A UHPC-NC combined shield tunnel segment and its preparation method

By setting up a UHPC area near the shield tunnel segment joint and connecting it with a permanent metal interface plate, the problems of insufficient resistance and interface connection of the shield tunnel segment joint under explosive impact were solved, thereby improving the local load-bearing capacity and overall integrity, while controlling material costs.

CN123109706APending Publication Date: 2026-11-17SOUTHEAST UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611581562.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-13
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

The joint area of ​​shield tunnel segments is prone to stress concentration under the impact of explosion. Existing technologies, such as using ultra-high performance concrete for the entire segment, are costly and have poor interface connections.

Method used

A UHPC zone is set up in the vicinity of the segment joint and connected to the NC zone through a permanent metal interface plate. The high strength and crack resistance of ultra-high performance concrete are utilized, combined with the mechanical connection of the permanent metal interface plate, to form a composite load-bearing structure.

Benefits of technology

It improves the local load-bearing capacity and integrity of shield tunnel segments under explosive impact, reduces material costs, enhances the force transmission capacity of interface connections, and improves resistance to damage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109706A_ABST
    Figure CN123109706A_ABST
Patent Text Reader

Abstract

This invention discloses a UHPC-NC combined shield tunnel segment and its preparation method, belonging to the field of shield tunnel construction technology. The combined shield tunnel segment of this invention includes an NC region in the center, a UHPC region on the periphery, and a permanent metal interface plate disposed at the interface between the two. The two regions are respectively composed of ordinary concrete, ultra-high performance concrete, and an internal reinforcing cage. The permanent metal interface plate includes a thin metal plate with mounting holes, a connecting sleeve passing through the mounting holes, and J-shaped anchors at both ends of the connecting sleeve. The connecting sleeve is fixed to the thin metal plate, and the J-shaped anchors on both sides are anchored to the NC region and the UHPC region, respectively. This invention achieves connection and coordinated stress distribution between the two regions through the permanent metal interface plate, and utilizes ultra-high performance concrete to locally reinforce weak areas such as segment joints, improving the overall resistance and damage resistance of the segment under explosive impact, while taking into account structural resistance, integrity, and material economy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of shield tunnel construction technology, specifically relating to a UHPC-NC combined shield tunnel segment and its preparation method. Background Technology

[0002] Shield tunnels are assembled from precast reinforced concrete segments through circumferential and longitudinal joints. Due to their advantages such as high construction efficiency, minimal impact on surface traffic, and strong adaptability to complex geological formations, they have been widely used in urban underground transportation and major infrastructure construction. However, with the rapid development of new energy vehicles, the increasing demand for hazardous chemical transportation, and the increasingly complex international security situation, shield tunnels and other critical underground infrastructure may face accidents or disasters during operation, including vehicle collisions, battery thermal runaway, hazardous chemical explosions, and, in extreme cases, weapon attacks.

[0003] Compared to the complete tunnel segment, the joint area of ​​the segment, due to the presence of localized weakening sections such as splicing seams, bolt holes, and manholes, is prone to significant stress concentration under explosive impact, making it a weak point in the shield tunnel structure. Currently, common approaches to improving the resistance of shield tunnel segments include increasing segment thickness, improving concrete strength, increasing reinforcement ratio, using high-performance concrete, and internally bonding steel plates or high-strength composite materials. Among these, ultra-high performance concrete (UHVPC) possesses high compressive strength, tensile strength, toughness, and crack resistance, exhibiting good deformation control and damage suppression capabilities under extreme loads such as impacts and explosions. Applying it to the joint area of ​​shield tunnel segments is expected to improve the local bearing capacity and impact resistance near the joint. However, replacing the entire segment with UHVPC would significantly increase material costs; furthermore, there are interface connection and co-stress issues between ordinary concrete and UHVPC. Therefore, localized reinforcement of the weak joint area necessitates a composite shield tunnel segment structure that balances structural resistance, integrity, and material economy. Summary of the Invention

[0004] Technical problem to be solved: In view of the technical problems existing in the background art, the present invention provides a UHPC-NC combined shield tunnel segment and its preparation method. The combined segment is formed by factory prefabrication. By setting a UHPC reinforcement area in the vicinity of the segment joint and using a permanent metal interface plate to achieve a reliable connection between the UHPC area and the NC area, the overall resistance of the shield tunnel segment under explosive impact is improved.

[0005] Technical solution: The UHPC-NC combined shield tunnel segment of the present invention includes an NC region located in the middle of the segment, a UHPC region disposed around the segment, and a permanent metal interface plate disposed at the interface between the NC region and the UHPC region. The NC area includes a regular concrete body and a steel cage set inside it. The UHPC area includes an ultra-high performance concrete body and a steel cage set inside it. The permanent metal interface plate includes a thin metal plate with mounting holes, a connecting sleeve fixedly inserted into the mounting holes, and J-shaped anchors respectively disposed at both ends of the connecting sleeve; the J-shaped anchors on both sides of the thin metal plate are respectively anchored to the NC region and the UHPC region, so that the NC region, the permanent metal interface plate and the UHPC region form a combined force-bearing structure.

[0006] Preferably, the UHPC region is located in the peripheral area of ​​the segment near the circumferential joint and the longitudinal joint, and covers at least one local stress concentration area among bolt holes, hand holes and corners of the segment.

[0007] Preferably, the width of the UHPC region extending from the edge of the tube segment toward the center is 100-400 mm.

[0008] Preferably, the connecting sleeve passes through the mounting hole, and the ends of the connecting sleeve located on both sides of the metal sheet are provided with limiting structures formed by upsetting. The size of the limiting structures is larger than the size of the mounting hole, so as to form axial limiting on both sides of the metal sheet.

[0009] Preferably, the straight end of the J-shaped anchor is provided with an external thread area, and both ends of the connecting sleeve are provided with internal thread areas that are adapted to the external thread area of ​​the J-shaped anchor. The J-shaped anchors located at both ends of the connecting sleeve are screwed into both ends of the connecting sleeve and fixed. Alternatively, the straight end of the J-shaped anchor is provided with a T-shaped locking head, and the end of the connecting sleeve is provided with a snap-fit ​​structure adapted to the T-shaped locking head. After the J-shaped anchor is inserted into the connecting sleeve, it forms an axial limit by rotation.

[0010] Preferably, the mounting hole is a non-circular hole, and the outer contour of the connecting sleeve passing through the mounting hole matches the shape of the mounting hole to limit relative rotation between the connecting sleeve and the metal sheet.

[0011] Preferably, the metal sheet is a steel plate with a thickness of 2-4 mm; The metal sheet has multiple mounting holes spaced apart along its length, with a spacing of 100-300mm between adjacent mounting holes.

[0012] Preferably, the metal sheet is an arc-shaped plate or a zigzag plate adapted to the boundary shape between the NC region and the UHPC region; The surface of the metal sheet is roughened and / or treated with anti-corrosion measures; and / or an anti-slip texture is provided.

[0013] Preferably, the J-shaped anchors on both sides of the metal sheet are arranged in a relative or staggered manner; The J-shaped anchor and connecting sleeve are staggered with the steel cage inside the NC area and the steel cage inside the UHPC area. The diameter of the J-shaped anchor is 8-16 mm.

[0014] This invention also discloses a method for preparing the above-mentioned UHPC-NC combined shield tunnel segments, comprising the following steps: Step 1: Determine the size and partition range of the NC area and UHPC area according to the structural design requirements of the tube segment, and cut, install, and drill holes in the metal sheet of the permanent metal interface plate. Step 2: Install the connecting sleeve into the corresponding mounting hole position on the metal sheet, and form a limiting structure by thickening the end to fix the connecting sleeve on the metal sheet; Step 3: Screw the external threaded area of ​​the straight rod end of the J-shaped anchor into the internal threaded areas at both ends of the connecting sleeve, and tighten it to fix the connection. Step 4: Tie the reinforcing cages for the NC area and the UHPC area respectively, and position and fix the reinforcing cages and permanent metal interface plates so that the permanent metal interface plates are located at the design boundary between the NC area and the UHPC area. Step 5: Using a permanent metal interface plate as a partition template between the NC area and the UHPC area, ordinary concrete and ultra-high performance concrete are poured into the NC area and the UHPC area respectively, and then vibrated, shaped and cured to obtain the UHPC-NC combined shield tunnel segment.

[0015] Compared with the prior art, the present invention has the following beneficial effects: 1. To address the problem of insufficient resistance of weak areas such as segment joints under explosive impact, this invention sets up UHPC areas only in the vicinity of the segment joints. By utilizing the high strength, toughness and crack resistance of ultra-high performance concrete, the local bearing capacity and resistance to damage of the joint area under explosive impact are improved, which helps to reduce the risk of concrete cracking, spalling and local damage near the joint. 2. To address the interface connection and collaborative stress-bearing issues between ordinary concrete and ultra-high performance concrete, this invention sets up a permanent metal interface plate between the NC region and the UHPC region. Through the connecting sleeve and the double-sided J-shaped anchors, a mechanical connection is formed, which can enhance the interface force transmission capacity between the two types of concrete, limit the relative slippage and interface separation between the two types of concrete, promote collaborative stress-bearing between the NC region and the UHPC region, and thus improve the overall integrity of the composite segment. 3. Regarding the integrity of construction and structure, the permanent metal interface panel can be used as a partition template during the casting process. After molding, it continues to be retained inside the structure and provides certain constraints on the NC area, thus taking into account the structural resistance, integrity and construction convenience. 4. This invention uses ultra-high performance concrete only in the area near the joints around the segments and ordinary concrete in the central main area, which can reduce the amount of ultra-high performance concrete used. While improving local resistance, it can control material costs and is suitable for the factory prefabrication of shield tunnel segments. Attached Figure Description

[0016] Figure 1 This is a schematic diagram of the overall structure of the UHPC-NC combined shield tunnel segment of the present invention; Figure 2 for Figure 1 Schematic diagram of the structure of the permanent metal interface plate and J-shaped anchor; Figure 3 for Figure 1 Schematic diagram of the internal steel reinforcement cage arrangement of the UHPC-NC combined shield tunnel segments; Figure 4 for Figure 2 A partial cross-sectional view of the connection between the permanent metal interface plate and the J-shaped anchor.

[0017] Reference numerals: 1. NC area; 11. NC area reinforcement cage; 2. UHPC area; 21. UHPC area reinforcement cage; 3. Permanent metal interface plate; 31. Metal sheet; 32. J-shaped anchor; 33. Connecting sleeve. Detailed Implementation

[0018] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the following will be described in conjunction with the accompanying drawings. Figures 1-4 The technical solutions of the embodiments of the present invention are clearly and completely described. Obviously, the described embodiments are only a part of the embodiments of the present invention, not all of them. All other embodiments obtained by those skilled in the art based on the described embodiments of the present invention are within the scope of protection of the present invention.

[0019] Example 1: As Figures 1-4 As shown, the present invention discloses a UHPC-NC combined shield tunnel segment, including an NC region 1 located in the middle of the segment, a UHPC region 2 disposed around the segment, and a permanent metal interface plate 3 disposed at the interface between the NC region 1 and the UHPC region 2.

[0020] like Figure 1 and Figure 3As shown, NC region 1 is located in the central main area of ​​the composite segment, consisting of ordinary concrete body and NC region steel cage 11 set inside it. The compressive strength of ordinary concrete body is 30-60MPa.

[0021] like Figure 1 and Figure 3 As shown, UHPC zone 2 is located in the periphery of the segment near the circumferential and longitudinal joints, and covers at least one local stress concentration area among bolt holes, hand holes, and the corners of the segment. UHPC zone 2 consists of an ultra-high performance concrete body and a UHPC zone reinforcement cage 21 set inside it. The ultra-high performance concrete body has a compressive strength greater than 100 MPa and is incorporating steel fibers to improve the crack resistance, tensile strength, and impact resistance of the area near the joint.

[0022] UHPC region 2 extends from the edge of the segment towards the center, and its width is determined according to the segment size, the stress range of the joint, and the structural design requirements. In this embodiment, it is 100-400mm. By using ultra-high performance concrete only in the vicinity of the joint around the segment, while using ordinary concrete in the main central area, it is possible to improve the local resistance of the joint area while reducing the amount of ultra-high performance concrete used, thus balancing structural resistance and material economy.

[0023] like Figure 2 As shown, a permanent metal interface plate 3 is disposed between NC region 1 and UHPC region 2, including a metal sheet 31, J-shaped anchors 32, and connecting sleeves 33. The metal sheet 31 is a steel plate with a thickness of 2-4 mm. The metal sheet 31 can be processed into a corresponding arc-shaped plate or a zigzag-shaped plate according to the boundary shape of NC region 1 and UHPC region 2. The metal sheet 31 has multiple mounting holes (not shown in the figure) spaced apart along its length, with a spacing of 100-300 mm between adjacent mounting holes. During the concrete pouring process, the metal sheet 31 serves as a partition template between NC region 1 and UHPC region 2. After the segment is formed, it is retained inside the structure and participates in the interface force transfer between the two materials.

[0024] like Figure 4 As shown, the connecting sleeve 33 is fixedly inserted through the mounting hole of the metal sheet 31. The connecting sleeve 33 passes through the mounting hole, and its ends on both sides of the metal sheet 31 are provided with limiting structures formed by upsetting. The size of the limiting structures is larger than the size of the mounting hole, thus forming axial limiting on both sides of the metal sheet 31, thereby fixing the connecting sleeve 33 to the metal sheet 31. To reduce the possibility of rotation of the connecting sleeve 33 during the installation of the J-shaped anchor 32, the mounting hole of the metal sheet 31 can be set as a square hole or other non-circular hole with other structures. The outer contour of the connecting sleeve 33 passing through the mounting hole matches the shape of the mounting hole, thereby restricting relative rotation between the connecting sleeve 33 and the metal sheet 31.

[0025] like Figure 4 As shown, the J-shaped anchors 32 located on both sides of the metal sheet 31 are mechanically connected through the same connecting sleeve 33; the J-shaped anchors 32 on both sides of the metal sheet 31 are respectively anchored in the NC region 1 and the UHPC region 2, so that the NC region 1, the permanent metal interface plate 3 and the UHPC region 2 form a combined load-bearing structure; the diameter of the J-shaped anchors 32 can be selected from 8-16 mm.

[0026] In one specific embodiment, the straight end of the J-shaped anchor 32 is provided with an external threaded area, and both ends of the connecting sleeve 33 are provided with internal threaded areas that are adapted to the external threaded areas of the J-shaped anchor 32. The J-shaped anchors 32 located at both ends of the connecting sleeve 33 are screwed into both ends of the connecting sleeve 33 and tightened for fixation. When there is a tendency for relative slippage or separation between the NC region 1 and the UHPC region 2, the J-shaped anchor 32 is mechanically anchored to the concrete on both sides through its hook portion, and transmits the interface shear force and normal tensile force through the connecting sleeve 33 and the metal plate 31, thereby enhancing the connection performance between the NC region 1 and the UHPC region 2 and reducing the possibility of interface slippage, cracking or peeling.

[0027] In an optional embodiment, the straight end of the J-shaped anchor 32 is provided with a T-shaped locking head (not shown in the figure), and the end of the connecting sleeve 33 is provided with a snap-fit ​​structure adapted to the T-shaped locking head (not shown in the figure). After the J-shaped anchor 32 is inserted into the connecting sleeve 33, it forms an axial limit by rotation to improve assembly efficiency.

[0028] like Figure 3 As shown, the NC region 1 has an independent NC region reinforcement cage 11, and the UHPC region 2 has an independent UHPC region reinforcement cage 21. The J-shaped anchors 32 on both sides of the metal sheet 31 are arranged in a relative or staggered manner to meet the stress and structural requirements of different regions. The J-shaped anchors 32 and the connecting sleeves 33 are staggered from the NC region reinforcement cage 11 in NC region 1 and the UHPC region reinforcement cage 21 in UHPC region 2 to avoid spatial interference between the permanent metal interface plate 3 and the reinforcement cage during installation. The arrangement position and spacing of the J-shaped anchors 32 can be adjusted according to the actual reinforcement configuration of the segment to ensure that they are located between adjacent reinforcement bars.

[0029] To further improve the interfacial bonding performance between the metal sheet 31 and the concrete on both sides, the surface of the metal sheet 31 is roughened by sandblasting, roughening, etc., and can be treated with anti-corrosion according to the service environment of the shield tunnel. Anti-slip texture can also be set.

[0030] Example 2: This invention also discloses a method for preparing the above-mentioned UHPC-NC combined shield tunnel segments, comprising the following steps: Step 1: Determine the size and partition range of NC region 1 and UHPC region 2 according to the structural size of the pipe segment and the stress characteristics of the joint area. Then, according to the boundary shape between the two regions, cut, shape, and form the metal sheet 31 of the permanent metal interface plate 3. Then, according to the design spacing, open the mounting holes on the metal sheet 31 for installing the connecting sleeve 33.

[0031] Step 2: Install the connecting sleeves 33 in sequence at the corresponding mounting hole positions of the metal sheet 31, and roughen the ends of the connecting sleeves 33 on both sides of the metal sheet 31 so that the connecting sleeves 33 form axial limiting and are fixed on the metal sheet 31.

[0032] Step 3: Install the J-shaped anchors 32 on both sides of the connecting sleeve 33. During installation, screw the external threaded area of ​​the straight end of the J-shaped anchor 32 into the internal threaded areas at both ends of the connecting sleeve 33, and tighten and fix it to the connecting sleeve 33, so that the J-shaped anchors 32, the connecting sleeve 33 and the metal sheet 31 together form a permanent metal interface plate 3.

[0033] Step 4: Tie the NC area reinforcement cage 11 of NC area 1 and the UHPC area reinforcement cage 21 of UHPC area 2 respectively, and position and fix the reinforcement cages and permanent metal interface plate 3 inside the two areas according to the design position, so that the permanent metal interface plate 3 is accurately located at the design boundary position between NC area 1 and UHPC area 2, while ensuring that there is sufficient construction space between the J-shaped anchor 32 and the reinforcement cages on both sides.

[0034] Step 5: After completing the positioning of the reinforcing cage and permanent metal interface plate 3, use the permanent metal interface plate 3 as the partition template between NC area 1 and UHPC area 2. Pour ordinary concrete and ultra-high performance concrete into NC area 1 and UHPC area 2 respectively, and adopt the corresponding vibration, compaction and molding process according to the working performance of the two materials. After the pouring is completed, curing is carried out. After the concrete reaches the specified strength, the formwork is demolded to obtain the UHPC-NC combined shield tunnel segment with permanent metal interface constraint structure.

[0035] The permanent metal interface plate 3 of this invention serves as a partition template for the two types of concrete during the construction phase and remains inside the structure after the tunnel segment is formed. The mechanical connection formed by the metal sheet 31, connecting sleeve 33, and double-sided J-shaped anchors 32 improves the interface force transmission capacity between NC region 1 and UHPC region 2, allowing both concrete materials to share the load. Under explosive impact, UHPC region 2, located near the circumferential and longitudinal joints, can withstand significant local dynamic forces due to its high strength, toughness, and crack resistance, reducing the risk of concrete cracking, spalling, and localized damage near the joints. The permanent metal interface plate 3, through the J-shaped anchors 32 and connecting sleeve 33, transfers part of the load borne by UHPC region 2 to NC region 1, while simultaneously limiting relative slippage and interface separation between the two types of concrete, thereby improving the integrity of the composite tunnel segment and its resistance to damage under explosive impact.

[0036] The above are preferred embodiments of the present invention. It should be noted that, for those skilled in the art, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications should also be considered within the scope of protection of the present invention.

Claims

1. A UHPC-NC combined shield tunnel segment, characterized in that, It includes an NC region (1) located in the middle of the tube segment, a UHPC region (2) located around the tube segment, and a permanent metal interface plate (3) located at the interface between the NC region (1) and the UHPC region (2). The NC area (1) includes a plain concrete body and a steel cage set inside it; The UHPC area (2) includes an ultra-high performance concrete body and a steel cage set inside it. The permanent metal interface plate (3) includes a thin metal plate (31) with mounting holes, a connecting sleeve (33) fixedly inserted into the mounting holes, and J-shaped anchors (32) respectively set at both ends of the connecting sleeve (33); the J-shaped anchors (32) on both sides of the thin metal plate (31) are respectively anchored in the NC region (1) and the UHPC region (2), so that the NC region (1), the permanent metal interface plate (3) and the UHPC region (2) form a combined force-bearing structure.

2. The UHPC-NC combined shield tunnel segment according to claim 1, characterized in that, The UHPC area (2) is located in the periphery of the segment near the circumferential joint and the longitudinal joint, and covers at least one local stress concentration area among the bolt holes, hand holes and the corners of the segment.

3. The UHPC-NC combined shield tunnel segment according to claim 2, characterized in that, The width of the UHPC region (2) extending from the edge of the tube to the center is 100-400 mm.

4. The UHPC-NC combined shield tunnel segment according to claim 1, characterized in that, The connecting sleeve (33) is inserted into the mounting hole. The ends of the connecting sleeve (33) located on both sides of the metal sheet (31) are provided with limiting structures formed by upsetting. The size of the limiting structure is larger than the size of the mounting hole, so as to form axial limiting on both sides of the metal sheet (31).

5. The UHPC-NC combined shield tunnel segment according to claim 1, characterized in that, The straight end of the J-shaped anchor (32) is provided with an external thread area, and both ends of the connecting sleeve (33) are provided with internal thread areas that are adapted to the external thread area of ​​the J-shaped anchor (32). The J-shaped anchors (32) located at both ends of the connecting sleeve (33) are screwed into both ends of the connecting sleeve (33) and fixed. Alternatively, the straight end of the J-shaped anchor (32) is provided with a T-shaped lock head, and the end of the connecting sleeve (33) is provided with a snap-fit ​​structure adapted to the T-shaped lock head. After the J-shaped anchor (32) is inserted into the connecting sleeve (33), it forms an axial limit by rotation.

6. The UHPC-NC combined shield tunnel segment according to claim 1, characterized in that, The mounting hole is a non-circular hole. The outer contour of the connecting sleeve (33) passing through the mounting hole matches the shape of the mounting hole to limit relative rotation between the connecting sleeve (33) and the metal sheet (31).

7. The UHPC-NC combined shield tunnel segment according to claim 1, characterized in that, The metal sheet (31) is a steel plate with a thickness of 2-4 mm; The metal sheet (31) has a plurality of mounting holes spaced apart along its length, with a spacing of 100-300 mm between adjacent mounting holes.

8. The UHPC-NC combined shield tunnel segment according to claim 7, characterized in that, The metal sheet (31) is an arc-shaped or zigzag-shaped sheet adapted to the boundary shape between the NC region (1) and the UHPC region (2); The surface of the metal sheet (31) is roughened and / or treated with anti-corrosion measures; and / or an anti-slip texture is provided.

9. The UHPC-NC combined shield tunnel segment according to claim 1, characterized in that, The J-shaped anchors (32) on both sides of the metal sheet (31) are arranged in a relative or staggered manner; The J-shaped anchor (32) and connecting sleeve (33) are staggered with the steel cage inside the NC region (1) and the steel cage inside the UHPC region (2). The diameter of the J-shaped anchor (32) is 8-16 mm.

10. A method for preparing UHPC-NC combined shield tunnel segments as described in any one of claims 1-9, characterized in that, Includes the following steps: Step 1: Determine the size and partition range of the NC area (1) and UHPC area (2) according to the structural design requirements of the tube segment, and cut, install holes and cut the metal sheet (31) of the permanent metal interface plate (3); Step 2: Install the connecting sleeve (33) on the corresponding mounting hole opening position of the metal sheet (31), and form a limiting structure by thickening the end, so that the connecting sleeve (33) is fixed on the metal sheet (31); Step 3: Screw the external thread area of ​​the straight rod end of the J-shaped anchor (32) into the internal thread area at both ends of the connecting sleeve (33), and tighten it to fix the connection with the connecting sleeve (33); Step 4: Tie the reinforcing cages of NC area (1) and UHPC area (2) respectively, and position and fix the reinforcing cages and permanent metal interface plate (3) so that the permanent metal interface plate (3) is located at the design boundary between NC area (1) and UHPC area (2). Step 5: Using the permanent metal interface plate (3) as the partition template between the NC region (1) and the UHPC region (2), ordinary concrete and ultra-high performance concrete are poured into the NC region (1) and the UHPC region (2) respectively, and then vibrated, shaped and cured to obtain the UHPC-NC combined shield tunnel segment.