Buffer device of water injection pump pipeline in crude benzene hydrogenation system
By designing a buffer device in the crude benzene hydrogenation system and using a high-pressure gas storage bladder to buffer the pump outlet medium, the problems of pipeline vibration and safety risks are solved, achieving stable gas supply and improving system safety.
Patent Information
- Application Number
- CN202420738100.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-10
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-04-10
AI Technical Summary
In the crude benzene hydrogenation system, the outlet pressure of the compound plunger metering pump is pulse pressure, which causes serious vibration in the pipeline and easily leads to leakage accidents. Especially in long-term use, the pipeline is easy to be damaged, increasing safety risks.
A system including the metering pump outlet pipe, outlet valve and buffer device is designed. The buffer device consists of an outer buffer tank, an inner baffle and an air storage bag. The air storage bag is made of cooked rubber and has a pressure resistance of above 4.0Mpa. , inflate with nitrogen to buffer the pump outlet medium and reduce pulse pressure.
It effectively reduces the vibration of the water injection pump pipeline, prevents the vibration of the pipe body, and improves the safety of the system. The structure is simple and easy to manufacture, and does not require manual operation. It completely solves the problem of pipeline vibration and safety risks.
Smart Images

Figure CN221922499U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of crude benzene hydrogenation systems, in particular to a buffer device for a water injection pump pipeline in a crude benzene hydrogenation system. Background Art
[0002] The outlet pressure of the compound plunger metering pump is a pulse pressure, and the pipeline vibrates greatly. Therefore, when the system is started, the pipeline will vibrate violently due to the instantaneous filling of water. Long-term vibration of the pipeline can easily lead to pipeline damage and leakage accidents. Especially when used in crude benzene hydrogenation system, the outlet pulse of the metering pump will directly affect the safe operation of the entire hydrogenation unit. The pipeline is more likely to be damaged due to long-term vibration. Once leaked, a large amount of flammable and explosive media will cause fire and explosion accidents due to excessive pressure. Utility Model Content
[0003] The utility model aims to provide a buffer device for a water injection pump pipeline in a crude benzene hydrogenation system to solve the problems raised in the above-mentioned background technology.
[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a buffer device for a water injection pump pipeline in a crude benzene hydrogenation system, comprising a metering pump outlet pipe, an outlet valve, and a buffer device; an outlet valve is installed on the metering pump outlet pipe, and the outlet valve is connected to the lower end of the buffer device to form the same root, and the inlet and outlet of the buffer device are the same buffer pipe, the buffer device comprises an outer buffer tank and a baffle and an air storage bag installed inside the buffer tank, a tank connecting port is provided at the lower end of the buffer tank, and the tank connecting port is screwed and fixed to the buffer pipe.
[0005] Furthermore, the buffer tank is composed of an upper and lower structure, and the two parts are connected by a flange.
[0006] Furthermore, a baffle protrusion is provided on the side of the baffle installed inside the buffer tank, and the baffle protrusion is installed in a groove on the side of the buffer tank.
[0007] Furthermore, the air storage bladder installed inside the buffer tank is made of cooked rubber and is filled with nitrogen.
[0008] Furthermore, the air storage bladder is communicated with an air charging port provided on the buffer tank, a control valve is provided on the air charging port, and the air charging port is connected to a nitrogen charging device.
[0009] Furthermore, the air storage bag installed inside the buffer tank is detachable.
[0010] Compared with the prior art, the beneficial effects of the utility model are:
[0011] In the crude benzene hydrogenation unit, the outlet pressure of the water injection pump is high. The medium at the pump outlet first enters the buffer tank, and then is buffered by the inflatable bladder before being stably delivered to the hydrogenation system. The material of the inflatable bladder has specific requirements and is made of clinker rubber with a pressure resistance of more than 4.0Mpa. After adding the buffer device, the vibration problem of the water injection pump pipeline is completely solved. It has a simple structure, is easy to use, and is easy to manufacture. It does not require manual operation, thereby preventing the vibration of the pipe body. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 This is a schematic diagram of the installation of the buffer device of the utility model;
[0013] Figure 2 This is a schematic diagram of a buffer device of the utility model;
[0014] Figure 3 This is a schematic diagram of the installation of the baffle of the utility model.
[0015] In the figure: 1. outlet valve; 2. metering pump outlet pipe; 3. buffer pipe; 4. buffer device; 41. tank connection port; 42. buffer tank; 43. baffle; 431. baffle protrusion; 44. air storage bladder; 45. inflation port. DETAILED DESCRIPTION
[0016] Embodiment 1:
[0017] See also Figure 1 -3, a buffer device for a water injection pump pipeline in a crude benzene hydrogenation system, comprising a metering pump outlet pipe 2, an outlet valve 1, and a buffer device 4; the metering pump outlet pipe 2 is provided with an outlet valve 1, and the outlet valve 1 is connected to the lower end of the buffer device 4 to form a same root, and the inlet and outlet of the buffer device 4 are the same buffer pipe 3, the buffer device 4 comprises an outer buffer tank 42 and a baffle 43 and an air storage bladder 44 installed inside the buffer tank 42, the lower end of the buffer tank 42 is provided with a tank connection port 41, and the tank connection port 41 is screwed and fixed to the buffer pipe 3.
[0018] The buffer tank 42 is composed of an upper and lower structure, and the two parts are connected by a flange for easy disassembly. The buffer tank is made of a high-pressure container head.
[0019] A baffle plate protrusion 431 is provided on the side of the baffle plate 43 installed inside the buffer tank 42 , and the baffle plate protrusion 431 is installed in a groove on the side of the buffer tank 42 .
[0020] The air storage bladder 44 installed inside the buffer tank 42 is made of cooked rubber and filled with nitrogen, with a pressure resistance of more than 4.0Mpa. After adding the buffer device, the vibration problem of the water injection pump pipeline is completely solved, and the safety risk caused by the vibration of the pipe body to the device is prevented. There are specific requirements for the material of the inflatable bladder. Because desalted water is used for crude benzene hydrogenation, nitrile rubber can be used. The nitrile rubber used in the airbag is made of cooked rubber.
[0021] The air storage bladder 44 is communicated with the inflation port 45 provided on the buffer tank 42, and a control valve is provided on the inflation port 45, and the inflation port 45 is connected to the nitrogen inflation device, so that the air storage bladder can be inflated at any time.
[0022] In the crude benzene hydrogenation unit, the outlet pressure of the water injection pump is high, and the medium at the pump outlet first enters the buffer tank 42, which has an enlarged space. After being buffered by the air-filled bladder 44 in the tank, most of the pulses are reduced, and the medium is then stably delivered to the hydrogenation system through the pipeline.
[0023] Embodiment 2: The main difference from Embodiment 1 is that the air storage bag 44 installed inside the buffer tank 42 is detachable, and the inflation port 45 provided on the buffer tank 42 is cancelled, thereby reducing unnecessary settings.
[0024] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A buffer device for a water injection pump pipeline in a crude benzene hydrogenation system, characterized in that: The invention comprises a metering pump outlet pipe (2), an outlet valve (1), and a buffer device (4); the metering pump outlet pipe (2) is provided with an outlet valve (1), and the outlet valve (1) is connected to the lower end of the buffer device (4) to form a same buffer pipe (3), and the inlet and outlet of the buffer device (4) are the same buffer pipe (3); the buffer device (4) comprises an outer buffer tank (42) and a baffle (43) and an air storage bag (44) installed inside the buffer tank (42); the lower end of the buffer tank (42) is provided with a tank connection port (41), and the tank connection port (41) is screwed and fixed to the buffer pipe (3).
2. The buffer device for the water injection pump pipeline in the crude benzene hydrogenation system according to claim 1, characterized in that: The buffer tank (42) is composed of an upper and lower structure, and the two parts are connected by a flange.
3. A buffer device for a water injection pump pipeline in a crude benzene hydrogenation system according to claim 2, characterized in that: A baffle plate protrusion (431) is provided on the side of the baffle plate (43) installed inside the buffer tank (42), and the baffle plate protrusion (431) is installed in a groove on the side of the buffer tank (42).
4. The buffer device for the water injection pump pipeline in the crude benzene hydrogenation system according to claim 3, characterized in that: The air storage bag (44) installed inside the buffer tank (42) is made of cooked rubber and is filled with nitrogen.
5. The buffer device for the water injection pump pipeline in the crude benzene hydrogenation system according to claim 4, characterized in that: The air storage bag (44) is communicated with an air charging port (45) provided on the buffer tank (42), a control valve is provided on the air charging port (45), and the air charging port (45) is connected to a nitrogen charging device.
6. The buffer device for the water injection pump pipeline in the crude benzene hydrogenation system according to claim 4, characterized in that: The air storage bag (44) installed inside the buffer tank (42) is detachable.