Balanced lifting appliance suitable for TBM (Tunnel Boring Machine)
By designing a balanced spreader for the TBM tunnel boring machine, and using the lifting device and lifting hoop traveling on the rails, the problems of difficult construction and high cost during the disassembly of the TBM tunnel boring machine are solved, and smooth lifting and transfer are achieved to the maximum extent. Host integrity is preserved.
Patent Information
- Application Number
- CN202420627313.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-28
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-03-28
AI Technical Summary
During the disassembly process of the TBM tunnel boring machine, the construction of the tunnel expansion and early excavation of the dismantling tank chamber is difficult, the work site is dangerous, the cost is high, it cannot be reused, the engineering volume is huge, and the work site risk factor is high.
Design a balanced spreader suitable for TBM tunnel boring machines, including two sets of spreaders for lifting shields and main engines. This is achieved by using a lifting device running on the track on the top wall of the tunnel, using lifting brackets and lifting hoops. Smooth hoisting and transfer to maximize the integrity of the TBM host.
It realizes the smooth hoisting and transfer of the TBM tunnel boring machine in a limited space, reduces the disassembly workload, reduces the construction difficulty and cost, improves the safety of the operation, and retains the integrity of the TBM host to the maximum extent.
Smart Images

Figure CN221876287U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of TBM construction, in particular to a balancing hanger suitable for a TBM. Background Art
[0002] Tunnel boring machine (TBM) is the most advanced tunnel excavation and construction equipment in the world, representing the development level of a country's major technical equipment. Usually, after completing the excavation task of one section, TBM will be transferred to another section for excavation. Due to the huge size of TBM, TBM needs to be disassembled before it can be transferred to the next construction section.
[0003] There are currently two methods for dismantling a TBM. The first is to dismantle the machine by abandoning the shell, that is, to destructively dismantle the shield in the tunnel excavated by the TBM to ensure the integrity of major components such as the drive box. However, the workload is large, and the integrity rate of the TBM host is low, resulting in economic losses. The second method is to dig a dismantling chamber at the other end of the terminal, and complete the dismantling of the TBM through a hoisting system, which can maintain the integrity of the TBM host. However, the expansion of the tunnel and the early excavation of the dismantling chamber are difficult to construct and dangerous at the work site; this dismantling and lifting method is costly, non-reusable, requires a huge amount of work, and has a high risk factor at the work site.
[0004] In view of this, this application is hereby filed. Utility Model Content
[0005] The technical problem to be solved by the utility model is that the current expansion of tunnels and early excavation of machine room dismantling are difficult to construct and dangerous at the work site. The disassembly and lifting methods are costly, non-reusable, huge in engineering workload and high in risk factor at the work site. The utility model aims to provide a balancing hoist suitable for TBM tunneling machines. By providing two sets of hoists for hoisting the shield and the main machine respectively, the stable hoisting and unloading of the TBM tunneling machine within the limited space of the tunnel can be achieved, thereby facilitating the subsequent disassembly of the TBM tunneling machine and retaining the integrity rate of the TBM main machine to the maximum extent.
[0006] The utility model is realized by the following technical solutions:
[0007] A balancing hanger suitable for a TBM tunneling machine, comprising a track for being fixedly arranged on a top wall of a tunnel, wherein the track is extended along the length direction of the tunnel;
[0008] The track is provided with a first lifting device, a second lifting device and a third lifting device along the length direction of the tunnel, a lifting bracket for lifting the TBM shield top block is hung between the lower ends of the first lifting device and the second lifting device, and a lifting hoop for being sleeved on the outside of the TBM main machine is hung at the lower end of the third lifting device;
[0009] The first lifting device, the second lifting device and the third lifting device can all move along the track.
[0010] The balancing hoist of the utility model can realize the smooth hoisting and unloading of the TBM tunneling machine within the limited space in the tunnel by arranging two sets of hoists respectively for hoisting the shield and the main machine, thereby facilitating the subsequent dismantling of the TBM tunneling machine and retaining the integrity rate of the TBM main machine to the maximum extent.
[0011] When the lifting device of the utility model is in use, the lifting bracket is horizontally inserted into the shield so that the lifting bracket fits with the inner wall of the shield top block, and then the hoop is installed on the outer wall of the main machine, and the first lifting device, the second lifting device and the third lifting device are started at the same time to lift the shield part and the main machine part at the same time; the utility model can solve the problem of lifting height by propping up the shield by the lifting bracket, and can avoid deformation of the main machine by lifting the main machine by setting the lifting hoop outside the main machine.
[0012] After the TBM is lifted, it can be easily disassembled. Since the first lifting device, the second lifting device and the third lifting device can all walk on the track, when the shield and other components are being disassembled, the first lifting device and the second lifting device can transfer the disassembled components to the transport vehicle, which greatly reduces the workload of disassembly.
[0013] In a specific embodiment, two tracks are arranged in parallel along the transverse direction of the tunnel, and a first lifting device, a second lifting device and a third lifting device are arranged on both tracks. The four corners of the lifting bracket are respectively hung on the two first lifting devices and the two second lifting devices.
[0014] The utility model can make the lifting and hoisting of the tunnel boring machine more stable by arranging two tracks.
[0015] In a specific embodiment, lifting ears are provided on both sides of the lifting hoop, and the two lifting ears are used to hang on two third lifting devices respectively. By providing two lifting ears on both sides, the situation in which the lifting hoop is locally deformed and causes deformation of the main engine when lifting the main engine can be avoided.
[0016] In a specific embodiment, the lifting bracket is an arc-shaped frame structure, and its arc-shaped structure fits the inner wall curvature of the TBM shield top block, so that the lifting bracket can provide a more stable supporting force for the shield top block, thereby improving the balance during the lifting process.
[0017] In a specific embodiment, a plurality of support columns are arranged on the lifting bracket along the length direction, and a support beam is arranged at the upper end of the support column.
[0018] In a specific embodiment, the support columns are arranged in two rows along the lateral direction of the lifting bracket, and a support beam is arranged at the upper ends of the two support columns in each row, and the upper end of the support beam fits the inner wall curvature of the TBM shield top block.
[0019] In a specific embodiment, the lifting hoop is assembled from two half hoops, the two half hoops include an upper hoop and a lower hoop, the two ends of the upper hoop and the lower hoop are detachably connected by high-strength bolts, and two lifting ears are respectively installed at the connection between the two ends of the upper hoop and the lower hoop. The utility model can facilitate the rapid installation of the lifting hoop outside the main machine by setting the upper and lower half hoops, wherein the lifting ears are set at the connection between the upper and lower half hoops to ensure that the connection between the upper and lower half hoop is subjected to force at the same time during the lifting process to avoid breakage of the connection.
[0020] In a specific embodiment, a top lifting ear is provided on the top of the lifting hoop, and the top lifting ear is simultaneously hung on the lower ends of two third lifting devices. The utility model forms a triangular force relationship between the third lifting device, the lifting ear and the top lifting ear by providing the top lifting ear, so that the force on the main engine during the lifting process is more balanced.
[0021] In a specific embodiment, the first lifting device, the second lifting device and the third lifting device all include a traveling trolley and a lifting hoist.
[0022] In a specific embodiment, anti-deformation plates are extended at intervals along the circumferential direction at both the front and rear ends of the lower half hoop. The anti-deformation plates are locally added at intervals to increase the contact area with the outer wall of the main machine, thereby avoiding deformation of the main machine caused by excessive concentration of force.
[0023] Compared with the prior art, the utility model has the following advantages and beneficial effects:
[0024] The embodiment of the utility model provides a balancing hoist suitable for a TBM tunneling machine. By arranging two sets of hoists for hoisting a shield and a main machine respectively, the stable hoisting and unloading of the TBM tunneling machine within a limited space in a tunnel can be achieved, thereby facilitating the subsequent dismantling of the TBM tunneling machine and retaining the integrity rate of the TBM main machine to the maximum extent. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without creative work.
[0026] Figure 1A schematic diagram of a balancing hanger structure suitable for a TBM tunneling machine provided in an embodiment of the utility model;
[0027] Figure 2 A schematic diagram of the structure of a lifting bracket provided in an embodiment of the utility model;
[0028] Figure 3 A schematic diagram of the lifting hoop structure provided in an embodiment of the utility model.
[0029] Marks and corresponding parts names in the attached drawings:
[0030] 1-track, 2-first lifting device, 3-second lifting device, 4-third lifting device, 5-lifting bracket, 6-lifting hoop, 7-lifting ear, 8-support column, 9-support beam, 10-tunnel, 11-top lifting ear, 12-anti-deformation plate. DETAILED DESCRIPTION
[0031] In order to make the purpose, technical solutions and advantages of the utility model more clearly understood, the utility model is further described in detail below in conjunction with embodiments and drawings. The schematic implementation manner of the utility model and its description are only used to explain the utility model and are not intended to limit the utility model.
[0032] In the following description, a large number of specific details are set forth in order to provide a thorough understanding of the present invention. However, it is apparent to those skilled in the art that these specific details are not necessary to implement the present invention. In other embodiments, in order to avoid confusing the present invention, well-known structures are not specifically described.
[0033] Throughout the specification, references to "one embodiment," "an embodiment," "an example," or "an example" mean that a particular feature, structure, or characteristic described in conjunction with the embodiment or example is included in at least one embodiment of the present invention. Therefore, the phrases "one embodiment," "an embodiment," "an example," or "an example" appearing in various places throughout the specification do not necessarily all refer to the same embodiment or example. In addition, particular features, structures, or characteristics may be combined in one or more embodiments or examples in any suitable combination and / or sub-combination. In addition, it will be appreciated by those of ordinary skill in the art that the figures provided herein are for illustrative purposes and that the figures are not necessarily drawn to scale. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.
[0034] In the description of the present invention, the terms "front", "rear", "left", "right", "up", "down", "vertical", "horizontal", "high", "low", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they should not be understood as limiting the scope of protection of the present invention.
[0035] Example
[0036] like Figure 1-Figure 3 As shown, an embodiment of the utility model provides a balancing hanger suitable for a TBM tunneling machine, comprising a track 1 for being fixedly arranged on the top wall of a tunnel 10, wherein the track 1 is extended along the length direction of the tunnel 10;
[0037] The track 1 is provided with a first lifting device 2, a second lifting device 3 and a third lifting device 4 along the length direction of the tunnel 10, a lifting bracket 5 for lifting the TBM shield top block is hung between the lower ends of the first lifting device 2 and the second lifting device 3, and a lifting hoop 6 for being sleeved on the outside of the TBM main machine is hung at the lower end of the third lifting device 4;
[0038] The first lifting device 2 , the second lifting device 3 and the third lifting device 4 can all move along the track 1 .
[0039] The balancing hoist of the utility model can realize the smooth hoisting and unloading of the TBM tunneling machine within the limited space in the tunnel by arranging two sets of hoists respectively for hoisting the shield and the main machine, thereby facilitating the subsequent dismantling of the TBM tunneling machine and retaining the integrity rate of the TBM main machine to the maximum extent.
[0040] When the lifting device of the utility model is in use, the lifting bracket is horizontally inserted into the shield so that the lifting bracket fits with the inner wall of the shield top block, and then the hoop is installed on the outer wall of the main machine, and the first lifting device, the second lifting device and the third lifting device are started at the same time to lift the shield part and the main machine part at the same time; the utility model can solve the problem of lifting height by propping up the shield by the lifting bracket, and can avoid deformation of the main machine by lifting the main machine by setting the lifting hoop outside the main machine.
[0041] After the TBM is lifted, it can be easily disassembled. Since the first lifting device, the second lifting device and the third lifting device can all walk on the track, when the shield and other components are being disassembled, the first lifting device and the second lifting device can transfer the disassembled components to the transport vehicle, which greatly reduces the workload of disassembly.
[0042] In a specific embodiment, two rails 1 are arranged in parallel along the transverse direction of the tunnel 10, and a first lifting device 2, a second lifting device 3 and a third lifting device 4 are provided on the two rails 1. The four corners of the lifting bracket 5 are respectively hung on the two first lifting devices 2 and the two second lifting devices 3.
[0043] The utility model can make the lifting and hoisting of the tunnel boring machine more stable by arranging two tracks.
[0044] In a specific embodiment, lifting ears 7 are provided on both sides of the lifting hoop 6, and the two lifting ears 7 are respectively used to hang on two third lifting devices 4. By providing two lifting ears on both sides, the local deformation of the lifting hoop can be avoided when lifting the main machine, causing deformation of the main machine.
[0045] In a specific embodiment, the lifting bracket 5 is an arc-shaped frame structure, and its arc-shaped structure fits the inner wall curvature of the TBM shield top block, so that the lifting bracket can provide a more stable supporting force for the shield top block, thereby improving the balance during the lifting process.
[0046] In a specific embodiment, a plurality of support columns 8 are provided on the lifting bracket 5 along the length direction, and a support beam 9 is provided at the upper end of the support column 8 .
[0047] In a specific embodiment, the support columns 8 are arranged in two rows along the lateral direction of the lifting bracket 5, and a support beam 9 is arranged at the upper ends of two support columns 8 in each row, and the upper end of the support beam 9 fits the inner wall curvature of the TBM shield top block.
[0048] In a specific embodiment, the lifting hoop 6 is assembled from two half hoops, the two half hoops include an upper hoop and a lower hoop, the two ends of the upper hoop and the lower hoop are detachably connected by high-strength bolts, and two lifting ears 7 are respectively installed at the connection between the two ends of the upper hoop and the lower hoop. The utility model can facilitate the rapid installation of the lifting hoop outside the main machine by setting the upper and lower half hoops, wherein the lifting ears are set at the connection between the upper and lower half hoops to ensure that the connection between the upper and lower half hoop is subjected to force at the same time during the lifting process to avoid breakage of the connection.
[0049] In a specific embodiment, a top lifting ear 11 is provided at the top of the lifting hoop 6, and the top lifting ear 11 is simultaneously hung on the lower ends of two third lifting devices 4. The utility model forms a triangular force relationship between the third lifting device, the lifting ear and the top lifting ear by providing a top lifting ear, so that the force on the main engine during the lifting process is more balanced.
[0050] In a specific embodiment, the first lifting device 2, the second lifting device 3 and the third lifting device 4 all include a traveling trolley and a lifting hoist.
[0051] In a specific embodiment, anti-deformation plates 12 are extended at intervals along the circumferential direction at both the front and rear ends of the lower half hoop. By locally adding anti-deformation plates at intervals to increase the contact area with the outer wall of the host, deformation of the host caused by excessive concentration of force can be avoided.
[0052] The specific implementation methods described above further illustrate the purpose, technical solutions and beneficial effects of the utility model in detail. It should be understood that the above description is only the specific implementation method of the utility model and is not used to limit the protection scope of the utility model. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the utility model should be included in the protection scope of the utility model.
Claims
1. A balancing sling suitable for TBM tunneling machine, It is characterized in that It comprises a track (1) for being fixedly arranged on the top wall of a tunnel (10), wherein the track (1) is extended along the length direction of the tunnel (10); A first lifting device (2), a second lifting device (3) and a third lifting device (4) are arranged on the track (1) along the length direction of the tunnel (10); a lifting bracket (5) for lifting the TBM shield top block is hung between the lower ends of the first lifting device (2) and the second lifting device (3); and a lifting hoist (6) for being sleeved on the outside of the TBM main machine is hung at the lower end of the third lifting device (4); The first lifting device (2), the second lifting device (3) and the third lifting device (4) can all move along the track (1).
2. A balancing hanger suitable for a TBM tunneling machine according to claim 1, It is characterized in that Two rails (1) are arranged in parallel along the transverse direction of the tunnel (10), and a first lifting device (2), a second lifting device (3) and a third lifting device (4) are arranged on the two rails (1), and the four corners of the lifting bracket (5) are respectively hung on the two first lifting devices (2) and the two second lifting devices (3).
3. A balancing hanger suitable for a TBM tunneling machine according to claim 2, It is characterized in that Lifting ears (7) are provided on both sides of the lifting hoop (6), and the two lifting ears (7) are used to be hung on two third lifting devices (4) respectively.
4. A balancing hanger suitable for a TBM tunneling machine according to claim 1, It is characterized in that The lifting bracket (5) is an arc-shaped frame structure, and its arc-shaped structure fits the inner wall curvature of the TBM shield top block.
5. A balancing hanger suitable for a TBM tunneling machine according to claim 1, It is characterized in that A plurality of support columns (8) are arranged on the lifting bracket (5) along the length direction, and a support beam (9) is arranged at the upper end of each support column (8).
6. A balancing hanger suitable for a TBM tunneling machine according to claim 5, It is characterized in that The support columns (8) are arranged in two rows along the transverse direction of the lifting bracket (5), and a support beam (9) is arranged at the upper ends of the two support columns (8) in each row, and the upper ends of the support beams (9) are in contact with the inner wall curvature of the TBM shield top block.
7. A balancing hanger suitable for a TBM tunneling machine according to claim 3, It is characterized in that The lifting hoop (6) is composed of two half hoops assembled together, the two half hoops include an upper hoop and a lower hoop, the two ends of the upper hoop and the lower hoop are detachably connected by high-strength bolts, and the two lifting ears (7) are respectively installed at the connection points at the two ends of the upper hoop and the lower hoop.
8. A balancing hanger suitable for a TBM tunneling machine according to claim 7, It is characterized in that A top lifting lug (11) is provided at the top of the lifting hoop (6), and the top lifting lug (11) is simultaneously hung on the lower ends of two third lifting devices (4).
9. The balancing hanger suitable for a TBM tunneling machine according to claim 1, It is characterized in that The first lifting device (2), the second lifting device (3) and the third lifting device (4) all comprise a traveling trolley and a lifting hoist.
10. A balancing hanger suitable for a TBM tunneling machine according to claim 7, It is characterized in that Anti-deformation plates (12) are spaced apart and extend along the circumferential direction at both the front and rear ends of the lower half hoop.