Hanging beam tool

By designing the lifting beam tooling, using lifting holes at different locations to connect the crane hooks, selectively connecting the counterweight, the limitations of the lifting range of the bridge crane are solved, and a more efficient cargo handling and safe operation process is achieved.

CN221955673UActive Publication Date: 2024-11-05CSSC HUANGPU WENCHONG SHIPBUILDING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420758768.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-12
Publication Date
2024-11-05
Estimated Expiration
2034-04-12

AI Technical Summary

Technical Problem

The effective lifting operation range of bridge cranes is limited to directly below the cross beam, which cannot meet the lifting needs in other areas, resulting in low efficiency in cargo handling and manpower assistance, which poses safety hazards.

Method used

A lifting beam tool is designed, including a first lifting beam assembly and a second lifting beam assembly, connected to the crane hook through lifting holes at different locations, selectively connecting the counterweight, expanding the lifting area, and reducing manpower participation.

Benefits of technology

The lifting operation area of ​​bridge cranes has been effectively expanded, the efficiency of cargo handling is improved, manpower consumption is reduced, operation safety is ensured, and the use of manpower cable-stayed cables is avoided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221955673U_ABST
    Figure CN221955673U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of lifting equipment, and discloses a lifting beam tool which comprises a first lifting beam assembly and a second lifting beam assembly, the first lifting beam assembly comprises a first beam frame, a center lifting lug and a first end lifting lug, and the center lifting lug is provided with a first lifting hole and a second lifting hole; the first lifting beam assembly comprises a first beam frame, a first center lifting lug and a second end lifting lug, the first end lifting lug is provided with a third lifting hole and a fourth lifting hole, the second lifting beam assembly comprises a second beam frame, a second center lifting lug and a second end lifting lug, the second beam frame is perpendicularly fixed to the first beam frame in a crossed mode, and the second center lifting lug is provided with a fifth lifting hole and a sixth lifting hole. The second end lifting lug is provided with a seventh lifting hole and an eighth lifting hole. The lifting beam tool provided by the utility model can be combined with the bridge crane for use, so that the effective lifting operation area of the bridge crane is further expanded, and the carrying efficiency is further improved, the manpower consumption is reduced and the operation safety is ensured when the lifting beam tool is applied to ship indoor cabin platform cargo lifting.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of hoisting equipment, in particular to a hoisting beam tooling. Background Art

[0002] At present, in order to save labor costs and improve cargo handling efficiency, bridge cranes are commonly used in indoor holds of ships to lift cargo on the holds.

[0003] Specifically, for bridge cranes, the effective lifting operation range is only located directly below the crane beam, which cannot meet the lifting requirements of other areas. When the indoor platform is not located directly below the bridge crane beam, human assistance is required to complete the lifting work through operations such as inclined hanging cables, which not only affects the overall efficiency of cargo handling, but also consumes a certain amount of manpower, and the manual operation process is dangerous. Utility Model Content

[0004] The purpose of the utility model is to provide a lifting beam tool that can be used in combination with a bridge crane to further expand the effective lifting operation area of ​​the bridge crane, further improve the handling efficiency when used for lifting cargo on the indoor platform of a ship, and complete the operation without the need for manual oblique hanging cables, thereby reducing manpower consumption and ensuring operation safety.

[0005] To achieve this purpose, the utility model adopts the following technical solutions:

[0006] A hanging beam tooling comprises a first hanging beam assembly and a second hanging beam assembly; wherein:

[0007] The first hanging beam assembly comprises a first beam frame, a center hanging ear and a first end hanging ear, wherein the center hanging ear is arranged at the center of the first beam frame in the length direction, the center hanging ear is provided with a first hanging hole and a second hanging hole, the first beam frame is provided with the first end hanging ears at both ends in the length direction thereof, and the first end hanging ears are provided with a third hanging hole and a fourth hanging hole;

[0008] The second hanging beam assembly includes a second beam frame and a second end lifting ear. The second beam frame is vertically cross-fixed to the first beam frame. The second beam frame is provided with the second end lifting ears at both ends in its length direction. The second end lifting ears are provided with a fifth lifting hole and a sixth lifting hole.

[0009] Preferably, the first beam frame is provided with at least one first end lifting ear at each of two ends in the length direction of the first beam frame.

[0010] Preferably, the first end lifting ear is provided with a first set of holes, and the first end lifting ear can be sleeved on the first beam through the first set of holes and slide along the length direction of the first beam.

[0011] Preferably, a first locking piece is provided on the first end lifting ear, and the first locking piece is suitable for locking the first end lifting ear when the first end lifting ear slides into place relative to the first beam frame.

[0012] Preferably, the first beam is made of stainless steel.

[0013] Preferably, the second beam frame is provided with at least one second end lifting ear at each of two ends in the length direction of the second beam frame.

[0014] Preferably, the second end lifting ear is provided with a second set of holes, and the second end lifting ear can be sleeved on the second beam frame through the second set of holes and slide along the length direction of the second beam frame.

[0015] Preferably, a second locking piece is provided on the second end lifting ear, and the second locking piece is suitable for locking the second end lifting ear when the second end lifting ear slides into place relative to the second beam frame.

[0016] Preferably, the second beam frame is made of stainless steel. Preferably, the second beam frame is welded and fixed to the first beam frame.

[0017] Beneficial effects:

[0018] The lifting beam tool provided by the utility model is provided with a first lifting beam assembly and a second lifting beam assembly. Specifically, the first lifting beam assembly includes a first beam frame, a central lifting ear and a first end lifting ear, wherein the central lifting ear is arranged at the center of the first beam frame in the length direction, and the first beam frame is provided with first end lifting ears at both ends in its own length direction. The central lifting ear is provided with a first lifting hole and a second lifting hole, the first lifting hole is used to connect with the hook of the crane, and the second lifting hole is used to connect with the cargo to be lifted. The first end lifting ear is provided with a third lifting hole and a fourth lifting hole. The third lifting hole is used to connect with the hook of the crane, and the fourth lifting hole is used to connect with the cargo to be lifted or the counterweight. The second lifting beam assembly includes a second beam frame and a second end lifting ear, wherein the second beam frame is provided with a second end lifting ear at both ends in its own length direction, and the second end lifting ear is provided with a fifth lifting hole and a sixth lifting hole. The fifth lifting hole is used to connect with the hook of the crane, and the sixth lifting hole is used to connect with the cargo to be lifted or the counterweight.

[0019] The lifting beam tool provided by the utility model connects the crane's hook with lifting holes at different positions and selectively connects a counterweight. In addition to enabling the crane to normally lift goods directly under the beam, the lifting area can also be expanded to the area beyond directly under the beam. When applied to lifting goods on indoor platforms of ships, the handling efficiency is further improved, the effective lifting operation area of ​​the bridge crane is expanded, and the operation can be completed without the need for manual oblique hanging cables, thereby reducing manpower consumption and ensuring operation safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a structural schematic diagram of the hanging beam tooling provided by the utility model;

[0021] Figure 2 It is a structural schematic diagram of the first hanging beam assembly provided by the utility model;

[0022] Figure 3 It is a structural schematic diagram of the second hanging beam assembly provided by the utility model;

[0023] Figure 4 It is a front view of a lifting beam tooling provided by an embodiment of the utility model applied to a crane;

[0024] Figure 5 It is a top view of a hanging beam tooling provided by an embodiment of the utility model applied to a crane;

[0025] Figure 6 This utility model is Figure 4 A partial schematic diagram of the first hoisting assembly in the embodiment;

[0026] Figure 7 This utility model is Figure 4 A partial schematic diagram of the second lifting assembly in the embodiment;

[0027] Figure 8 It is a top view of a hanging beam tooling provided by another embodiment of the utility model applied to a crane;

[0028] Fig. 9 This utility model is Figure 8 A partial schematic diagram of the first hoisting assembly in the embodiment;

[0029] Fig.10 This utility model is Figure 8 A partial schematic diagram of the second lifting assembly in the embodiment;

[0030] Fig.11 It is a top view of a hanging beam tooling provided by another embodiment of the utility model applied to a crane;

[0031] Fig.12 This utility model is Fig.11A partial schematic diagram of the first hoisting assembly in the embodiment;

[0032] Fig.13 This utility model is Fig.11 A partial schematic diagram of the second lifting assembly in the embodiment.

[0033] In the figure:

[0034] 1. First hanging beam assembly; 11. First beam frame; 12. Center hanging ear; 121. First hanging hole; 122. Second hanging hole; 13. First end hanging ear; 131. Third hanging hole; 132. Fourth hanging hole;

[0035] 2. Second hanging beam assembly; 21. Second beam frame; 22. Second end hanging ear; 221. Fifth hanging hole; 222. Sixth hanging hole;

[0036] 3. crossbeam; 31. first hook; 32. second hook; 33. third hook;

[0037] 4. Counterweight;

[0038] 5. Goods;

[0039] 6. Cabin platform. DETAILED DESCRIPTION

[0040] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only the parts related to the present invention, rather than all structures, are shown in the accompanying drawings.

[0041] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0042] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0043] In the description of this embodiment, the terms "upper", "lower", "right", etc., are based on the directions or positions shown in the drawings, and are only for the convenience of description and simplified operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation of the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.

[0044] This embodiment provides a beam lifting tool. Figures 1 to 3 As shown, the hanging beam tooling includes a first hanging beam assembly 1 and a second hanging beam assembly 2. The first hanging beam assembly 1 includes a first beam frame 11, a center hanging ear 12 and a first end hanging ear 13. The center hanging ear 12 is arranged at the center of the first beam frame 11 in the length direction. The center hanging ear 12 is provided with a first hanging hole 121 and a second hanging hole 122. The first beam frame 11 is provided with first end hanging ears 13 at both ends in the length direction. The first end hanging ears 13 are provided with a third hanging hole 131 and a fourth hanging hole 132. The second hanging beam assembly 2 includes a second beam frame 21, a second center hanging ear 12 and a second end hanging ear 22. The second beam frame 21 is vertically cross-fixed to the first beam frame 11. The second center hanging ear 12 is provided with a fifth hanging hole 221 and a sixth hanging hole 222. The second beam frame 21 is provided with second end hanging ears 22 at both ends in the length direction. The second end hanging ears 22 are provided with a fifth hanging hole 221 and a sixth hanging hole 222.

[0045] In this embodiment, the first beam 11 and the second beam 21 are perpendicular bisectors to each other, that is, the lengthwise center of the first beam 11 perpendicularly intersects the lengthwise center of the second beam 21. The first hanging lug is disposed at the intersection of the first beam 11 and the second beam 21.

[0046] Specifically, Figures 4 to 5 The figure shows a crane corresponding to the lifting beam tooling provided in this embodiment, which is arranged in the ship room. The crane includes a crossbeam 3, on which a first hook 31, a second hook 32 and a third hook 33 are arranged.

[0047] Specifically, the directions a and b in the drawings refer to two mutually orthogonal horizontal directions, and the direction c refers to a vertical direction. The first hook 31 , the second hook 32 and the third hook 33 can all move along the direction a and adjust their positions relative to the crossbeam 3 .

[0048] Specifically, the center lifting lug 12 is provided with a first lifting hole 121 and a second lifting hole 122. The first lifting hole 121 is used to connect with the hook of the crane, and the second lifting hole 122 is used to connect with the cargo 5 to be lifted. The first end lifting lug 13 is provided with a third lifting hole 131 and a fourth lifting hole 132. The third lifting hole 131 is used to connect with the hook of the crane, and the fourth lifting hole 132 is used to connect with the cargo 5 to be lifted or the counterweight 4.

[0049] Figure 4 and Figure 7 An optional embodiment of the assembly of a crane and a beam fixture is provided in FIG. Figures 2 to 7 As shown, in this embodiment, Figure 6 The third lifting hole 131 of the first end lifting ear 13 at the right end of the first beam 11 is hooked to the first hook 31 through a sling, the fourth lifting hole 132 is hooked to the counterweight 4 through a sling, and the fourth lifting hole 132 of the first end lifting ear 13 on the left side of the first beam 11 is hooked to the cargo 5 to be lifted through a sling. Figure 7 The fifth hoisting holes 221 of the two second end lifting ears 22 at the left and right ends of the second beam frame 21 are respectively hooked to the second hook 32 and the third hook 33 through a sling.

[0050] Specifically, when it is necessary to lift the cargo 5, first hang the counterweight 4 on the fourth lifting hole 132 of the first end lifting ear 13 at the right end of the first beam 11, hang the first hook 31 on the third lifting hole 131, and hang the cargo 5 on the fourth lifting hole 132 of the first end lifting ear 13 at the left end. Then the crane controls the first hook 31, the second hook 32 and the third hook 33 to rise, and adjusts the force of each hook in the process to keep the first beam 11 and the second beam 21 in a horizontal state respectively. When the lifting beam tooling is raised to a certain height, that is, when the cargo 5 is lifted to a certain height, Figure 3 to Figure 4With the direction as a reference, the first hook 31, the second hook 32 and the third hook 33 move synchronously to the left to move the cargo 5 to the top of the target platform 6, and then the first hook 31, the second hook 32 and the third hook 33 are synchronously lowered to place the cargo 5 on the platform 6. When the cargo 5 is separated from the fourth lifting hole 132, the crane is controlled to move the first hook 31, the second hook 32 and the third hook 33 synchronously to the right, so that the lifting beam fixture leaves the platform 6 area and completes the current lifting work. The cooperation between the above-mentioned lifting beam fixture and the crane, in addition to enabling the crane to normally lift the cargo 5 directly under the beam 3, can also further expand the lifting area along the direction a, that is, to the areas on the left and right sides of the beam 3, effectively expanding the effective lifting operation area of ​​the bridge crane and giving full play to the lifting performance of the crane.

[0051] Figure 8 and Fig.10 Another optional embodiment of the assembly of a crane and a beam fixture is given in FIG. Figures 2 to 3 , Figures 8 to 10 As shown, in this embodiment, Fig. 9 The first lifting hole 121 of the central lifting ear 12 of the first beam frame 11 is connected to the second hook 32 through a sling. Fig.10 The sixth lifting hole 222 of the second end lifting ear 22 on the left side of the second beam frame 21 is connected to the cargo 5 to be lifted by a sling, the fifth lifting hole 221 of the second end lifting ear 22 on the right side of the second beam frame 21 is connected to the first hook 31 by a sling, and the sixth lifting hole 222 of the same second end lifting ear 22 is connected to the counterweight 4 by a sling. Figures 8 to 10 With direction as a reference, the cargo 5 can be extended to the front of the beam 3 through the lifting beam tooling, and the lifting area can be further expanded along direction b. The lifting area can be extended to the front of the beam 3, further expanding the effective lifting operation area of ​​the bridge crane.

[0052] Fig.11 and Fig.13 Another optional embodiment of the assembly of a crane and a beam fixture is provided in FIG. Figures 2 to 3 , Figures 11 to 13 As shown, in this embodiment, the first lifting hole 121 of the central lifting ear 12 of the first beam frame 11 is connected to the third hook 33 through a lifting rope. Fig.13 The fifth lifting hole 221 of the second end lifting lug 22 on the left side of the second beam frame 21 is hooked to the first hook 31 through a sling, the sixth lifting hole 222 of the same second end lifting lug 22 is hooked to the counterweight 4 through a sling, and the sixth lifting hole 222 of the second end lifting lug 22 on the right side of the second beam frame 21 is hooked to the cargo 5 to be lifted through a sling. Figures 11 to 13Taking direction as a reference, the cargo 5 can be extended to the rear of the beam 3 through the lifting beam tooling, and the lifting area can be further expanded along direction b. The lifting area can be extended to the rear of the beam 3, further expanding the effective lifting operation area of ​​the bridge crane.

[0053] Specifically, continue to refer to Figures 1 to 3 As shown, the center lifting ear 12 is provided with a first lifting hole 121 above the first beam 11, and the center lifting ear 12 is provided with a second lifting hole 122 below the first beam 11. The first end lifting ear 13 is provided with a third lifting hole 131 above the first beam 11, and the first end lifting ear 13 is provided with a fourth lifting hole 132 below the first beam 11.

[0054] Specifically, the second end lifting ear 22 defines a fifth lifting hole 221 above the second beam 21 , and the second end lifting ear 22 defines a sixth lifting hole 222 below the second beam 21 .

[0055] In this embodiment, at least one first end lifting lug 13 is provided at each end of the first beam frame 11 in the length direction. Specifically, in this embodiment, three first end lifting lugs 13 are provided at each of the opposite ends of the first beam frame 11, with the central lifting lug 12 as the boundary. Such a configuration can effectively increase the number of lifting holes on the first beam frame 11, further ensuring applicability.

[0056] As an optional embodiment, the first end lifting ear 13 is provided with a first set of holes, and the first end lifting ear 13 can be sleeved on the first beam frame 11 through the first set of holes and slide along the length direction of the first beam frame 11. In this way, the position of the first end lifting ear 13 relative to the first beam frame 11 is adjustable, and the position of the first end lifting ear 13 can be further adjusted according to the lifting distance.

[0057] Further optionally, a first locking member is provided on the first end lifting ear 13, and the first locking member is suitable for locking the first end lifting ear 13 when the first end lifting ear 13 slides into place relative to the first beam frame 11. Exemplarily, the first locking member can be set as a first locking bolt (not shown), and a first screw hole (not shown) is provided on the first end lifting ear 13, and the first locking bolt is threadedly connected with the first screw hole. Specifically, when the first end lifting ear 13 slides into place relative to the first beam frame 11, the first locking bolt is screwed into the first screw hole, thereby tightly abutting against the surface of the first beam frame 11, thereby achieving the locking of the first end lifting ear 13 relative to the first beam frame 11.

[0058] In this embodiment, at least one second end lifting lug 22 is provided at each end of the second beam 21 in the length direction. Specifically, in this embodiment, three second end lifting lugs 22 are provided at each of the two opposite ends of the second beam 21. This arrangement can effectively increase the number of lifting holes on the second beam 21, further ensuring applicability.

[0059] As an optional embodiment, the second end lifting ear 22 is provided with a second set of holes, and the second end lifting ear 22 can be sleeved on the second beam 21 through the second set of holes and slide along the length direction of the second beam 21. In this way, the position of the second end lifting ear 22 relative to the second beam 21 is adjustable, and the position of the second end lifting ear 22 can be further adjusted according to the lifting distance.

[0060] Further optionally, a second locking piece is provided on the second end lifting ear 22, and the second locking piece is suitable for locking the second end lifting ear 22 when the second end lifting ear 22 slides into place relative to the second beam frame 21. Exemplarily, the second locking piece can be set as a second locking bolt (not shown), and a second screw hole (not shown) is provided on the second end lifting ear 22, and the second locking bolt is threadedly connected with the second screw hole. Specifically, when the second end lifting ear 22 slides into place relative to the second beam frame 21, the second locking bolt is screwed into the second screw hole, thereby tightly abutting against the surface of the second beam frame 21, thereby achieving the locking of the second end lifting ear 22 relative to the second beam frame 21.

[0061] Optionally, the first beam frame 11 and the second beam frame 21 are both made of stainless steel. Stainless steel has reliable strength, strong corrosion resistance and rust resistance, and is reliable and durable.

[0062] In this embodiment, the second beam frame 21 is welded to the first beam frame 11. The welding connection method has high operation efficiency, reliable connection strength, and does not require the use of external connecting parts such as screws and bolts, and is reliable and durable.

[0063] To summarize, the lifting beam tooling provided in the present embodiment, by connecting the crane's hook with the lifting holes at different positions and selectively connecting the counterweight 4, can not only enable the crane to normally lift the cargo 5 directly below the beam 3, but also expand the lifting area to the area outside the beam 3. When applied to lifting the cargo 5 on the indoor platform 6 of a ship, the handling efficiency is further improved, the effective lifting operation area of ​​the bridge crane is expanded, and the operation can be completed without the need for manual oblique hanging cables, thereby reducing manpower consumption and ensuring operation safety.

[0064] Obviously, the above embodiments of the present invention are merely examples for the purpose of clearly illustrating the present invention, and are not intended to limit the implementation methods of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the scope of protection of the present invention. It is not necessary and impossible to list all implementation methods here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention shall be included in the scope of protection of the claims of the present invention.

Claims

1. A beam hanging tool, characterized in that: It comprises a first suspension beam assembly (1) and a second suspension beam assembly (2); wherein: The first suspension beam assembly (1) comprises a first beam frame (11), a center lifting ear (12) and a first end lifting ear (13); the center lifting ear (12) is arranged at the center of the first beam frame (11) in the length direction; the center lifting ear (12) is provided with a first lifting hole (121) and a second lifting hole (122); the first beam frame (11) is provided with the first end lifting ears (13) at both ends in the length direction; the first end lifting ears (13) are provided with a third lifting hole (131) and a fourth lifting hole (132); The second suspension beam assembly (2) comprises a second beam frame (21) and a second end lifting ear (22); the second beam frame (21) is vertically cross-fixed to the first beam frame (11); the second beam frame (21) is provided with the second end lifting ears (22) at both ends in its length direction; the second end lifting ears (22) are provided with a fifth lifting hole (221) and a sixth lifting hole (222).

2. The beam lifting tooling according to claim 1, characterized in that: The first beam frame (11) is provided with at least one first end lifting ear (13) at each of the two ends in the length direction of the first beam frame (11).

3. The hanging beam tooling according to claim 1, characterized in that: The first end lifting ear (13) is provided with a first set of holes, and the first end lifting ear (13) can be sleeved on the first beam frame (11) through the first set of holes and slide along the length direction of the first beam frame (11).

4. The beam lifting tool according to claim 1, characterized in that: The first end lifting ear (13) is provided with a first locking piece, and the first locking piece is suitable for locking the first end lifting ear (13) when the first end lifting ear (13) slides into place relative to the first beam frame (11).

5. The beam lifting tool according to claim 1, characterized in that: The material of the first beam frame (11) is set to be stainless steel.

6. The beam lifting tool according to claim 1, characterized in that: The second beam frame (21) is provided with at least one second end lifting ear (22) at each of the two ends in the length direction of the second beam frame (21).

7. The beam lifting tool according to claim 1, characterized in that: The second end lifting ear (22) is provided with a second set of holes, and the second end lifting ear (22) can be sleeved on the second beam frame (21) through the second set of holes and slide along the length direction of the second beam frame (21).

8. The beam lifting tool according to claim 1, characterized in that: A second locking piece is provided on the second end lifting ear (22), and the second locking piece is suitable for locking the second end lifting ear (22) when the second end lifting ear (22) slides into place relative to the second beam frame (21).

9. The beam lifting tool according to claim 1, characterized in that: The material of the second beam frame (21) is set to be stainless steel.

10. The beam lifting tool according to claim 1, characterized in that: The second beam frame (21) is fixed to the first beam frame (11) by welding.