Multi-split air conditioning system
By designing a multi-functional cut-off device integrating refrigerant cut-off and pressure relief protection in the multi-split air conditioning system, the problem that the existing technology cannot meet the branch cut-off and pressure relief protection is solved, and the safe cut-off and high-pressure protection of the refrigerant pipeline are realized. Improved system reliability and security.
Patent Information
- Application Number
- CN202420188563.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-01-25
AI Technical Summary
The existing cut-off device cannot meet the refrigerant cut-off requirements of branch circuits or single rooms in multi-split air conditioning systems, and cannot provide effective pressure relief protection when the refrigerant pipeline pressure rises, resulting in potential refrigerant leakage risks.
A multi-functional cut-off device is designed that integrates refrigerant cut-off and pressure relief protection functions. The cut-off and pressure relief protection of the refrigerant pipeline is realized through the first cut-off pipeline, the second cut-off pipeline and the pressure relief pipeline. It is suitable for main circuits. And the multi-branch application of branch circuits ensures reasonable control of the opening or closing of pipelines under different operating conditions.
It effectively avoids refrigerant leakage, improves the operational reliability and safety of the air conditioning system, meets the refrigerant cutoff requirements for multi-line air conditioning system branches or single rooms, and provides pressure relief protection under high pressure conditions.
Smart Images

Figure CN221923712U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of air conditioning, in particular to a multi-connected air conditioning system. Background Art
[0002] Refrigerants such as R32 used in air-conditioning systems have the characteristic of low flammability. If a leak occurs during use, a safety accident is likely to occur if the concentration is too high. Usually, a cut-off device is installed in the refrigerant pipeline to recover the refrigerant after leakage in the indoor unit and to cut off the refrigerant in the gas and liquid pipelines, so as to reduce the amount of refrigerant that spreads to the living space after leakage, thereby reducing hidden dangers.
[0003] The existing cut-off device has a relatively simple function and can only realize the cut-off of the refrigerant between the indoor unit side and the outdoor unit side. The existing cut-off device also has the following shortcomings:
[0004] (1) The cut-off device is generally arranged on the main refrigerant circuit. For a multi-split air conditioning system, it cannot solve the cut-off requirements of the branch circuit or single room, and cannot meet the application scenarios;
[0005] (2) When the pressure in the refrigerant pipeline of the air-conditioning system rises and exceeds the bearing pressure of the pipeline, it is easy to cause the pipeline to rupture and cause refrigerant leakage. In this case, the cut-off device cannot perform corresponding pressure relief protection. Therefore, the air-conditioning system needs to be equipped with an independent pressure relief protection module.
[0006] The above information disclosed in the background technology is only used to increase the understanding of the background technology of the present application, and therefore, it may include information that does not constitute the prior art known to ordinary technicians in the field. Summary of the invention
[0007] In response to the problems pointed out in the background technology, the utility model provides a multi-split air-conditioning system, in which the cut-off device has the dual functions of refrigerant cut-off and pressure relief protection, is multi-functionally integrated, and can realize the simultaneous application of main circuits and branches, meeting the cut-off requirements of branches or single rooms of the multi-split air-conditioning system.
[0008] In order to achieve the above-mentioned utility model purpose, the utility model adopts the following technical solutions:
[0009] In some embodiments of the present application, a multi-split air conditioning system is provided, comprising:
[0010] Outdoor unit;
[0011] A plurality of indoor units, wherein a loop is formed between the outdoor units through a first refrigerant pipeline and a second refrigerant pipeline, wherein the first refrigerant pipeline includes a first refrigerant main pipeline and a plurality of first refrigerant branch pipelines, and the second refrigerant pipeline includes a second refrigerant main pipeline and a plurality of second refrigerant branch pipelines, wherein the outdoor unit is connected to the first refrigerant main pipeline and the second refrigerant main pipeline, and the indoor unit is connected to the first refrigerant branch pipeline and the second refrigerant branch pipeline;
[0012] At least one cut-off device, the cut-off device comprising:
[0013] A cut-off pipeline, the cut-off pipeline is connected to the first refrigerant main pipeline and the second refrigerant main pipeline; and / or is connected to the first refrigerant branch pipeline and the second refrigerant branch pipeline, the cut-off pipeline is used to close or conduct the refrigerant pipeline to transport the refrigerant from one of the indoor unit and the outdoor unit to the other;
[0014] The pressure relief pipeline is used to guide the high-pressure refrigerant in the refrigerant pipeline between the indoor unit and the outdoor unit to the compressor of the air-conditioning system to provide pressure relief protection for the air-conditioning system.
[0015] The cut-off device integrates the dual functions of refrigerant cut-off and pressure relief protection. The cut-off device realizes the cut-off and pressure relief protection functions of the refrigerant pipeline through the first cut-off pipeline, the second cut-off pipeline, and the pressure relief pipeline. It has a compact structure and multi-functional integration. According to the different operating states of the air-conditioning system, the first cut-off pipeline, the second cut-off pipeline, and the pressure relief pipeline are controlled to be reasonably opened or closed to realize the cut-off of the refrigerant pipeline or the pressure relief protection of the high-pressure refrigerant, avoid refrigerant leakage, and improve the operating reliability and safety of the air-conditioning system.
[0016] At least one set of cut-off devices is arranged on the refrigerant main line and the refrigerant branch line, which can not only meet the refrigerant cut-off requirements of the refrigerant main line, but also meet the refrigerant cut-off requirements of the refrigerant branch line as needed. The cut-off device arranged on the refrigerant main line can cut off the refrigerant between the outdoor unit and multiple indoor units at the same time. The cut-off device arranged on the refrigerant branch line can cut off the refrigerant between the outdoor unit and the target indoor unit (where refrigerant leakage occurs or maintenance is required) separately. The main line and multiple branches can be used simultaneously to meet the cut-off requirements of the branch line or single room of the multi-split air conditioning system.
[0017] The utility model also provides a multi-split air conditioning system, comprising:
[0018] Outdoor unit;
[0019] Multiple indoor units;
[0020] At least one cut-off device, the cut-off device comprising a first cut-off pipeline and a second cut-off pipeline, the first cut-off pipeline is connected to a refrigerant pipeline connected to a refrigerant inflow end of the indoor unit, the second cut-off pipeline is connected to a refrigerant pipeline connected to a refrigerant outflow end of the indoor unit, one of the first cut-off pipeline and the second cut-off pipeline is closed and the other is opened, so as to transport the refrigerant from one of the outdoor unit and at least one of the indoor units to the other;
[0021] The cut-off device also includes a pressure relief pipeline connected between the first cut-off pipeline and the second cut-off pipeline, which is used to guide the high-pressure refrigerant in the refrigerant pipeline between the indoor unit and the outdoor unit to the compressor of the air-conditioning system to provide pressure relief protection for the air-conditioning system.
[0022] After reading the specific embodiments of the present invention in conjunction with the accompanying drawings, other features and advantages of the present invention will become more clear. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0024] Figure 1 is a structural diagram of a cutting device according to some embodiments;
[0025] Figure 2 is another structural diagram of a cutting device according to some embodiments; Figure 3 is an exploded view of a cutting device according to some embodiments;
[0026] Figure 4 is another exploded view of a cutting device according to some embodiments;
[0027] Figure 5 is a structural diagram of an electrical box according to some embodiments;
[0028] Figure 6 A structural diagram of a cutting device body with a cover removed according to some embodiments;
[0029] Figure 7 is an exploded view of a shell body according to some embodiments;
[0030] Figure 8 is another exploded view of a shell body according to some embodiments;
[0031] Fig. 9is a structural diagram of a first cut-off pipeline, a second cut-off pipeline, and a pressure relief pipeline according to some embodiments;
[0032] Fig.10 is another structural diagram of a first cut-off pipeline, a second cut-off pipeline, and a pressure relief pipeline according to some embodiments;
[0033] Fig.11 is a structural diagram of a first cut-off pipeline according to some embodiments;
[0034] Fig.12 is a structural diagram of a second cut-off pipeline according to some embodiments;
[0035] Fig.13 A structural diagram of a heat preservation part, a cut-off pipeline, and a pressure relief pipeline according to some embodiments;
[0036] Fig.14 Another structural diagram of a heat preservation part, a cut-off pipeline, and a pressure relief pipeline according to some embodiments;
[0037] Fig.15 is another structural diagram of a heat preservation part, a cut-off pipeline, and a pressure relief pipeline according to some embodiments;
[0038] Fig.16 is a structural diagram of a heat-insulating main body according to some embodiments;
[0039] Fig.17 is a schematic diagram of a multi-split air conditioning system according to some embodiments;
[0040] Fig.18 Another schematic diagram of a multi-split air conditioning system according to some embodiments. DETAILED DESCRIPTION
[0041] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0042] In the description of the present application, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0043] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.
[0044] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0045] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0046] The disclosure below provides many different embodiments or examples for realizing different structures of the utility model. In order to simplify the disclosure of the utility model, the components and settings of specific examples are described below. Of course, they are merely examples, and the purpose is not to limit the utility model. In addition, the utility model may repeat reference numbers and / or reference letters in different examples, and such repetition is for the purpose of simplification and clarity, and does not itself indicate the relationship between the various embodiments and / or settings discussed. In addition, the utility model provides various specific examples of processes and materials, but those of ordinary skill in the art may be aware of the application of other processes and / or the use of other materials.
[0047] This embodiment discloses a multi-split air conditioning system. Fig.17 or Fig.18, including an outdoor unit 20 and a plurality of indoor units 10, a loop is formed between the outdoor unit 20 and the outdoor unit 10 through a first refrigerant pipeline and a second refrigerant pipeline, the first refrigerant pipeline includes a first refrigerant main pipeline 31 and a plurality of first refrigerant branch pipelines 32, the second refrigerant pipeline includes a second refrigerant main pipeline 41 and a plurality of second refrigerant branch pipelines 42, the outdoor unit 20 is connected to the first refrigerant main pipeline 31 and the second refrigerant main pipeline 32, and the indoor unit 10 is connected to the first refrigerant branch pipeline 32 and the second refrigerant branch pipeline 42. The indoor throttling device 12 is arranged on the first refrigerant branch pipeline 32, and the outdoor throttling device 22 is arranged on the first refrigerant main pipeline 31.
[0048] Fig.17 and Fig.18 It is an embodiment of a multi-split air conditioning system, including an outdoor unit 20 and three indoor units 10, and the three indoor units 10 are respectively denoted as indoor unit 10a, indoor unit 10a, and indoor unit 10c.
[0049] The air conditioning system performs a refrigeration cycle of the air conditioner by using a compressor 24, a condenser, an expansion valve and an evaporator. The refrigeration cycle includes a series of processes involving compression, condensation, expansion and evaporation to cool or heat the indoor space.
[0050] The low-temperature and low-pressure refrigerant enters the compressor 24, which compresses it into a high-temperature and high-pressure refrigerant gas and discharges the compressed refrigerant gas. The discharged refrigerant gas flows into the condenser. The condenser condenses the compressed refrigerant into a liquid phase, and heat is released to the surrounding environment through the condensation process.
[0051] The expansion valve expands the high-temperature and high-pressure liquid refrigerant condensed in the condenser into a low-pressure liquid refrigerant. The evaporator evaporates the refrigerant expanded in the expansion valve and returns the low-temperature and low-pressure refrigerant gas to the compressor 24. The evaporator can achieve a refrigeration effect by utilizing the latent heat of evaporation of the refrigerant to exchange heat with the material to be cooled. In the entire cycle, the air conditioner can adjust the temperature of the indoor space.
[0052] The outdoor unit 20 is provided with an outdoor heat exchanger 21, a compressor 24, an outdoor throttling device 22, an outdoor fan 23, a four-way valve 25, a liquid storage tank 26, etc., and the indoor unit 10 is provided with an indoor heat exchanger 11, an indoor throttling valve, and an indoor fan 13, etc.
[0053] The indoor heat exchanger 11 and the outdoor heat exchanger 21 function as a condenser or an evaporator. When the indoor heat exchanger 11 functions as a condenser, the air conditioning system functions as a heater in a heating mode, and when the indoor heat exchanger 11 functions as an evaporator, the air conditioning system functions as a cooler in a cooling mode.
[0054] The multi-split air conditioning system in this embodiment further includes at least one cut-off device 50. Figures 1 to 16 is a schematic structural diagram of the cutting device 50, Fig.17 FIG. 5 is a schematic diagram showing the application principle of a cutoff device 50 in a multi-split air conditioning system. Fig.18 The schematic diagram of the application principle of two cut-off devices 50 in a multi-split air conditioning system. The arrangement of the multiple indoor units 10 and the multiple cut-off devices 50 is not limited to Fig.17 and Fig.18 There can be various arrangements according to user needs, which are not specifically limited in this embodiment. The cut-off device 50 is arranged between the indoor unit 10 and the outdoor unit 20, specifically between the indoor throttling device 12 and the outdoor throttling device 22. The indoor unit 10 and the outdoor unit 20 are connected to the inlet and outlet of the cut-off device 50 through the refrigerant pipeline. The cut-off device 50 can be installed between the outdoor unit 20 and the indoor unit 10 according to the site conditions, usually installed outside the indoor room, but can also be installed indoors.
[0055] The cut-off device 50 includes a cut-off pipeline, which is arranged on the refrigerant pipeline between the indoor unit 10 and the outdoor unit 20. The cut-off pipeline is used to cut off or conduct the refrigerant pipeline to achieve the refrigerant cut-off function. Specifically, the cut-off pipeline is connected to the first refrigerant main pipeline 31 and the second refrigerant main pipeline 41; and / or connected to the first refrigerant branch pipeline 32 and the second refrigerant branch pipeline 42. The cut-off pipeline is used to close or conduct the refrigerant pipeline to transport the refrigerant from one of the indoor unit 10 and the outdoor unit 20 to the other.
[0056] When the cut-off pipe of the cut-off device 50 is connected to the first refrigerant main pipe 31 and the second refrigerant main pipe 41, the cut-off device 50 can cut off the refrigerant between the outdoor unit 20 and the plurality of indoor units 10 at the same time. Fig.17 .
[0057] That is, Fig.17 The multi-split air conditioning system is provided with a cut-off device 50, which is arranged between the first refrigerant main line 31 and the second refrigerant main line 41. The cut-off device 50 can cut off the refrigerant of the outdoor unit 20 and the three indoor units 10 at the same time.
[0058] When the cut-off pipeline of the cut-off device 50 is connected to the first refrigerant branch pipeline 32 and the second refrigerant branch pipeline 42, the cut-off device can cut off the refrigerant between the outdoor unit 20 and the indoor unit 10 where the cut-off device is located, so as to cut off the refrigerant of the indoor unit 10 separately, for example Fig.18 The cut-off device 50a in.
[0059] for example, Fig.18The multi-split air conditioning system in the embodiment is provided with two cut-off devices 50, which are denoted as the cut-off device 50A and the cut-off device 50a. The cut-off device 50A is arranged between the first refrigerant main line 31 and the second refrigerant main line 41, and the cut-off device 50A can cut off the refrigerant of the outdoor unit 20 and the three indoor units 10 at the same time. The cut-off device a is used to cut off the refrigerant of the outdoor unit 20 and one of the indoor units 10 (such as the indoor unit 10a), and the cut-off device 50a is arranged on the first refrigerant branch 32a and the second refrigerant branch 42a connected to the indoor unit 10a. The cut-off pipeline includes a first cut-off pipeline 110 and a second cut-off pipeline 120. The first cut-off pipeline 110 is connected to the first refrigerant pipeline between the indoor unit 10 and the outdoor unit 20, and is used to close or conduct the first refrigerant pipeline. Specifically, the first cut-off pipe 110 is connected between the indoor heat exchanger 11 and the outdoor heat exchanger 21 , or in other words, the first cut-off pipe 110 is connected between the indoor throttling device 12 and the outdoor throttling device 22 .
[0060] The first cutoff pipeline 110 is turned on or off by a first switch 114. The first switch 114 is used to control the first cutoff pipeline 110 to be turned on or off.
[0061] The second cut-off pipeline 120 is connected to the second refrigerant pipeline between the indoor unit 10 and the outdoor unit 20 , and is used to close or open the second refrigerant pipeline. Specifically, the second cut-off pipeline 120 is connected between the indoor unit 10 and the compressor 24 .
[0062] The second cut-off line 120 is turned on / off by the second switch 124. The second switch 124 is used to control the first cut-off line 110 to be turned on or off.
[0063] One of the first cutoff line 110 and the second cutoff line 120 is closed and the other is opened, so that the refrigerant is transported from one of the indoor unit 10 and the outdoor unit 20 to the other.
[0064] The cut-off device 50 further includes a pressure relief pipeline 130 for realizing a pressure relief protection function. The pressure relief pipeline 130 is connected between the first cut-off pipeline 110 and the second cut-off pipeline 120, and a pressure relief valve 131 is provided on the pressure relief pipeline 130. The pressure relief pipeline 130 is used to guide the high-pressure refrigerant in the refrigerant pipeline between the indoor unit 10 and the outdoor unit 20 to the compressor 24 of the air-conditioning system to provide pressure relief protection for the air-conditioning system.
[0065] The first end of the pressure relief pipeline 130 is connected to the refrigerant pipeline between the first switch component 114 and the indoor unit 10 , that is, the first end of the pressure relief pipeline 130 is connected between the first switch component 114 and the indoor throttling device 12 .
[0066] The second end of the pressure relief line 130 is connected to the refrigerant line between the second switch element 124 and the outdoor unit 20 , that is, the second end of the pressure relief line 130 is connected between the second switch element 124 and the compressor 24 .
[0067] by Fig.17 For example, when the air conditioning system is cooling normally, the indoor unit 10 and the outdoor unit 20 operate normally, at this time, the first switch 114 and the second switch 124 are opened, the pressure relief valve 131 is closed, the first cut-off pipeline 110 and the second cut-off pipeline 120 are in a conducting state, the pressure relief pipeline 130 is closed, and the first refrigerant pipeline and the second refrigerant pipeline are conducting. The refrigerant flowing out of the compressor 24 flows through the outdoor heat exchanger 21, the outdoor throttling device 22, the first cut-off pipeline 110, multiple indoor units 10 (indoor throttling device 12, indoor heat exchanger 11), the second cut-off pipeline 120, the liquid storage tank 26 and the compressor 24 in sequence, completing a circulation flow.
[0068] by Fig.17 For example, when the air-conditioning system is cooling, if a leak occurs on the indoor unit 10 side, in this state, if it is not detected and handled in time, an accident is likely to occur. The present air-conditioning system simultaneously cuts off the refrigerant from the outdoor unit 20 and multiple indoor units 10 through the cut-off device 50, and guides the refrigerant on the multiple indoor units 10 to the compressor 24 on the outdoor unit 20 side. Specifically, the present air-conditioning system detects the refrigerant through the refrigerant sensor 14 arranged on the indoor unit 10 side. The refrigerant sensor 14 transmits the leakage signal to the controller of the indoor unit 10. The controller of the indoor unit 10 uses the communication between the outdoor unit 20 and the indoor unit 10 to transmit the detection signal to the controller of the outdoor unit 20 and the control end of the cut-off device 50. The first switch 114 is closed, and the first cut-off line 110 is controlled to be closed, thereby blocking the refrigerant from continuing to flow to the indoor unit 10 side. The pressure relief valve 131 is closed, and the pressure relief line 131 is closed. 130 is closed, and the second switch 124 is opened, so that the second shut-off pipe 120 is turned on, and the outdoor unit 20 receives the refrigerant leakage signal and runs the refrigerant recovery mode. The compressor 24 continues to run, and the refrigerant on the indoor unit 10 side is sucked into the compressor 24, compressed and recovered and stored on the outdoor unit 20 side. When the refrigerant recovery operation time of the compressor 24 is completed, the control end of the shut-off device 50 controls the first shut-off pipe 110 and the second shut-off pipe 120 to close, and at the same time the compressor 24 stops working, notifying and waiting for the refrigerant leakage fault to be handled.
[0069] by Fig.17For example, when the air conditioning system is heating normally, the indoor unit 10 and the outdoor unit 20 operate normally, at this time, the first switch 114 and the second switch 124 are opened, the pressure relief valve 131 is closed, the first cut-off pipeline 110 and the second cut-off pipeline 120 are in a conducting state, the pressure relief pipeline 130 is closed, and the first refrigerant pipeline and the second refrigerant pipeline are conducting. The refrigerant flowing out of the compressor 24 flows through the second cut-off pipeline 120, multiple indoor units 10 (indoor heat exchanger 11, indoor throttling device 12), the first cut-off pipeline 110, the outdoor throttling device 22, the outdoor heat exchanger 21, the liquid storage tank 26 and the compressor 24 in sequence, completing a circulation flow.
[0070] by Fig.17 For example, when the air-conditioning system is heating, if a leak occurs on the indoor unit 10 side, in this state, if it is not detected and handled in time, an accident is likely to occur. The present air-conditioning system cuts off the outdoor unit 20 from multiple indoor units 10 through the cut-off device 50, and guides the refrigerant on the multiple indoor units 10 to the compressor 24 on the outdoor unit 20 side. Specifically, the present air-conditioning system detects the refrigerant through the refrigerant sensor 14 arranged on the indoor unit 10 side. The refrigerant sensor 14 transmits the leakage signal to the controller of the indoor unit 10. The controller of the indoor unit 10 uses the communication between the outdoor unit 20 and the indoor unit 10 to transmit the detection signal to the controller of the outdoor unit 20 and the control end of the cut-off device 50. The second switch 124 is closed, and the second cut-off line 120 is controlled to be closed, thereby blocking the refrigerant from continuing to flow to the indoor unit 10 side. The pressure relief valve 131 is closed, and the pressure relief line 131 is closed. 130 is closed, and the first switch 114 is opened, so that the first shut-off pipe 110 is turned on, and the outdoor unit 20 receives the refrigerant leakage signal and runs the refrigerant recovery mode. The compressor 24 continues to run, and the refrigerant on the indoor unit 10 side is sucked into the compressor 24, compressed and recovered and stored on the outdoor unit 20 side. When the refrigerant recovery operation time of the compressor 24 is completed, the control end of the shut-off device 50 controls the first shut-off pipe 110 and the second shut-off pipe 120 to close, and at the same time the compressor 24 stops working, notifying and waiting for the refrigerant leakage fault to be handled.
[0071] by Fig.18 For example, when the air conditioner is cooling or heating normally, the first switch element 114A and the second switch element 124A on the cut-off device 50A are normally open and the pressure relief valve 131A is normally closed, and the first switch element 114a and the second switch element 124a on the cut-off device 50a are normally open and the pressure relief valve 131a is normally closed, and the refrigerant circulates between the outdoor unit 20 and multiple outdoor units 10.
[0072] by Fig.18For example, when the multi-split unit is cooling, if the indoor unit 10a has a refrigerant leak, in this state, if it is not detected and handled in time, an accident is likely to occur. The present air-conditioning system cuts off the indoor unit 10a and the outdoor unit 20 through the cut-off device 50a. At this time, the cut-off device 50A conducts the refrigerant pipeline and guides the refrigerant on the indoor unit 10a side to the compressor 24 on the outdoor unit 20 side. Specifically, the present air-conditioning system detects the refrigerant through the refrigerant sensor 14 arranged on the indoor unit 10a side. The refrigerant sensor 14 transmits the leakage signal to the controller of the indoor unit 10a. The controller of the indoor unit 10a uses the communication between the outdoor unit 20 and the indoor unit 10a to transmit the detection signal to the controller of the outdoor unit 20 and the control end of the cut-off device 50a. The first switch 114a is closed, and the first cut-off pipeline 110a is controlled to be closed, thereby blocking the refrigerant from continuing to flow to the indoor unit 10a side. The pressure relief valve 131a is closed, and the pressure relief pipe 131a is closed. The circuit 130a is closed, and the second switch 124a is opened, so that the second shut-off circuit 120a is connected. The outdoor unit 20 receives the refrigerant leakage signal and runs the refrigerant recovery mode. The compressor 24 continues to run, and the refrigerant on the indoor unit 10a side is sucked into the compressor 24, compressed and recovered and stored on the outdoor unit 20 side. When the refrigerant recovery operation time of the compressor 24 is completed, the control end of the shut-off device 50a controls the first shut-off circuit 110a and the second shut-off circuit 120a to close, and at the same time the compressor 24 stops working, notifying and waiting for the refrigerant leakage fault to be handled.
[0073] The multi-split air conditioning system detects refrigerant leakage faults, closes the gas and liquid pipelines of the refrigerant through the cut-off device 50, and completely blocks the refrigerant from continuing to flow to the indoor unit 10 to cause a refrigerant leakage accident, and recovers the refrigerant to the outdoor unit 20, thereby solving the hidden danger of large-scale leakage of flammable and explosive refrigerants such as R32 and R290.
[0074] When the cut-off device 50 is applied to the air conditioning system, at least one set of the cut-off device 50 is set on the refrigerant main line and the refrigerant branch line, which can not only meet the refrigerant cut-off requirements of the refrigerant main line, but also meet the refrigerant cut-off requirements of the refrigerant branch line as needed. The cut-off device 50 provided on the refrigerant main line can cut off the refrigerant between the outdoor unit 20 and multiple indoor units 10 at the same time. The cut-off device 50 provided on the refrigerant branch line can cut off the refrigerant between the outdoor unit 20 and the target indoor unit 10 (where refrigerant leakage occurs or maintenance is required) separately.
[0075] Considering the different working modes of the air-conditioning system, as the environment changes, the high-pressure refrigerant pressure increases and there is a problem of system pipeline rupture and leakage. The air-conditioning system simultaneously performs high-pressure pressure relief protection through the cut-off device 50 to solve the above hidden dangers.
[0076] One embodiment of the air conditioning system being protected from pressure relief by the cut-off device 50a is to Fig.18For example, at this time, the air conditioning system executes the cooling mode, multiple indoor units 10, outdoor units 20, and compressors 24 operate according to normal settings, the first cut-off pipeline 110A and the second cut-off pipeline 120A of the cut-off device 50A are connected, and the pressure relief pipeline 130A is closed, and the first cut-off pipeline 110a and the second cut-off pipeline 120a of the cut-off device 50a are connected, and the pressure relief pipeline 130a is closed. During the air conditioning cooling operation, when the user turns off the indoor unit 10a, the indoor throttling device 12a will be closed at the same time. In this state, the refrigerant pipeline from the outdoor unit 20 side to the indoor throttling device 12a will be sealed with high-pressure refrigerant. With changes in the external environment, such as temperature increases, the pressure of the liquid-sealed refrigerant will increase and exceed the pipeline bearing pressure, thereby causing pipeline rupture and refrigerant leakage accidents. When the pressure Pa1 value in the liquid seal pipeline is greater than the opening pressure Pa2 of the pressure relief valve 131a, the pressure relief valve 131a opens to provide pressure relief protection for the high-pressure end, and the high-pressure refrigerant flows to the compressor 24 through the pressure relief pipeline 130a. When the pressure drops to the closing pressure Pa3 of the pressure relief valve 131a, the pressure relief valve 131a closes. This cycle protects the system pipeline and prevents refrigerant leakage.
[0077] The second embodiment of the pressure relief protection of the air conditioning system by the cut-off device 50a is as follows: Fig.18 For example, at this time, the air conditioning system executes the cooling mode, multiple indoor units 10, outdoor units 20, and compressors 24 operate according to normal settings, the first cut-off pipeline 110A and the second cut-off pipeline 120A of the cut-off device 50A are connected, and the pressure relief pipeline 130A is closed, and the first cut-off pipeline 110a and the second cut-off pipeline 120a of the cut-off device 50a are connected, and the pressure relief pipeline 130a is closed. During the operation of the air conditioner, when the user turns off the indoor unit 10a, the indoor throttling device 12a will be closed at the same time. In this state, if a refrigerant leaks on the indoor unit 10a side, the system will turn off the first switch 114a. At this time, the high-pressure refrigerant will be sealed in the pipeline between the first switch 114a and the indoor throttling device 12a. With the changes in the external environment, such as the increase in temperature, the pressure of the sealed refrigerant will increase and exceed the bearing pressure of the pipeline, thereby causing the pipeline to rupture and the refrigerant to leak. When the liquid seal pipeline pressure Pa1 value is greater than the opening pressure Pa2 of the pressure relief valve 131a, the pressure relief valve 131a opens to provide pressure relief protection for the high-pressure end, and the high-pressure refrigerant flows to the compressor 24 through the pressure relief pipeline 130a. When the pressure drops to the closing pressure Pa3 of the pressure relief valve 131a, the pressure relief valve 131a will close. This cycle protects the system pipeline and prevents refrigerant leakage.
[0078] The cut-off device 50 of this embodiment realizes the refrigerant pipeline cut-off and pressure relief protection functions through the first cut-off pipeline 110, the second cut-off pipeline 120, and the pressure relief pipeline 130. It has a compact structure and multi-functional integration. According to the different operating states of the air-conditioning system, the first cut-off pipeline 110, the second cut-off pipeline 120, and the pressure relief pipeline 130 are controlled to be reasonably opened or closed to realize the refrigerant pipeline cut-off or the pressure relief protection of the high-pressure refrigerant, avoid refrigerant leakage, and improve the operating reliability of the air-conditioning system.
[0079] In some embodiments, a first filter 115 is disposed on the first cut-off line 110 and a second filter 125 is disposed on the second cut-off line 120 for filtering impurities in the system.
[0080] There are two first filters 115 disposed on both sides of the first switch element 114 . There are two second filters 125 disposed on both sides of the second switch element 124 .
[0081] Reference Fig.17 One end of the pressure relief line 130 is connected between the first switch 114 and one of the first filters 115, and the first filter 115 is arranged on the side close to the indoor unit 10. The other end of the pressure relief line 130 is connected between the second switch 124 and one of the second filters 125, and the second filter 125 is arranged on the side close to the outdoor unit 20.
[0082] In some embodiments, reference Figures 1 to 4 The cutting device 50 includes a cutting device body 100 and an electrical box 200 .
[0083] The cut-off device body 100 includes a housing 140, in which the first cut-off line 110, the second cut-off line 120, and the pressure relief line 130 are installed. Both ends of the first cut-off line 110 and the second cut-off line 120 extend from the housing 140 to be connected to an external refrigerant line.
[0084] The electrical box 200 includes a box body 210 , in which a control panel 220 is disposed. The control panel 220 is used to control the opening and closing of the first switch element 114 , the second switch element 124 , and the pressure relief valve 131 .
[0085] The main body 100 of the cut-off device is connected and arranged side by side with the electrical box 200, that is, the housing 140 is connected and arranged side by side with the box body 210. In this way, the refrigerant pipeline and the control board 220 are respectively installed in independent spaces, and the refrigerant pipeline and the control board 220 are separated, so as to prevent the condensed water generated by the refrigerant pipeline in the housing 140 from contacting the control board 220 and causing abnormalities such as short circuit of the control board 220, which helps to improve the operating reliability of the air conditioning system.
[0086] The split design of the cut-off device body 100 and the electrical box 200 also facilitates the assembly of the cut-off device 50. During installation, the cut-off device body 100 and the electrical box 200 are assembled separately, that is, the first cut-off pipeline 110, the second cut-off pipeline 120 and the pressure relief pipeline 130 are installed in the housing 140, the control board 220 is installed in the box body 210, and then the cut-off device body 100 and the electrical box 200 are connected side by side.
[0087] In some embodiments, a first connection portion 214 is provided on the side wall of the electrical box 200, and second connection portions 148 are provided on two opposite side walls of the housing 140, respectively, and the first connection portion 214 is selectively connected to the second connection portion 148 on one side of the housing 140. That is, the electrical box 200 can be assembled on both sides to adapt to different installation scenarios on site.
[0088] In a specific embodiment, referring to Figure 3 and Figure 5 The first connecting portion 214 is a hook. Hooks are respectively provided at two corners of the upper side of the electrical box 200. Correspondingly, bayonet holes are provided on the two opposite side walls of the shell 140. By hanging the hook into the bayonet hole, the electrical box 200 can be assembled to the main body 100 of the cutting device, which is convenient for installation.
[0089] In some embodiments, the box body 210 of the electrical box 200 includes a first box body 211 and a second box body 212 , and the first box body 211 and the second box body 212 are snap-fitted and connected.
[0090] In some embodiments, a first wiring opening 213 is provided on the side wall of the electrical box 200, and the first wiring opening 213 and the first connecting portion 214 are provided on the same side. Correspondingly, a second wiring opening 146 is provided on the two opposite side walls of the shell 140. When the electrical box 200 is assembled to the side of the cut-off device body 100, the first wiring opening 213 and the second wiring opening 146 are directly opposite to each other, which facilitates the wiring between the electrical box 200 and the cut-off device body 100.
[0091] In some embodiments, when the refrigerant flows through the first cut-off line 110, the second cut-off line 120, and the pressure relief line 130, condensation may occur on these refrigerant lines. Figure 6 , Figures 13 to 16 In this embodiment, a heat preservation part 300 is provided in the shell 140. The heat preservation part 300 may be a foam part, etc. The heat preservation part 300 wraps the first cut-off pipeline 110, the second cut-off pipeline 120, and the pressure relief pipeline 130 to avoid condensation on these pipelines.
[0092] The insulation part 300 is placed in the inner cavity of the shell 140 and is adapted to the inner cavity of the shell 140, that is, the insulation part 300 is fixed in the inner cavity of the shell 140. In this way, the insulation part 300 not only plays a role in insulating the refrigerant pipeline, but also plays a role in fixing the refrigerant pipeline.
[0093] In some embodiments, a groove structure is formed on the insulation part 300 for the first cut-off line 110, the second cut-off line 120, and the pressure relief line 130 to pass through. The first cut-off line 110, the second cut-off line 120, and the pressure relief line 130 pass through the groove structure, so that the insulation part 300 wraps the first cut-off line 110, the second cut-off line 120, and the pressure relief line 130, and also plays a limiting role for these lines.
[0094] In some embodiments, continue to refer to Figures 13 to 16 The heat preservation part 300 includes a heat preservation main body part 310 and a heat preservation cover part 320. The heat preservation main body part 310 is provided with a groove structure. The heat preservation cover part 320 is connected to the heat preservation main body part 310 to cover the groove structure.
[0095] A groove structure is dug at the corresponding position of the insulation main body 310, and the groove structure is a concave structure with one side open, so as to facilitate the installation of the first cut-off pipeline 110, the second cut-off pipeline 120, and the pressure relief pipeline 130. Then, the insulation cover portion 320 is installed on the insulation main body 310 to cover the opening of the groove structure, that is, to limit the first cut-off pipeline 110, the second cut-off pipeline 120, and the pressure relief pipeline 130 to the corresponding groove structure, thereby realizing all-round wrapping and limiting of these refrigerant pipelines.
[0096] The split design of the heat-insulating main body 310 and the heat-insulating cover plate 320 facilitates the installation of the refrigerant pipeline and realizes all-round wrapping and limiting of the refrigerant pipeline.
[0097] In some embodiments, the groove structure is arranged on two opposite outer sides of the insulation main body 310. Specifically, a first groove structure 311 is arranged on one side of the insulation main body 310, and the first cut-off line 110 is arranged in the first groove structure 311; a second groove structure 312 is arranged on the other side opposite to the insulation main body 310, and the second cut-off line 120 is arranged in the second groove structure 312; a third groove structure 313 is arranged between the first groove structure 311 and the second groove structure 312, and the pressure relief line 130 is arranged in the third groove structure 313.
[0098] By arranging the first groove structure 311 and the second groove structure 312 on two opposite side surfaces of the insulation main body 310 to separate the first cut-off pipeline 110 and the second cut-off pipeline 120, on the one hand, it can effectively avoid heat exchange between the two refrigerants when the refrigerants flow through the first cut-off pipeline 110 and the second cut-off pipeline 120; on the other hand, it is convenient to install the first cut-off pipeline 110 and the second cut-off pipeline 120 from different sides of the insulation main body 310; in addition, the insulation cover plate part 320 has two, one insulation cover plate part 320 is used to cover the first groove structure 311, and the other insulation cover plate part 320 is used to cover the second groove structure 312, so as to reliably wrap and limit the first cut-off pipeline 110 and the second cut-off pipeline 120.
[0099] The pressure relief pipeline 130 is routed from the top of the heat-insulating main body 310 , which facilitates the installation of the pressure relief pipeline 130 .
[0100] In some embodiments, the shell 140 includes a shell body 141 and a cover body 142 , the heat preservation part 300 is disposed in the shell body 141 , and the cover body 142 is disposed on the top of the shell body 141 .
[0101] The first switch member 114, the second switch member 124, and the pressure relief valve 131 are exposed from the top of the heat preservation main body 310, and both ends of the first cut-off pipeline 110 and both ends of the second cut-off pipeline 120 extend from the side of the heat preservation main body 310. Pipe outlets 145 are respectively provided on opposite sides of the shell body 141, and both ends of the first cut-off pipeline 110 and both ends of the second cut-off pipeline 120 extend from the pipe outlets 145 on the corresponding sides.
[0102] In some embodiments, both ends of the first cut-off pipeline 110 and the second cut-off pipeline 120 pass through the pipe opening 145, and the pipe sections of the first cut-off pipeline 110 and the second cut-off pipeline 120 passing through the pipe opening 145 are sleeved with a heat-insulating member 150, such as Fig. 9 Most of the pipeline sections of the first cut-off pipeline 110 and the second cut-off pipeline 120 are located in the heat preservation part 300, and the end portions extending out of the heat preservation part 300 are wrapped with the heat preservation member 150. On the one hand, the extending portions of the end portions are insulated to avoid condensation; on the other hand, the heat preservation member 150 is located in the pipe outlet 145 to prevent the extending portions of the end portions of the first cut-off pipeline 110 and the second cut-off pipeline 120 from hard contact with the pipe outlet 145, thereby playing a role in protecting the pipelines.
[0103] In some embodiments, reference Figure 7 and Figure 8 End plates 143 are respectively disposed at opposite ends of the shell body 141 . The height of the end plates 143 is lower than the height of the shell body. A first notch 1431 is disposed at the top of the end plates 143 .
[0104] A side plate 144 is disposed above the end plate 143 , and a second notch 1441 is disposed at the bottom of the side plate 144 . The first notch 1431 and the second notch 1441 face each other to form a pipe opening 145 for the first cut-off pipeline 110 and the second cut-off pipeline 120 to pass through.
[0105] During installation, the side plate 144 and the cover body 142 are not installed first. First, the heat preservation part 300 together with the cut-off pipeline and the pressure relief pipeline 130 are installed into the shell body 141. At this time, the end protruding parts of the first cut-off pipeline 110 and the second cut-off pipeline 120 fall from top to bottom to the first notch 1431 and abut in place; then the side plate 144 is installed, and the first notch 1431 and the second notch 1441 are directly opposite to each other up and down, thereby limiting the end protruding parts of the first cut-off pipeline 110 and the second cut-off pipeline 120; finally, the cover body 142 is installed.
[0106] In some embodiments, a connection portion 147 is provided on the side plate 144, and the cut-off device body 100 is installed at a desired installation position through the connection portion 147. The connection portion 147 can be a hook structure, etc., and this embodiment does not make any specific restrictions.
[0107] In some embodiments, the first cut-off pipeline 110 and the second cut-off pipeline 120 are bent and routed on the heat-insulating main body 310. That is, the first cut-off pipeline 110 and the second cut-off pipeline 120 have a bent structure, and correspondingly, the first groove structure 311 and the second groove structure 312 are also bent groove structures, the first cut-off pipeline 110 is bent and routed along the first groove structure 311, and the second cut-off pipeline 120 is bent and routed along the second groove structure 312.
[0108] The first disconnecting pipeline 110 is a Z-shaped structure, including a first disconnecting pipeline section 111, a first disconnecting pipeline section 2 112, and a first disconnecting pipeline section 3 113 which are connected in sequence, and the first disconnecting pipeline section 2 112 is connected between the height distance between the first disconnecting pipeline section 111 and the first disconnecting pipeline section 3 113. The first disconnecting pipeline section 111 and the first disconnecting pipeline section 3 113 extend in the horizontal direction, and the first disconnecting pipeline section 2 112 extends in the vertical direction. The first switch 114 is arranged at the bend intersection of the first disconnecting pipeline section 2 112 and the first disconnecting pipeline section 3 113, so that the first switch 114 can be arranged upward to be exposed from the top of the heat-insulating main body 310. The first disconnecting pipeline section 111 and the first disconnecting pipeline section 3 113 are respectively provided with a first filter 115.
[0109] The second cut-off pipeline 120 is also a Z-shaped structure, including a first section 121, a second section 122, and a third section 123 of the second cut-off pipeline connected in sequence, and the second section 122 of the second cut-off pipeline is connected between the height distance of the first section 121 and the third section 123 of the second cut-off pipeline. The first section 121 and the third section 123 of the second cut-off pipeline extend in the horizontal direction, and the second section 122 of the second cut-off pipeline extends in the vertical direction. The second switch 124 is arranged at the bending intersection of the second section 122 and the third section 123 of the second cut-off pipeline, so that the second switch 124 can be arranged upward to be exposed from the top of the heat-insulating main body 310. The first section 121 and the third section 123 of the second cut-off pipeline are respectively provided with a second filter 125.
[0110] The bent pipe structure of the first cut-off pipe 110 and the second cut-off pipe 120, on the one hand, enables the first switch component 114 and the second switch component 124 to be exposed from the top of the insulation main body 310; on the other hand, it also helps to improve the pipe stability of the first cut-off pipe 110 and the second cut-off pipe 120 in the insulation part 300, and prevents the first cut-off pipe 110 and the second cut-off pipe 120 from moving left and right or up and down in the insulation part 300.
[0111] In some embodiments, the pressure relief line 130 is connected between the first cut-off line 110 and the second cut-off line 120 in a bending structure, and the first cut-off line 110 and the second cut-off line 120 form a pipe routing area for the pressure relief line 130 to bend and route.
[0112] Specifically, a pipe routing area for the pressure relief pipe 130 is formed above the first cut-off pipe section 111 and the second cut-off pipe section 121. Correspondingly, a third groove structure 313 for accommodating the bent pipe section of the pressure relief pipe 130 is provided in the heat-insulating body. The third groove structure 313 is provided on the same side as the first groove structure 311 and is connected to the first groove structure 311. A portion of the pressure relief pipe 130 is accommodated in the third groove structure 313, and the other portion is routed from the top of the heat-insulating body 310 so as to extend to the other side of the heat-insulating body 310 to connect with the second cut-off pipe 120.
[0113] In some embodiments, the installation process of the cut-off device 50 is as follows:
[0114] Assemble the first cut-off pipeline 110, the second cut-off pipeline 120, and the pressure relief pipeline 130 to form a pipeline assembly;
[0115] Install the pipeline assembly onto the heat-insulating main body 310 from top to bottom;
[0116] Install the heat-insulating cover plate 320 to the left and right sides of the heat-insulating main body 310 to limit the pipeline assembly to the heat-insulating main body 310;
[0117] The heat preservation part 300 and the pipeline assembly are installed into the shell body 141, and the protruding parts of the ends of the first cut-off pipeline 110 and the second cut-off pipeline 120 fall from top to bottom to the first notches 1431 at the top of the end plates 143 on the left and right sides of the shell body 141;
[0118] The side plate 144 is mounted on the end plate 143, and the second notch 1441 at the bottom of the side plate 144 is aligned with the first notch 1431 on the corresponding side, so as to limit the extended portions of the ends of the first cut-off pipeline 110 and the second cut-off pipeline 120;
[0119] Install the cover 142 to the top of the shell body 141;
[0120] The electric device box 200 is mounted to the side of the case body 141 .
[0121] In the description of the above embodiments, specific features, structures, materials or characteristics may be combined in a suitable manner in any one or more embodiments or examples.
[0122] The above is only a specific implementation of the utility model, but the protection scope of the utility model is not limited to this. Any changes or substitutions that can be easily thought of by technicians familiar with the technical field within the technical scope disclosed by the utility model should be included in the protection scope of the utility model. Therefore, the protection scope of the utility model should be based on the protection scope of the claims.
Claims
1. A multi-split air conditioning system, comprising: Outdoor unit; A plurality of indoor units, wherein a loop is formed between the outdoor units through a first refrigerant pipeline and a second refrigerant pipeline, wherein the first refrigerant pipeline includes a first refrigerant main pipeline and a plurality of first refrigerant branch pipelines, and the second refrigerant pipeline includes a second refrigerant main pipeline and a plurality of second refrigerant branch pipelines, wherein the outdoor unit is connected to the first refrigerant main pipeline and the second refrigerant main pipeline, and the indoor unit is connected to the first refrigerant branch pipeline and the second refrigerant branch pipeline; Characterized in that the air conditioning system also includes: At least one cut-off device, the cut-off device comprising: A cut-off pipeline, the cut-off pipeline is connected to the first refrigerant main pipeline and the second refrigerant main pipeline; and / or is connected to the first refrigerant branch pipeline and the second refrigerant branch pipeline, the cut-off pipeline is used to close or conduct the refrigerant pipeline to transport the refrigerant from one of the indoor unit and the outdoor unit to the other; The pressure relief pipeline is used to guide the high-pressure refrigerant in the refrigerant pipeline between the indoor unit and the outdoor unit to the compressor of the air-conditioning system to provide pressure relief protection for the air-conditioning system.
2. The multi-split air conditioning system according to claim 1, characterized in that: The cut-off device comprises a first cut-off pipeline and a second cut-off pipeline; The first cut-off pipeline is connected to the first refrigerant pipeline between the indoor unit and the outdoor unit, and is used to close or conduct the first refrigerant pipeline; The second cut-off pipeline is connected to the second refrigerant pipeline between the indoor unit and the outdoor unit, and is used to close or conduct the second refrigerant pipeline; One of the first cutoff pipe and the second cutoff pipe is closed and the other is opened to transport the refrigerant from one of the indoor unit and the outdoor unit to the other.
3. The multi-split air conditioning system according to claim 2, characterized in that: A first switch is provided on the first cut-off pipeline, and the first switch is used to control the closing or opening of the first cut-off pipeline; A second switch is provided on the second cut-off pipeline, and the second switch is used to control the closing or opening of the second cut-off pipeline; A first end of the pressure relief pipeline is connected to a refrigerant pipeline between the first switch component and the indoor unit, and a second end of the pressure relief pipeline is connected to a refrigerant pipeline between the second switch component and the outdoor unit.
4. The multi-split air conditioning system according to claim 3, characterized in that: The cut-off device comprises a cut-off device body and an electrical box, wherein the cut-off device body comprises a shell, and the shell is connected in parallel with the electrical box; The first cut-off pipeline and the second cut-off pipeline pass through the shell, and two ends of the first cut-off pipeline and two ends of the second cut-off pipeline extend out of the shell.
5. The multi-split air conditioning system according to claim 4, characterized in that: A pressure relief valve is provided on the pressure relief pipeline, and the first switch component, the second switch component and the pressure relief valve are arranged in the housing.
6. The multi-split air conditioning system according to claim 4, characterized in that: The shell is provided with pipe openings at opposite ends, and both ends of the first cut-off pipeline and the second cut-off pipeline pass through the pipe openings. Insulation components are sleeved on the pipe sections of the first cut-off pipeline and the second cut-off pipeline passing through the pipe openings.
7. The multi-split air conditioning system according to claim 4, characterized in that: A first connection portion is disposed on the side wall of the electrical box, and second connection portions are disposed on two opposite side walls of the shell respectively. The first connection portion is selectively connected to the second connection portion on one side of the shell.
8. The multi-split air conditioning system according to claim 4, characterized in that: The shell comprises a shell body and a cover body, wherein the cover body is arranged on the top of the shell body, and end plates are respectively arranged at opposite ends of the shell body, wherein the height of the end plates is lower than the height of the shell body, and a first notch is arranged on the top of the end plates; A side plate is arranged above the end plate, and a second notch is arranged at the bottom of the side plate. The first notch and the second notch are directly opposite to form a pipe passage for the first cut-off pipeline and the second cut-off pipeline to pass through.
9. The multi-split air conditioning system according to claim 8, characterized in that: The side plate is provided with a connecting portion.
10. A multi-split air conditioning system, comprising: Outdoor unit; Multiple indoor units; Characterized in that the air conditioning system also includes: At least one cut-off device, the cut-off device comprising a first cut-off pipeline and a second cut-off pipeline, the first cut-off pipeline is connected to a refrigerant pipeline connected to a refrigerant inflow end of the indoor unit, the second cut-off pipeline is connected to a refrigerant pipeline connected to a refrigerant outflow end of the indoor unit, one of the first cut-off pipeline and the second cut-off pipeline is closed and the other is opened, so as to transport the refrigerant from one of the outdoor unit and at least one of the indoor units to the other; The cut-off device also includes a pressure relief pipeline connected between the first cut-off pipeline and the second cut-off pipeline, which is used to guide the high-pressure refrigerant in the refrigerant pipeline between the indoor unit and the outdoor unit to the compressor of the air-conditioning system to provide pressure relief protection for the air-conditioning system.
Citation Information
Cited By
Air conditioning system
WO2026011681A1