with frost-resistant concrete is: pile foundation construction → filling with frost-resistant concrete between piles → construction of the pile cap and superstructure. This method conforms to conventional construction logic, but it also has the drawback of a long construction period. After the frost-resistant concrete is filled, it needs to be cured separately for 14-21 days until its strength reaches the required level before the cofferdam can be removed, and only then can the pile cap be constructed. This leads to disjointed processes and an extended overall construction period. Furthermore, the traditional method involves the frost-resistant concrete directly contacting the steel cofferdam wall. As a highly efficient heat conductor, the steel cofferdam wall rapidly conducts the external low temperature to the interior of the filling material in winter, causing a sharp drop in the overall temperature of the filling concrete. Traditional methods rely solely on the frost-resistant concrete itself to resist frost heave, lacking structural measures to actively block cold bridges and weaken the transmission of frost heave forces.

[0003] To address the aforementioned issues, there is an urgent need to develop a novel construction method that addresses the increased risk of concrete frost heave caused by the thermal conduction of the steel cofferdam wall panels leading to cold bridging, and that allows for simultaneous cantilever construction of the upper beams, adapting to the special working conditions of cold reservoir areas. Summary of the Invention

[0004] This invention addresses the shortcomings of existing technologies by providing a construction method suitable for high-altitude and cold reservoir areas, which involves filling the gaps between piles with antifreeze concrete after the foundation is laid. This method can solve the problems of long construction period, rapid temperature drop of the filling concrete, and cold bridging effect caused by heat conduction of the steel cofferdam wall in existing technologies.

[0005] To address the aforementioned technical problems, this invention provides a construction method for constructing bridge piers in high-altitude reservoir areas by first constructing a foundation and then filling the gaps between piles with antifreeze concrete. This method is for pile foundation construction of bridge piers in high-altitude reservoir areas, where the pile foundation comprises multiple piles, and specifically includes the following steps:

[0006] S1. After the pile foundation construction is completed, the pile casing is removed, the clamps are installed on the pile body, the pile cap construction platform is erected, the pile cap construction is carried out, and after the pile cap construction is completed, the upper pier body and 0# block are constructed.

[0007] S2. After the construction of block 0 is completed, the construction of block 1 and the lowering of the cofferdam are carried out simultaneously. After the standard section of the cofferdam is made, a composite functional board is fixedly attached to the inner wall of the cofferdam. The composite functional board includes, from the outside to the inside, an insulation layer, a buffer isolation layer and an antifreeze adhesive layer. The insulation layer is tightly attached to the inner wall of the cofferdam.

[0008] S3. After the cofferdam is lowered to the design position, concrete is filled between the piles using a layered pouring process. The pouring height of each layer is ≤2.0m and the pouring rate is ≤0.5m / h to reduce the lateral pressure of the concrete on the composite functional panel. During the pouring process, the vibrator is ≥100mm away from the surface of the composite functional panel.

[0009] S4. The cofferdam is removed after the concrete filling between the piles reaches the required strength.

[0010] The preferred technical solution of the present invention is as follows: After the pile foundation is completed in step S1, the pile foundation casing is removed and the pile body is inspected. After the pile body is inspected and qualified, the pile body is constructed by setting up a bearing platform with clamps on the pile body. After the bearing platform is constructed, the pier body and block 0 are completed in sequence. When the block 0 is constructed, the holes are reserved in the bottom plate of the box girder section for the subsequent insertion of steel strands to lower the cofferdam.

[0011] The preferred technical solution of the present invention is as follows: In step S2, after the standard section of the cofferdam is manufactured, the prefabricated composite functional panel is cut according to the size of the cofferdam blocks and installed on the inner wall of the cofferdam by means of pasting and anchoring. After the composite functional panel is installed, flexible sealant is applied to the joint of the panel and aluminum foil waterproof tape is attached as an auxiliary sealant.

[0012] The preferred technical solution of the present invention is as follows: In step S2, the composite functional layer comprises, from the outside to the inside, a 4-6 cm thick polystyrene board, a 2-4 cm thick cross-linked polyethylene foam board, and a 0.8-1.2 mm thick modified polyurethane coating layer; specifically, the cross-linked polyethylene foam board is laid flat on the upper surface of the polystyrene board, and polyurethane composite material is filled between the two layers to press them together into a heat insulation-buffering double-layer substrate. After lamination, it is left to stand for 24 hours to allow it to fully cure. A modified polyurethane coating is sprayed on the other side of the cross-linked polyethylene foam board, spraying 3-4 times with an interval of 5-10 minutes between each coat, until the coating thickness reaches 1 mm.

[0013] The preferred technical solution of the present invention is as follows: In step S2, after the construction of block 0# is completed, the hanging basket is installed to construct block 1#. The cofferdam lifting system is installed inside block 0#. After the hanging basket and the cofferdam lifting system are installed, the upper block 1# and the lower cofferdam are constructed simultaneously. During construction, the construction status is monitored in real time by stress, displacement and temperature sensors installed on the cofferdam, hanging basket and lifting system, so as to realize real-time data feedback and dynamic adjustment of construction.

[0014] This invention employs a method of constructing the foundation first, followed by concrete filling, significantly shortening the overall construction cycle. A composite functional layer is installed between the inner side of the cofferdam wall and the frost-resistant concrete between the piles. This composite functional layer includes a thermal insulation layer, a buffer energy absorption layer, and an anti-frost bonding layer. The integrated pile-to-pile structure formed by this composite functional layer and the pile-to-pile filling concrete integrates three functions: thermal insulation, buffer energy absorption, and anti-frost bonding. Through the thermal insulation and buffer energy absorption mechanisms of the composite functional layer, external low temperatures and frost heave stress transmitted through the steel cofferdam wall are isolated and reduced, enabling process adjustments and stabilizing the filling temperature. This addresses the structural safety challenges posed by extreme temperatures and resolves the cold bridge effect caused by thermal conduction in the steel cofferdam wall. Simultaneously, this invention introduces multi-source sensor real-time monitoring technology to construct a synchronous construction process coordination control system. This enables dynamic control of the overlapping operations of cantilever casting and cofferdam lowering, ensuring efficient collaboration and precise control of the construction process. Attached Figure Description

[0015] Figure 1 This is a schematic diagram of the construction of the hanging basket No. 1 block and the cofferdam being lowered and the concrete filling between the piles in an embodiment of the present invention;

[0016] Figure 2 This is a schematic diagram of the main structure of the bridge in an embodiment of the present invention;

[0017] Figure 3 This is a schematic diagram of the hanging basket structure in an embodiment of the present invention;

[0018] Figure 4 This is a schematic diagram of the cofferdam lifting system in an embodiment of the present invention;

[0019] Figure 5 This is a schematic diagram of the standard section of the cofferdam in an embodiment of the present invention;

[0020] Figure 6 This is a schematic diagram of the cofferdam in an embodiment of the present invention;

[0021] Figure 7 This is a schematic diagram of the composite functional layer in an embodiment of the present invention;

[0022] Figure 8 This is a schematic diagram of the overall system architecture of the control device in an embodiment of the present invention.

[0023] In the diagram: 1. Bridge main structure; 1-1. Pile foundation; 1-2. Abutment; 1-3. Pier; 1-4. Block 0; 1-5. Block 1; 2. Hanging basket; 2-1. Hanging basket main body; 2-2. Hanging basket anchoring system; 2-3. Hanging basket suspension; 2-4. Hanging basket formwork; 2-5. Hanging basket monitoring data cable; 2-6. Hanging basket data monitoring processor; 3. Cofferdam lifting system; 3-1. Lifting beam; 3-2. Lifting jack; 3-3. Steel strand; 3-4. Spreader beam; 3-5. Lifting system monitoring data cable; 3-6. Lifting system data monitoring processor; 4. Cofferdam; 4-1. Cofferdam standard section; 4-2. Cofferdam lowering bracket; 4-3. Cofferdam internal support; 5. Composite functional layer; 5-1. Insulation layer; 5-2. Buffer isolation layer; 5-3. Anti-freeze adhesive surface layer; 6. Construction water level; 7. Concrete filling between piles. Detailed Implementation

[0024] The construction method of the present invention will be described in detail below with reference to the accompanying drawings and specific embodiments; for example... Figures 1 to 8 All accompanying drawings are detailed illustrations of the embodiments, drawn in a simplified manner, and are only used to clearly and concisely illustrate the purpose of the embodiments of the present invention. The technical solutions shown in the drawings below are specific solutions of the embodiments of the present invention and are not intended to limit the scope of the claimed invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0025] The construction method of first constructing the pile cap and then filling the gap between piles with antifreeze concrete provided in this embodiment of the invention is for the pile foundation construction of bridge piers in a high-altitude reservoir area. The main bridge structure 1 in this construction method is as follows: Figure 2 As shown, the structure includes pile foundation 1-1, pile cap 1-2, pier 1-3, block 0# 1-4, and block 1# 1-5. Pile foundation 1-1 comprises four piles. Pile cap 1-2 is erected on top of the four piles. Pier 1-3 is located above the center of pile cap 1-2. Block 0# 1-4 is located on top of pier 1-3. Two sets of blocks 1# are symmetrically arranged on both sides of block 0# 1-4. The construction equipment used in the construction method includes a hanging basket 2 and a cofferdam lifting system 3. The hanging basket 2 is as follows... Figure 3 As shown, the structure includes a hanging basket body 2-1, a hanging basket anchoring system 2-2, a hanging basket suspension 2-3, and a hanging basket template 2-4. The hanging basket anchoring system 2-2 is used to anchor the basket to block 0# 1-4. The hanging basket 2 is used to assist in the construction of block 1# 1-5 and other subsequent bridge blocks. Monitoring sensors are installed on the hanging basket, and these sensors are connected to the hanging basket data monitoring processor 2-6 via the hanging basket monitoring data line 2-5, transmitting the monitoring data to the hanging basket data monitoring processor 2-6 to monitor the construction status in real time, enabling real-time data feedback and dynamic adjustment of the construction. The cofferdam lifting system 3, as shown... Figure 4As shown, the system includes lifting beams 3-1 and 3-2, lifting jacks 3-2, steel strands 3-3, and a spreading beam 3-4. Lifting beam 3-1 is installed inside block 0# 1-4. The spreading beam 3-4 supports the cofferdam 4, which is then lowered. Alternatively, other cofferdam lifting devices can be used for lowering the cofferdam 4. No monitoring sensors are installed on the cofferdam lifting system 3. Monitoring sensors are connected to the lifting system data monitoring processor 3-6 via the lifting system monitoring data line 3-5, transmitting monitoring data to the lifting system data monitoring processor 3-6 for real-time monitoring of the construction status, enabling real-time data feedback and dynamic adjustment of the construction.

[0026] The construction method in this embodiment is to first construct the pile cap, pier body, and No. 0 block, and then fill the gaps between the piles with concrete. By optimizing the construction sequence and setting a composite functional layer between the inner side of the cofferdam wall and the filling concrete between the piles to isolate the cold bridge effect, the method includes the following steps:

[0027] S1. First, carry out the construction of pile foundation 1-1. After the pile foundation is completed, remove the protective casing of pile foundation 1-1 and inspect pile foundation 1-1. After the pile foundation 1-1 passes the inspection, set up a hoop on the pile body of pile foundation 1-1 to build the construction platform of pile cap 1-2 and carry out the construction of pile cap 1-2. After the construction of pile cap 1-2 is completed, complete the pier body 1-3 and block 0# 1-4 in sequence. When constructing block 0# 1-4, reserve holes in the bottom plate of the box girder section for the subsequent insertion of steel strand 3-3 and lowering of cofferdam 4.

[0028] S2. Construction of the upper beam begins with the installation of the hanging basket 2, and construction of the lower cofferdam 4 begins with the installation of the cofferdam lifting system 3 inside block 0# 1-4. After installation, construction is carried out simultaneously at the upper and lower levels. During construction, data is transmitted to the hanging basket data monitoring 2-6 and the lifting system data monitoring 3-6 through monitoring sensors deployed on the cofferdam 4, hanging basket 2, and lifting system 3 via the hanging basket data monitoring data line 2-6 and the lifting system data monitoring data line 3-5, thereby monitoring the construction status in real time and realizing real-time data feedback and dynamic adjustment of construction.

[0029] The specific control process is as follows: Figure 8 As shown, Figure 8 As shown, the signal monitoring unit integrates various current monitoring data (stress, deformation, formwork posture, and cofferdam stress, deformation, and verticality of the lowering, etc.) to dynamically calculate the current actual load status and safety margin of each construction area. When it is determined that the risk of the cofferdam lowering load and the formwork construction load overlapping at a certain time is low, and all parameters are below 70% of the design value, the system maintains the normal synchronous operation rhythm, and each execution unit continues to operate according to the current state. When a monitored parameter reaches 85%~90% of the corresponding threshold upper limit, a pre-alarm is triggered. Active intervention is initiated before the problem worsens based on the actual situation on site. Specifically, this includes:

[0030] Cofferdam verticality deviation pre-alarm: When the verticality and stroke deviation of the cofferdam reach the set synchronization accuracy during the lowering of the cofferdam, the system triggers a pre-alarm and automatically adjusts the hydraulic output of the lifting jacks 3-2 at each lifting point to restore the stroke of each lifting point to a synchronized state.

[0031] Pre-alarm for hanging basket construction: When the measured value of the hanging basket stress sensor reaches 85% of the design value, the system triggers a pre-alarm, immediately stops the construction of the upper bridge and the lower cofferdam, and notifies on-site technical personnel to check the hanging basket construction status and adjust the construction status in a timely manner.

[0032] Emergency Alarm and Forced Protection: When the monitored data rapidly reaches and exceeds the maximum threshold of a certain parameter, a Level 1 alarm is triggered at the corresponding point and data monitoring module, and the point and alarm parameters are recorded. Simultaneously, a red alarm window pops up on the human-machine interface, listing the alarm point, alarm parameters, real-time values, and executed control commands in detail. Specifically, during the lowering of the cofferdam, if the displacement sensor signal at any lifting point is lost or suddenly changes beyond 150% of the design value, or if the four-point synchronization deviation exceeds ±10mm, the system determines that there is a risk of cofferdam jamming or steel strand breakage, and automatically executes emergency braking—that is, stopping all lifting jacks 3-2 and locking the hydraulic system to prevent the cofferdam from falling out of control.

[0033] When the inclination meter of the main truss of the hanging basket detects a risk of overturning or excessive stress in key members, the central control unit immediately issues an emergency braking command for the hanging basket, automatically locks the traveling track and anchoring system, suspends all hanging basket operations, and simultaneously issues an audible and visual alarm to on-site personnel.

[0034] After the standard section 4-1 of the cofferdam is fabricated, the prefabricated composite functional panel 5 is cut to the dimensions of the cofferdam 3 blocks and installed on the inner side of the cofferdam 3 using a "gluing + anchoring" method. After the composite functional panel 5 is installed, flexible sealant is applied to the joints, and aluminum foil waterproof tape is applied as an auxiliary seal. The composite functional panel 5, as... Figure 7 As shown, a three-layer structure is set from the outside to the inside: the first layer is the thermal insulation layer 5-1, the second layer is the buffer isolation layer 5-2, and the third layer is the antifreeze adhesive layer 5-3. The thermal insulation layer 5-1 is a 5cm thick polystyrene board, the buffer isolation layer 5-2 is a 3cm thick cross-linked polyethylene foam board, and the antifreeze adhesive layer 5-3 is a 1mm thick modified polyurethane coating layer. The modified polyurethane coating is a directly purchased modified polyurethane topcoat coating of model SC-08. The manufacturing process of the composite functional board 5 is as follows: the cross-linked polyethylene foam board is laid flat on the upper surface of the polystyrene board, and polyurethane composite material is filled between the two layers. The two are pressed into a thermal insulation-buffering double-layer substrate. The polyurethane composite material is an existing product, also known as polyurethane rigid foam composite polyether. After lamination, it is left to stand for 24 hours to fully cure. The modified polyurethane coating is sprayed on the other side of the cross-linked polyethylene foam board, sprayed 3 to 4 times, with an interval of 5 to 10 minutes between each coat, until the spray thickness reaches 1mm.

[0035] S4. The cofferdam 4 is lowered to its design position by hooking the crossbeam 3-4 on the cofferdam lifting system 3 onto the cofferdam lowering bracket 4-2 at its bottom. After the cofferdam 4 is lowered to the design position, concrete 7 is filled between the piles. The concrete 7 is frost-resistant concrete and is poured in layers, with each layer having a height ≤2.0m and a pouring rate ≤0.5m / h to reduce the lateral pressure of the concrete 7 between the piles on the composite functional slab 5. During the pouring process, the vibrator is kept at least 100mm away from the surface of the composite functional slab 5 to avoid mechanical damage to the composite functional slab 5.

[0036] S5. After the concrete filling between the piles reaches the required strength, the cofferdam 4 is removed, and the entire construction is completed.

[0037] The above description is merely one embodiment of the present invention, and while it is detailed and specific, it should not be construed as limiting the scope of the invention. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of the present invention, and these modifications and improvements all fall within the scope of protection of the present invention. Therefore, the scope of protection of the present invention should be determined by the appended claims.

Claims

1. A construction method for constructing a foundation pier followed by filling the gaps between piles with antifreeze concrete in a high-altitude reservoir area, wherein the pile foundation comprises multiple piles, characterized in that... Specifically, the following steps are included: S1. After the pile foundation construction is completed, the pile casing is removed, the clamps are installed on the pile body, the pile cap construction platform is erected, the pile cap construction is carried out, and after the pile cap construction is completed, the upper pier body and 0# block are constructed. S2. After the construction of block 0 is completed, the construction of block 1 and the lowering of the cofferdam are carried out simultaneously. After the standard section of the cofferdam is made, a composite functional board is fixedly attached to the inner wall of the cofferdam. The composite functional board includes, from the outside to the inside, an insulation layer, a buffer isolation layer and an antifreeze adhesive layer. The insulation layer is tightly attached to the inner wall of the cofferdam. S3. After the cofferdam is lowered to the design position, concrete is filled between the piles using a layered pouring process. The pouring height of each layer is ≤2.0m and the pouring rate is ≤0.5m / h to reduce the lateral pressure of the concrete on the composite functional panel. During the pouring process, the vibrator is ≥100mm away from the surface of the composite functional panel. S4. The cofferdam is removed after the concrete filling between the piles reaches the required strength.

2. The construction method for filling the gaps between piles with antifreeze concrete in a high-altitude reservoir area according to claim 1, characterized in that: After the pile foundation is completed in step S1, the pile casing is removed and the pile body is inspected. After the pile body passes the inspection, the pile cap construction platform is erected on the pile body with clamps to carry out the pile cap construction. After the pile cap construction is completed, the pier body and block #0 are completed in sequence. When constructing block #0, holes are reserved in the bottom plate of the box girder section for the subsequent insertion of steel strands to lower the cofferdam.

3. The construction method for filling the gaps between piles with antifreeze concrete in a high-altitude reservoir area according to claim 1, characterized in that: In step S2, after the standard section of the cofferdam is manufactured, the prefabricated composite functional panels are cut according to the dimensions of the cofferdam blocks and installed on the inner wall of the cofferdam by pasting and anchoring. After the composite functional panels are installed, flexible sealant is applied to the joints of the panels and aluminum foil waterproof tape is applied as an auxiliary sealant.

4. The construction method for filling the gaps between piles with antifreeze concrete in a high-altitude reservoir area according to claim 1, characterized in that: In step S2, the composite functional layer comprises, from the outside in, a 4-6 cm thick polystyrene board, a 2-4 cm thick cross-linked polyethylene foam board, and a 0.8-1.2 mm thick modified polyurethane coating layer. Specifically, the cross-linked polyethylene foam board is laid flat on the upper surface of the polystyrene board, and polyurethane composite material is filled between the two layers to press them together to form a heat insulation-buffering double-layer substrate. After lamination, it is left to cure for 24 hours. A modified polyurethane coating is then sprayed on the other side of the cross-linked polyethylene foam board, 3-4 times, with an interval of 5-10 minutes between each coat, until the coating thickness reaches 1 mm.

5. The construction method for filling the gaps between piles with antifreeze concrete in a high-altitude reservoir area according to claim 1, characterized in that: In step S2, after the construction of block 0 is completed, the hanging basket is installed to construct block 1. The cofferdam lifting system is installed inside block 0. After the installation of the hanging basket and the cofferdam lifting system, the upper block 1 and the lower cofferdam are constructed simultaneously. During construction, the construction status is monitored in real time by stress, displacement and temperature sensors installed on the cofferdam, hanging basket and lifting system, so as to realize real-time data feedback and dynamic adjustment of construction.