Drainage structure for highway tunnel
By introducing an electric heating tape layer and a convenient maintenance device into the drainage structure of the highway tunnel, the problem of freezing and maintenance problems in low-temperature weather has been solved, and the efficient operation and convenient maintenance of the drainage ditch have been achieved.
Patent Information
- Application Number
- CN202323667443.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-29
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2033-12-29
AI Technical Summary
The existing highway tunnel drainage structure is easily blocked by ice in low-temperature weather, and the underground central drainage channel lacks maintenance equipment, making it difficult to maintain it regularly.
A highway tunnel drainage structure including a drainage ditch, a seepage cover and an electric heating tape layer is designed. The electric heating tape layer is heated to prevent water from freezing at low temperatures, and convenient maintenance access is provided through manhole covers and maintenance covers.
It effectively avoids the blockage of the drainage ditch caused by ice, ensures the drainage effect, and allows maintenance personnel to easily access the central drainage channel for maintenance.
Smart Images

Figure CN221799889U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of highway tunnels, in particular to a drainage structure for highway tunnels. Background Art
[0002] It is often necessary to set up drainage structures inside highway tunnels to promptly discharge surface water in the tunnel and seepage water in the mountain above the tunnel to ensure tunnel safety and driving safety.
[0003] When the existing tunnel drainage gutters are in use, the drainage gutters at the tunnel entrances and exits are prone to freezing in low temperature weather, thereby blocking the drainage of the gutters. At the same time, the buried central drainage channels of existing tunnels lack maintenance equipment in the tunnel, making it inconvenient for maintenance personnel to regularly enter the central drainage channels for maintenance. Utility Model Content
[0004] The technical problem to be solved by the utility model is to overcome the existing defects and provide a drainage structure for a highway tunnel. By setting up a drainage ditch, a seepage cover plate and an electric heating tape layer, when encountering low temperature weather, the electric heating tape layer in the drainage ditch at the entrance and exit of the tunnel starts to heat up to prevent water from freezing, thereby ensuring the drainage effect, and can effectively solve the problems in the background technology.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a drainage structure for a highway tunnel, comprising a central drainage channel, a maintenance cover is arranged on the upper side of the central drainage channel, a manhole cover is arranged on the upper side of the maintenance cover, a pavement layer is arranged around the manhole cover, a drainage ditch is arranged on one side of the pavement layer, a seepage cover is arranged on the upper side of the drainage ditch, an electric heating tape layer is arranged in the drainage ditch, transverse water diversion pipes are symmetrically arranged on both sides of the central drainage channel, a longitudinal drainage pipe is arranged on one end of the transverse water diversion pipe away from the central drainage channel, and a circular guide pipe is arranged on the upper side of the longitudinal drainage pipe.
[0006] Furthermore, a waterproof coiled material layer is provided on the inner arc side surface of the annular flow guide pipe, and a secondary lining is provided on the inner arc side surface of the waterproof coiled material layer.
[0007] Furthermore, the outer arc-shaped side surface of the annular guide pipe is provided with a primary lining, and the manhole cover is connected to the road surface layer through a slot.
[0008] Furthermore, the central drainage channel is formed by casting concrete, the drainage ditch is formed by casting concrete, and the electric heating tape layer is arranged in the drainage ditch near the tunnel entrance.
[0009] Furthermore, the water seepage cover plate is connected to the drainage chute through a slot, and the transverse water diversion pipe and the longitudinal drainage pipe are both corrugated pipes.
[0010] Compared with the prior art, the beneficial effects of the utility model are:
[0011] 1. The utility model provides drainage ditch, seepage cover plate and electric heating tape layer. When encountering low temperature weather, the electric heating tape layer in the drainage ditch at the entrance and exit of the tunnel starts to heat up to prevent water from freezing, thereby ensuring the drainage effect.
[0012] 2. The utility model provides a manhole cover, a maintenance cover and a central drainage channel, so that when maintenance personnel need to repair the buried central drainage channel, they can open the manhole cover and the maintenance cover to facilitate maintenance personnel to enter the central drainage channel for maintenance. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a front view schematic diagram of the structure of the utility model;
[0014] Figure 2 It is an enlarged structural schematic diagram of the drainage ditch in the utility model;
[0015] Figure 3 It is a schematic diagram of the top view of the drainage ditch in the utility model;
[0016] Figure 4 For this utility model Figure 1 Schematic diagram of the enlarged structure at point A in the middle.
[0017] In the figure: 1. Primary lining; 2. Secondary lining; 3. Circumferential guide pipe; 4. Waterproof membrane layer; 5. Longitudinal drainage pipe; 6. Horizontal water diversion pipe; 7. Central drainage channel; 8. Pavement layer; 9. Drainage ditch; 10. Seepage cover; 11. Electric heating tape layer; 12. Manhole cover; 13. Maintenance cover. DETAILED DESCRIPTION
[0018] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0019] See also Figure 1-4This embodiment provides a technical solution: a drainage structure for a highway tunnel, including a central drainage channel 7, a maintenance cover 13 is arranged on the upper side of the central drainage channel 7, a manhole cover 12 is arranged on the upper side of the maintenance cover 13, a road surface layer 8 is arranged around the manhole cover 12, a drainage ditch 9 is arranged on one side of the road surface layer 8, a seepage cover plate 10 is arranged on the upper side of the drainage ditch 9, an electric heating tape layer 11 is arranged in the drainage ditch 9, transverse water diversion pipes 6 are symmetrically arranged on both sides of the central drainage channel 7, a longitudinal drainage pipe 5 is arranged at one end of the transverse water diversion pipe 6 away from the central drainage channel 7, and a circular flow guide pipe 3 is arranged on the upper side of the longitudinal drainage pipe 5. Figure 1-Figure 4 As shown, the annular drainage pipe 3 can guide the water seeping between the primary lining 1 and the waterproof membrane layer 4 to the longitudinal drainage pipe 5, and finally flow into the central drainage channel 7 through the transverse water diversion pipe 6.
[0020] The inner arc side of the circumferential flow guide pipe 3 is provided with a waterproof roll layer 4, and the inner arc side of the waterproof roll layer 4 is provided with a secondary lining 2. Figure 1-Figure 4 As shown, the waterproof coiled material layer 4 can improve the waterproof effect of the secondary lining 2, and the secondary lining 2 can improve the strength of the tunnel structure.
[0021] The outer arc side of the annular guide pipe 3 is provided with a primary lining 1, and the manhole cover 12 is connected to the road surface layer 8 through a slot. Figure 1-Figure 4 As shown, after the manhole cover 12 is opened, the maintenance cover 13 can be opened to facilitate maintenance of the central drainage channel 7.
[0022] The central drainage channel 7 is cast by concrete, the drainage ditch 9 is cast by concrete, and the electric heating tape layer 11 is arranged in the drainage ditch 9 near the tunnel entrance. Figure 1-Figure 4 As shown, the seepage cover plate 10 on the upper side of the drainage ditch 9 can guide the flowing water on the upper side of the pavement layer 8 into the drainage ditch 9.
[0023] The water seepage cover plate 10 is connected to the drainage ditch 9 through a slot, and the horizontal water pipe 6 and the longitudinal drainage pipe 5 are both corrugated pipes. Figure 1-Figure 4 As shown, the drainage ditch 9 can drain the road water in time.
[0024] The working principle of the drainage structure for highway tunnels provided by the utility model is as follows: Figure 1-Figure 4 As shown, when there is water accumulation in the pavement layer 8, the slope setting of the pavement layer 8 allows the accumulated water to flow into the seepage cover plate 10, and finally into the drainage ditch 9, and finally out of the tunnel. When encountering low temperature weather, the electric heating tape layer 11 can be powered on for heating, so that the inside of the drainage ditch 9 is heated to avoid water freezing and ensure the drainage efficiency of the drainage ditch 9. When the central drainage channel 7 needs to be repaired, the manhole cover 12 is opened, and then the maintenance cover 13 is opened, so as to facilitate maintenance personnel to enter the central drainage channel 7 for maintenance.
[0025] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A drainage structure for a highway tunnel, comprising a central drainage channel (7), characterized in that: A maintenance cover (13) is provided on the upper side of the central drainage channel (7), a manhole cover (12) is provided on the upper side of the maintenance cover (13), a road surface layer (8) is provided around the manhole cover (12), a drainage ditch (9) is provided on one side of the road surface layer (8), a water seepage cover plate (10) is provided on the upper side of the drainage ditch (9), an electric heating tape layer (11) is provided in the drainage ditch (9), transverse water diversion pipes (6) are symmetrically provided on both sides of the central drainage channel (7), a longitudinal drainage pipe (5) is provided at one end of the transverse water diversion pipe (6) away from the central drainage channel (7), and a circular flow guide pipe (3) is provided on the upper side of the longitudinal drainage pipe (5).
2. The drainage structure for a highway tunnel according to claim 1, characterized in that: The inner arc side surface of the annular flow guide pipe (3) is provided with a waterproof coiled material layer (4), and the inner arc side surface of the waterproof coiled material layer (4) is provided with a secondary lining (2).
3. The drainage structure for a highway tunnel according to claim 1, characterized in that: The outer arc-shaped side surface of the annular flow guide pipe (3) is provided with a primary lining (1), and the manhole cover (12) is connected to the road surface layer (8) via a slot.
4. The drainage structure for a highway tunnel according to claim 1, characterized in that: The central drainage channel (7) is formed by casting concrete, the drainage ditch (9) is formed by casting concrete, and the electric heating tape layer (11) is arranged in the drainage ditch (9) near the tunnel entrance.