Concrete pile composite foundation

By arranging vertical steel bars and fixing devices in the concrete pile composite foundation, combined with foam waterproof concrete, the problems of pile settlement and offset are solved, the stability and water permeability of the foundation are improved, and the bearing capacity of the foundation is enhanced.

CN221837616UActive Publication Date: 2024-10-15ANHUI ANSHUN WATER CONSERVANCY CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323551157.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-25
Publication Date
2024-10-15
Estimated Expiration
2033-12-25

AI Technical Summary

Technical Problem

The concrete pile composite foundation is prone to settlement and deflection under load, and has poor water permeability, which affects the stability and load-bearing capacity of the foundation.

Method used

Multiple soil pile bodies are set up in the base soil, vertical steel bars are set up inside the soil pile bodies, and fixing devices are set between adjacent soil pile bodies, including fastening plates, connecting rods, sleeves, limiting plates and springs. The soil pile bodies are fixedly connected through these devices to increase stability, and foam waterproof concrete is used in the soil pile bodies to improve water permeability.

Benefits of technology

It can effectively prevent the settlement and offset of the soil pile body, improve the stability and water permeability of the foundation, enhance the bearing capacity of the foundation, and prevent uneven foundation surface.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221837616U_ABST
    Figure CN221837616U_ABST
Patent Text Reader

Abstract

The utility model discloses a concrete pile composite foundation which comprises foundation soil, a plurality of soil pile bodies are arranged in the foundation soil, a fixing device is arranged between every two adjacent soil pile bodies, and vertical steel bars are arranged in the soil pile bodies. The water permeability and the stability of the composite foundation can be improved conveniently.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction engineering, in particular to a concrete pile composite foundation. Background Art

[0002] In recent years, foundation treatment technology has been greatly developed, among which composite foundation technology is the most widely used. Composite foundation refers to the artificial foundation in which part of the soil of the natural foundation is strengthened or replaced during the foundation treatment process, or reinforcement materials are set in the natural foundation. The reinforcement area is composed of a matrix (natural foundation soil or improved natural foundation soil) and a reinforcement. Under the action of load, the matrix and the reinforcement jointly bear the load. According to the load transfer mechanism of the composite foundation, the composite foundation is divided into two categories: vertical reinforcement composite foundation and horizontal reinforcement composite foundation. The vertical reinforcement composite foundation is further divided into three types: bulk material pile composite foundation, flexible pile composite foundation and rigid pile composite foundation.

[0003] In the prior art, during the construction of building projects, composite foundations are often used to reinforce weak foundations. Concrete pile composite foundations are high-bonding strength pile composite foundations represented by cement fly ash gravel pile composite foundations. A cushion layer of a certain thickness is set between the base and the pile top to ensure that the pile and soil bear the load together.

[0004] However, since the concrete piles themselves are heavy and have poor water permeability, the concrete piles in the concrete pile composite foundation will settle during the load-bearing process, and the pile bodies will be offset from each other due to being buried underground for a long time. Utility Model Content

[0005] The present application provides a concrete pile composite foundation, which is convenient for improving the water permeability and stability of the composite foundation.

[0006] The present application provides a concrete pile composite foundation, which adopts the following technical solution:

[0007] A concrete pile composite foundation comprises foundation soil, wherein a plurality of soil pile bodies are arranged in the foundation soil, a fixing device is arranged between two adjacent soil pile bodies, and vertical steel bars are arranged in the soil pile bodies.

[0008] By adopting the above technical scheme, a concrete pile composite foundation designed by the utility model, when in use, a soil pile body is first set in the base soil, and vertical steel bars for reinforcement are set in the soil pile body. The vertical steel bars can prevent the soil pile body from shifting on the one hand, and prevent the soil pile body from sinking on the other hand. A fixing device is set between adjacent soil pile bodies, and the fixing device can improve the stability of the soil pile body.

[0009] Preferably, the fixing device comprises a fastening plate arranged on the outer wall of the soil pile body, a connecting rod is fixedly connected to the side of the fastening plate away from the soil pile body, a sleeve is sleeved on the outer wall of the connecting rod, and the fastening plate is used to lock two adjacent soil pile bodies.

[0010] By adopting the above technical solution, the fastening plate is arranged to facilitate fastening the soil pile body; the connecting rod is arranged to facilitate connecting two adjacent soil pile bodies to each other to prevent the position of the soil pile body from shifting; the sleeve is arranged to prevent the foundation soil from damaging the connecting rod on the one hand, and to facilitate supporting the foundation soil above on the other hand.

[0011] Preferably, a limiting plate is provided on one side of the connecting rod close to the soil pile body, a limiting hole is provided in the soil pile body, a plurality of springs are provided in the limiting hole, one end of the spring close to the limiting plate abuts against the limiting plate, and the limiting plate is clamped in the limiting hole.

[0012] By adopting the above technical solution, the setting of the limit plate makes it easy to clamp the connecting rod into the soil pile body through the limit plate; the setting of the spring makes it easy to connect the limit plate and the limit hole more tightly; the setting of the limit hole is used to clamp the limit plate.

[0013] Preferably, two fixing plates are arranged on the fastening plate, threaded holes are arranged on both fixing plates, and fastening bolts are arranged on the threaded holes.

[0014] By adopting the above technical solution, the set fixing plate is convenient for setting threaded holes; the set threaded holes are convenient for threaded connection bolts; the set fastening bolts are convenient for fixing the two fixing plates together, thereby locking the soil pile body.

[0015] Preferably, a gravel layer is arranged around the top of the soil pile body, and a cushion layer is arranged on the top of the gravel layer.

[0016] By adopting the above technical solution, the gravel layer is provided to improve the bearing capacity of the foundation; the cushion layer is provided to prevent the foundation surface from being uneven.

[0017] Preferably, a plurality of transverse steel bars are arranged in the cushion layer, and the transverse steel bars are connected to the vertical steel bars.

[0018] By adopting the above technical solution, the transverse steel bars are arranged, so that the transverse steel bars and the vertical steel bars are fixed to each other, thereby fixing the soil pile body and preventing the soil pile body from settling during the bearing process.

[0019] Preferably, a pile cap is provided on the top of the soil pile body, and a through hole is provided on the pile cap for vertical steel bars to pass through.

[0020] By adopting the above technical solution, the pile cap is arranged to wrap the top of the soil pile body, thereby preventing the pile head of the soil pile body from being damaged and the pile body from tilting; the through hole arranged can be used to fix the transverse steel bars.

[0021] Preferably, foam waterproof concrete is provided in the soil pile body.

[0022] By adopting the above technical solution, the foam waterproof concrete is arranged, which is convenient for improving the water permeability of the entire soil pile body, and is also convenient for contact with the vertical steel bars.

[0023] In summary, this application has the following beneficial effects:

[0024] 1. The connecting rod is provided to facilitate the connection of two adjacent soil pile bodies to each other to prevent the position of the soil pile bodies from shifting;

[0025] 2. The cushion layer is set to prevent uneven foundation surface;

[0026] 3. The pile cap is set to wrap the top of the soil pile body to prevent the pile head from being damaged and the pile body from tilting. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a structural schematic diagram of an embodiment;

[0028] Figure 2 A cross-sectional view showing a limiting hole in an embodiment;

[0029] Figure 3 A cross-sectional view showing a fixing device in an embodiment;

[0030] Figure 4 Schematic diagram of the structure inside the earth pile body in the embodiment;

[0031] Explanation of the accompanying drawings: 1. base soil; 2. soil pile body; 3. fixing device; 31. fastening plate; 4. vertical steel bar; 5. connecting rod; 6. sleeve; 7. limit plate; 8. limit hole; 9. spring; 10. fixing plate; 11. threaded hole; 12. fastening bolt; 13. gravel layer; 14. cushion layer; 15. transverse steel bar; 16. pile cap; 17. through hole; 18. foam waterproof concrete. DETAILED DESCRIPTION

[0032] The present invention is further described in detail below in conjunction with the accompanying drawings. The same components are denoted by the same reference numerals. It should be noted that the terms "front", "rear", "left", "right", "upper", "lower", "bottom" and "top" used in the following description refer to directions in the accompanying drawings, and the terms "inside" and "outside" refer to directions toward or away from the geometric center of a specific component, respectively.

[0033] The utility model discloses a concrete pile composite foundation, such as Figures 1 to 4 As shown, it includes a foundation soil 1, a plurality of soil pile bodies 2 are arranged in the foundation soil 1, and foam waterproof concrete 18 is arranged in the soil pile body 2. Compared with general concrete, the waterproof performance of the foam waterproof concrete 18 is greatly enhanced. The plurality of soil pile bodies 2 are evenly distributed inside the foundation soil 1, and a fixing device 3 is arranged between two adjacent soil pile bodies 2. The fixing device 3 includes a fastening plate 31 arranged on the outer wall of the soil pile body 2. The fastening plate 31 is annular, and the fastening plate 31 abuts against the outer side of the soil pile body 2. Two fixing plates 10 are arranged on the fastening plate 31. The two fixing plates 10 are of the same size and shape. The top and bottom of the two fixing plates 10 are both provided with threaded holes 11 of the same size. The threaded holes 11 are provided with fastening bolts 12. The two fixing plates 10 are connected to each other by bolts, so as to fix the position of each soil pile body 2. The fastening plate 31 is used to lock the soil pile body 2. The fastening plate 31 is horizontally fixed away from the side of the soil pile body 2. A connecting rod 5 is connected, and two fastening plates 31 are fixedly connected at both ends of the connecting rod 5 respectively. The two fastening plates 31 are installed on two adjacent soil pile bodies 2. The connecting rod 5 can fix the soil pile bodies 2 fixed in position by the fastening plates 31 to each other. A sleeve 6 is sleeved on the outer wall of the connecting rod 5. The sleeve 6 can prevent the external foundation soil 1 from eroding the connecting rod 5, and also help the connecting rod 5 to disperse the pressure of a part of the foundation soil 1 above. A limiting plate 7 is arranged on the side of the connecting rod 5 close to the soil pile body 2. The limiting plate 7 is circular, and a limiting hole 8 is arranged in the soil pile body 2. The limiting hole 8 is "T"-shaped. The diameter of the limiting plate 7 is larger than the opening size of the limiting hole 8. A plurality of springs 9 are arranged in the limiting hole 8. One end of the spring 9 close to the limiting plate 7 abuts against the limiting plate 7, and the limiting plate 7 is clamped in the limiting hole 8. The elasticity of the spring 9 can better prevent the limiting plate 7 from loosening, thereby preventing the position of the soil pile body 2 from shifting.

[0034] A vertical steel bar 4 is arranged in the soil pile body 2, and the vertical steel bar 4 is tightly inserted into the soil pile body 2, and is filled with foam waterproof concrete 18 around it. A crushed stone layer 13 is arranged around the top of the soil pile body 2, and a cushion layer 14 is arranged on the top of the crushed stone layer 13. A plurality of transverse steel bars 15 are arranged in the cushion layer 14, and the transverse steel bars 15 are connected to the vertical steel bars 4. A pile cap 16 is arranged on the top of the soil pile body 2, and the diameter of the pile cap 16 is larger than the soil pile body 2. When in use, the pile cap 16 is covered on the top of the soil pile body 2 to prevent the pile head of the soil pile body 2 from being scratched by gravel, etc. A through hole 17 is arranged on the pile cap 16, and the through hole 17 is for the vertical steel bars 4 and the transverse steel bars 15 to pass through. The plurality of vertical steel bars 4 in the cushion layer 14 and the transverse steel bars 15 are fixedly connected to each other through the pile cap 16, which plays a role of mutual fixing.

[0035] Working principle: The utility model designs a concrete pile composite foundation. When in use, deep digging is first carried out at a determined position. After the shape of the soil pile body 2 is dug out, the cast soil pile body 2 is inserted into the foundation soil 1. The cast soil pile body 2 is provided with vertical steel bars 4. Then, a fastening plate 31 is installed on each soil pile body 2. The fixing plate 10 on the fastening plate 31 is locked by the fastening bolts 12. Then, the connecting rod 5 and the sleeve 6 are installed to connect the adjacent soil pile bodies 2. After the pile cap 16 is installed on the top of the soil pile body 2, a layer of crushed stone layer 13 is laid. After the laying is completed, the transverse steel bars 15 are connected to the vertical steel bars 4. After the connection is completed, a cushion layer 14 is finally laid to ensure the stability of the entire composite foundation.

[0036] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A concrete pile composite foundation, characterized in that: The invention comprises a foundation soil (1), wherein a plurality of soil pile bodies (2) are arranged in the foundation soil (1), a fixing device (3) is arranged between two adjacent soil pile bodies (2), a vertical steel bar (4) is arranged in the soil pile body (2), the fixing device (3) comprises a fastening plate (31) arranged on the outer wall of the soil pile body (2), a connecting rod (5) is fixedly connected to the side of the fastening plate (31) away from the soil pile body (2), the outer wall of the connecting rod (5) is sleeved on a sleeve (6), and the fastening plate (31) is used to lock two adjacent soil pile bodies (2).

2. A concrete pile composite foundation according to claim 1, characterized in that: A limiting plate (7) is arranged on one side of the connecting rod (5) close to the soil pile body (2); a limiting hole (8) is arranged in the soil pile body (2); a plurality of springs (9) are arranged in the limiting hole (8); one end of the spring (9) close to the limiting plate (7) abuts against the limiting plate (7); and the limiting plate (7) is clamped in the limiting hole (8).

3. The concrete pile composite foundation according to claim 1, characterized in that: Two fixing plates (10) are arranged on the fastening plate (31), threaded holes (11) are arranged on the two fixing plates (10), and fastening bolts (12) are arranged on the threaded holes (11).

4. The concrete pile composite foundation according to claim 1, characterized in that: A crushed stone layer (13) is arranged around the top of the soil pile body (2), and a cushion layer (14) is arranged on the top of the crushed stone layer (13).

5. The concrete pile composite foundation according to claim 4, characterized in that: A plurality of transverse steel bars (15) are arranged in the cushion layer (14), and the transverse steel bars (15) are connected to the vertical steel bars (4).

6. The concrete pile composite foundation according to claim 1, characterized in that: A pile cap (16) is arranged on the top of the soil pile body (2), and a through hole (17) is arranged on the pile cap (16), and the through hole (17) is used for the vertical steel bar (4) to pass through.

7. The concrete pile composite foundation according to claim 1, characterized in that: Foam waterproof concrete (18) is arranged in the soil pile body (2).