A construction method for a main plant building
By employing a construction method that combines simultaneous excavation and phased pouring, the problems of poor environment, high safety risks, and long construction period in the main plant construction were solved, achieving safe and civilized construction and improved efficiency.
Patent Information
- Application Number
- CN202611581311.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-13
- Publication Date
- 2026-11-17
AI Technical Summary
The existing construction methods for the main plant building involve the overlapping construction of underground and above-ground parts, resulting in a poor site environment, high safety risks, long construction period, large investment in scaffolding turnover materials, and delayed handover of civil engineering and safety.
The construction method of simultaneous excavation and phased pouring was adopted. First, the foundation construction of the underground part of the main plant was completed. Then, the above-ground structure was carried out in layers, including the simultaneous excavation of each foundation pit and foundation, and the pouring of concrete in layers to form independent construction sections.
It reduced the amount of scaffolding turnover materials used, improved construction safety and a civilized appearance, shortened the construction cycle, completed the entry time of electrical, thermal control and other specialties ahead of schedule, and improved construction efficiency.
Smart Images

Figure CN123109192A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of building construction technology, and specifically relates to a construction method for a main plant building. Background Technology
[0002] The main plant is the core building of the power plant, including deep underground foundation pits such as the condensate pump pit and circulating water pit, as well as large-volume above-ground equipment such as the A-column frame, B-column frame, C-column frame, vehicle base, coal mill base, and furnace front connection platform.
[0003] Current construction methods for the main plant often involve overlapping underground construction with above-ground construction, and the above-ground construction is frequently a sequential, continuous process, i.e., the A-column frame, B-column frame, C-column frame, turbine foundation, and furnace connection platform are constructed in sequence, with the next item only starting after the previous one is completed. This method has the following problems: 1. The underground and above-ground parts are constructed in an interspersed manner. The underground part cannot be sealed off at one time, and the zero-meter ground level cannot be formed as a whole. The site is muddy, dusty, and the working environment is poor. Furthermore, the secondary excavation of the underground part during the interspersed construction can easily disturb the already formed foundation components, causing rework and posing high safety risks. 2. The handover of civil engineering work was delayed, and the installation of turbine, electrical, and thermal control systems was delayed, resulting in a long construction period; 3. The construction cycle of serial assembly line operations is long, and the amount of turnover materials such as scaffolding is large.
[0004] Therefore, a construction method for the main plant is designed to solve the above problems. Summary of the Invention
[0005] To address the problems mentioned in the background section, this invention provides a construction method for a main plant building, which features reduced use of scaffolding materials, shorter construction period, and significantly improved on-site safety and civility.
[0006] To achieve the above objectives, the present invention provides the following technical solution: a construction method for a main plant building, comprising the following steps: S1: Simultaneously excavate the foundation pits in column A, column B, column C, steam turbine foundation pit, coal mill foundation pit, condensate pump pit, and circulating water pit, and simultaneously pour concrete to form the underground foundations in column A, column B, column C, condensate pump pit, circulating water pit, and steam turbine foundation. S2: Backfill the turbine foundation pit and the area around the circulating water pit, and then pour the underground foundation of the furnace connection platform. S3: Pour the underground foundation of the coal mill base in the foundation pit; S4: After backfilling the foundation pits in column A and the area around the coal mill foundation pit, construct underground facilities; S5: Overall backfilling, pouring ground beams and zero-meter rough ground, sealing the underground part, underground part construction completed; S6: Using the underground foundations of column B, column C, and turbine base as construction nodes, construct column B, column C, and turbine base to the intermediate layer height. During construction, using the underground foundations of column A, furnace front connecting platform underground foundation, and turbine base intermediate layer as construction nodes, construct column A and furnace front connecting platform to the intermediate layer height. S7: Using the middle layer of columns B and C as construction nodes, construct columns B and C to the operating floor height. During construction, using the middle layer of column A and the furnace front connection platform as construction nodes, construct column A and the furnace front connection platform to the operating floor height. S8: Using the intermediate layer of the turbine foundation as the construction node, the turbine foundation is constructed to the height of the operating layer, and the above-ground construction is completed.
[0007] Furthermore, the specific steps of step S1 include: Excavate the turbine foundation pit, and simultaneously excavate the foundation pits in columns A, B, and C, as well as the coal mill foundation pit; After the turbine foundation pit is excavated to the design elevation, the condensate pump pit is excavated at the bottom, and the circulating water pit is excavated on the outside at the same time. The bottom slab and wall reinforcement are tied inside the condensate pump pit and circulating water pit excavated to the design elevation, and the pit formwork is erected. In the turbine foundation pit excavated to the design elevation, the bottom slab reinforcement, the bottom anchorage reinforcement of the lower solid section of the foundation, and the bottom anchorage reinforcement of the underground cylinder extending to the design elevation are tied. The bottom slab reinforcement is reserved with a structural opening connected to the condensate pump pit, and the pit formwork is erected. When tying steel bars in the foundation pits of condensate pump pits, circulating water pits, and turbine foundation pits, simultaneously tie the bottom slab steel bars and the short column steel bars of the underground section that are anchored into the bottom slab and extended to the design elevation in the foundation pits of column A, column B, and column C excavated to the design elevation, and erect the pit formwork. Concrete is poured into the formwork, cured to the specified strength, and then the formwork is removed to form the underground foundations of the pump pit, circulating water pit, turbine base, and columns A, B, and C.
[0008] Furthermore, the specific steps of step S2 include: On the foundation surface backfilled to the design elevation, the short column reinforcement extending to the design elevation at the top is tied between the underground foundation of column A and the turbine foundation, and formwork is erected. Concrete is poured into the formwork, cured to the specified strength, and then the formwork is removed to form the underground foundation of the furnace front connection platform.
[0009] Furthermore, the specific steps of step S3 include: In the coal mill foundation pit excavated to the design elevation, the bottom slab and the lower solid steel reinforcement anchored into the bottom slab are tied, and the anchor bolt sleeves are pre-embedded and the pit formwork is erected. Concrete is poured into the formwork, cured to the specified strength, and then the formwork is removed to form the underground foundation of the coal mill.
[0010] Furthermore, the specific steps of step S4 include: Excavate ground beams on the foundation surface that has been backfilled to the design elevation; Tie the reinforcing bars that are lapped and welded to the short column reinforcing bars of the underground foundation in columns A, B and C within the ground beam excavated to the design elevation, and erect the pit formwork. Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and the ground beam is formed; A floor slab layer is laid on the foundation surface that has been backfilled to the design elevation. Two-way steel mesh is tied on the subfloor layer, and structural openings are reserved in the bottom slab steel bars to connect with the condensate pump pit, and pit formwork is erected. Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and a zero-meter rough floor is formed.
[0011] Furthermore, the specific steps of step S6 include: Using the underground short column reinforcement of the underground foundation of columns B and C as connection points, tie the reinforcement of the above-ground frame columns of columns B and C that extend to the design elevation of the intermediate floor, and the top reinforcement of the above-ground frame columns of columns B and C that are anchored at the top of the design elevation of the intermediate floor. Using the above-ground frame column reinforcement in columns B and C as connection points, tie the intermediate layer beam reinforcement in columns B and C; Using the intermediate beam reinforcement in columns B and C as connection points, tie the intermediate slab reinforcement in columns B and C; Using the underground cylinder reinforcement of the turbine foundation as the connection point, tie the turbine foundation intermediate layer reinforcement extending to the intermediate layer design elevation, the side reinforcement of the turbine foundation intermediate layer with one end anchored into the intermediate layer design elevation, and the top reinforcement of the turbine foundation intermediate layer anchored at the top of the intermediate layer design elevation. Erect formwork, pour concrete into the formwork, cure until the specified strength is reached, remove the formwork, and form columns B and C and the intermediate layer of the turbine base are formed; During construction, the short column reinforcement of the underground section of the underground foundation of column A is used as the connection point to tie the reinforcement of the above-ground frame column of column A that extends to the design elevation of the intermediate layer, and the top reinforcement of the above-ground frame column of column A that is anchored at the top of the design elevation of the intermediate layer. Using the underground short column reinforcement of the furnace front connection platform foundation as the connection point, the above-ground frame column reinforcement extending to the design elevation of the intermediate floor is tied. Using the above-ground frame column reinforcement in column A, the above-ground frame column reinforcement in the furnace front connecting platform, and the side reinforcement of the intermediate layer of the turbine base as connection points, tie the reinforcement of the intermediate layer floor slab of the furnace front connecting platform. Erect formwork, pour concrete into the formwork, cure until the specified strength is reached, remove the formwork, and form an integral intermediate layer structure.
[0012] Furthermore, the specific steps of step S7 include: Using the top reinforcement bars at the top of the above-ground frame columns in columns B and C as connection points, tie the reinforcement bars of the above-ground frame columns in columns B and C extending to the design elevation of the operating floor; Using the above-ground frame column reinforcement bars in columns B and C as connection points, tie the working floor beam reinforcement bars in columns B and C; Using the reinforcement bars of the moving layer beams in columns B and C as connection points, tie the reinforcement bars of the moving layer slabs in columns B and C; Erect formwork, pour concrete into the formwork, cure until the specified strength is reached, remove the formwork, and form the B and C column operating layers; Using the top steel bars at the top of the above-ground frame column of column A as the connection point, tie the steel bars of the above-ground frame column of column A that extend to the design elevation of the operating floor; Using the reinforcement bars of the above-ground frame columns of column A, which extend to the design elevation of the operating floor, as connection points, the reinforcement bars of the operating floor beams are tied. Using the reinforcing bars of the operating layer beam as connection points, tie the reinforcing bars of the large platform slab of the operating layer of the furnace front connecting platform. Erect formwork, pour concrete into the formwork, cure until the specified strength is reached, remove the formwork, and formwork to form the A-column and furnace front communication platform operation layer.
[0013] Furthermore, the specific steps of step S8 include: Using the top steel bars at the top of the intermediate layer of the turbine foundation as connection points, tie the steel bars of the above-ground frame columns of the turbine foundation extending to the design elevation of the operating layer; Using the steel reinforcement of the above-ground frame column of the turbine base extending to the design elevation of the operating floor as the connection point, the steel reinforcement of the operating floor slab is tied, and the pad plate and anchor bolt are pre-embedded. Erect formwork, pour concrete into the formwork, cure until the specified strength is reached, remove the formwork, and form the operating layer of the turbine base.
[0014] Compared with the prior art, the beneficial effects of the present invention are: 1. This invention treats the entire underground part of the main plant as an independent construction section. After the entire underground part is completed and the concrete floor is poured, the above-ground structure of the main plant is started. This can minimize the cross-operations in the conventional construction process, improve the construction working environment, enhance construction safety, and significantly improve the safety and civilized image of the site.
[0015] 2. The construction of the main plant's above-ground structure of this invention involves the simultaneous construction of the ABC column frame structure, the furnace front connection platform, and the turbine foundation. The concrete is poured layer by layer, starting with the intermediate layer and then the operating layer. Compared with the existing sequential assembly line operation of A column, B column, C column, turbine foundation, and furnace front connection platform, the upper and lower hard isolation can be completed in advance. Electrical, thermal control, and turbine professionals can enter the site earlier for layered construction, shortening the construction period.
[0016] 3. In this invention, the concrete is poured in layers, first the intermediate layer and then the operating layer, and the poured intermediate layer can be used as a working platform, reducing the height and size of the scaffolding and reducing the amount of scaffolding turnover materials used. Attached Figure Description
[0017] Figure 1 This is a flowchart of the method of the present invention. Detailed Implementation
[0018] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0019] This invention provides the following technical solution: a construction method for a main plant building, comprising the following steps: S1: Simultaneous excavation of foundation pits in columns A, B, and C, including steam turbine foundation pit, coal mill foundation pit, condensate pump pit, and circulating water pit. Steam turbine foundation pit, condensate pump pit, and circulating water pit are considered deep foundation pits. Pit A, pit B, pit C, and coal mill foundation pit are considered shallow foundation pits. Earthwork excavation should follow the principle of excavating deep pits first and then shallow pits, and the steps are as follows: Excavate the turbine foundation pit between column A and column B, and simultaneously excavate column A, column B, column C, and the coal mill foundation pit between column B and column C. After the turbine foundation pit is excavated to the design elevation, the condensate pump pit is excavated at the bottom, and the circulating water pit is excavated on the outside at the same time. Simultaneous excavation can avoid the disturbance of secondary excavation after backfilling, reduce the need for earthmoving machinery to enter the site twice, and shorten the earthmoving phase construction period. S2: Simultaneous pouring of underground foundations in columns A, B, and C, including condensate pump pits, circulating water pits, and turbine foundations. Prioritizing the completion of the main structure of deep foundation pits can shorten the exposure time of the bare pits and reduce the risk of slope instability and water seepage. The steps are as follows: The bottom slab and wall reinforcement are tied inside the condensate pump pit and circulating water pit excavated to the design elevation, and the pit formwork is erected. In the turbine foundation pit excavated to the design elevation, the bottom slab reinforcement, the bottom anchorage reinforcement of the lower solid section of the foundation, and the bottom anchorage reinforcement of the underground cylinder extending to the design elevation are tied. The bottom slab reinforcement is reserved with a structural opening connected to the condensate pump pit, and the pit formwork is erected. Pour concrete into the formwork of the condensate pump pit and the circulating water pit, cure it to the specified strength, remove the formwork, and the condensate pump pit and the circulating water pit are formed. Concrete is poured into the formwork of the turbine foundation pit, cured to the specified strength, and then the formwork is removed to form the underground foundation of the turbine foundation. Columns A, B, and C are the foundation of the main load-bearing upper part of the factory building. These should be completed first to establish the load-bearing points. The steps are as follows: When tying steel bars in the foundation pits of condensate pump pits, circulating water pits, and steam turbine foundation pits, simultaneously tie the bottom slab steel bars and the short column steel bars of the underground section that are anchored into the bottom slab and extended to the design elevation in the foundation pits of column A, column B, and column C, and erect the pit formwork. Concrete was poured into the formwork of foundation pits A, B, and C, cured to the specified strength, and the formwork was removed to form the underground foundations of columns A, B, and C. Because the underground foundations of columns B and C will undergo early consolidation settlement under the action of the superstructure load after pouring, if the coal mill foundation pit is poured at the same time, the different consolidation settlement rate between it and the underground foundations of columns B and C will result in a settlement difference. The settlement difference will generate additional shear stress in the coal mill foundation, causing cracking. Cracking will cause the coal mill to vibrate excessively, affecting safe operation. Therefore, the coal mill foundation pit will not be constructed for the time being. S3: Backfilling construction around the turbine foundation pit and circulating water pit. After the underground foundations of columns A, B, and C are poured, lateral soil constraints are needed to restore the actual service stress boundary conditions, allowing the underground foundations of columns A, B, and C to release early consolidation settlement and provide foundation conditions at zero ground level. The steps are as follows: Locally backfill and compact the soil in layers around the outer perimeter of the turbine foundation pit and the circulating water pit until the design elevation of the furnace front connection platform foundation is reached. S4: Underground foundation construction of furnace front communication platform The underground foundation of the furnace front connecting platform is the load-bearing base of the upper part of the platform and should be completed first. This will establish a stress point and avoid the risk of disturbing the pre-embedded components of the coal mill foundation during earthwork construction. The steps are as follows: On the foundation surface backfilled to the design elevation, the short column reinforcement extending to the design elevation at the top is tied between the underground foundation of column A and the turbine foundation, and formwork is erected. Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and form the underground foundation of the furnace front connection platform; S5: Construction of underground foundation for coal mill The underground foundations in columns B and C can be constructed faster than those in column A. Since the coal mill foundation's load-bearing capacity depends on the underground foundations in columns B and C, its construction should be prioritized to shorten the construction period. The steps are as follows: In the coal mill foundation pit excavated to the design elevation, the bottom slab and the lower solid steel reinforcement anchored into the bottom slab are tied, and the anchor bolt sleeves are pre-embedded and the pit formwork is erected. Pour concrete into the formwork of the coal mill base pit, cure it to the specified strength, remove the formwork, and form the coal mill foundation; S6: Backfilling construction around the foundation pit and coal mill foundation pit in column A. Locally backfill and compact the soil in layers around the outer perimeter of the foundation pit in column A and the coal mill foundation pit; S7: Underground facility construction Underground facilities are constructed according to the drawings, including underground pipe trenches, underground drainage structures, and pre-buried underground pipelines; S8: Overall backfilling construction The underground cylindrical steel reinforcement of the turbine foundation and the underground short column steel reinforcement of columns A, B and C are wrapped and protected. The soil is backfilled and compacted in layers until the design elevation of the foundation surface is reached; S9: Ground beam pouring Excavate ground beams on the foundation surface that has been backfilled to the design elevation; Tie the reinforcing bars that are lapped and welded to the short column reinforcing bars of the underground foundation in columns A, B and C within the ground beam excavated to the design elevation, and erect the pit formwork. Concrete is poured into the formwork of the ground beam, cured to the specified strength, and the formwork is removed to form the ground beam of the underground section short column steel reinforcement of columns A, B and C underground foundation into an integral structure. S10: Zero-meter rough ground pouring A floor slab layer is laid on the foundation surface that has been backfilled to the design elevation. Two-way steel mesh is tied on the subfloor layer, and structural openings are reserved in the bottom slab steel bars to connect with the condensate pump pit, and pit formwork is erected. Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and a zero-meter rough floor is formed; S11: Simultaneous construction of columns B and C, and the intermediate layer of the turbine foundation. Columns B and C have smaller dimensions and spans, requiring less reinforcement and formwork work, and allowing for faster construction. Therefore, the intermediate layers of columns B and C should be constructed first to avoid the overall construction period being constrained by the long construction period of the large-span furnace front connection platforms in columns A and B. Meanwhile, the intermediate layer of the turbine foundation is a cylindrical foundation structure and does not serve as a load-bearing platform for the turbine generator; therefore, it should be constructed simultaneously with the intermediate layers of columns B and C, following these steps: Erecting scaffolding templates; Using the underground short column reinforcement of the underground foundation of columns B and C as connection points, tie the reinforcement of the above-ground frame columns of columns B and C extending to the design elevation of the intermediate floor, the top reinforcement of the above-ground frame columns of columns B and C anchored at the top of the design elevation of the intermediate floor, and set up the formwork. Using the above-ground frame column reinforcement bars in columns B and C as connection points, tie the intermediate layer beam reinforcement bars in columns B and C, and erect formwork; Using the intermediate beam reinforcement in columns B and C as connection points, tie the intermediate slab reinforcement in columns B and C, and erect the formwork; Using the underground cylinder reinforcement of the turbine foundation as the connection point, tie the turbine foundation intermediate layer reinforcement extending to the intermediate layer design elevation, the side reinforcement of the turbine foundation intermediate layer with one end anchored into the intermediate layer design elevation, and the top reinforcement of the turbine foundation intermediate layer anchored at the top of the intermediate layer design elevation, and erect the formwork. Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and form the intermediate layer of frame columns, beams and slabs and turbine base in columns B and C; S12: Construction of the intermediate layer of column A, furnace front connection platform During the construction of columns B and C, and the intermediate layer of the turbine foundation, the formwork erection and rebar binding of column A and the intermediate layer of the furnace front connecting platform are carried out simultaneously. However, due to the long construction period of the formwork erection and rebar binding of column A and the intermediate layer of the furnace front connecting platform, they are not poured simultaneously with columns B and C and the intermediate layer of the turbine foundation. Instead, they are constructed after columns B and C and the intermediate layer of the turbine foundation to shorten the construction period. The steps are as follows: Erecting scaffolding templates; Using the underground short column reinforcement of column A underground foundation as the connection point, tie the reinforcement of column A above ground frame column extending to the design elevation of the intermediate floor, the top reinforcement of column A above ground frame column anchored at the top of the design elevation of the intermediate floor, and set up the formwork. Using the underground short column reinforcement of the furnace front connection platform foundation as the connection point, the above-ground frame column reinforcement extending to the design elevation of the intermediate floor is tied and the formwork is erected. Using the above-ground frame column reinforcement in column A, the above-ground frame column reinforcement in the furnace front connecting platform, and the side reinforcement of the intermediate layer of the turbine base as connection points, tie the intermediate layer floor slab reinforcement of the furnace front connecting platform and set up the formwork. Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and form an integral intermediate layer structure, which serves as the first rigid isolation working surface; S13: Construction of the operating layers in columns B and C The B and C columns of the operating layer use the middle layer of B and C columns as the working support surface for upward formwork construction. This eliminates the need to rebuild the bottom scaffolding, reducing the amount of scaffolding work and improving the efficiency of upper construction. The steps are as follows: Upward-folding formwork is used to erect scaffolding templates; Using the top reinforcement bars at the top of the above-ground frame columns in columns B and C as connection points, tie the reinforcement bars of the above-ground frame columns in columns B and C extending to the design elevation of the operating floor, and erect formwork. Using the steel bars of the above-ground frame columns in columns B and C as connection points, tie the steel bars of the moving floor beams in columns B and C, and erect the formwork; Using the reinforcement bars of the moving floor beams in columns B and C as connection points, tie the reinforcement bars of the moving floor slabs in columns B and C, and erect the formwork; Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and form the B and C column operating layers; S14: Construction of Column A, Furnace Front Connecting Platform Operation Layer During the construction of the B and C column operating levels, the A column and furnace front connecting platform operating levels will use the middle layer of the A column and furnace front connecting platform as the working support surface for upward formwork construction. This eliminates the need to rebuild the bottom scaffolding, reducing the amount of scaffolding construction work and improving the efficiency of upper construction. The steps are as follows: Upward-folding formwork is used to erect scaffolding templates; Using the top steel bars at the top of the above-ground frame column of column A as the connection point, tie the steel bars of the above-ground frame column of column A extending to the design elevation of the operating floor, and erect the formwork; Using the reinforcement bars of the above-ground frame columns in column A, which extend to the design elevation of the operating floor, as connection points, the reinforcement bars of the operating floor beams are tied, and formwork is erected. Using the reinforcing bars of the operating layer beam as connection points, tie the reinforcing bars of the large platform slab of the operating layer of the furnace front connecting platform, and set up the formwork; Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and form the A column and furnace front communication platform operation layer; S15: Construction of the operating layer of the steam turbine foundation The turbine foundation operating layer is constructed by flipping the formwork upwards from the intermediate layer of the turbine foundation. The operating layer requires pre-embedded pads and anchor bolts, demanding high precision. It cannot be poured simultaneously with other operating layers to avoid disturbance from construction in other areas affecting positioning accuracy. The steps are as follows: Upward-folding formwork is used to erect scaffolding templates; Using the top steel bars at the top of the intermediate layer of the turbine foundation as connection points, tie the steel bars of the above-ground frame columns of the turbine foundation extending to the design elevation of the operating layer, and erect formwork. Using the steel reinforcement of the above-ground frame column of the turbine base extending to the design elevation of the operating floor as the connection point, the steel reinforcement of the operating floor slab is tied, and at the same time, pads and anchor bolts are pre-embedded, and formwork is erected. Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and form the turbine base operating layer; Overall construction completed; Suitable for single-unit construction, and also suitable for multi-unit construction. In multi-unit construction, the construction of later units is delayed by 7-15 days compared to earlier units, with the following effects: To avoid the excavation of foundation pits for subsequent unit construction affecting preceding units and causing rework; Staggered construction allows for the construction of the above-ground parts of some units to begin after the underground parts of some units are completed, without having to wait for the underground parts of all units to be completed, breaking the current limitation of completely sequential assembly line operations for multiple units. Staggered construction and the distribution of civil engineering and installation work across different unit areas can avoid a large number of overlapping operations in the same space.
[0020] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A construction method for a main plant building, characterized in that, Includes the following steps: S1: Simultaneously excavate the foundation pits in column A, column B, column C, steam turbine foundation pit, coal mill foundation pit, condensate pump pit, and circulating water pit, and simultaneously pour the underground foundations in column A, column B, column C, condensate pump pit, circulating water pit, and steam turbine foundation. S2: Backfill the turbine foundation pit and the area around the circulating water pit, and then pour the underground foundation of the furnace connection platform. S3: Pour the underground foundation of the coal mill base in the foundation pit; S4: After backfilling the foundation pits in column A and the area around the coal mill foundation pit, construct underground facilities; S5: Overall backfilling, pouring ground beams and zero-meter rough ground, sealing the underground part, underground part construction completed; S6: Using the underground foundations of column B, column C, and turbine base as construction nodes, construct column B, column C, and turbine base to the intermediate layer height. During construction, using the underground foundations of column A, furnace front connecting platform underground foundation, and turbine base intermediate layer as construction nodes, construct column A and furnace front connecting platform to the intermediate layer height. S7: Using the middle layer of columns B and C as construction nodes, construct columns B and C to the operating floor height. During construction, using the middle layer of column A and the furnace front connection platform as construction nodes, construct column A and the furnace front connection platform to the operating floor height. S8: Using the intermediate layer of the turbine foundation as the construction node, the turbine foundation is constructed to the height of the operating layer, and the above-ground construction is completed.
2. The construction method for a main plant building according to claim 1, characterized in that: The specific steps of step S1 include: Excavate the turbine foundation pit, and simultaneously excavate the foundation pits in column A, column B, column C, and the coal mill foundation pit; After the turbine foundation pit is excavated to the design elevation, the condensate pump pit is excavated at the bottom, and the circulating water pit is excavated on the outside at the same time. The bottom slab and wall reinforcement are tied inside the condensate pump pit and circulating water pit excavated to the design elevation, and the pit formwork is erected. In the turbine foundation pit excavated to the design elevation, the bottom slab reinforcement, the bottom anchorage reinforcement of the lower solid section of the foundation, and the bottom anchorage reinforcement of the underground cylinder extending to the design elevation are tied. The bottom slab reinforcement is reserved with a structural opening connected to the condensate pump pit, and the pit formwork is erected. When tying steel bars in the foundation pits of condensate pump pits, circulating water pits, and turbine foundation pits, simultaneously tie the bottom slab steel bars and the short column steel bars of the underground section that are anchored into the bottom slab and extended to the design elevation in the foundation pits of column A, column B, and column C excavated to the design elevation, and erect the pit formwork. Concrete is poured into the formwork, cured to the specified strength, and then the formwork is removed to form the underground foundations of the pump pit, circulating water pit, turbine base, and columns A, B, and C.
3. The construction method for a main plant building according to claim 2, characterized in that: The specific steps of step S2 include: On the foundation surface backfilled to the design elevation, the short column reinforcement extending to the design elevation at the top is tied between the underground foundation of column A and the turbine foundation, and formwork is erected. Concrete is poured into the formwork, cured to the specified strength, and then the formwork is removed to form the underground foundation of the furnace front connection platform.
4. The construction method for a main plant building according to claim 3, characterized in that: The specific steps of step S3 include: In the coal mill foundation pit excavated to the design elevation, the bottom slab and the lower solid steel reinforcement anchored into the bottom slab are tied, and the anchor bolt sleeves are pre-embedded and the pit formwork is erected. Concrete is poured into the formwork, cured to the specified strength, and then the formwork is removed to form the underground foundation of the coal mill.
5. The construction method for a main plant building according to claim 4, characterized in that: The specific steps of step S4 include: Excavate ground beams on the foundation surface that has been backfilled to the design elevation; Tie the reinforcing bars that are lapped and welded to the short column reinforcing bars of the underground foundation in columns A, B and C within the ground beam excavated to the design elevation, and erect the pit formwork. Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and the ground beam is formed; A floor slab layer is laid on the foundation surface that has been backfilled to the design elevation. Two-way steel mesh is tied on the subfloor layer, and structural openings are reserved in the bottom slab steel bars to connect with the condensate pump pit, and pit formwork is erected. Pour concrete into the formwork, cure it to the specified strength, remove the formwork, and a zero-meter rough floor is formed.
6. The construction method for a main plant building according to claim 5, characterized in that: The specific steps of step S6 include: Using the underground short column reinforcement of the underground foundation of columns B and C as connection points, tie the reinforcement of the above-ground frame columns of columns B and C that extend to the design elevation of the intermediate floor, and the top reinforcement of the above-ground frame columns of columns B and C that are anchored at the top of the design elevation of the intermediate floor. Using the above-ground frame column reinforcement in columns B and C as connection points, tie the intermediate layer beam reinforcement in columns B and C; Using the intermediate beam reinforcement in columns B and C as connection points, tie the intermediate slab reinforcement in columns B and C; Using the underground cylinder reinforcement of the turbine foundation as the connection point, tie the turbine foundation intermediate layer reinforcement extending to the intermediate layer design elevation, the side reinforcement of the turbine foundation intermediate layer with one end anchored into the intermediate layer design elevation, and the top reinforcement of the turbine foundation intermediate layer anchored at the top of the intermediate layer design elevation. Erect formwork, pour concrete into the formwork, cure until the specified strength is reached, remove the formwork, and form columns B and C and the intermediate layer of the turbine base are formed; During construction, the short column reinforcement of the underground section of the underground foundation of column A is used as the connection point to tie the reinforcement of the above-ground frame column of column A that extends to the design elevation of the intermediate layer, and the top reinforcement of the above-ground frame column of column A that is anchored at the top of the design elevation of the intermediate layer. Using the underground short column reinforcement of the furnace front connection platform foundation as the connection point, the above-ground frame column reinforcement extending to the design elevation of the intermediate floor is tied. Using the above-ground frame column reinforcement in column A, the above-ground frame column reinforcement in the furnace front connecting platform, and the side reinforcement of the intermediate layer of the turbine base as connection points, tie the reinforcement of the intermediate layer floor slab of the furnace front connecting platform. Erect formwork, pour concrete into the formwork, cure until the specified strength is reached, remove the formwork, and form an integral intermediate layer structure.
7. The construction method for a main plant building according to claim 6, characterized in that: The specific steps of step S7 include: Using the top reinforcement bars at the top of the above-ground frame columns in columns B and C as connection points, tie the reinforcement bars of the above-ground frame columns in columns B and C extending to the design elevation of the operating floor; Using the above-ground frame column reinforcement bars in columns B and C as connection points, tie the working floor beam reinforcement bars in columns B and C; Using the reinforcement bars of the moving layer beams in columns B and C as connection points, tie the reinforcement bars of the moving layer slabs in columns B and C; Erect formwork, pour concrete into the formwork, cure until the specified strength is reached, remove the formwork, and form the B and C column operating layers; Using the top steel bars at the top of the above-ground frame column of column A as the connection point, tie the steel bars of the above-ground frame column of column A that extend to the design elevation of the operating floor; Using the reinforcement bars of the above-ground frame columns of column A, which extend to the design elevation of the operating floor, as connection points, the reinforcement bars of the operating floor beams are tied. Using the reinforcing bars of the operating layer beam as connection points, tie the reinforcing bars of the large platform slab of the operating layer of the furnace front connecting platform. Erect formwork, pour concrete into the formwork, cure until the specified strength is reached, remove the formwork, and formwork to form the A-column and furnace front communication platform operation layer.
8. The construction method of a main plant building according to claim 7, characterized in that: The specific steps of step S8 include: Using the top steel bars at the top of the intermediate layer of the turbine foundation as connection points, tie the steel bars of the above-ground frame columns of the turbine foundation extending to the design elevation of the operating layer; Using the steel reinforcement of the above-ground frame column of the turbine base extending to the design elevation of the operating floor as the connection point, the steel reinforcement of the operating floor slab is tied, and the pad plate and anchor bolt are pre-embedded. Erect formwork, pour concrete into the formwork, cure until the specified strength is reached, remove the formwork, and form the operating layer of the turbine base.