Steel corbel supporting structure
By pre-embedding threaded rods and connecting plates in prefabricated columns, combined with T-shaped rods pre-embedded in composite beams, rapid installation and disassembly of steel corbels is achieved, solving the low production efficiency and cost of prefabricated columns in the existing technology. It improves construction efficiency and maintains the functionality and beauty of the building.
Patent Information
- Application Number
- CN202323366580.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-11
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2033-12-11
AI Technical Summary
In the existing technology, prefabricated columns use a permanent concrete corbel support system when pouring superimposed beams, resulting in low production efficiency and high cost, and affecting the building function and appearance.
The steel corbel support structure is adopted, including threaded rods and connecting plates embedded in the prefabricated columns. The threaded rods are connected to the steel corbel body to achieve rapid installation and disassembly, and through the T-shaped rods embedded in the composite beams and connectors for quick positioning and removal.
It improves the production efficiency and construction efficiency of prefabricated columns, reduces production costs, and avoids any impact on building functions and aesthetics.
Smart Images

Figure CN221799156U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction equipment, in particular to a steel corbel support structure. Background Art
[0002] The cross-section of the frame beam is generally rectangular or T-shaped. When the floor structure is a prefabricated floor, in order to reduce the height occupied by the structure and increase the building clearance, the cross-section of the frame beam is often cross-shaped or basket-shaped. In the assembled integral frame structure, the prefabricated beam is often made into a T-shaped cross-section. After the prefabricated panel is installed in place, some concrete is poured to form the so-called composite beam.
[0003] Composite beams are beams that are poured with concrete twice. The first time is at the prefabrication site to make the beam prefabricated. The second time is at the construction site. After the prefabricated beam is hoisted onto the prefabricated column and placed, the upper concrete is poured to connect it with the prefabricated column as a whole. In the existing method, when the composite beam is poured with the prefabricated column, a permanent concrete bracket is set on the side of the prefabricated column to serve as a composite beam support system. When the concrete bracket support system is used, there are not only problems such as low production efficiency and high production cost of the prefabricated column, but also the column bracket will have a certain adverse effect on the use function and aesthetics of the building. Utility Model Content
[0004] The technical problem to be solved by the utility model is to overcome the deficiencies in the prior art and aim to provide a steel corbel support structure for temporarily supporting the composite beams on the prefabricated columns during casting. After the casting is completed, it is convenient and quick to disassemble and ensures that the prefabricated columns can support multiple composite beams at the same time, thereby improving construction efficiency.
[0005] The utility model is realized by the following technical solutions:
[0006] A steel corbel support structure comprises a first threaded rod embedded in a prefabricated column, a first steel corbel body and two connecting plates being provided on the first threaded rod, the two connecting plates being respectively located on both sides of the prefabricated column, and the first steel corbel body being located on one side of one of the connecting plates; a plurality of second threaded rods are also provided between the two connecting plates, a second steel corbel body is also provided on the second threaded rod, and the top of the first steel corbel body and the top of the second steel corbel body are both flush with the top of the prefabricated column.
[0007] Furthermore, the first steel corbel body and the second steel corbel body each include a support plate and a rib plate, the support plate includes a horizontal plate and a vertical plate, the horizontal plate and the vertical plate are welded to form an L-shaped structure, the rib plate is welded to the side wall of the vertical plate, and the top of the rib plate is welded to the bottom of the vertical plate;
[0008] The first threaded rod passes through the vertical plate of the first steel corbel body;
[0009] Both ends of the first threaded rod are also sleeved with first nuts, and the first nuts are used to fix the connecting plate and the first steel corbel body to the prefabricated column respectively.
[0010] Further, the second threaded rod is connected to the rib plate of the second steel corbel body through threads;
[0011] Both ends of the second threaded rod are sleeved with second nuts, and the second nuts are used to fix the second threaded rod on the connecting plate.
[0012] Furthermore, the tops of the transverse plates of the first steel corbel body and the second steel corbel body are both provided with connecting rods;
[0013] It also includes a connecting piece embedded in the bottom of the composite beam, and the connecting rod is detachably connected to the connecting piece.
[0014] Furthermore, the connecting member comprises a T-shaped rod embedded in the composite beam, a vertical rod is provided at the bottom of the T-shaped rod, and a limiting hole is provided on the side wall of the vertical rod;
[0015] The bottom end of the connecting rod vertically passes through the cross plate and is connected to the third nut. A blind hole is provided at the top of the connecting rod. A connecting hole is provided on the inner wall of the blind hole. A first spring and a limiting rod are provided in the connecting hole. The first spring is used to push the limiting rod to be inserted into the limiting hole to fix the vertical rod in the blind hole of the connecting rod.
[0016] Furthermore, a cavity is provided inside the connecting rod, an air bag is provided inside the cavity, a catheter is provided on the air bag, and the catheter extends into the blind hole;
[0017] A guide hole whose inner diameter is consistent with the outer diameter of the catheter is also provided at the bottom of the vertical rod. The guide hole is connected to the limiting hole. When the airbag is compressed, the fluid inside the airbag can push the limiting rod to retract into the connecting hole.
[0018] Furthermore, a release rod is provided at the bottom of the connecting rod, and the release rod is vertically inserted into the cavity, and the release rod is used to compress the airbag.
[0019] Furthermore, a second spring is provided in the connecting rod, and the second spring is sleeved on the unlocking rod.
[0020] Compared with the prior art, the utility model has the following advantages and beneficial effects:
[0021] 1. In the utility model, since a connecting plate is sleeved on the first threaded rod, the second threaded rod between the connecting plates can provide support force for the second steel corbel body, thereby ensuring that the second steel corbel body can be quickly installed on the other side wall of the prefabricated column. In this way, the prefabricated column only needs to embed one first threaded rod in the production process to meet the support of multiple steel corbels;
[0022] 2. The utility model can quickly connect with the connecting rods on the first steel corbel body and the second steel corbel body through the T-bar and the vertical rod embedded in the composite beam, thereby improving the stability of the composite beam placed on the steel corbel. At the same time, after the casting is completed, the air bag can be used to realize the disassembly between the connecting rod and the vertical rod. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] The drawings described herein are used to provide a further understanding of the embodiments of the present utility model, constitute a part of this application, and do not constitute a limitation of the embodiments of the present utility model. In the drawings:
[0024] Figure 1 It is a schematic diagram of the structure of the utility model;
[0025] Figure 2 For this utility model Figure 1 The structural diagram of the enlarged part A in the middle;
[0026] Figure 3 For this utility model Figure 1 The structural diagram of the enlarged part B in the middle;
[0027] Figure 4 It is a top view of the first steel corbel body and the second steel corbel body of the utility model when they are installed on the prefabricated column;
[0028] Figure 5 It is a structural schematic diagram of the second threaded rod and the second steel bracket body being connected to each other in the utility model;
[0029] Figure 6 This is a schematic diagram of the structure of the utility model when the connecting rod is connected to the vertical rod;
[0030] Figure 7 For this utility model Figure 6 Schematic diagram of the structure after enlarging part C in the middle.
[0031] Marks and corresponding parts names in the attached drawings:
[0032] 1. Prefabricated column; 2. Composite beam; 3. Connector; 4. Connecting plate; 5. Second threaded rod; 6. Second nut; 7. Rib; 8. First nut; 9. First threaded rod; 10. First steel corbel body; 11. Second steel corbel body; 12. Connecting rod; 13. T-bar; 14. Unlocking rod; 15. Gasket; 16. Third nut; 17. First spring; 18. Limit rod; 19. Guide hole; 21. Airbag; 22. Catheter; 23. Vertical rod. DETAILED DESCRIPTION
[0033] In order to make the purpose, technical solutions and advantages of the utility model more clearly understood, the utility model is further described in detail below in conjunction with embodiments and drawings. The schematic implementation manner of the utility model and its description are only used to explain the utility model and are not intended to limit the utility model.
[0034] Example
[0035] like Figures 1 to 7 As shown, the utility model includes a first threaded rod 9 embedded in the prefabricated column 1, and a first steel corbel body 10 and two connecting plates 4 are provided on the first threaded rod 9. The two connecting plates 4 are respectively located on both sides of the prefabricated column 1, and the first steel corbel body 10 is located on one side of one of the connecting plates 4; a plurality of second threaded rods 5 are also provided between the two connecting plates 4, and a second steel corbel body 11 is also provided on the second threaded rod 5, and the top of the first steel corbel body 10 and the top of the second steel corbel body 11 are both flush with the top of the prefabricated column 1.
[0036] When the precast column 1 in the prior art is poured and connected with the composite beam 2, a composite beam support system is usually formed by building a permanent concrete corbel on the side wall of the precast column 1. When the concrete corbel support system is used, there are not only problems such as low production efficiency and high production cost of the precast columns, but also certain adverse effects on the use function and aesthetic manufacturing of the building. Although some of the existing precast columns 1 also use pre-embedded threaded rods in the precast column 1, and the threaded rods are connected with the steel corbels to realize the construction of the support system, such a design allows the steel corbels to be removed from the precast column 1 after the construction is completed. However, since some of the precast columns 1 need to be installed with steel corbels on multiple side walls to meet the casting of composite beams 2 and precast columns 1 in different directions, this makes the precast column 1 inconvenient during the manufacturing process, and it is impossible to unify the threaded rods pre-embedded in the precast column 1. For this reason, the technical solution also provides two additional connecting plates 4 on the first threaded rod 9. The two connecting plates 4 are respectively located on the opposite sides of the precast column 1, and then the first steel corbel body 10 is connected to the first threaded rod 9, so that the first steel corbel body 10 is stably fixed on one side of the precast column 1, and then the second threaded rod 5 is installed between the two connecting plates 4. On the one hand, the installed second threaded rod 5 can reinforce the two connecting plates 4 and improve the fixing ability of the connecting plates 4 on the precast column 1. On the other hand, since the second threaded rod 5 installed between the two connecting plates 4 is located on the other two sides of the precast column 1, the second steel corbel body 11 is installed on the second threaded rod 5, so that the installation of the steel corbel on the other side of the precast column 1 can be realized. Therefore, in actual application, the technical solution only needs to embed a first threaded rod 9 in the precast column 1. When it is necessary to cast the composite beam 2 on the other side of the precast column 1, the second threaded rod 5 on the connecting plate 4 can be used to realize the installation of the second steel corbel body 11, thereby meeting the support of the composite beam 2 in multiple directions.
[0037] The first steel corbel body 10 and the second steel corbel body 11 both include a support plate and a rib plate 7, the support plate includes a horizontal plate and a vertical plate, the horizontal plate and the vertical plate are welded to form an L-shaped structure, the rib plate 7 is welded to the side wall of the vertical plate, and the top of the rib plate 7 is welded to the bottom of the vertical plate; the first threaded rod 9 passes through the vertical plate of the first steel corbel body 10; the first nuts 8 are also sleeved at both ends of the first threaded rod 9, and the first nuts 8 are used to fix the connecting plate 4 and the first steel corbel body 10 to the prefabricated column 1 respectively.
[0038] The first steel corbel body 10 and the second steel corbel body 11 provided in the present embodiment are both steel corbel structures in the prior art, which include an L-shaped support structure consisting of a vertical plate and a horizontal plate, wherein when the first steel corbel body 10 is connected to the first threaded rod 9, the end of the first threaded rod 9 passes through the vertical plate of the first steel corbel 10 and is connected to the first nut 8. The restraining force of the first nut 8 on the vertical plate is utilized to stably fix the first steel corbel body 10 on the side wall of the prefabricated column 1. When supporting the composite beam 2, the supporting force provided by the horizontal plate in the vertical direction is utilized to ensure that the composite beam 2 can be stably cast with the prefabricated column 1.
[0039] The second threaded rod 5 is connected to the ribs 7 of the second steel corbel body 11 via threads; both ends of the second threaded rod 5 are sleeved with second nuts 6, which are used to fix the second threaded rod 5 on the connecting plate 4.
[0040] When the other side of the prefabricated column 1 needs to be installed with the composite beam 2, first pass the second threaded rod 5 through one of the connecting plates 4, then connect the rib plate 7 of the second steel corbel body 11 with the second threaded rod 5, and then let the second threaded rod 5 pass through the two connecting plates 4, and finally install the second nuts 6 at both ends of the second threaded rod 5, and use the second nuts 6 to fix the second threaded rod 5 on the connecting plates 4, so that the second steel corbel body 11 is stably fixed on the other side of the prefabricated column 1, thereby realizing the rapid installation of the steel corbel on the other side of the prefabricated column 1.
[0041] The first steel corbel body 10 and the second steel corbel body 11 are both provided with connecting rods 12 at the top of the transverse plates; they also include connecting members 3 embedded in the bottom of the composite beam 2, and the connecting rods 12 are detachably connected to the connecting members 3.
[0042] In this embodiment, in order to ensure that the composite beam 2 placed on the first steel corbel body 10 and the second steel corbel body 11 can be stably located at the top of the prefabricated column 1, thereby facilitating the pouring of the connection between the prefabricated column 1 and the composite beam 2, a connecting rod 12 is provided on the top of the first steel corbel body 10 and the second steel corbel body 11, and the connecting rod 12 is detachably connected to the cross plate. At the same time, a connecting member 3 is pre-embedded in the composite beam 2. The provided connecting member 3 and the connecting rod 2 can be used to quickly position the composite beam 2, ensuring that the composite beam 2 can be quickly poured with the prefabricated column 1. At the same time, the provided connecting rod 3 and the connecting rod 2 are detachably connected, which is convenient for rapid removal after pouring.
[0043] The connecting member 3 includes a T-shaped rod 13 embedded in the composite beam 2, a vertical rod 23 is provided at the bottom of the T-shaped rod 13, and a limiting hole is also provided on the side wall of the vertical rod 23; the bottom end of the connecting rod 12 vertically passes through the cross plate and is connected to the third nut 16, the top of the connecting rod 12 is provided with a blind hole, and a connecting hole is provided on the inner wall of the blind hole, and a first spring 17 and a limiting rod 18 are provided in the connecting hole, and the first spring 17 is used to push the limiting rod 18 to be inserted into the limiting hole to fix the vertical rod 23 in the blind hole of the connecting rod 12.
[0044] The T-shaped rod 13 provided in this embodiment is pre-buried in the composite beam 2, and ensures that the T-shaped rod 13 can be stably fixed inside the composite beam 2. At the same time, a vertical rod 23 is provided at the bottom of the T-shaped rod 13. During installation, after the first steel corbel body 10 and the second steel corbel body 11 are installed on different side walls of the prefabricated column 1, the composite beam 2 is lifted to the top of the first steel corbel body 10 or the second steel corbel body 11 by a crane, and then the connecting rod 12 is inserted upward from the bottom of the horizontal plate of the first steel corbel body 10 and / or the second steel corbel body 11. To the composite beam 2, and make the vertical rod 23 in the composite beam 2 extend into the blind hole of the connecting rod 12, and when the limiting rod 18 on the vertical rod 23 is at the same height as the limiting hole, the limiting rod 18 is inserted into the limiting hole under the action of the first spring 17, and the vertical rod 23 is constrained by the set limiting rod 18, and finally the third nut 16 is screwed on the bottom of the connecting rod 12, so as to connect the connecting rod 12 and the T-bar 13 together, ensuring that the composite beam 2 can be stably located on the first steel corbel body 10 or the second steel corbel body 11.
[0045] In the initial state, the limit rod 18 is extended into the blind hole of the connecting rod 12 under the action of the first spring 17. In this embodiment, in order to ensure that the vertical rod 23 is obstructed by the limit rod 18 when it is extended into the blind hole of the connecting rod 12, a hypotenuse is provided at the end of the limit rod 18, so that when the bottom of the vertical rod 23 acts on the hypotenuse of the limit rod 18, it can generate a horizontal component of force on the limit rod 18, thereby squeezing the limit rod 18 back into the connecting hole. After the limit hole on the vertical rod 23 moves to be flush with the limit rod 18, the limit rod 18 is extended into the limit hole again under the action of the first spring 17.
[0046] In order to improve the fixing ability of the third nut to the connecting rod 12 in this embodiment, a gasket 15 is further sleeved on the connecting rod 12 .
[0047] A cavity is also provided inside the connecting rod 12, in which an airbag 21 is provided, and a catheter 22 is also provided on the airbag 21, and the catheter 22 extends into the blind hole; a guide hole 19 whose inner diameter is consistent with the outer diameter of the catheter 22 is also provided at the bottom of the vertical rod 23, and the guide hole 19 is connected to the limiting hole. When the airbag 21 is compressed, the fluid inside the airbag 21 can push the limiting rod 18 to retract into the connecting hole.
[0048] After the pouring of the connection point between the composite beam 2 and the prefabricated column 1 is completed, in order to facilitate the rapid separation of the connecting rod 12 and the vertical rod 23, an airbag 21 is also arranged inside the connecting rod 12. The airbag 21 is filled with gas. When the airbag 21 is compressed, its volume becomes smaller, which causes the gas inside it to be squeezed into the conduit 22. Then the gas enters the limiting hole of the vertical rod 23 through the guide hole 19, and acts on the end of the limiting rod 18, forcing the limiting rod 18 located in the limiting hole to retreat into the connecting hole of the connecting rod 12, thereby removing the constraint of the limiting rod 18 on the vertical rod 23 and realizing the rapid separation of the connecting rod 12 and the vertical rod 23.
[0049] A unlocking rod 14 is also provided at the bottom of the connecting rod 12 . The unlocking rod 14 is vertically inserted into the cavity. The unlocking rod 14 is used to compress the airbag 21 .
[0050] In this embodiment, when the unlocking rod 14 is moved upward, the airbag 21 can be squeezed, so that the gas inside the airbag 21 is squeezed into the limiting hole, thereby unlocking the limiting rod 18.
[0051] A second spring is further disposed in the connecting rod 12 , and the second spring is sleeved on the unlocking rod 14 .
[0052] In this embodiment, in order to prevent the unlocking rod 14 from falling downward in a natural state and causing the unlocking rod 14 to slide off the connecting rod 12, a second spring is provided. The second spring is connected to the unlocking rod 14 and is used to generate a supporting force on the unlocking rod 14 in the vertical direction.
[0053] The specific implementation methods described above further illustrate the purpose, technical solutions and beneficial effects of the utility model in detail. It should be understood that the above description is only the specific implementation method of the utility model and is not used to limit the protection scope of the utility model. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the utility model should be included in the protection scope of the utility model.
Claims
1. A steel corbel support structure, characterized in that: It comprises a first threaded rod (9) embedded in a prefabricated column (1), a first steel corbel body (10) and two connecting plates (4) being provided on the first threaded rod (9), the two connecting plates (4) being respectively located on two sides of the prefabricated column (1), and the first steel corbel body (10) being located on one side of one of the connecting plates (4); A plurality of second threaded rods (5) are provided between the two connecting plates (4), and a second steel corbel body (11) is provided on the second threaded rods (5), and the top of the first steel corbel body (10) and the top of the second steel corbel body (11) are both flush with the top of the prefabricated column (1).
2. A steel corbel support structure according to claim 1, characterized in that: The first steel corbel body (10) and the second steel corbel body (11) both comprise a support plate and a rib plate (7), wherein the support plate comprises a horizontal plate and a vertical plate, wherein the horizontal plate and the vertical plate are welded to form an L-shaped structure, and the rib plate (7) is welded to the side wall of the vertical plate, and the top of the rib plate (7) is welded to the bottom of the vertical plate; The first threaded rod (9) passes through the vertical plate of the first steel corbel body (10); The two ends of the first threaded rod (9) are also sleeved with first nuts (8), and the first nuts (8) are used to fix the connecting plate (4) and the first steel corbel body (10) to the prefabricated column (1) respectively.
3. A steel corbel support structure according to claim 2, characterized in that: The second threaded rod (5) is connected to the rib plate (7) of the second steel corbel body (11) via threads; Second nuts (6) are sleeved on both ends of the second threaded rod (5), and the second nuts (6) are used to fix the second threaded rod (5) on the connecting plate (4).
4. A steel corbel support structure according to claim 2, characterized in that: The tops of the transverse plates of the first steel corbel body (10) and the second steel corbel body (11) are both provided with connecting rods (12); It also comprises a connecting piece (3) pre-buried in the bottom of the composite beam (2), and the connecting rod (12) is detachably connected to the connecting piece (3).
5. A steel corbel support structure according to claim 4, characterized in that: The connecting member (3) comprises a T-shaped rod (13) pre-buried in the composite beam (2); a vertical rod (23) is provided at the bottom of the T-shaped rod (13); and a limiting hole is also provided on the side wall of the vertical rod (23); The bottom end of the connecting rod (12) vertically passes through the horizontal plate and is connected to the third nut (16). A blind hole is provided at the top of the connecting rod (12). A connecting hole is provided on the inner wall of the blind hole. A first spring (17) and a limiting rod (18) are provided in the connecting hole. The first spring (17) is used to push the limiting rod (18) to be inserted into the limiting hole, so as to fix the vertical rod (23) in the blind hole of the connecting rod (12).
6. A steel corbel support structure according to claim 5, characterized in that: The connecting rod (12) is further provided with a cavity inside, an air bag (21) is provided in the cavity, a catheter (22) is further provided on the air bag (21), and the catheter (22) extends into the blind hole; The bottom of the vertical rod (23) is also provided with a guide hole (19) whose inner diameter is consistent with the outer diameter of the catheter (22); the guide hole (19) is connected to the limiting hole; when the airbag (21) is compressed, the fluid inside the airbag (21) can push the limiting rod (18) to retract into the connecting hole.
7. A steel corbel support structure according to claim 6, characterized in that: An unlocking rod (14) is also provided at the bottom of the connecting rod (12), and the unlocking rod (14) is vertically inserted into the cavity. The unlocking rod (14) is used to compress the airbag (21).
8. A steel corbel support structure according to claim 7, characterized in that: A second spring is also provided in the connecting rod (12), and the second spring is sleeved on the unlocking rod (14).