Plugging structure for steel mould trolley
By installing observation hole sealing templates and endoscopes on the steel formwork trolley, the problem of exhaust and slurry discharge from the concrete side arches of the water conveyance tunnel has been solved, replacing PVC pipes and achieving an efficient concrete pouring process. Control and quality improvements reduce construction costs and complexity.
Patent Information
- Application Number
- CN202420175860.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-23
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-01-23
AI Technical Summary
During the concrete pouring process of the lining of the existing water conveyance tunnel, the exhaust and laitance discharge technology of the side arches is not perfect, resulting in low concrete strength or cavity quality problems, and the existing PVC pipe layout method is easy to be blocked, making it difficult to accurately judge the concrete The timing of pouring completion increases project investment and installation complexity.
A sealing structure for steel formwork trolleys is designed, including a sealing template with an observation hole and an endoscope. The exhaust and slurry discharge in the warehouse are realized through the circular through hole, replacing the traditional PVC exhaust pipe. Reduces the use of sensing instruments and PVC pipes, simplifying the installation and removal process.
It achieves efficient and convenient concrete surface rising and vibrating quality observation, avoids problems of concrete falling and holes, reduces construction costs, simplifies the engineering process, and improves concrete appearance quality and construction efficiency.
Smart Images

Figure CN221879409U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel construction, in particular to a blocking structure for a steel mold trolley. Background Art
[0002] Due to the imperfect process of the floating slurry and gas emission of the side top arch during the pouring of the lining concrete of the water conveyance tunnel, it is easy to cause quality problems such as the side top arch cavity or low concrete strength. The construction quality of the side top arch pouring of the lining concrete of the water conveyance tunnel is the key to the success of the project. When the concrete is poured to the 120° range of the side top arch, the rigid mold trolley must close all windows to prevent the concrete from overflowing. At that time, the air and floating slurry emission of the side top arch during the remaining concrete pouring process will become a difficult problem for quality control. Improper handling will cause low strength of the top arch concrete after demolding, or even cavity quality accidents.
[0003] In the process of pouring concrete for the lining of existing water supply tunnels, the problem of exhaust and slurry discharge is usually solved by evenly arranging PVC pipes with a diameter of 5 cm on the top arch, and keeping a distance of 2 to 3 cm between the pipes and the inner wall of the top arch, so as to achieve the problem of air discharge during the concrete pouring process within the range of 120° of the side top arch and the slurry can be discharged through the PVC pipe when the concrete pouring surface rises to 2 to 3 cm from the inner wall of the top arch. In addition, a sensing instrument is installed on the top arch of the inner wall of the tunnel in advance. When the concrete contacts the sensing instrument, the construction personnel outside the warehouse can receive an electronic signal on the electronic device to judge that the pouring of the lining concrete of this warehouse has been completed and the conditions for stopping the warehouse are met. However, the above technology has the following shortcomings: 1. When the concrete surface rises to 2 to 3 cm away from the main top arch, a large amount of floating slurry has accumulated in the bin, and the time to complete the pouring of the remaining concrete is extremely short, and the vertically arranged PVC pipe is very easy to be blocked by aggregates, affecting the slurry discharge effect; 2. After the pouring is completed, it is difficult to pull out the PVC pipe pre-arranged in the main top arch, and the pipe pulling process will bring out part of the concrete, which may easily cause the quality problem of the cavity in the top arch after the demolding; 3. After the PVC pipe is pulled out, the problem of sealing the holes in the top arch of the rigid mold trolley is a more difficult task, which affects the appearance quality of the concrete; 4. During the pouring process of the side top arch within 120°, it is impossible to judge the rising situation of the concrete pouring surface in the bin, which makes it difficult to accurately grasp the timing of stopping the pouring of concrete; 5. The sensing instruments and vertical PVC pipes installed in the top arch not only increase the project investment, but also have cumbersome installation procedures and extend the warehouse preparation time.
[0004] Therefore, the utility model aims to provide a blocking structure for a steel mold trolley to solve the problems of exhaust, slurry discharge and observation of the side top arch. Utility Model Content
[0005] In order to overcome the technical problems described in the prior art, the purpose of the utility model is to provide a blocking structure for a steel mold trolley.
[0006] The utility model discloses a blocking structure for a steel mold trolley, comprising:
[0007] A plugging template, wherein the plugging template is provided with an observation hole;
[0008] An endoscope, which is used to observe the concrete construction conditions in the bin through the observation hole;
[0009] The observation hole is a circular through hole, the center of which is 8 to 12 cm away from the top arch of the blocking template, and the radius of the circular through hole is 4 to 6 cm. The observation hole is used for exhaust and slurry discharge in the bin.
[0010] As a preferred technical solution, the blocking structure further includes an external container, and the external container is used to contain the floating slurry in the bin discharged through the observation hole.
[0011] As a preferred technical solution, the blocking structure further includes a connecting pipe, which connects the observation hole and the external container.
[0012] As a preferred technical solution, the blocking structure further includes a blocking member, and the blocking member is used to block the observation hole.
[0013] As a preferred technical solution, the blocking member includes a square wooden board whose side length is consistent with the diameter of the observation hole and a wedge-shaped stopper.
[0014] As a preferred technical solution, the blocking template is installed in a groove of a water-stop steel belt of a steel template trolley.
[0015] As a preferred technical solution, at least one of the front and rear ends of the steel mold trolley is provided with the blocking structure.
[0016] As a preferred technical solution, the blocking template is provided with at least one observation hole at the same elevation.
[0017] In summary, the utility model has the following technical effects:
[0018] The utility model discloses a plugging structure for a steel mold trolley, comprising a plugging template provided with an observation hole, and an endoscope capable of observing the concrete construction condition in a bin through the observation hole, wherein the observation hole is a circular through hole, the center of which is 8 to 12 cm away from the top arch of the plugging template, and the radius of the circular through hole is 4 to 6 cm, and the observation hole can be used for timely and effective exhaust and slurry discharge in the bin. By adopting the above-mentioned blocking structure, the utility model has the following advantages: 1. By means of an endoscope inserted into the observation hole, the rising situation of the concrete surface in the bin and the vibration quality after all the windows of the steel mold trolley are closed are efficiently and conveniently solved, providing accurate judgment basis for construction personnel to grasp the vibration time, frequency and closing time of the trolley; 2. By opening an observation hole in the blocking template, the problem of gas emission in the bin and the problem of floating slurry emission of the side top arch after all the windows of the steel mold trolley are closed are effectively solved; 3. The blocking structure can replace the method of pre-embedded PVC exhaust pipes in the side top arch in the existing process, effectively avoiding the problem of concrete falling due to exhaust pipe extraction and the problem of holes left at the exhaust pipe position after demolding that affect the appearance quality, and at the same time greatly reducing the use of sensing instruments and PVC exhaust pipes during the construction of tunnel lining concrete, so as to reduce construction costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0020] Figure 1 It is a schematic diagram of a blocking template provided by an embodiment of the utility model;
[0021] Figure 2 It is a three-view drawing of the wedge-shaped stopper provided in the embodiment of the utility model;
[0022] Figure 3 This is a schematic diagram of the blocking member provided in the embodiment of the utility model blocking the observation hole;
[0023] The meanings of the reference numerals are as follows:
[0024] 1-Plugging template;
[0025] 2-Observation hole;
[0026] 3-Wedge-shaped stopper;
[0027] 4- Square wooden planks. DETAILED DESCRIPTION
[0028] The following will be combined with the drawings in this embodiment to clearly and completely describe the technical solution in this embodiment. The embodiment described in this article is only for illustrative purposes, and is not intended to limit the scope of protection of the utility model. Therefore, it should be understood that various modifications and changes can be made to this embodiment without departing from the scope of protection of the utility model.
[0029] In the description of the present invention, unless otherwise clearly specified and limited, the term "and / or" includes any and all combinations of one or more associated listed items. Unless otherwise specified or explained, the terms "connection", "fixed", etc. should be understood in a broad sense. For example, "connection" can be a fixed connection, a detachable connection, an integral connection, an electrical connection, or a signal connection; "connection" can be a direct connection or an indirect connection through an intermediate medium. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0030] Further, in the description of the present utility model, it should be understood that the directional words described in the present embodiment are described at the angles shown in the accompanying drawings and should not be understood as limiting the present embodiment. It should also be understood that in the context, when it is mentioned that an element or feature is connected to another element (one or more), it can not only be directly connected to the other (one or more) elements, but also indirectly connected to the other (one or more) elements through an intermediate element.
[0031] Before introducing the technical solution of the utility model, it is necessary to explain the creation background of the invention of this application. The steel mold trolley is a special equipment designed and manufactured to improve the surface finish and lining speed of tunnel lining and reduce labor intensity. The casting efficiency of the steel mold trolley is 30% higher than that of the traditional template, the mold loading and demolding speed is 2 to 3 times faster, and the manpower used is 1 / 5 of the past. The utility model is an innovative transformation of the user-prepared tools or spare parts on the upper part of the steel mold trolley to solve the problems of exhaust, slurry discharge and observation of the side top arch.
[0032] For example embodiments of the present invention, please refer to Figure 1, a plugging structure for a steel mold trolley of the utility model is provided, comprising a plugging template 1 provided with an observation hole 2, and an endoscope capable of observing the concrete construction condition in the bin through the observation hole 2, wherein the observation hole 2 is a circular through hole, the center of the circular through hole is 8 to 12 cm away from the positive top arch of the plugging template 1, and the radius of the circular through hole is 4 to 6 cm, and the observation hole 2 can be used for timely and effective exhaust and slurry discharge in the bin. First, when the concrete pouring surface rises to the 120° range of the top arch of the steel mold trolley side, the construction personnel can insert the endoscope through the observation hole 2 on the plugging template 1 to observe the rising situation of the concrete surface in the bin and the vibration effect; in addition, when the concrete surface rises to the bottom elevation of the observation hole 2, the floating slurry in the bin will flow out quickly and naturally through the observation hole 2.
[0033] By adopting the above-mentioned blocking structure, the utility model has the following advantages: 1. By means of an endoscope inserted into the observation hole 2, the rising situation of the concrete surface in the bin and the vibration quality after all the windows of the steel mold trolley are closed are efficiently and conveniently solved, providing accurate judgment basis for construction personnel to grasp the vibration time, frequency and closing time of the trolley; 2. By opening the observation hole 2 in the blocking template 1, the problem of gas emission in the bin and the problem of floating slurry emission of the side top arch after all the windows of the steel mold trolley are closed is effectively solved; 3. The blocking structure can replace the method of pre-embedded PVC exhaust pipe in the side top arch in the existing process, effectively avoiding the problem of concrete falling due to exhaust pipe extraction and the problem of holes left at the exhaust pipe position after demolding that affect the appearance quality, and at the same time greatly reducing the use of sensing instruments and PVC exhaust pipes during the construction of tunnel lining concrete, so as to reduce construction costs.
[0034] In some embodiments, the blocking structure further includes an external container, which is used to contain the floating slurry in the bin discharged through the observation hole 2. When the concrete surface rises to the bottom elevation of the exhaust hole, the floating slurry in the bin will quickly flow out through the exhaust holes reserved on both sides, and the construction personnel only need to prepare an external container to install the overflowed floating slurry at the bottom of the observation hole 2. Furthermore, the blocking structure further includes a connecting pipe, which connects the observation hole 2 and the external container, that is, to ensure that the floating slurry can flow out of the observation hole 2 and smoothly flow into the external container through the connecting pipe.
[0035] When the concrete surface in the bin continues to rise, the construction workers need to block the observation hole 2. Therefore, in some embodiments, the blocking structure also includes a blocking member, which is used to block the observation hole 2. When the coarse and fine aggregate content in the slurry to be discharged reaches one-third, the construction workers can start to block the observation hole 2. As a preferred technical solution, please refer to Figure 2 and Figure 3, the blocking member includes a square wooden board 4 and a wedge-shaped stopper 3, the side length of which is consistent with the diameter of the observation hole 2. For example, in this embodiment, the blocking template 1 is 25 cm high, and a circular through hole with a radius of 5 cm is provided at a distance of 10 cm from the top of the blocking template 1. The corresponding blocking member is a square wooden board 4 and a wedge-shaped stopper 3 with a side length of 10 cm. The side height of one side of the wedge-shaped stopper 3 is 10 cm to provide support for the square wooden board 4. The wedge-shaped stopper 3 abuts the square wooden board 4 against the outer surface of the observation hole 2 to block the observation hole 2, thereby ensuring that the concrete in the bin continues to be poured smoothly.
[0036] In some embodiments, the plugging template 1 is installed in the groove of the water-stop steel belt of the steel mold trolley. At the construction site, first, the steel mold trolley is put in place according to the established procedures, the plugging steel mold is installed, the water-stop steel belt is installed and welded and fixed, and then the plugging template 1 prepared on site is installed in the groove of the water-stop steel belt to achieve the position of the plugging template 1. It should be noted that in some embodiments, at least one of the front and rear ends of the steel mold trolley is provided with the plugging structure. For example, the steel mold trolley can be provided with the plugging structure at one end, or at both ends to achieve exhaust and slurry discharge in the warehouse. In addition, as a preferred technical solution, the plugging template 1 is provided with at least one observation hole 2 at the same elevation. That is, multiple observation holes 2 can be provided at the same elevation, so that the floating slurry in the warehouse can flow out more quickly from multiple observation holes 2, further improving the efficiency of tunnel lining.
[0037] In summary, it can be seen that the utility model has a simple structure and is easy to use, and has unexpected effects compared with the prior art. By setting a circular through hole with a radius of 4 to 6 cm at a distance of 8 to 12 cm from the top of the sealing template 1, the observation hole can not only cooperate with an endoscope to facilitate construction personnel to observe inside the warehouse, but the observation hole 2 can also realize the exhaust and slurry discharge functions inside the warehouse.
[0038] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the utility model.
Claims
1. A plugging structure for a steel mold trolley, characterized in that: include: A plugging template, wherein the plugging template is provided with an observation hole; An endoscope, which is used to observe the concrete construction conditions in the bin through the observation hole; The observation hole is a circular through hole, the center of which is 8 to 12 cm away from the top arch of the blocking template, and the radius of the circular through hole is 4 to 6 cm. The observation hole is used for exhaust and slurry discharge in the bin.
2. The blocking structure for a steel mold trolley according to claim 1, characterized in that: The blocking structure further includes an external container, and the external container is used to contain the floating slurry in the bin discharged through the observation hole.
3. The blocking structure for the steel mold trolley according to claim 2 is characterized in that: The blocking structure further includes a connecting pipe, which connects the observation hole and the external container.
4. The blocking structure for a steel mold trolley according to claim 1, characterized in that: The blocking structure also includes a blocking piece, and the blocking piece is used to block the observation hole.
5. The blocking structure for the steel mold trolley according to claim 4 is characterized in that: The blocking member comprises a square wooden board whose side length is consistent with the diameter of the observation hole and a wedge-shaped stopper.
6. The blocking structure for a steel mold trolley according to claim 1, characterized in that: The blocking template is installed in the groove of the water-stop steel belt of the steel template trolley.
7. The blocking structure for a steel mold trolley according to claim 1, characterized in that: The blocking structure is provided at least at one of the front and rear ends of the steel mold trolley.
8. The blocking structure for a steel mold trolley according to claim 1, characterized in that: The blocking template is provided with at least one observation hole at the same elevation.