Bearing wall for fatigue test

By introducing steel reinforcement into the load-bearing wall, and utilizing the tensile properties of the steel reinforcement and the compressive properties of the concrete wall, the problem of easy cracking of existing load-bearing walls under high-cycle fatigue test loads is solved, and the load-bearing wall can effectively bear high-cycle fatigue test loads.

CN221803392UActive Publication Date: 2024-10-01CHINA AVIATION INT CONSTR & INVESTMENT CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323236692.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-29
Publication Date
2024-10-01
Estimated Expiration
2033-11-29

AI Technical Summary

Technical Problem

Existing load-bearing wall structures are prone to cracking and cannot withstand high-frequency fatigue test loads, lacking design basis.

Method used

The design employs a steel frame embedded in a concrete wall, utilizing the excellent tensile properties of the steel frame combined with the compressive properties of the concrete wall. The steel frame, concrete wall, and base work together to bear the load, preventing the concrete wall from failing due to high-cycle fatigue loads.

Benefits of technology

It effectively avoids the failure of concrete walls due to high-frequency fatigue loads and meets the load requirements of high-frequency fatigue tests.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221803392U_ABST
    Figure CN221803392U_ABST
Patent Text Reader

Abstract

The utility model discloses a load-bearing wall for a fatigue test, the load-bearing wall comprises a base (10), a concrete wall (20) and a steel rib (30), the steel rib (30) is embedded in the base (10), the steel rib (30) and the concrete wall (20) are poured into a whole, the concrete wall (20) comprises a test surface (21), and the test surface (21) is provided with a fixing piece (40) for fixing a test piece. Load borne by the fixing piece can be transmitted to the steel rib through the concrete wall, so that the concrete wall, the steel rib and the base bear the load together, and the concrete wall can be prevented from losing efficacy due to the fact that the concrete wall bears fatigue loads for a large number of times by means of the good tensile property of the steel rib.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of construction engineering, and more specifically, to a load-bearing wall for fatigue testing. Background Art

[0002] Load-bearing wall structures are widely used in industrial buildings, mainly for load bearing tests in the fields of aircraft, automobiles, ships, etc. Many of these tests require a high number of loading and unloading fatigue tests, with both tension and pressure in the load direction. With the development of industrial technology, the required fatigue test load magnitude is getting larger and larger, and the number of fatigue test loads is also getting higher and higher. The existing load-bearing wall structures are mainly cast-in-place reinforced concrete. The fatigue calculation of concrete in the existing "Concrete Structure Design Code" GB 50010-2010 is based on 2x10 6 Within the fatigue test range. 6 Under the test load, there is no design basis for cast-in-place reinforced concrete bearing wall structures. Under high-frequency fatigue test loads, cast-in-place concrete is prone to cracking, and when the fatigue test load is large, cast-in-place reinforced concrete is also unable to withstand it.

[0003] Therefore, how to provide a bearing wall that can withstand a high number of fatigue test loads becomes a technical problem that needs to be solved in this application. Utility Model Content

[0004] In view of this, the present application proposes a load-bearing wall for fatigue testing to meet the needs of high-frequency fatigue testing.

[0005] The present application provides a load-bearing wall for fatigue testing, wherein the load-bearing wall comprises a base, a concrete wall and a steel frame, the steel frame is embedded in the base and cast as a whole with the concrete wall, the concrete wall comprises a test surface, and the test surface is provided with fixings for fixing the test piece.

[0006] Optionally, the steel frame includes a steel frame body and bolts arranged on the steel frame body.

[0007] Optionally, the steel frame includes a plurality of the bolts arranged at intervals on the surface of the steel frame body.

[0008] Optionally, the base is a reinforced concrete structure, and the top of the base is provided with reserved steel bars connected to the vertical steel bars of the concrete wall.

[0009] Optionally, the load-bearing wall comprises a mounting structure for fixing the fixing member to the concrete wall.

[0010] Optionally, the mounting structure comprises a fixing plate arranged on a surface of the concrete wall opposite to the test surface and a connecting piece connecting the fixing plate and the fixing piece, wherein the connecting piece passes through the concrete wall.

[0011] Optionally, the connecting member is a screw rod, the fixing plate and the fixing member are provided with mounting holes for passing the screw rod, and both ends of the screw rod are fixed by nuts respectively.

[0012] Optionally, a steel pipe for passing the screw rod is provided in the concrete wall.

[0013] Optionally, the fixing plate and the fixing member are connected via a plurality of the connecting members.

[0014] Optionally, a fixing groove for fixing the test piece is provided on the surface of the fixing piece.

[0015] According to the technical solution of the present application, the load borne by the fixing parts can be transferred to the steel frame through the concrete wall, so that the load is borne by the concrete wall, the steel frame and the base together, and the good tensile properties of the steel frame can be utilized to avoid failure of the concrete wall due to high-frequency fatigue loads.

[0016] Other features and advantages of the present application will be described in detail in the subsequent detailed description. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The accompanying drawings constituting a part of the present application are used to provide a further understanding of the present application, and the schematic implementation modes and descriptions of the present application are used to explain the present application. In the accompanying drawings:

[0018] Figure 1 It is a structural schematic diagram of a load-bearing wall according to a preferred embodiment of the present application;

[0019] Figure 2 for Figure 1 A top view of

[0020] Figure 3 for Figure 1 Schematic diagram of the structure of the steel frame;

[0021] Figure 4 for Figure 1 A schematic diagram of the structure of the fixing parts;

[0022] Figure 5 and Figure 6 Yes Description Figure 1 Schematic diagram of the construction process of the load-bearing wall. DETAILED DESCRIPTION

[0023] The technical solution of the present application will be described in detail below with reference to the accompanying drawings and in combination with the implementation modes.

[0024] The present application provides a load-bearing wall for fatigue testing, wherein the load-bearing wall includes a base 10, a concrete wall 20 and a steel frame 30, the steel frame 30 is embedded in the base 10 and cast as a whole with the concrete wall 20, the concrete wall 20 includes a test surface 21, and the test surface 21 is provided with a fixing part 40 for fixing a test piece.

[0025] By using the load-bearing wall of the present application, the load borne by the fixing member 40 can be transferred to the steel frame 30 through the concrete wall 20, so that the load is borne by the concrete wall 20, the steel frame 30 and the base 10 together, and the good tensile performance of the steel frame 30 can be utilized to avoid failure of the concrete wall 20 due to high-frequency fatigue loads.

[0026] Specifically, the steel frame 30 has good tensile performance, and the concrete wall 20 has good compressive performance. The combination of the two can meet the fatigue tensile and compressive load requirements. In addition, during the test, the fixing member 40 and the concrete wall 20 become a whole, and the fixing member 40 transfers the load to the steel frame 30 through the concrete wall 20, so that the load is borne by the concrete wall 20, the steel frame 30, and the base 10 together, and mainly borne by the steel frame 30, thereby avoiding the concrete wall 20 from failing due to a high number of fatigue loads.

[0027] The steel frame 30 can be in an appropriate form and should be mainly a steel structure to meet the test force requirements. In order to strengthen the pouring combination with the concrete wall 20, it is preferred that Figure 1 and Figure 3 As shown, the steel frame 30 includes a steel frame body 31 and studs 32 arranged on the steel frame body 31. The steel frame body 31 may be a steel frame structure, and the studs 32 may increase the bonding area between the steel frame 30 and the concrete wall 20. Preferably, in order to further improve the bonding between the steel frame 30 and the concrete wall 20, the steel frame 30 includes a plurality of studs 32 arranged at intervals on the surface of the steel frame body 31. Specifically, as Figure 3 As shown, the bolts 32 can be distributed on the outer contour surface of the steel frame body 31 at a set interval.

[0028] The base 10 can be in any suitable form. To meet the test requirements and facilitate manufacturing, preferably, the base 10 can be a reinforced concrete structure. During manufacturing, the base 10 can be cast first. In order to combine the base 10 with the concrete wall 20, preferably, as Figure 5 As shown, the top of the base 10 is provided with a reserved steel bar 11 connected to the vertical steel bar of the concrete wall 20. When the concrete wall 20 is manufactured, the vertical steel bar of the concrete wall 20 can be connected to the reserved steel bar 11, so that the concrete wall 20 and the base 10 can be integrally formed by pouring at the reserved steel bar 11.

[0029] The fixing member 40 can be disposed on the test surface 21 in an appropriate manner. Preferably, in order to replace the fixing member 40 according to the specific conditions of the test, the load-bearing wall can include a mounting structure for fixing the fixing member 40 to the concrete wall 20 .

[0030] The mounting structure may be in any suitable form as long as the fixing member 40 can be detachably arranged. Figure 1 and Figure 2 In the illustrated embodiment, the mounting structure may include a fixing plate 50 disposed on a surface of the concrete wall 20 that is away from the test surface 21 and a connecting member 60 connecting the fixing plate 50 and the fixing member 40, wherein the connecting member 60 penetrates the concrete wall 20. Thus, the connecting member 60 connects the fixing plate 50 and the fixing member 40 to be fixed as a whole relative to the concrete wall 20. During the test, the fixing member 40 transmits the load to the concrete wall 20 through the connecting member 60 and the fixing plate 50.

[0031] In order to facilitate penetration of the concrete wall 20 and convenient connection of the fixing member 40 and the fixing plate 50, the connecting member 60 can be a screw, and the fixing plate 50 and the fixing member 40 are provided with mounting holes for penetrating the screw, and the two ends of the screw are fixed by nuts respectively.

[0032] To facilitate installation and adjustment of the fixing member 40 after the concrete wall 20 is poured, preferably, a steel pipe 70 for passing the screw is provided in the concrete wall 20. When the concrete wall 20 is poured, the steel pipe 70 can be poured and fixed together, and the screw can be passed through the steel pipe 70.

[0033] The fixing member 40 can be arranged along a large part of the test surface 21 to be suitable for tests at different positions. For example, the fixing member 40 can be plate-shaped or multiple fixing members 40 can be arranged. In order to provide stable fixation for the plate-shaped or multiple fixing members 40, preferably, the fixing plate 50 and the fixing member 40 are connected by multiple connecting members 60. The specifications (such as plate thickness and area) of the fixing member 40 and the fixing plate 50 and the number of connecting members 60 are determined by the fatigue test load size and the fatigue test load times of the load-bearing wall.

[0034] The fixing member 40 may be provided with a suitable structure for fixing the test piece. Figure 2 and Figure 4 In the illustrated embodiment, a fixing groove 41 for fixing the test piece is provided on the surface of the fixing member 40. The fixing member 40 may be plate-shaped, and a plurality of fixing grooves 41 may be provided at intervals along the plate width direction of the fixing member 40, and mounting holes 42 for passing the connecting member 60 may be provided between the fixing grooves 41. The fixing groove 41 may be in an appropriate shape, such as a T-shaped groove.

[0035] The construction process of the load-bearing wall of the present application is described below with reference to the accompanying drawings.

[0036] like Figure 5 As shown, first, the base 10 is cast. Specifically, the base main frame 12 is placed on the foundation, and steel bars (including reserved steel bars 11) are tied on the base main frame 12. Then, the steel frame 30 can be positioned to a set position, and the lower end of the steel frame 30 is inserted into the base main frame 12 to a predetermined depth (the specific positioning position and insertion depth are determined according to the specifications of the steel frame 30, the base 10, and the concrete wall 20, the fatigue test requirements, etc., but a certain distance should be left between the steel frame 30 and the outer surface of the concrete wall 20), and then concrete can be cast to form the base 10, as shown in FIG. Figure 5 shown.

[0037] After the base 10 is vibrated and compacted and cured to reach the set strength, the steel bars of the concrete wall 20 can be tied, such as the horizontal steel bars 22 and the vertical steel bars 23, wherein the vertical steel bars 23 are connected to the reserved steel bars 11, and the steel pipe 70 is preset in place. Subsequently, pouring can be performed to form the base 10, the steel frame 30, and the concrete wall 20 as a whole, such as Figure 6 shown.

[0038] After the base 10, steel frame 30, and concrete wall 20 are vibrated and compacted and cured to reach a preset strength, the fixings 40 and fixing plates 50 can be positioned, and the connecting piece 60 (screw) can be inserted into the steel pipe 70, with its two ends passing through the corresponding mounting holes on the fixings 40 and fixing plates 50 and fixed by nuts S.

[0039] When performing a fatigue test, the test piece may be fixed in the fixing groove 41 .

[0040] The preferred embodiments of the present application are described in detail above; however, the present application is not limited to the specific details in the above embodiments. Within the technical concept of the present application, a variety of simple modifications can be made to the technical solution of the present application, and these simple modifications all fall within the protection scope of the present application.

[0041] It should also be noted that the various specific technical features described in the above specific embodiments can be combined in any suitable manner without contradiction. In order to avoid unnecessary repetition, this application will not further describe various possible combinations.

[0042] In addition, the various implementation modes of the present application may be arbitrarily combined, and as long as they do not violate the concept of the present application, they should also be regarded as the contents disclosed in the present application.

Claims

1. A load-bearing wall for fatigue testing, characterized in that: The load-bearing wall comprises a base (10), a concrete wall (20) and a steel frame (30); the steel frame (30) is embedded in the base (10) and cast integrally with the concrete wall (20); the concrete wall (20) comprises a test surface (21); and the test surface (21) is provided with a fixing member (40) for fixing a test piece.

2. The load-bearing wall for fatigue test according to claim 1, characterized in that: The steel frame (30) comprises a steel frame body (31) and bolts (32) arranged on the steel frame body (31).

3. The load-bearing wall for fatigue test according to claim 2, characterized in that: The steel frame (30) includes a plurality of the bolts (32) arranged at intervals on the surface of the steel frame body (31).

4. The load-bearing wall for fatigue test according to claim 1, characterized in that: The base (10) is a reinforced concrete structure, and a reserved steel bar (11) connected to the vertical steel bars of the concrete wall (20) is arranged on the top of the base (10).

5. The load-bearing wall for fatigue test according to any one of claims 1 to 4, characterized in that: The load-bearing wall comprises a mounting structure for fixing the fixing member (40) to the concrete wall (20).

6. The load-bearing wall for fatigue test according to claim 5, characterized in that: The mounting structure comprises a fixing plate (50) arranged on a surface of the concrete wall (20) which is opposite to the test surface (21) and a connecting member (60) connecting the fixing plate (50) and the fixing member (40), wherein the connecting member (60) penetrates the concrete wall (20).

7. The load-bearing wall for fatigue test according to claim 6, characterized in that: The connecting member (60) is a screw rod, the fixing plate (50) and the fixing member (40) are provided with mounting holes for passing the screw rod, and both ends of the screw rod are fixed by nuts respectively.

8. The load-bearing wall for fatigue test according to claim 7, characterized in that: The concrete wall (20) is provided with a steel pipe (70) for passing the screw rod.

9. The load-bearing wall for fatigue test according to claim 6, characterized in that: The fixing plate (50) and the fixing member (40) are connected via a plurality of connecting members (60).

10. The load-bearing wall for fatigue test according to claim 5, characterized in that: A fixing groove (41) for fixing the test piece is arranged on the surface of the fixing piece (40).

Citation Information

Cited By

  • Steel frame concrete test platform for helicopter propeller hub central part

    CN119469697A