Piping processing structure

By building a steel plate cofferdam and cement mixing pile structure on the embankment, the problems of low construction efficiency and poor integrity in the existing technology are solved, rapid and efficient piping disposal is achieved, and manpower requirements and construction time are reduced.

CN221878135UActive Publication Date: 2024-10-22POWERCHINA HUADONG ENG CORP LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420110475.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-17
Publication Date
2024-10-22
Estimated Expiration
2034-01-17

AI Technical Summary

Technical Problem

The existing technology has low construction efficiency when dealing with piping surges, requires a lot of manpower and material resources, and the integrity of the filled sandbag cofferdam is poor, making it difficult to quickly handle the danger.

Method used

It adopts a structure of steel plate cofferdam and cement mixing piles. The steel plate cofferdam is spliced ​​by Larson steel sheet piles. It is equipped with geotextile cushion bags, filter material layers and clay soil covering layers. The cement mixing piles are used to block piping surges. The mechanical construction is Quickly block the development of piping surges.

Benefits of technology

It achieves rapid response and efficient disposal of piping surges. The steel plate cofferdam can be reused, reducing manpower requirements, and the construction speed is fast, effectively blocking the development of piping surges.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221878135U_ABST
    Figure CN221878135U_ABST
Patent Text Reader

Abstract

The utility model provides a piping treatment structure. The piping treatment structure comprises a steel plate cofferdam and a cement mixing pile, the steel plate cofferdams are arranged around the piping point in a circumferential mode. The steel plate cofferdam is formed by splicing Larsen steel plate piles; a geotechnical cloth cushion layer bag, an inverted filter material layer and a cohesive soil covering layer are sequentially arranged in the steel plate cofferdam from bottom to top. The cement mixing piles are located on the downstream side of the dike to block piping, and the cement mixing piles extend towards the two sides in the axis direction of the dike. The Larsen steel sheet piles can be pulled out and reused after piping treatment is completed, compared with a sandbag cofferdam, the construction speed is high, the construction efficiency is high, the geotechnical cloth cushion bags can be manufactured in advance before flood, mechanical construction is adopted, a large amount of manpower is not needed, rapid response can be achieved, piping can be treated in time, and piping development is effectively blocked.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of levee engineering, in particular to a pipe burst processing structure. Background Art

[0002] Piping is a phenomenon in which fine particles in cohesive soil or soil with very little cohesion move or are gradually washed away through the pores between coarse particles under the action of seepage water flow. Piping is one of the common hazards in embankment projects. Piping will cause the soil at the bottom of the dam to be continuously discharged outward under the action of seepage force. After a long period of time, the soil skeleton of the dam foundation will be destroyed, the pores will be expanded, the foundation soil will be hollowed out, causing the dam to collapse, resulting in dam breaches and other hazards. During the basin-wide flood in the Yangtze River in 1998, a total of 73,825 embankments in the middle and lower reaches occurred, of which piping accounted for 35.2%, of which 1,702 were major hazards, of which piping accounted for 51.2%; there were 698 major hazards on the main stream of the Yangtze River, of which piping accounted for 52.4%.

[0003] At present, the methods used to deal with pipe bursts include anti-filtration wells, anti-filtration layer pressure covers, and water basins. That is, artificially fill sandbags, build sandbag cofferdams at the outlet of the pipe burst, and then fill the sandbag cofferdams with anti-filtration materials, or use sand and gravel to press stones or earthbags to form a water filtration pressure immersion platform to deal with pipe bursts. The above methods require a lot of manpower, material resources and time to move earthbags, which is time-consuming and labor-intensive, and cannot quickly deal with pipe bursts. In addition, the integrity of the filled sandbag cofferdam is poor, and the difficulty of manual filling increases when the water pressure inside and outside the pipe burst is high. Utility Model Content

[0004] The main purpose of the utility model is to provide a pipe burst processing structure, hoping to effectively solve the problems in the background technology.

[0005] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0006] A pipe burst treatment structure, characterized in that: the pipe burst treatment structure comprises a steel plate cofferdam and a cement mixing pile;

[0007] The steel plate cofferdam is arranged around the piping point;

[0008] The steel plate cofferdam is formed by splicing Larsen steel sheet piles;

[0009] The steel plate cofferdam is provided with a geotextile cushion bag, a filter material layer, and a clay soil cover layer from bottom to top;

[0010] The cement mixing piles are located on the backwater side of the dike to block pipe bursts, and the cement mixing piles are extended to both sides along the axis direction of the dike.

[0011] While adopting the above technical solutions, the present invention can also adopt or combine the following technical solutions:

[0012] As a preferred technical solution of the utility model: two adjacent geotextile cushion bags are overlapped in pairs, and the overlap length is 5-10cm.

[0013] As a preferred technical solution of the utility model: the geotextile cushion bag adopts geotextile with a weight of more than 380g / m2.

[0014] As a preferred technical solution of the utility model: a single geotextile cushion bag is 1.5m long, 1m wide and 20cm thick.

[0015] As a preferred technical solution of the utility model: the filter material layers are respectively a mung bean sand layer, a graded crushed stone layer and a block stone layer from bottom to top.

[0016] As a preferred technical solution of the utility model: the thickness of the mung bean paste layer is 10-20cm.

[0017] As a preferred technical solution of the utility model: the thickness of the graded crushed stone layer is 10-20 cm.

[0018] As a preferred technical solution of the utility model: the thickness of the block stone layer is 10-20cm.

[0019] As a preferred technical solution of the utility model: the laying thickness of the clay soil covering layer is 20-30cm.

[0020] The utility model provides a pipe burst treatment structure, which has the following beneficial effects:

[0021] 1) Larsen steel sheet piles can be pulled out and reused after the pipe burst is dealt with. Compared with sandbag cofferdams, the construction speed is fast and the construction efficiency is high.

[0022] 2) Geotextile cushion bags can be made in advance before the flood season, stored in the emergency material warehouse, and transported to the site when needed.

[0023] 3) The pipe burst treatment structure is constructed mechanically, does not require a large amount of manpower, can respond quickly, and handle the pipe burst in time, effectively blocking the development of the pipe burst. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 An overall structural layout diagram of a pipe burst treatment structure provided by the utility model;

[0025] Figure 2 A top view of a pipe burst treatment structure provided by the utility model;

[0026] Figure 3 for Figure 2 A magnified image of area A;

[0027] Figure 4 It is a schematic diagram of geotextile cushion bags overlapping each other;

[0028] In the figure: 1- steel plate cofferdam; 2- geotextile cushion bag; 3- filter material layer; 4- clay soil cover layer; 5- cement mixing pile; 6- pipe burst point; 7- mung bean sand layer; 8- graded gravel layer; 9- block stone layer; 10- embankment; 11- Larsen steel sheet pile. DETAILED DESCRIPTION

[0029] The present invention will be further described in detail with reference to the accompanying drawings and specific embodiments.

[0030] like Figure 1-3 As shown, a pipe burst treatment structure includes a steel plate cofferdam 1 and a cement mixing pile 5;

[0031] The steel plate cofferdam 1 is arranged around the piping point 6; the steel plate cofferdam 1 is composed of Larsen steel sheet piles 1; a geotextile cushion bag 2, a filter material layer 3, and a clay cover layer 4 are arranged in sequence from bottom to top in the steel plate cofferdam 1; cement mixing piles 5 are located on the backwater side of the levee 10 to block the piping, and the cement mixing piles 5 are extended to both sides along the axis direction of the levee 10.

[0032] like Figure 1-3 The specific construction steps are as follows:

[0033] Professional surveying personnel mark out the steel plate cofferdam 1 and the longitudinal axis of the cement mixing pile on site.

[0034] The mechanical hammer pile driver arrives at the designated location and inserts the Larsen steel sheet pile 1 1-2 m below the ground to form a steel pile cofferdam 1. The Larsen steel sheet pile 11 is 2 m away from the outside of the pipe burst point 6.

[0035] After the steel plate cofferdam 1 is installed, a geotextile cushion bag 2 is laid inside the steel plate cofferdam 1. The geotextile cushion bag 2 is made of 380g / m 2 For the above geotextiles, two adjacent geotextile cushion bags are overlapped in pairs with an overlap length of 5-10cm, covering the entire steel cofferdam.

[0036] While laying the geotextile cushion bag 2, cement mixing piles 5 can be constructed. The cement mixing piles 5 are constructed in sequence along the longitudinal axis of the cement mixing piles, and the piles are interlocked with each other. Since cement mixing piles are a mature construction process, the specific construction process is not repeated here. A single geotextile cushion bag 2 is 1.5m long, 1m wide, and 20cm thick.

[0037] After the geotextile cushion bag 2 is laid, the filter material layer 3 is laid on the geotextile cushion bag 2. First, the mung bean sand layer 7 is laid with a thickness of 10cm-20cm; then, the graded gravel layer 8 is laid on the mung bean sand layer 7 with a thickness of 10cm-20cm; then, the block stone layer 9 is laid on the graded gravel layer 8 with a thickness of 10cm-20cm.

[0038] After the reverse filter material layer 3 is laid, the water outflow at the pipe burst point 6 is observed. When the water potential weakens and the water outflow is not large, a clay cover layer 4 is laid on the reverse filter material layer 3 with a thickness of 20cm-30cm, and finally the air is sealed.

[0039] After the construction of the clay cover layer 4 and the cement mixing piles 5 is completed and there is no water seepage at the piping point, the Larsen steel sheet piles 11 can be pulled out, the debris on the construction site can be cleaned up, and the treatment of the piping point 6 is completed.

[0040] The above-mentioned specific implementation methods are used to explain the present invention and are only preferred embodiments of the present invention, rather than limiting the present invention. Any modifications, equivalent substitutions, improvements, etc. made to the present invention within the spirit of the present invention and the protection scope of the claims shall fall within the protection scope of the present invention.

Claims

1. A piping treatment structure, characterized in that: The pipe burst treatment structure comprises a steel plate cofferdam (1) and a cement mixing pile (5); The steel plate cofferdam (1) is arranged around the piping point (6); The steel plate cofferdam (1) is formed by splicing Larsen steel sheet piles (11); The steel plate cofferdam (1) is provided with a geotextile cushion bag (2), a filter material layer (3), and a clay soil cover layer (4) in order from bottom to top; The cement mixing piles (5) are located on the backwater side of the embankment (10) to block pipe bursts, and the cement mixing piles (5) are arranged to extend to both sides along the axis direction of the embankment (10).

2. A pipe surge treatment structure according to claim 1, characterized in that: Two adjacent geotextile cushion bags (2) are overlapped in pairs, and the overlap length is 5-10 cm.

3. A pipe burst treatment structure according to claim 1 or 2, characterized in that: The geotextile cushion bag (2) is made of 380g / m 2 Geotextile above.

4. A piping treatment structure according to claim 3, characterized in that: The length of a single geotextile cushion bag (2) is 1.5 m, the width is 1 m, and the thickness is 20 cm.

5. The piping treatment structure according to claim 1, characterized in that: The reverse filter material layers (3) are respectively a mung bean sand layer (7), a graded crushed stone layer (8) and a block stone layer (9) from bottom to top.

6. A piping treatment structure according to claim 5, characterized in that: The thickness of the mung bean paste layer (7) is 10-20 cm.

7. A piping treatment structure according to claim 5, characterized in that: The thickness of the graded crushed stone layer (8) is 10-20 cm.

8. The piping treatment structure according to claim 5, characterized in that: The thickness of the block stone layer (9) is 10-20 cm.

9. The piping treatment structure according to claim 1, characterized in that: The laying thickness of the clay soil covering layer (4) is 20-30 cm.

10. The piping treatment structure according to claim 1, characterized in that: The cement mixing piles (5) are interlocked with each other in pairs.