By setting up straight concrete sealing bodies between the gas storage chambers, the forces at both ends are offset, which solves the problems of large sealing body size and high construction difficulty, realizes efficient and reliable construction of underground high-pressure gas storage facilities, and optimizes the utilization of underground space.
Patent Information
- Application Number
- CN202611594574.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-15
- Publication Date
- 2026-11-17
AI Technical Summary
In existing technologies, the sealing bodies of underground high-pressure gas storage facilities are large in size, require high investment, and have long construction periods. Furthermore, they are highly dependent on the friction between the sealing body and the surrounding rock, making them prone to shear cracks or slippage damage. This results in high construction difficulty and low efficiency.
A straight concrete sealing body is installed between the gas storage chambers, which cancels out the forces at both ends, reduces the dependence on friction, optimizes the shape of the sealing body, reduces construction difficulty and improves efficiency.
The design of the straight concrete sealing body reduced the amount of engineering work and investment, shortened the construction period, improved construction efficiency and surrounding rock stability, enhanced the reliability of the sealing body, optimized the utilization rate of underground space, and solved the problem of limited storage capacity of underground high-pressure gas storage facilities.
Smart Images

Figure CN123109780A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of compressed gas energy storage technology, and in particular to an underground high-pressure gas storage system and its construction method. Background Technology
[0002] Compressed air energy storage is a technology that uses compressed air as a medium to store energy and generate electricity. Currently, salt caverns and artificially excavated chambers are commonly used as storage containers. For newly built underground gas storage facilities using artificial excavation chambers, the storage pressure can reach over 10 MPa. These gas storage facilities often use sealing steel plates as the sealing material, with concrete backfilled between the steel plates and the surrounding rock to transfer the load to the surrounding rock, which then bears more than 80% of the load. During the excavation of the gas storage facility, a construction passage is set up, which connects to the underground gas storage facility. After the gas storage sealing system is completed, the construction passage needs to be properly sealed, and the sealing body also serves to bear the pressure load of the gas storage chamber.
[0003] Domestic underground high-pressure gas storage facilities generally employ sliding-type sealing bodies, relying on the friction between the sealing body and the surrounding rock to resist the gas storage pressure. This method suffers from limitations such as large sealing body size, high investment, and long construction periods. Traditional techniques include using a constricted structure within the gas storage cavern to transfer pressure, transferring most of the high-pressure gas thrust to the constricted structure and the sidewalls of the access tunnel as the sealing structure. This type of design involves circumferential force transmission, resulting in large tension areas. Alternatively, T-shaped sealing bodies are used to transfer the high-pressure gas thrust to the surrounding rock. This type involves radial force transmission, but it results in asymmetrical stress, making the concrete and surrounding rock structures prone to stress concentration. Under the traditional non-concrete sealing body technology, the design and construction processes for wedge-shaped and T-shaped junction sections are demanding, with risks of overall sliding failure and localized shear failure in specific areas.
[0004] Therefore, there is an urgent need for an underground high-pressure gas storage system that forms a concrete sealing body with opposing forces, optimizes the shape of the concrete sealing body, reduces construction difficulty, and improves construction efficiency. Summary of the Invention
[0005] The purpose of this invention is to provide an underground high-pressure gas storage system and construction method to solve the problems existing in the prior art. A straight concrete sealing body is set between two gas storage chambers, and the forces at both ends of the concrete sealing body are offset, which effectively optimizes the shape of the concrete sealing body, reduces the construction difficulty and improves the construction efficiency.
[0006] To achieve the above objectives, the present invention provides the following solution: The present invention provides an underground high-pressure gas storage system, comprising: At least two gas storage chambers, wherein the gas storage chambers are located underground; At least one construction passage, with both ends of the construction passage connected to the gas storage chamber; A concrete sealing body, which is straight in shape, is installed in the construction channel, and its two ends respectively contact the gas storage chamber; And connecting wells, which are connected to the external environment and the construction passage respectively.
[0007] In one embodiment, the gas storage chambers at both ends of the construction channel are located on the same horizontal plane, and the construction channel is horizontally arranged.
[0008] In one embodiment, the gas storage chambers at both ends of the construction channel are parallel to each other.
[0009] In one embodiment, the concrete sealing body is perpendicular to the gas storage chambers on both sides.
[0010] In one embodiment, the internal steel reinforcement density of the concrete sealing body near the gas storage chamber is greater than that far from the gas storage chamber.
[0011] In one embodiment, an inflation / deflation pipe is pre-embedded in the concrete sealing body, and the inflation / deflation pipe is connected to an external inflation / deflation device through the concrete sealing body and the connecting well.
[0012] In one embodiment, the concrete sealing body is provided with an operation and maintenance passage, which is connected to the connecting well.
[0013] The present invention also provides a construction method for the construction of the above-mentioned underground high-pressure gas storage system, comprising the following steps: S1: Construct connecting wells, construction passages, and gas storage chambers; S2: The inner wall of the gas storage tunnel is fitted with sealing steel plates, and concrete is backfilled between the surrounding rock and the sealing steel plates. S3: Erect formwork and reinforcing bars in the construction passage, and pour concrete to form a concrete seal after the erection is completed.
[0014] In one embodiment, a cooling water passage is pre-embedded within the concrete seal, and cooling water is circulated into it after the concrete is poured.
[0015] In one embodiment, after the concrete sealant has cooled, backfill grouting and contact grouting are performed.
[0016] The present invention achieves the following main technical effects compared to the prior art: Overcoming the current limitations of underground high-pressure gas storage sealing technology, this paper proposes a novel underground high-pressure gas storage system. The linear concrete sealing element, installed within the construction passage, experiences pressure from the gas storage chambers on both ends during actual use. This pressure is transmitted through the linear concrete sealing element, allowing the forces at both ends to cancel each other out. This reduces reliance on friction between the concrete sealing element and the surrounding rock, significantly lowering the risk of shear cracks or slippage at the sealing element-rock interface. Stability is not improved by extending the sealing element length, thus reducing the amount of reinforced concrete, excavation, and grouting required. This optimizes the shape of the concrete sealing element and significantly reduces construction costs. The design reduces the amount of work and investment, shortens the construction period, lowers the construction difficulty, enhances the stability of the surrounding rock, and further improves construction efficiency. It also avoids stress concentration issues caused by unidirectional pressure in traditional single-end plugs, improving the reliability of the concrete sealing body. Furthermore, while ensuring the stability of the surrounding rock of the underground high-pressure gas storage facility and optimizing the shape of the concrete sealing body, it significantly reduces the length of auxiliary chambers such as construction access routes, improving the effective utilization rate of underground space. This solves the problem of limited underground space and restricted storage capacity in energy bases and industrial parks, and is of great significance to the development of underground gas storage construction technology for compressed air energy storage power stations.
[0017] Other solutions of the present invention achieve the following technical effects compared with the prior art: The design of the gas storage chambers at both ends of the construction channel being parallel to each other, and the concrete sealing bodies being perpendicular to the gas storage chambers on both sides, ensures that the forces on both ends of the concrete sealing bodies are similar in magnitude but opposite in direction, forming a force balance system.
[0018] The installation of inflation / deflation pipelines and maintenance access channels can improve the functionality of the concrete sealing body, reduce the excavation work of additional channels, and serve as a pressure balancing channel between the two chambers in emergencies, thereby improving system reliability. Attached Figure Description
[0019] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0020] Figure 1 This is a schematic diagram of the underground high-pressure gas storage system in an embodiment of the present invention; Figure 2 This is a schematic diagram of the structure of the gas storage chamber in an embodiment of the present invention; Figure 3 This is a schematic diagram of the horizontal cross-section of the concrete sealing body in an embodiment of the present invention; Figure 4 This is a schematic diagram of the vertical cross-section of the concrete sealing body in an embodiment of the present invention; Figure 5 for Figure 4 A magnified view of a section at point A in the middle; Figure 6 This is a schematic diagram of the inflation / deflation pipeline in an embodiment of the present invention; Figure 7 This is a schematic diagram of the operation and maintenance channel in an embodiment of the present invention; The components include: 1. Gas storage chamber; 2. Construction access; 3. Concrete sealing body; 4. Connecting well; 5. Gas filling and venting pipeline section; 6. Reserved access section; 7. Gas filling and venting pipeline; 8. Sealing steel plate; 9. Backfill concrete; 10. Operation and maintenance access; and 11. Pump pit. Detailed Implementation
[0021] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0022] The purpose of this invention is to provide an underground high-pressure gas storage system and construction method to solve the problems existing in the prior art. A straight concrete sealing body is set between two gas storage chambers. The forces at both ends of the concrete sealing body are offset, which effectively optimizes the shape of the concrete sealing body, reduces the construction difficulty and improves the construction efficiency.
[0023] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0024] Please refer to the following: Figures 1-7As shown, an underground high-pressure gas storage system is provided, comprising: at least two gas storage chambers 1, at least one construction passage 2, a concrete sealing body 3, and a connecting well 4. The gas storage chambers 1 are located underground. The two ends of the construction passage 2 are respectively connected to the gas storage chambers 1 (for example, when two gas storage chambers 1 are set, at least one construction passage 2 is set between the two gas storage chambers 1; when four gas storage chambers 1 are set, at least one construction passage 2 is set between every two gas storage chambers 1). The concrete sealing body 3 is straight to ensure stable force transmission. The concrete sealing body 3 is set in the construction passage 2, and the two ends of the concrete sealing body 3 are respectively in contact with the gas storage chambers 1. The connecting well 4 is connected to the external environment and the construction passage 2. The connecting well 4 can be vertically set in the middle of the construction passage 2. In actual use, the two ends of the concrete sealing body 3 are subjected to the pressure of the two gas storage chambers 1 on both sides. Through the transmission of the straight concrete sealing body 3, the forces at both ends can be offset, reducing the pressure on the concrete sealing body. The dependence of the frictional force between body 3 and the surrounding rock significantly reduces the risk of shear cracks or slippage at the interface between the plug and the surrounding rock. It eliminates the need to extend the length of the plug to improve stability, reducing the amount of reinforced concrete, excavation, and grouting required. This optimizes the shape of the concrete plug body 3, significantly reducing the workload and investment, shortening the construction period, lowering construction difficulty, and enhancing the stability of the surrounding rock. It also further improves construction efficiency and avoids stress concentration issues caused by unidirectional pressure in traditional single-end plugs, thus improving the reliability of the concrete plug body 3. Furthermore, while ensuring the stability of the surrounding rock of the underground high-pressure gas storage facility and optimizing the shape of the concrete plug body 3, it significantly reduces the length of auxiliary chambers such as construction passage 2, improving the effective utilization of underground space. This solves the problem of limited underground space and restricted storage capacity in energy bases and industrial parks, and is of great significance to the development of underground gas storage construction technology for compressed air energy storage power plants.
[0025] In one embodiment, the gas storage chambers 1 at both ends of the construction channel 2 are located on the same horizontal plane. The construction channel 2 is set horizontally. During the subsequent grouting process to form the concrete sealing body 3, the flow characteristics of the concrete are used to make the concrete sealing body 3 stably formed.
[0026] In one embodiment, the gas storage chambers 1 at both ends of the construction channel 2 are parallel to each other, which helps to improve the space occupancy rate, so as to increase the number of gas storage chambers 1 in the designated area and increase the gas storage capacity.
[0027] In actual design, the gas storage chamber 1 can be a circular tunnel structure with a diameter of 10m to 15m, and the distance between two parallel gas storage chambers 1 is about 6 to 8 times the diameter.
[0028] With the gas storage chambers 1 at both ends of the construction channel 2 being parallel to each other, the concrete sealing body 3 is set perpendicular to the gas storage chambers 1 on both sides, so that the pressure load can be transmitted and offset more in the concrete sealing body 3.
[0029] For ease of construction (excavation of gas storage chamber 1 and installation of sealing steel plate 8), the bottom of construction passage 2 is flush with the bottom of gas storage chamber 1. Construction passage 2 actually connects not the middle part of gas storage chamber 1, but the lower half.
[0030] In one embodiment, the internal steel reinforcement density of the concrete sealing body 3 near the gas storage chamber 1 is greater than that far from the gas storage chamber 1, so as to ensure the radial coordinated deformation of the gas storage chamber 1, avoid the excessive stress at the branch pipe caused by the uncoordinated radial deformation of the gas storage chamber 1, and effectively improve the service life of the structure at the branch pipe.
[0031] In one embodiment, an inflation / deflation pipe 7 is pre-embedded in the concrete sealing body 3. The inflation / deflation pipe 7 is connected to the external inflation / deflation equipment through the concrete sealing body 3 and the connecting well 4. Although this reduces the structural strength of the concrete sealing body 3 to a certain extent, it improves the functionality of the concrete sealing body 3, reduces the excavation work of additional channels, and the concrete sealing body 3 can still maintain good stress stability after the inflation / deflation pipe 7 is opened.
[0032] Similarly, a maintenance and repair passage 10 can be set inside the concrete sealing body 3. The maintenance and repair passage 10 is connected to the connecting well 4, which further enhances the functionality of the concrete sealing body 3 and reduces the excavation work of additional passages.
[0033] When both the gas filling / discharging pipeline 7 and the maintenance and repair passage 10 are installed, the portion of the gas filling / discharging pipeline 7 corresponding to the maintenance and repair passage 10 can be located inside the maintenance and repair passage 10 or buried in the concrete sealing body 3 surrounding the maintenance and repair passage 10. When the portion of the gas filling / discharging pipeline 7 is located inside the maintenance and repair passage 10, the portion of the gas filling / discharging pipeline 7 inside the maintenance and repair passage 10 is an exposed pipe, and the portion of the gas filling / discharging pipeline 7 located in the concrete sealing body 3 is a buried pipe. The buried pipe and the exposed pipe can be connected by a valve, which allows for convenient shut-off of the gas filling / discharging pipeline 7 and facilitates maintenance of the gas filling / discharging pipeline 7. The gas filling / discharging pipeline 7 with exposed and buried pipes and the maintenance and repair passage 10 can serve as a pressure balancing passage between the two chambers in an emergency (the connection between the exposed and buried pipes can be disassembled and the connecting well 4 can be sealed to achieve the connection between the two gas storage chambers 1), improving the reliability of the system.
[0034] When actually pouring the concrete sealing body 3, the overall concrete sealing body 3 can be divided into an air filling and venting pipeline section 5 and a reserved passage section 6. The reserved passage section 6 has air filling and venting pipeline sections 5 on both sides, which correspond to the concealed pipes of the air filling and venting pipeline 7. The reserved passage section 6 corresponds to the maintenance and repair passage 10. The two sections can be poured in batches. The top of the concrete sealing body 3 at the connection of the two sections is reserved with a lifting device, and the bottom is reserved with a maintenance groove. The reserved lifting device is used to lift the valve between the buried pipe and the exposed pipe, and the maintenance groove serves as the valve maintenance position.
[0035] A side space is provided on one side of the maintenance and repair passage 10, and a pump pit is provided on the bottom surface of the side space.
[0036] The present invention also provides a construction method for the construction of the above-mentioned underground high-pressure gas storage system, comprising the following steps: S1: Construct connecting well 4, construction passage 2, and gas storage chamber 1; S2: A sealing steel plate 8 is installed on the inner wall of the gas storage cavern 1, and backfill concrete 9 is filled between the surrounding rock and the sealing steel plate 8. S3: Erect formwork and reinforcing bars in the construction passage 2, and pour concrete to form concrete sealing body 3 after the erection is completed.
[0037] Specifically, based on the design of the inflation / deflation pipeline section 5 and the reserved channel section 6, the actual pouring process is as follows: 1) Construction preparation 2) Drilling and installing reinforcing bars in construction passage 2, and tying the reinforcing bars: 3) Install pre-embedded components such as backfill grouting pipes and consolidation grouting pipes in construction access road 2: 4) Formwork is erected to separate the inflation / deflation pipeline section 5. Concrete is poured into the inflation / deflation pipeline section 5, and the inflation / deflation pipeline 7 within the inflation / deflation pipeline section 5 is embedded in the poured concrete. 5) Cooling water circulation (a cooling water passage is pre-embedded within the concrete sealing body 3, and cooling water is circulated in after pouring): 6) After the concrete sealing body 3 cools, the sealing body of the inflation / deflation pipeline section 5 is backfilled with grout and contact grouting is performed: 7) Roughen the concrete sealing body 3 of the inflation / deflation pipeline section 5 to improve the adhesion between it and the concrete sealing body 3 of the reserved channel section 6: 8) Concrete sealing of reserved passage section 6 (with central formwork to form maintenance and repair passage 10): 9) Cooling water circulation (a cooling water passage is pre-embedded within the concrete sealing body 3, and cooling water is circulated in after pouring): 10) Backfilling and grouting of the reserved passage section 6 sealing body, and contact grouting.
[0038] The following points should be noted during actual construction: (1) Foundation surface treatment During the construction preparation phase, a comprehensive inspection was conducted to identify any areas where the foundation surface was under-excavated. Manual labor combined with hand-held pneumatic drills was used to precisely address the under-excavated areas to ensure the base plate was flat. High-pressure air and water were used to flush the side arch areas to thoroughly remove loose rocks, sharp rock corners, and slopes, while simultaneously clearing away debris and accumulated water.
[0039] (2) Roughening of reinforced concrete At the ends of the concrete sealing body 3, the sealing body 5 of the inflation / deflation pipeline section and the sealing body 6 of the reserved passage section, other phased concrete sections, and small areas with dense reinforcement and corners, the surface should be roughened manually or with a pneumatic hammer to thoroughly remove laitance, loose materials, and contaminants until coarse sand or small stones are slightly exposed. The treated construction joint surface must be cleaned promptly and kept clean and moist before concrete pouring to ensure good interlayer bonding.
[0040] (3) Drilling and installation of reinforcing bars The contact zone between the concrete sealing body 3 and the surrounding rock requires systematic drilling and installation of reinforcing bars. The depth of the reinforcing bars into the rock and the spacing between rows must be strictly controlled. The hole diameter and depth must meet the structural stability requirements. The reinforcing bars extend into part of the concrete sealing body 3 and are welded to the tied reinforcing bars.
[0041] (4) Pre-embedding of grouting pipes Contact grouting pipes are installed on the sidewalls near the concrete sealing body 3, and backfill grouting pipes are installed on the arch and sidewalls. Repeatable grouting pipes are used, and one end of each pipe must be tightly fitted to the formwork. Reliable sealing measures are employed at the fitting points to prevent grout from seeping into the pipes and causing blockages during concrete pouring. (The formwork for sealing the contact grouting pipes and backfill grouting pipes is additionally installed between the space where the concrete sealing body 3 needs to be poured and the surrounding rock. After the concrete sealing body 3 is formed, this formwork can be removed to expose the contact grouting pipes and backfill grouting pipes for contact grouting and backfill grouting.) Through contact grouting and backfill grouting, the pouring quality is controlled to ensure that the concrete sealing body 3 is in contact with the surrounding rock.
[0042] (5) Construction of waterstop Waterstops or copper waterstops are installed at the ends of the concrete sealing body 3, the joint between the sealing body of the inflation / deflation pipeline section 5 and the sealing body of the reserved channel section 6. The two wings of the waterstop embedded in the concrete must be precisely positioned with the steel reinforcement cage and the formwork to ensure that they are tightly bonded to the concrete after pouring, without gaps or detachment.
[0043] (6) Concrete sealing body 3 pouring The sealing body is continuously poured in layers using the flat-layer through-compartment method. During the pouring process, the material is poured symmetrically on both sides, and the vibration rate is controlled to ensure that the pouring is dense, while protecting the sealing steel plate 8 from damage.
[0044] (7) Water cooling is applied to the concrete sealing body 3. Water cooling strictly follows the principles of "small temperature difference, early cooling, and slow cooling" to control concrete temperature changes throughout the process and prevent temperature stress cracks.
[0045] Any adaptive changes made according to actual needs are within the scope of protection of this invention.
[0046] It should be noted that, for those skilled in the art, it is obvious that the present invention is not limited to the details of the exemplary embodiments described above, and that the invention can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. Therefore, the embodiments should be considered illustrative and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description. Thus, all variations falling within the meaning and scope of equivalents of the claims are intended to be included within the present invention. No reference numerals in the claims should be construed as limiting the scope of the claims.
[0047] Specific examples have been used to illustrate the principles and implementation methods of this invention. The descriptions of the above embodiments are only for the purpose of helping to understand the method and core ideas of this invention. Furthermore, those skilled in the art will recognize that, based on the ideas of this invention, there will be changes in the specific implementation methods and application scope. Therefore, the content of this specification should not be construed as a limitation of this invention.
Claims
1. An underground high pressure gas storage system, characterized in that, The application relates to a high-pressure underground gas storage system. The application comprises: at least two gas storage cavities arranged underground; at least one construction channel, two ends of the construction channel being respectively communicated with the gas storage cavities; a concrete blocking body arranged in the construction channel, two ends of the concrete blocking body being respectively contacted with the gas storage cavities; 2. The underground high-pressure gas storage system according to claim 1, characterized in that and a communication well communicated with the outside environment and the construction channel.
3. The underground high-pressure gas storage system according to claim 1, characterized in that The gas storage cavities at two ends of the construction channel are located on the same horizontal plane, and the construction channel is horizontally arranged.
4. The underground high-pressure gas storage system according to claim 3, characterized in that The gas storage cavities at two ends of the construction channel are parallel to each other.
5. The underground high-pressure gashouse system according to claim 1, characterized in that, The concrete blocking body is vertically arranged with the gas storage cavities on two sides.
6. The underground high-pressure gashouse system of claim 1, wherein, The internal steel bar density of the concrete blocking body close to the gas storage cavities is greater than that far away from the gas storage cavities.
7. The underground high pressure gas storage system of claim 1, wherein, A gas charging and discharging pipeline is pre-embedded in the concrete blocking body, and the gas charging and discharging pipeline is communicated with the outside gas charging and discharging equipment through the concrete blocking body and the communication well.
8. A construction method, characterized by, An operation and maintenance channel is arranged in the concrete blocking body, and the operation and maintenance channel is communicated with the communication well. Construction of the high-pressure underground gas storage system according to any one of claims 1-7, comprising the following steps: S1: opening the communication well, the construction channel and the gas storage cavities; S2: arranging a sealing steel plate on the inner wall of the gas storage cavity, and backfilling concrete between the surrounding rock and the sealing steel plate; 9. The construction method according to claim 8, characterized in that, S3: erecting a formwork and a steel bar in the construction channel, pouring concrete to form the concrete blocking body after the erection is completed.
10. The construction method according to claim 9, characterized in that, A cooling water passage is pre-embedded in the concrete blocking body, and cooling water is circulated and input after pouring is completed. After the concrete blocking body is cooled, backfill grouting and contact grouting are carried out.