Water circulating device for cooling electrode paste

By designing an electrode paste cooling water circulation device and using precipitation and separation technology to treat the cooling wastewater generated during the electrode paste production process, the problems of high treatment costs and oily substance blockage are solved, efficient separation and recycling of water is achieved, and production costs are reduced. cost.

CN221905901UActive Publication Date: 2024-10-29SHIZUISHAN GREAT WALL CARBON CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323528945.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-22
Publication Date
2024-10-29
Estimated Expiration
2033-12-22

AI Technical Summary

Technical Problem

The large amount of cooling wastewater generated during the electrode paste production process is costly to treat, and the presence of oily substances in the cooling water causes filter clogging, making it difficult to effectively treat it with existing technology.

Method used

An electrode paste cooling water circulation device is designed, including a sedimentation tank, a support rod, an oil film gap, a collection tank, a clean water pipe and a slag discharge tank. The impurities in the water are separated through sedimentation and separation technology, using a horizontal pull-out rod and scraper structure. Filtration of oil film and reuse of sediment.

Benefits of technology

It achieves efficient separation and recycling of water, reduces treatment costs, reduces water waste, and meets production needs without requiring additional filtration equipment or electrical equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221905901U_ABST
    Figure CN221905901U_ABST
Patent Text Reader

Abstract

The utility model discloses an electrode paste cooling water circulation device which comprises a sedimentation tank, a plurality of supporting rods are fixed to the sedimentation tank, an oil film notch is formed in one side of the sedimentation tank, the supporting rods are lower than the oil film notch, a collecting tank is further installed on the side, located on the oil film notch, of the sedimentation tank, and an oil film collecting structure is arranged on one side of the collecting tank. A slag discharging groove is formed in one side of the bottom of the sedimentation tank, a plurality of clear water pipes are further installed on one side of the sedimentation tank and located on the same horizontal plane, and a clear water groove is further formed in one side of the clear water pipes. According to the electrode paste cooling water treatment device, electrode paste cooling water is treated in a precipitation mode, oily substances and precipitates can be separated in the treatment process, the treatment efficiency completely meets the production requirement, filtering equipment and additional electric equipment are not needed in the circulating water treatment process, the treatment cost is low, the cooling water is effectively recycled, and the production cost is reduced. The waste of water resources is reduced, so that the production cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of electrode paste production, in particular to an electrode paste cooling water circulation device. Background Art

[0002] Electrode paste is a conductive material used in electric furnaces such as ferroalloy furnaces and calcium carbide furnaces. Electrode paste is also called self-baking electrode. It relies on the heat in the ore-fired furnace to complete the baking. Its production uses anthracite, graphite, petroleum coke, and asphalt coke as raw materials, asphalt and coal tar as binders, and is formed by extrusion equipment and cooling.

[0003] The cooling and molding of electrode paste is mainly achieved by spraying water. Specifically, water pipes are installed on the molding machine to cool the molding machine and the electrode paste inside it by spraying water. In this link, a large amount of cooling water will be collected under the molding machine. The cooling water is filtered and reused repeatedly. However, there are more oily substances in the cooling water, and the raw materials of the electrode paste are fine materials ground by a roller press before synthesis, and the particle size is small, which can easily cause the filter to be blocked. For this reason, we proposed an electrode paste cooling water circulation device to solve the above problems. Utility Model Content

[0004] The present application provides an electrode paste cooling water circulation device, which solves the problem of a large amount of cooling wastewater generated during the production process of the electrode paste and high treatment costs.

[0005] The present application provides an electrode paste cooling water circulation device, comprising a sedimentation tank, a plurality of support rods are fixed on the sedimentation tank, an oil film notch is provided on one side of the sedimentation tank, the support rods are lower than the height of the oil film notch, a collecting trough is also installed on one side of the sedimentation tank located at the oil film notch, an oil film collecting structure is provided on one side of the collecting trough, a slag discharge trough is provided on one side of the bottom of the sedimentation tank, a plurality of clean water pipes are also installed on one side of the sedimentation tank, the plurality of clean water pipes are located on the same horizontal plane, and a clean water trough is also provided on one of the clean water pipes.

[0006] Preferably, the oil film collection structure comprises an oil drain pipe installed on one side of the bottom of the collection tank, a third control valve is installed on the oil drain pipe, the collection tank is inclined, and the oil drain pipe is located at the lowest end of the collection tank.

[0007] Preferably, a water outlet bucket is installed at the oil film notch, and the water outlet bucket is located in the collecting tank.

[0008] Preferably, a slag discharge pipe is installed at the bottom of the slag discharge trough, the slag discharge pipe extends to the outside of the sedimentation tank, and a first control valve is installed on the slag discharge pipe.

[0009] Preferably, the plurality of clean water pipes are connected to a drain pipe via a connecting pipe, and a second control valve is provided on the drain pipe.

[0010] Preferably, it further comprises a buffer tank installed on one side of the sedimentation tank, wherein a stirring motor is installed on the buffer tank, and a water inlet pipe is also installed on one side of the buffer tank, and a water outlet pipe of the buffer tank extends into the sedimentation tank.

[0011] Preferably, the buffer tank is located at one end away from the clean water tank.

[0012] Preferably, a fixing rod fixed to the bottom of the sedimentation tank is also fixed on the supporting rod.

[0013] Preferably, the sedimentation tank is in the shape of a cuboid.

[0014] Preferably, it further comprises a horizontal pull rod, the hand-held portion of the horizontal pull rod is connected via a universal joint.

[0015] It can be seen from the above technical scheme that the present application provides an electrode paste cooling water circulation device. The sedimentation tank in the present application can be set on the ground or under the ground. It must be installed horizontally during installation. The wastewater generated during the electrode paste production process is sent to the sedimentation tank so that the liquid surface and the bottom of the oil film gap are on the same horizontal plane. After standing for 2-4 hours, a horizontal pull rod is used. The length of the horizontal pull rod must be greater than the distance between the two support rods. The horizontal pull rod is placed between the two support rods and moves from the end away from the oil film gap to the end of the oil film gap. The upper oil film is scraped into the collection tank, and the clean water pipe is opened to discharge the upper layer into the clean water tank, which can be directly used as cooling water. When the clean water above the clean water pipe is completely drained, the horizontal pull rod is still used to scrape the sediment at the bottom of the sedimentation tank into the slag discharge tank, and the slag discharge tank is opened to discharge it into the collection bucket. After drying, it can be used as a carbon source.

[0016] Compared with the prior art, the beneficial effects of the utility model are:

[0017] 1. Through the setting of the sedimentation tank, the present application uses sedimentation to separate impurities in the water, and can process the circulating water of a sedimentation tank at a time. The processing efficiency fully meets the production needs, and the processing cost is low and the use is reliable;

[0018] 2. Through the setting of the support rod and the oil film notch, the oily substance can form an oil film on the water surface during the sedimentation process. The scraper is set on the support rod, and the side of the oil film notch is slowly moved to scrape the oil film into the collection tank to complete the filtration of oily impurities;

[0019] 3. Through the setting of the slag discharge trough, after the sedimentation is completed, the clean water is discharged, and the bottom sediment can be scraped into the slag discharge trough. The slag discharge trough is opened to discharge the sediment and reuse it as a carbon source.

[0020] To sum up, in the utility model, the electrode paste cooling water is treated by precipitation. During the treatment process, the oily substance and the precipitate can be separated, and the treatment efficiency fully meets the production needs. In the circulating water treatment process, not only filtering equipment is not required, but also additional electrical equipment is not required. The treatment cost is low, and the cooling water is effectively recycled, which reduces the waste of water resources and thus reduces production costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the technical solution of the present application, the following is a brief introduction to the drawings required for use in the implementation cases. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.

[0022] Figure 1 This is a structural schematic diagram of an electrode paste cooling water circulation device proposed by the utility model;

[0023] Figure 2 This is a schematic diagram of the structure of a sedimentation tank of an electrode paste cooling water circulation device proposed by the utility model;

[0024] Figure 3 This is an enlarged structural diagram of location A of an electrode paste cooling water circulation device proposed by the utility model;

[0025] In the figure: 1 sedimentation tank, 2 support rod, 3 fixing rod, 4 buffer tank, 5 water inlet pipe, 6 stirring motor, 7 oil film notch, 8 collecting tank, 9 drainage pipe, 10 clean water tank, 11 water outlet bucket, 12 oil discharge pipe, 13 collecting bucket, 14 slag discharge pipe, 15 slag discharge tank, 16 first control valve, 17 clean water pipe, 18 connecting pipe, 19 second control valve. DETAILED DESCRIPTION

[0026] In order to enable those skilled in the art to better understand the technical solutions in the present application, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the accompanying drawings.

[0027] See also Figure 1-3, a water circulation device for cooling electrode paste, the present application is mainly used for the treatment of water for cooling electrode paste, because the impurities in the electrode paste are of fine particle size, generally drugs are added to make them flocculate and precipitate before filtering, the treatment cost through filtering equipment is high, and some manufacturers directly use waste water for cooling, and then treat it after several uses, but this process easily leads to pipe blockage, in order to solve the above problems, the present application is proposed, including sedimentation tank 1, sedimentation tank 1 can be directly dug out on the ground and painted with waterproof material, or it can be built on the ground through brick-concrete structure, or a water tank can be directly customized for use as sedimentation tank 1, due to environmental protection requirements, before the factory is built, an anti-seepage layer has been set on the factory ground, so a customized water tank is preferred, not only does not need to change the layout of the original factory area, the customized water tank is also easy to move, and can be adjusted according to the different layouts of the factory area;

[0028] During installation, a plurality of support rods 2 are fixed on the sedimentation tank 1. In order to reduce the deformation of the support rods 2, a fixing rod 3 fixed to the bottom of the sedimentation tank 1 is also fixed on the support rods 2 to support and limit the support rods 2. The setting of the support rods 2 can not only observe the water level, but also the water level needs to be higher than the support rods 2 when draining water. The installation of the support rods 2 is conducive to placing a scraper for scraping the oil film. The scraper only needs to be placed on the support rods 2 and slowly move to one side, and the oil film can be moved to one side to discharge the oil film. Specifically, an oil film notch 7 is provided on one side of the sedimentation tank 1. When scraping the oil film, it moves to one side of the oil film notch 7, and the oil film is discharged at the oil film notch 7. The support rods 2 are lower than the height of the oil film notch 7. When water is poured into the sedimentation tank 1, the water level and the oil film notch 7 are displaced to the same horizontal position, which can meet the requirement that the water level is higher than the support rods 2.

[0029] When collecting the oil film, a collecting tank 8 is installed on one side of the oil film notch 7 of the sedimentation tank 1, and the oil film is scraped into the collecting tank 8. An oil film collecting structure is provided on one side of the collecting tank 8 to collect the oil film. After the oil film is collected, it can be handed over to a qualified manufacturer for processing;

[0030] A plurality of clean water pipes 17 are also installed on one side of the sedimentation tank 1. The position of the clean water pipes 17 is higher than the position where the sediment is formed. When the cooling water is discharged to the designated position, it is precipitated for 2-4 hours. After the oil film is scraped off, the clean water pipes 17 are opened to discharge the clean water precipitated in the sedimentation tank 1 by natural flow. The plurality of clean water pipes 17 are located on the same horizontal plane and drain water at the same position. In order to reduce the amount of sediment brought out by the clean water pipes 17, a groove can be provided at one end of the clean water pipe 17 of the sedimentation tank 1 to increase the distance between the sediment and the clean water pipe 17 and to discharge the clean water to the greatest extent. A clean water trough 10 is also provided at one end of the clean water pipe 17. The precipitated water is discharged to the clean water trough 10 and stored in the clean water trough 10 as cooling water. The water is pumped to the cooling pipe for cooling through the water pump of the original cooling system. The amount of water discharged into the clean water trough 10 each time can meet the cooling water consumption of the molding machine.

[0031] A slag discharge trough 15 is provided at one side of the bottom of the sedimentation tank 1. The height of the slag discharge trough 15 is lower than other positions of the sedimentation tank 1. After the clean water is discharged, the muddy water at the bottom of the sedimentation tank 1 is scraped into the slag discharge trough 15 by a scraper. The slag discharge trough 15 is opened to discharge and dry it and then used as a carbon source.

[0032] In the utility model, the oil film collection structure includes an oil drain pipe 12 installed on one side of the bottom of the collection tank 8, a third control valve is installed on the oil drain pipe 12, the collection tank 8 is tilted, and the oil drain pipe 12 is located at the lowest end of the collection tank 8.

[0033] After the oil film is scraped into the collecting tank 8, it can be collected by placing a collecting bucket 13 at the bottom of the oil drain pipe 12. Since the amount of oil film is small, it can be collected multiple times and then piled up for processing on a quarterly or monthly basis.

[0034] A water outlet bucket 11 is installed at the oil film notch 7, and the water outlet bucket 11 is located in the collecting tank 8. The end of the water outlet bucket 11 away from the oil film notch 7 can be tilted downward. The oil film can be discharged quickly after being scraped to the water outlet bucket 11, thereby preventing the oil film at the oil film notch 7 from flowing back into the sedimentation tank 1.

[0035] In some embodiments, in order to improve the sealing of the bottom of the sedimentation tank 1 and facilitate slag discharge, a slag discharge pipe 14 is installed at the bottom of the slag discharge trough 15. The slag discharge pipe 14 extends to the outside of the sedimentation tank 1, and a first control valve 16 is installed on the slag discharge pipe 14. The slag discharge at the bottom of the sedimentation tank 1 is controlled by the first control valve 16 to ensure that the sealing of the bottom does not leak. When discharging slag, a collection bucket 13 can be placed at the lower end of the slag discharge pipe 14 to collect the sediment. After collecting and controlling the water, it can be dried and reused. If the processing volume is large, a filter press can be installed for processing.

[0036] In some embodiments, in order to facilitate unified water control, multiple clean water pipes 17 are connected to a drain pipe 9 through a connecting pipe 18. Multiple clean water pipes 17 drain water through one drain pipe 9. A second control valve is provided on the drain pipe 9 for controlling the switch and flow.

[0037] In some embodiments, in order to buffer the cooling water refluxed in the electrode paste cooling system, the present embodiment also includes a buffer tank 4 installed on one side of the sedimentation tank 1. When a large amount of cooling water is generated during the cooling process of the electrode paste and the original cooling system cannot store it, the cooling water can be sent to the buffer tank 4. With this arrangement, on the one hand, the cooling reflux water in the original system can be collected, and on the other hand, the size of the sedimentation tank 1 can be designed according to production needs so that the water processed during the sedimentation time meets the use of the cooling system during the sedimentation time. Therefore, the reserve of the sedimentation tank 1 will be greater than the reserve of the cooling water recovery tank of the original system. Adding the buffer tank 4 increases the reserve of the recovered cooling water. Since there are more impurities in the recovered cooling water, a stirring motor 6 is installed on the buffer tank 4. When the buffer tank 4 is stored, the stirring motor 6 is turned on to avoid the precipitation of impurities at the bottom of the buffer tank 4. A water inlet pipe 5 is also installed on one side of the buffer tank 4 for conveying the recovered cooling water, and the outlet pipe of the buffer tank 4 extends into the sedimentation tank 1.

[0038] In this embodiment, the buffer tank 4 is located at one end away from the clean water tank 10. During the water injection process, the sediment is now deposited near the end of the buffer tank 4, so there is less sediment at the clean water tank 10, and the discharge of sediment can be reduced during drainage.

[0039] In some embodiments, the sedimentation tank 1 is in a rectangular shape. This embodiment is conducive to the installation of the collecting tank 8. When the slag and oil film are discharged, it is moved from one end of the sedimentation tank 1 to the other end, which is also conducive to the discharge of slag and oil film.

[0040] In some embodiments, a horizontal pull rod 20 is also included. The hand-held part of the horizontal pull rod 20 is connected by a universal joint. The horizontal pull rod 20 can also be set separately for scraping oil film and sedimentation. The length of the horizontal pull rod 20 is greater than the distance between the two support rods 2, so that it is convenient to place it on the two support rods 2, and the hand-held part connected by the universal joint is conducive to placing the horizontal pull rod 20 in various positions.

[0041] It can be seen from the above technical scheme that when in use, the sedimentation tank 1 in the present application can be set on the ground or under the ground. It must be installed horizontally during installation. The wastewater generated during the production of electrode paste is sent to the sedimentation tank 1 so that the liquid surface and the bottom of the oil film notch 7 are on the same horizontal plane. After standing for 2-4 hours, a horizontal pull rod 20 is used. The length of the horizontal pull rod 20 must be greater than the distance between the two support rods 2. The horizontal pull rod 20 is placed between the two support rods 2, and moves from the end away from the oil film notch 7 to the end of the oil film notch 7 to pull the upper oil film into the collection tank 8. The clean water pipe 17 is opened to discharge the upper layer into the clean water tank 10, which can be directly used as cooling water. When the clean water above the clean water pipe 17 is completely drained, the horizontal pull rod 20 is still used to scrape the sediment at the bottom of the sedimentation tank 1 into the slag discharge tank 15, and the slag discharge tank 15 is opened to discharge it into the collection bucket 13. After drying, it can be used as a carbon source.

[0042] Those skilled in the art will readily appreciate other embodiments of the present application after considering the specification and practicing the application disclosed herein. The present application is intended to cover any variations, uses or adaptations of the present application, which follow the general principles of the present application and include common knowledge or customary techniques in the art that are not disclosed in the present application. The specification and examples are intended to be exemplary only, and the true scope of the present application is indicated by the claims.

[0043] It should be understood that the present application is not limited to the precise structure described above and shown in the drawings, and various modifications and changes can be made without departing from its scope. The above-described embodiments of the present application do not constitute a limitation on the scope of protection of the present application.

Claims

1. An electrode paste cooling water circulation device, comprising a sedimentation tank (1), characterized in that: A plurality of support rods (2) are fixed on the sedimentation tank (1); an oil film notch (7) is provided on one side of the sedimentation tank (1); the support rod (2) is lower than the height of the oil film notch (7); a collecting trough (8) is also installed on one side of the sedimentation tank (1) located at the oil film notch (7); an oil film collecting structure is provided on one side of the collecting trough (8); a slag discharge trough (15) is provided on one side of the bottom of the sedimentation tank (1); a plurality of clean water pipes (17) are also installed on one side of the sedimentation tank (1); the plurality of clean water pipes (17) are located on the same horizontal plane; and a clean water trough (10) is also provided on one of the clean water pipes (17).

2. The electrode paste cooling water circulation device according to claim 1, characterized in that: The oil film collection structure comprises an oil drain pipe (12) installed on one side of the bottom of the collection tank (8), a third control valve is installed on the oil drain pipe (12), the collection tank (8) is arranged obliquely, and the oil drain pipe (12) is located at the lowest end of the collection tank (8).

3. The electrode paste cooling water circulation device according to claim 2, characterized in that: A water outlet bucket (11) is installed at the oil film notch (7), and the water outlet bucket (11) is located in the collecting tank (8).

4. The electrode paste cooling water circulation device according to claim 1, characterized in that: A slag discharge pipe (14) is installed at the bottom of the slag discharge trough (15), the slag discharge pipe (14) extends outside the sedimentation tank (1), and a first control valve (16) is installed on the slag discharge pipe (14).

5. The electrode paste cooling water circulation device according to claim 1, characterized in that: The plurality of clean water pipes (17) are connected to a drainage pipe (9) via a connecting pipe (18), and a second control valve is provided on the drainage pipe (9).

6. The electrode paste cooling water circulation device according to claim 1, characterized in that: It also comprises a buffer tank (4) installed on one side of the sedimentation tank (1), a stirring motor (6) being installed on the buffer tank (4), a water inlet pipe (5) being installed on one side of the buffer tank (4), and a water outlet pipe of the buffer tank (4) extending into the sedimentation tank (1).

7. The electrode paste cooling water circulation device according to claim 6, characterized in that: The buffer tank (4) is located at one end away from the clean water tank (10).

8. The electrode paste cooling water circulation device according to claim 1, characterized in that: A fixing rod (3) fixed to the bottom of the sedimentation tank (1) is also fixed on the supporting rod (2).

9. The electrode paste cooling water circulation device according to claim 1, characterized in that: The sedimentation tank (1) is in the shape of a rectangular parallelepiped.

10. The electrode paste cooling water circulation device according to claim 1, characterized in that: It also comprises a horizontal pulling rod (20), the hand-held part of the horizontal pulling rod (20) being connected via a universal joint.