By using embedded parts, sealing units and temporary blocking units in the construction of prefabricated stairs, the problems of grouting material outflow and garbage blockage are solved, construction quality is improved and costs are reduced.
Patent Information
- Application Number
- CN202420457352.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-11
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-03-11
AI Technical Summary
During the construction process of prefabricated stairs, the grouting material easily flows out from the gaps between the prefabricated stairs and the ladder beams, and the reserved holes are easily blocked by garbage, resulting in poor construction quality and material waste.
An installation device is designed that includes embedded parts, reserved through holes, sealing units and temporary blocking units. The sealing unit tightly combines the ladder beam and the reserved through holes to prevent the grouting material from flowing out, and the temporary blocking unit prevents the grouting material from flowing out. Garbage is blocked and the device can be recycled.
It effectively prevents grouting materials from flowing out from the gaps between prefabricated stairs and ladder beams, ensuring that reserved holes are not blocked, improving construction quality and reducing costs.
Smart Images

Figure CN221878718U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of assembled staircase construction, in particular to an installation device for assembled staircase supports. Background Art
[0002] In recent years, with the vigorous advocacy of the Chinese government, relevant specifications for the design, construction, supervision, quality control, etc. of prefabricated buildings have been continuously issued, and prefabricated buildings have also been widely used. Prefabricated buildings are divided into pure prefabricated buildings and partially prefabricated buildings, among which prefabricated stairs are an important part of partially prefabricated buildings. Compared with traditional cast-in-place stairs, prefabricated stairs have the advantages of less on-site work, short construction period, energy saving and environmental protection, and low cost.
[0003] However, during the construction of prefabricated stairs, there are the following problems:
[0004] 1. Because the flatness of the upper surface of the ladder beam is difficult to ensure, there is a gap between the prefabricated stairs and the ladder beam after hoisting. When pouring grouting material, it is easy to flow out from the bottom, resulting in material waste and poor construction quality. In addition, the surface under the stairs needs to be cleaned before the putty construction in the later stage, which is time-consuming and laborious.
[0005] 2. After the lifting is completed and the reserved holes are not sealed, construction waste often blocks the reserved holes, resulting in the need for secondary cleaning during sealing and poor results.
[0006] Therefore, how to effectively prevent the grouting material from flowing out of the gap between the prefabricated stairs and the ladder beams and prevent garbage from clogging the reserved holes is a technical problem that needs to be solved urgently. Utility Model Content
[0007] In view of the deficiencies in the above-mentioned background technology, the utility model proposes an installation device for assembled stair supports, which solves the problems that grouting material easily flows out of the gap between the prefabricated stairs and the ladder beams, and garbage easily blocks the reserved holes.
[0008] The technical solution of this application is:
[0009] A mounting device for an assembled stair support, comprising an embedded part embedded in a ladder beam, and a reserved through hole provided on a prefabricated staircase, wherein one end of the embedded part is embedded in the ladder beam, and the other end of the embedded part is plugged and matched with the reserved through hole, a sealing unit is provided between the ladder beam and the prefabricated staircase, and a temporary blocking unit is provided at the top of the reserved through hole. By using the sealing unit, the leveling structure layer above the ladder beam is tightly combined with the reserved through hole, the gap between the leveling structure layer and the reserved through hole is filled, and the grouting material is prevented from flowing out of the gap between the prefabricated staircase and the ladder beam, and after the hoisting is completed, the temporary blocking unit is used to directly place it in the prefabricated through hole to ensure that the channel is not blocked, and the temporary blocking unit is taken out during grouting for turnover and recycling; the device used is simple to manufacture, can be industrially processed and produced, and can reduce construction costs while improving construction quality.
[0010] Furthermore, the sealing unit includes a sealing gasket inserted into the bottom of the reserved through hole to prevent the grouting material from leaking due to a loose bottom during grouting.
[0011] Furthermore, the sealing gasket is made of elastic material, has good sealing performance, good elasticity and friction, and can be supported in the reserved through hole to prevent slipping out.
[0012] Furthermore, the sealing gasket includes an annular base gasket, and the upper surface of the annular base gasket is connected to a connecting ring for fitting against the inner wall of the reserved through hole.
[0013] Furthermore, the diameter of the annular base gasket is larger than the diameter of the reserved through hole, and the bottom of the reserved through hole is covered to prevent the generation of gaps and leakage of slurry.
[0014] Furthermore, the temporary blocking unit includes a cap plugged into the top of the reserved through hole.
[0015] Furthermore, the cap is made of synthetic resin material, has tight sealing, is easy to operate, and is temporarily blocked before grouting to prevent garbage from filling the grouting hole.
[0016] Furthermore, the cap comprises a cap body, the cap body is plug-fitted with the reserved through hole, and the top of the cap body is provided with a brim which cooperates with the prefabricated stair stopper.
[0017] Furthermore, the cover body is cylindrical or wide at the top and narrow at the bottom. When the cover body is wide at the top and narrow at the bottom, the wide part is engaged with the reserved through hole, and the synthetic resin material has a certain elasticity and can be squeezed into the reserved through hole to prevent falling off.
[0018] Furthermore, the upper surface of the brim is a plane or a curved surface with a higher center and lower surroundings.
[0019] The specific beneficial effects of the utility model include:
[0020] 1. The utility model uses a sealing unit to make the leveling structure layer above the ladder beam and the reserved through hole tightly combined, fill the gap between the leveling structure layer and the reserved through hole, and prevent the grouting material from flowing out of the gap between the prefabricated stairs and the ladder beam. After the hoisting is completed, a temporary blocking unit is used and directly placed in the prefabricated through hole to ensure that the channel is not blocked, and the temporary blocking unit is taken out during grouting for turnover and recycling;
[0021] 2. The device adopted by the utility model is simple to manufacture and can be industrially processed and produced, which can improve the construction quality and reduce the construction cost at the same time. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the embodiments of the present utility model, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0023] Figure 1 This is a schematic diagram of the use state of the utility model;
[0024] Figure 2 for Figure 1 The enlarged view of point A in the middle;
[0025] Figure 3 is a schematic diagram of a sealing gasket;
[0026] Figure 4 is a cross-sectional view of a sealing gasket;
[0027] Figure 5 is a schematic diagram of cap embodiment 1;
[0028] Figure 6 is a cross-sectional view of cap embodiment 1;
[0029] Figure 7 is a schematic diagram of cap embodiment 2;
[0030] Figure 8 It is a cross-sectional view of cap embodiment 2.
[0031] Description of Figure Numbers:
[0032] 1. Stair beam; 2. Prefabricated stairs; 3. Embedded parts; 4. Reserved through holes;
[0033] 5. Sealing unit; 6. Temporary plugging unit; 7. Leveling structure layer;
[0034] 51. annular base pad; 52. connecting ring;
[0035] 61. Cover body; 62. Brim. DETAILED DESCRIPTION
[0036] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0037] Embodiment 1, a mounting device for a prefabricated stair support, such as Figure 1 , Figure 2 As shown, it includes an embedded part 3 embedded in the ladder beam 1 and a reserved through hole 4 set on the prefabricated staircase 2, one end of the embedded part 3 is embedded in the ladder beam 1, and the other end of the embedded part 3 is plugged and matched with the reserved through hole 4, a leveling structure layer 7 is arranged between the ladder beam 1 and the prefabricated staircase 2, a sealing unit 5 is arranged between the leveling structure layer 7 and the reserved through hole 4, and a temporary blocking unit 6 is arranged at the top of the reserved through hole 4. By using the sealing unit, the leveling structure layer above the ladder beam and the reserved through hole are tightly combined, the gap between the leveling structure layer and the reserved through hole is filled, and the grouting material is prevented from flowing out of the gap between the prefabricated staircase and the ladder beam, and after the hoisting is completed, the temporary blocking unit is used to directly place it in the prefabricated through hole to ensure that the channel is not blocked, and the temporary blocking unit is taken out during grouting for turnover and recycling; the device used is simple to make, can be industrialized and produced, and can improve the construction quality while reducing the construction cost.
[0038] On the basis of the above-mentioned embodiment, as a preferred embodiment, the sealing unit 5 includes a sealing gasket inserted into the bottom of the reserved through hole 4, so that the leveling structure layer 7 above the ladder beam is tightly combined with the reserved through hole 4, thereby filling the gap between the leveling structure layer 7 and the reserved through hole 4 and preventing the grouting material from flowing out from the gap between the prefabricated staircase 2 and the ladder beam 1.
[0039] Based on the above implementation, as a preferred implementation, the sealing gasket is made of elastic material.
[0040] Preferably, the sealing gasket is an annular rubber-plastic gasket with good sealing performance, good elasticity and friction, so as to prevent the grouting material from leaking due to loose bottom during grouting.
[0041] Based on the above implementation, as a preferred implementation, Figure 3 , Figure 4As shown, the sealing gasket includes an annular base gasket 51, and the upper surface of the annular base gasket 51 is connected to a connecting ring 52 for fitting the inner wall of the reserved through hole 4. The connecting ring 52 fills the gap between the annular base gasket 51 and the reserved through hole, effectively preventing leakage of slurry. Moreover, the connecting ring 52 is also made of elastic material, has good elasticity and friction, and can be supported in the reserved through hole to prevent slipping out.
[0042] On the basis of the above-mentioned embodiment, as a preferred embodiment, the diameter of the annular base gasket 51 is larger than the diameter of the reserved through hole 4 , and surrounds the reserved through hole 4 .
[0043] On the basis of the above-mentioned embodiment, as a preferred embodiment, the temporary blocking unit 6 includes a cap inserted into the top of the reserved through hole 4 .
[0044] On the basis of the above-mentioned implementation manner, as a preferred implementation manner, the cover cap is made of synthetic resin material, has a tight seal, is easy to operate, and is temporarily sealed before grouting to prevent garbage from filling the grouting hole.
[0045] On the basis of the above-mentioned embodiment, as a preferred embodiment, the cover cap includes a cover body 61, and the cover body 61 is plugged into the reserved through hole 4. The top of the cover body 61 is provided with a brim 62 that cooperates with the prefabricated staircase 2 to stop. The brim 62 effectively closes the opening of the reserved through hole, and the brim 62 is convenient for workers to disassemble and install.
[0046] On the basis of the above-mentioned embodiment, as a preferred embodiment, the cover body 61 is cylindrical, the cover body 61 is plug-fitted with the reserved through hole 4 , and the diameter of the cover body 61 is smaller than the diameter of the reserved through hole 4 .
[0047] On the basis of the above-mentioned embodiment, as a preferred embodiment, the upper surface of the brim 62 is a plane, the diameter of the brim 62 is larger than the diameter of the reserved through hole 4, and the brim 62 is clamped above the reserved through hole 4 to prevent it from falling into the reserved through hole 4, and is convenient for workers to install and disassemble.
[0048] Example 2, as a preferred embodiment of the installation device for the assembled stair support, is different from Example 1 in that it includes an embedded part 3 embedded in the ladder beam 1 and a reserved through hole 4 arranged on the prefabricated stair 2, one end of the embedded part 3 is embedded in the ladder beam 1, and the other end of the embedded part 3 is plugged into the reserved through hole 4, a leveling structure layer 7 is arranged between the ladder beam 1 and the prefabricated stair 2, a sealing unit 5 is arranged between the leveling structure layer 7 and the reserved through hole 4, and a temporary blocking unit 6 is arranged at the top of the reserved through hole 4. By using a sealing unit, the leveling structure layer above the ladder beam is tightly combined with the reserved through hole, the gap between the leveling structure layer and the reserved through hole is filled, and the grouting material is prevented from flowing out of the gap between the prefabricated stairs and the ladder beam. After the lifting is completed, a temporary blocking unit is used and placed directly in the prefabricated through hole to ensure that the channel is not blocked. During grouting, the temporary blocking unit is taken out for turnover and recycling. The device used is simple to manufacture and can be industrially processed and produced, which can reduce construction costs while improving construction quality.
[0049] On the basis of the above-mentioned embodiment, as a preferred embodiment, the sealing unit 5 includes a sealing gasket inserted into the bottom of the reserved through hole 4, so that the leveling structure layer 7 above the ladder beam is tightly combined with the reserved through hole 4, thereby filling the gap between the leveling structure layer 7 and the reserved through hole 4 and preventing the grouting material from flowing out from the gap between the prefabricated staircase 2 and the ladder beam 1.
[0050] Based on the above implementation, as a preferred implementation, the sealing gasket is made of elastic material.
[0051] Preferably, the sealing gasket is an annular rubber-plastic gasket with good sealing performance, good elasticity and friction, so as to prevent the grouting material from leaking due to loose bottom during grouting.
[0052] Based on the above implementation, as a preferred implementation, Figure 3 , Figure 4 As shown, the sealing gasket includes an annular base gasket 51, and the upper surface of the annular base gasket 51 is connected to a connecting ring 52 for fitting the inner wall of the reserved through hole 4. The connecting ring 52 fills the gap between the annular base gasket 51 and the reserved through hole, effectively preventing leakage of slurry. Moreover, the connecting ring 52 is also made of elastic material, has good elasticity and friction, and can be supported in the reserved through hole to prevent slipping out.
[0053] On the basis of the above-mentioned embodiment, as a preferred embodiment, the diameter of the annular base gasket 51 is larger than the diameter of the reserved through hole 4 , and surrounds the reserved through hole 4 .
[0054] On the basis of the above-mentioned embodiment, as a preferred embodiment, the temporary blocking unit 6 includes a cap inserted into the top of the reserved through hole 4 .
[0055] On the basis of the above implementation, as a preferred implementation, the cap is made of elastic material, specifically, the cap is made of synthetic resin material, the synthetic resin material has tight sealing, simple operation, and can be temporarily sealed before grouting to prevent garbage from filling the grouting hole.
[0056] On the basis of the above-mentioned embodiment, as a preferred embodiment, the cover cap includes a cover body 61, and the cover body 61 is plugged into the reserved through hole 4. The top of the cover body 61 is provided with a brim 62 that cooperates with the prefabricated staircase 2 to stop. The brim 62 effectively closes the opening of the reserved through hole, and the brim 62 is convenient for workers to disassemble and install.
[0057] On the basis of the above-mentioned embodiment, as a preferred embodiment, the cover body 61 is wide at the top and narrow at the bottom, and the cover body 61 is plugged into the reserved through hole 4. When the cover body 61 is wide at the top and narrow at the bottom, the wide part is snapped into the reserved through hole, and the synthetic resin material has a certain elasticity and can be squeezed into the reserved through hole to prevent it from falling off.
[0058] On the basis of the above-mentioned embodiment, as a preferred embodiment, the upper surface of the brim 62 is an arc surface with a high center and low surroundings. The diameter of the brim 62 is larger than the diameter of the reserved through hole 4. The brim 62 is clamped above the reserved through hole 4 to prevent it from falling into the reserved through hole 4 and to facilitate workers to install and disassemble.
[0059] The method of using the utility model is as follows:
[0060] 1. Construction Preparation
[0061] (1) Before hoisting the prefabricated staircase 2, prepare a detailed hoisting plan, select the appropriate hoisting slings, and carefully check the hoisting slings to ensure that they maintain normal working performance.
[0062] (2) Prepare the sealing unit 5 and temporary blocking unit 6 to be used, and install the sealing unit 5 on the prefabricated staircase 2 before lifting.
[0063] (3) Measure and pop out the control lines of the ends and sides of the prefabricated stairs at the predetermined installation location, and review the installation control lines and cast-in-place stair beam elevations to save hoisting calibration time and ensure installation quality.
[0064] 2. Operation points
[0065] (1) Stair positioning line: Before hoisting the prefabricated staircase 2, measure and pop out the control lines of the ends and sides of the corresponding staircase components at the predetermined installation position, and review the installation control lines and platform beam elevations to save hoisting calibration time and ensure installation quality. A 30 mm gap is reserved between the side of the staircase and the edge of the shear wall to ensure space for the subsequent building plastering surface layer. A 1:1 cement mortar leveling structure layer (strength grade ≥ M15) is laid on the ears of the staircase beams at both ends of the staircase. The elevation of the leveling structure layer must also be accurately controlled.
[0066] (2) Inspection and straightening of steel bars: Check the vertical connecting steel bars and make corrections for any misaligned steel bars.
[0067] (3) Hoisting: A trial hoisting must be conducted before formal hoisting. First, stop when the hoist is 500mm from the ground, check the force of the wire rope and the hook, keep the step surface level, and then hoist it to the top of the working floor. Use hooks and long and short hoisting ropes to hoist the prefabricated stairs. Two signalmen are set up during hoisting, one at the component hoisting location and one on the hoisting floor. In addition, a hooking person is equipped during stair hoisting, and two people are equipped on the floor to place and fix the stairs. Before hoisting, the quality manager shall check the model and size of the stairs. After checking the quality, a special person shall be responsible for hooking. When the hooking person evacuates to a safe area, the signalman below shall confirm the safety of the components around and command to hoist slowly. The hoisting shall be about 0.5m from the ground. After the tower crane hoisting device is confirmed to be safe, continue hoisting.
[0068] (4) Staircase installation
[0069] A. Install the sealing unit 5 at the bottom of the reserved through hole 4 of the prefabricated staircase 2.
[0070] B. When the prefabricated staircase 2 is lowered to a distance of 0.5m from the ladder beam, a professional operator will stabilize the prefabricated staircase, slowly lower the staircase according to the horizontal control line, align it with the embedded steel bars, and install it to the designed position. When lowering, it must be stopped and lowered slowly. It is strictly forbidden to lower it quickly and violently to avoid excessive impact force causing cracks on the board surface.
[0071] C. Correction: After the prefabricated staircase 2 is basically in place, use a crowbar to fine-tune it until the position is correct. When hoisting the prefabricated staircase 2, special attention should be paid to the correct elevation. The reserved connecting steel bars at the upper and lower ends of the stairs should coincide with the reserved holes, and the upper and lower ends of the stairs should be located on the leveling structure layer of the ladder beam 1.
[0072] (5) Temporary plugging of grouting holes: Temporary plugging is performed using a temporary plugging unit 6 at the top of the grouting hole.
[0073] (6) Caulking and grouting of hinged support: After the plane positioning and elevation of the prefabricated staircase 2 are accepted, pull out the temporary blocking unit 6, and use grouting materials of no less than C40 and CGM to block the reserved through hole 4 of the staircase (fixed hinge). The blocking surface should be flat, dense and smooth. For the lower part of the staircase (sliding hinge), only the nut gasket of the embedded bolt is filled and blocked. Steel gaskets need to be added before installing the nuts. After installation, lay an isolation layer and seal with mortar. The reserved cavity under the gasket is used for the free sliding deformation of the staircase. The gaps between the two ends of the prefabricated staircase and the platform beam are filled with polystyrene boards.
[0074] The vertical gap between the prefabricated stairs and the ladder beams shall be filled with polystyrene boards before floor construction, and then sealed with sealant. The net thickness of the sealant shall be ≥ 20mm.
[0075] (7) Formwork grouting of stair joints: After two stair sections are installed on each floor slab, the position and elevation are checked to ensure that they are correct. Then, the gaps between the stair sections and the surrounding wall panels or columns can be filled with foamed polyethylene rods and sealed with sealant.
[0076] The parts not described in detail in the present invention are all conventional technical means known to those skilled in the art.
[0077] The above content shows and describes the basic principle, main features and beneficial effects of the utility model. The above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. An installation device for an assembled stair support, comprising an embedded part (3) embedded in a stair beam (1), and a reserved through hole (4) provided on a prefabricated staircase (2), characterized in that: A leveling structure layer (7) is provided between the ladder beam (1) and the prefabricated staircase (2), a sealing unit (5) is provided between the leveling structure layer (7) and the reserved through hole (4), and a temporary blocking unit (6) is provided at the top of the reserved through hole (4).
2. The installation device for assembled stair support according to claim 1, characterized in that: The sealing unit (5) comprises a sealing gasket inserted into the bottom of the reserved through hole (4).
3. The installation device for assembled stair support according to claim 2, characterized in that: The sealing gasket is made of elastic material.
4. The installation device for assembled stair support according to claim 2 or 3, characterized in that: The sealing gasket comprises an annular base gasket (51), and the upper surface of the annular base gasket (51) is connected to a connecting ring (52) for fitting against the inner wall of the reserved through hole (4).
5. The installation device for assembled stair support according to claim 4, characterized in that: The diameter of the annular base gasket (51) is greater than the diameter of the reserved through hole (4).
6. The installation device for assembled stair support according to claim 1, characterized in that: The temporary blocking unit (6) comprises a cap plugged into the top of the reserved through hole (4).
7. The installation device for assembled stair support according to claim 6, characterized in that: The cover cap is made of elastic material.
8. The installation device for assembled stair support according to claim 6 or 7, characterized in that: The cap comprises a cap body (61) which is plugged into the reserved through hole (4), and a cap brim (62) which is engaged with the prefabricated staircase (2) is provided on the top of the cap body (61).
9. The installation device for assembled stair support according to claim 8, characterized in that: The cover body (61) is cylindrical or wide at the top and narrow at the bottom.
10. The installation device for assembled stair support according to claim 8, characterized in that: The upper surface of the brim (62) is a plane or a curved surface with a high center and low surrounding areas.