Four-pipe cooling and heating unit

By using the first three-way valve and the second three-way valve in the four-way cooling unit to adjust the heat exchanger's communication status, the stability problem of the traditional four-way cooling unit during water temperature fluctuation and switching is solved, and multi-mode is realized Switch and energy efficiency improvement.

CN221959082UActive Publication Date: 2024-11-05ZHEJIANG DUNAN MASCH & ELECTRONICS TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420201787.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-26
Publication Date
2024-11-05
Estimated Expiration
2034-01-26

AI Technical Summary

Technical Problem

Traditional four-pipe cooling and heating units require a large energy storage water tank when the water temperature fluctuates or frequent switching on the hot water side and/or the cold water side, which is complicated to operate, and the cold water heat exchanger is prone to freezing and the compressor is prone to damage.

Method used

A four-pipe cooling and heating unit is designed, and the communication state between the cold water-side heat exchanger, the hot water-side heat exchanger and the balanced heat exchanger is adjusted through the configuration of the first three-way valve and the second three-way valve to realize the connection state of the cold water-side heat exchanger, the hot water-side heat exchanger and the balanced heat exchanger. Switching the cooling, heating and full heat recovery modes to avoid liquid hits caused by too low cold water temperature and refrigerant migration.

Benefits of technology

It achieves simplicity of operation, avoids cold water heat exchanger freezing and compressor damage, improves unit energy efficiency and stability, and reduces the impact of hot water-side heat exchanger on refrigerant.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221959082U_ABST
    Figure CN221959082U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of heat pumps, and provides a four-pipe cooling and heating unit. The four-pipe cooling and heating unit comprises a compressor, a cold water side heat exchanger, a hot water side heat exchanger and a balance heat exchanger. The compressor is provided with an exhaust port and an air suction port, a first three-way valve is arranged at the exhaust port, a second three-way valve is arranged at the air suction port, the first three-way valve is connected with one end of the hot-water-side heat exchanger and one end of the balance heat exchanger, and the second three-way valve is connected with one end of the cold-water-side heat exchanger and one end of the balance heat exchanger. The four-pipe refrigerating and heating unit at least has a refrigerating mode, a heating mode and a total heat recovery mode, and the four-pipe refrigerating and heating unit is configured to switch the refrigerating mode, the heating mode and the total heat recovery mode in response to the adjusting states of the first three-way valve and the second three-way valve. The four-pipe cooling and heating unit provided by the utility model can meet the switching of multiple modes, and is simple and convenient to operate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of heat pumps, and in particular to a four-tube refrigeration and heat unit. Background Art

[0002] The four-pipe cooling and heating unit can provide cold water and hot water at the same time. It is particularly suitable for occasions that require both cold source and heat source. It is widely used in hospitals, archives rooms, high-end hotels, constant temperature and humidity workshops, etc.

[0003] When the water temperature on the hot water side and / or the cold water side meets the requirements, the traditional four-pipe cooling and heating unit switches between the three modes of "cooling water, hot water, hot water + cooling water" through the setting of a four-way valve. Since this switching is the switching of the entire system of the four-pipe heat pump unit, it is usually necessary to configure a larger energy storage tank to avoid large fluctuations in water temperature or frequent switching. At the same time, some units also use the setting of a balanced heat exchanger to ensure the stability of the cut-in and cut-out of the cold water side and the hot water side, but this direction often requires step-by-step adjustment of the balanced heat exchanger, which is more complicated to operate; and, under certain operating conditions, it is easy to cause the compressor to inhale liquid and be damaged, and the cold water heat exchanger to be frozen due to too low evaporation temperature. Utility Model Content

[0004] Based on this, it is necessary to provide a four-tube cooling and heating unit that meets the needs of "cooling water, hot water, hot water + cooling water", and is simple and convenient to operate, and can avoid the problem of the cold water heat exchanger being frozen due to the evaporation temperature being too low as much as possible.

[0005] A four-pipe cooling and heating unit, comprising a compressor, a cold water side heat exchanger, a hot water side heat exchanger and a balancing heat exchanger; the compressor has an exhaust port and an air intake port, a first three-way valve is arranged at the exhaust port, and a second three-way valve is arranged at the air intake port, the first three-way valve is connected to one end of the hot water side heat exchanger and one end of the balancing heat exchanger, the second three-way valve is connected to one end of the cold water side heat exchanger and one end of the balancing heat exchanger; the other end of the cold water side heat exchanger is connected to the other end of the hot water side heat exchanger through a first pipeline, the other end of the cold water side heat exchanger is connected to the other end of the balancing heat exchanger through a second pipeline, and the other end of the hot water side heat exchanger is connected to the other end of the balancing heat exchanger through a third pipeline; the first pipeline and the second pipeline are connected in parallel with a first parallel point , the first pipeline and the third pipeline are connected in parallel with a second parallel point, and the first parallel point is located upstream of the second parallel point; a first one-way valve and a first expansion valve are arranged on the first pipeline, and the first one-way valve is located upstream of the first parallel point, and the first expansion valve is located downstream of the second parallel point, the second pipeline is provided with a second one-way valve, and the third pipeline is provided with a second expansion valve, the second one-way valve is located upstream of the first parallel point, and the second expansion valve is located downstream of the second parallel point; the four-pipe cooling and heat unit has at least a cooling mode, a heating mode and a full heat recovery mode, and the four-pipe cooling and heat unit is configured to switch the cooling mode, the heating mode and the full heat recovery mode in response to the adjustment status of the first three-way valve and the second three-way valve.

[0006] It can be understood that by using the settings of the first three-way valve and the second three-way valve, the connection state between the cold water side heat exchanger, the hot water side heat exchanger and the balancing heat exchanger can be adjusted to achieve the switching of the three modes, and the overall operation is simple and convenient. In the heating mode, the second three-way valve makes it unnecessary for the refrigerant to pass through the cold water side heat exchanger, thereby preventing the unevaporated refrigerant in the cold water side heat exchanger from continuing to evaporate and causing the cold water temperature to be too low; and such a setting can prevent the refrigerant from migrating into the cold water side heat exchanger, resulting in excessive refrigerant entering the compressor when restarting, causing liquid hammer. In the full heat recovery mode, the second three-way valve makes it unnecessary for the refrigerant to pass through the balancing heat exchanger, ensuring the amount of refrigerant between the cold water side heat exchanger and the hot water side heat exchanger, thereby ensuring the energy efficiency of the unit. In the cooling mode, the first three-way valve makes it unnecessary for the refrigerant to pass through the hot water side heat exchanger, thereby reducing the impact of the hot water side heat exchanger on the refrigerant and making the temperature unable to meet the cooling requirements of the terminal water-using equipment.

[0007] In some embodiments, in the cooling mode, the first three-way valve adjusts the exhaust port of the compressor to be connected to the balanced heat exchanger, the second three-way valve adjusts the suction port of the compressor to be connected to the cold water side heat exchanger, and the compressor, the balanced heat exchanger, the second pipeline, the first expansion valve and the cold water side heat exchanger are connected to form a cooling circuit; in the heating mode, the first three-way valve adjusts the exhaust port of the compressor to be connected to the hot water side heat exchanger, the second three-way valve adjusts the suction port of the compressor to be connected to the balanced heat exchanger, and the compressor, the hot water side heat exchanger, the third pipeline, the second expansion valve and the balanced heat exchanger are connected to form a heating circuit; in the full heat recovery mode, the first three-way valve adjusts the exhaust port of the compressor to be connected to the hot water side heat exchanger, the second three-way valve adjusts the suction port of the compressor to be connected to the cold water side heat exchanger, and the compressor, the hot water side heat exchanger, the first pipeline, the first expansion valve and the cold water side heat exchanger are connected to form a full heat recovery circuit.

[0008] In some embodiments, the four-pipe refrigeration and heat unit also has a partial heat recovery mode and a partial cold recovery mode; in the partial heat recovery mode, the first three-way valve adjusts the hot water side heat exchanger and the balancing heat exchanger to be connected to the exhaust port of the compressor, and the second three-way valve adjusts the suction port of the compressor to be connected to the cold water side heat exchanger, and the full heat recovery circuit and the refrigeration circuit are both connected; in the partial cold recovery mode, the first three-way valve adjusts the exhaust port of the compressor to be connected to the hot water side heat exchanger, and the second three-way valve adjusts the balancing heat exchanger and the cold water side heat exchanger to be connected to the suction port of the compressor, and the full heat recovery circuit and the heating circuit are both connected.

[0009] In some embodiments, a fourth pipeline is provided between the suction port of the compressor and one end of the hot water side heat exchanger, and a first two-way valve is provided on the fourth pipeline; a fifth pipeline is provided between the other end of the hot water side heat exchanger and the other end of the balancing heat exchanger, the fifth pipeline is connected in parallel with the third pipeline and has an opposite flow direction, and a third expansion valve is provided on the fifth pipeline.

[0010] In some embodiments, the four-pipe refrigeration and heating unit also has a defrost mode; in the defrost mode, the first three-way valve adjusts the exhaust port of the compressor to be connected to the balancing heat exchanger, the first two-way valve is configured to be in an open state, and the compressor, the balancing heat exchanger, the fifth pipeline, the third expansion valve, the hot water side heat exchanger and the fourth pipeline are connected to form a defrost circuit.

[0011] In some embodiments, the four-tube cooling and heating unit also includes a liquid reservoir, the inlet of the liquid reservoir is connected in parallel with a first branch and a second branch, and the outlet of the liquid reservoir is connected in parallel with a third branch and a fourth branch; the first branch is connected to the hot water side heat exchanger, the third branch is connected to the cold water side heat exchanger, the first one-way valve is arranged on the first branch, the first expansion valve is arranged on the third branch, the first branch and the third branch are connected to jointly define the first pipeline; the second branch is connected to the balanced heat exchanger, the second one-way valve is arranged on the second branch, the second branch and the third branch are connected to jointly define the second pipeline; the fourth branch is connected to the balanced heat exchanger, the second expansion valve is arranged on the fourth branch, the first branch and the fourth branch are connected to jointly define the third pipeline.

[0012] In some embodiments, the outlet of the liquid storage tank is also connected in parallel with a fifth branch, the fifth branch is connected to the hot water side heat exchanger, the third expansion valve is arranged on the fifth branch, and the second branch and the fifth branch are connected to jointly define the fifth pipeline.

[0013] In some of the embodiments, the cold water side heat exchanger and the hot water side heat exchanger respectively have a delivery pipe for connecting to the terminal water-using equipment, and the delivery pipe is provided with a first temperature sensor; the first three-way valve and the second three-way valve are both configured to adjust the opening degree in response to the detection signal of the first temperature sensor corresponding to each other.

[0014] In some of the embodiments, the balanced heat exchanger adopts an air heat exchanger, and the balanced heat exchanger is provided with a second temperature sensor, and the second temperature sensor is used to detect the ambient temperature; when the four-pipe refrigeration and heat unit is switched to the partial cold recovery mode, the second three-way valve is configured to adjust the opening degree in response to the detection signal of the second temperature sensor.

[0015] In some of the embodiments, a pressure sensor is provided at least at one end of the cold water side heat exchanger facing the compressor; when the four-pipe refrigeration and heat unit is switched to the partial cold recovery mode, the second three-way valve is configured to adjust the opening degree in response to the detection signal of the pressure sensor.

[0016] In some embodiments, the exhaust port and the intake port of the compressor are respectively connected in parallel with the sixth branch and the seventh branch; at the exhaust port, the corresponding sixth branch and the seventh branch are respectively connected to the hot water side heat exchanger and the balancing heat exchanger, and are respectively provided with a second two-way valve; at the intake port, the corresponding sixth branch and the seventh branch are respectively connected to the cold water side heat exchanger and the balancing heat exchanger, and are respectively provided with a third two-way valve. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the conventional technology, the drawings required for use in the embodiments or the conventional technology descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0018] Figure 1 Schematic diagram of a four-tube refrigeration and heating unit provided for this application;

[0019] Figure 2 for Figure 1 A schematic diagram of a four-pipe refrigeration and heating unit in cooling mode is provided;

[0020] Figure 3 for Figure 1 A schematic diagram of a four-pipe cooling and heating unit in heating mode is provided;

[0021] Figure 4 for Figure 1 A schematic diagram of a four-pipe refrigeration and heating unit in full heat recovery mode is provided;

[0022] Figure 5 for Figure 1 A schematic diagram of a four-pipe refrigeration and heating unit in partial heat recovery mode is provided;

[0023] Figure 6 for Figure 1 A schematic diagram of a four-pipe refrigeration and heating unit in partial cold recovery mode is provided;

[0024] Figure 7 for Figure 1 A schematic diagram of a four-pipe refrigeration and heating unit in defrost mode is provided;

[0025] Figure 8 A flow chart of switching various working modes of the four-pipe cooling and heating unit provided in this application;

[0026] Fig. 9 A flow chart of the control of the first three-way regulating valve of the four-pipe refrigeration and heating unit provided in the present application in the partial heat recovery mode;

[0027] Fig.10 A flow chart of the control of the second three-way regulating valve of the four-pipe refrigeration and heating unit in the partial cold recovery mode provided in the present application.

[0028] Figure numerals: 10, compressor; 20, hot water side heat exchanger; 30, cold water side heat exchanger; 40, balancing heat exchanger; 50, liquid storage tank; 61, first three-way valve; 62, second three-way valve; 71, first check valve; 72, second check valve; 73, first expansion valve; 74, second expansion valve; 75, third expansion valve; 76, first two-way valve; 81, pressure sensor. DETAILED DESCRIPTION

[0029] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present application. However, the present application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present application, so the present application is not limited by the specific embodiments disclosed below.

[0030] It should be noted that when a component is referred to as being "fixed to" or "disposed on" another component, it may be directly on the other component or there may also be a central component. When a component is considered to be "connected to" another component, it may be directly connected to the other component or there may be a central component at the same time. The terms "vertical", "horizontal", "upper", "lower", "left", "right" and similar expressions used in the specification of this application are for illustrative purposes only and do not represent the only implementation method.

[0031] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features.

[0032] In this application, unless otherwise clearly specified and limited, a first feature "above" or "below" a second feature may be that the first feature is directly in contact with the second feature, or the first feature and the second feature are indirectly in contact through an intermediate medium. The term "and / or" used in the specification of this application includes any and all combinations of one or more related listed items.

[0033] Unless otherwise defined, all technical and scientific terms used in the specification of this application have the same meaning as those commonly understood by those skilled in the art of the technical field of this application. The terms used in the specification of this application are only for the purpose of describing specific embodiments and are not intended to limit this application.

[0034] like Figures 1 to 4As shown, an embodiment of the present application provides a four-tube refrigeration and heating unit, including a compressor 10, a cold water side heat exchanger 30, a hot water side heat exchanger 20 and a balancing heat exchanger 40. The compressor 10 has an exhaust port and an air intake port, and a first three-way valve 61 is provided at the exhaust port, and a second three-way valve 62 is provided at the air intake port. The first three-way valve 61 has a port A, a port B and a port C, the port A is connected to the exhaust port of the compressor 10, the port B is connected to one end of the hot water side heat exchanger 20, and the port C is connected to one end of the balancing heat exchanger 40; at the same time, the second three-way valve 62 has a port D, a port E and a port F, the port D is connected to the air intake port of the compressor 10, the port E is connected to one end of the cold water side heat exchanger 30, and the port F is connected to one end of the balancing heat exchanger 40. The other end of the cold water side heat exchanger 30 is connected to the other end of the hot water side heat exchanger 20 through a first pipe, and the other end of the cold water side heat exchanger 30 is connected to the other end of the balancing heat exchanger 40 through a second pipe, that is, the hot water side heat exchanger 20 and the balancing heat exchanger 40 are arranged in parallel, and the other end of the hot water side heat exchanger 20 is connected to the other end of the balancing heat exchanger 40 through a third pipe.

[0035] The first pipeline and the second pipeline are connected in parallel with a first parallel point, the first pipeline and the third pipeline are connected in parallel with a second parallel point, and the first parallel point is located upstream of the second parallel point. The first pipeline is provided with a first check valve 71 and a first expansion valve 73, and the first check valve 71 is located upstream of the first parallel point, and the first expansion valve 73 is located downstream of the second parallel point, the second pipeline is provided with a second check valve 72, and the third pipeline is provided with a second expansion valve 74, the second check valve 72 is located upstream of the first parallel point, and the second expansion valve 74 is located downstream of the second parallel point.

[0036] In actual use, the first three-way valve 61 is used to adjust the connection state of the hot water side heat exchanger 20 and the balance heat exchanger 40 relative to the exhaust port of the compressor 10, and the second three-way valve 62 is used to adjust the connection state of the cold water side heat exchanger 30 and the balance heat exchanger 40 relative to the suction port of the compressor 10. The four-pipe cooling and heat unit has at least a cooling mode, a heating mode and a full heat recovery mode, and the four-pipe cooling and heat unit is configured to switch the cooling mode, the heating mode and the full heat recovery mode in response to the adjustment state of the first three-way valve 61 and the second three-way valve 62.

[0037] The following describes the circulation of refrigerant in the four-pipe refrigeration and heating unit for the above three modes respectively.

[0038] like Figure 2As shown, in the cooling mode, the first three-way valve 61 adjusts the exhaust port of the compressor 10 to communicate with the balanced heat exchanger 40, that is, port A is connected to port B, and port A is not connected to port C; the second three-way valve 62 adjusts the suction port of the compressor 10 to communicate with the cold water side heat exchanger 30, that is, port D is connected to port E, and port D is not connected to port F. At this time, the compressor 10, the balanced heat exchanger 40, the second pipeline, the first expansion valve 73 and the cold water side heat exchanger 30 are connected to form a refrigeration circuit. The refrigeration circuit is used to generate coldness. In actual use, the cold water side heat exchanger 30 can be connected to the terminal water-using equipment to provide cold water to the terminal water-using equipment. When the terminal water-using equipment needs low-temperature water or cold water, the gaseous refrigerant sent out from the exhaust port of the compressor 10 flows to the balancing heat exchanger 40 to condense and release heat, and then flows along the second pipeline, expands through the first expansion valve 73, and flows to the cold water side heat exchanger 30. After absorbing heat in the cold water side heat exchanger 30, it becomes a gaseous refrigerant and flows to the air intake port of the compressor 10; the water flow temperature after absorbing heat in the cold water side heat exchanger is reduced and supplied to the terminal water-using equipment. That is, in the cooling mode, the hot water side heat exchanger 20 does not participate in heat exchange, the balancing heat exchanger 40 acts as a condenser, and the cold water side heat exchanger 30 acts as an evaporator.

[0039] like Figure 3 As shown, in the heating mode, the first three-way valve 61 adjusts the exhaust port of the compressor 10 to communicate with the hot water side heat exchanger 20, that is, port A is connected to port C, and port A is not connected to port B; the second regulating valve adjusts the suction port of the compressor 10 to communicate with the balancing heat exchanger 40, that is, port D is connected to port F, and port D is not connected to port E. At this time, the compressor 10, the hot water side heat exchanger 20, the third pipeline, the second expansion valve 74 and the balancing heat exchanger 40 are connected to form a heating circuit. The heating circuit is used to generate heat. In actual use, the hot water side heat exchanger 20 can be connected to the terminal water-using equipment to provide hot water to the terminal water-using equipment. When the terminal water-using equipment needs high-temperature water or hot water, the gaseous refrigerant sent out through the exhaust port of the compressor 10 flows to the hot water side heat exchanger 20 to condense and release heat, and then flows along the third pipeline through the second expansion valve 74 to expand and flow to the balancing heat exchanger 40, where it evaporates and absorbs heat to become a gaseous refrigerant and flows to the air intake of the compressor 10; the water flow that absorbs heat in the hot water side heat exchanger 20 increases in temperature and is supplied to the terminal water-using equipment. That is, in the heating mode, the cold water side heat exchanger 30 does not participate in heat exchange, the hot water side heat exchanger 20 acts as a condenser, and the balancing heat exchanger 40 acts as an evaporator.

[0040] like Figure 4As shown, in the full heat recovery mode, the first three-way valve 61 adjusts the exhaust port of the compressor 10 to communicate with the hot water side heat exchanger 20, that is, port A is connected to port C, and port A is not connected to port B; the second three-way valve 62 adjusts the air intake port of the compressor 10 to communicate with the cold water side heat exchanger 30, that is, port D is connected to port E, and port D is not connected to port F; then the compressor 10, the hot water side heat exchanger 20, the first pipeline, the first expansion valve 73, and the cold water side heat exchanger 30 are connected to form a full heat recovery loop. That is to say, the gaseous refrigerant sent out through the exhaust port of the compressor 10 flows to the hot water side heat exchanger 20 to condense and release heat, and then flows along the first pipeline, expands through the first expansion valve 73, and then flows to the cold water side heat exchanger 30, and then evaporates and absorbs heat in the cold water side heat exchanger 30 to become a gaseous refrigerant and flows to the air intake port of the compressor 10. That is, in the total heat recovery mode, the hot water side heat exchanger 20 serves as a condenser, and the cold water side heat exchanger 30 serves as an evaporator.

[0041] In summary, by using the settings of the first three-way valve 61 and the second three-way valve 62, the connection state between the cold water side heat exchanger 30, the hot water side heat exchanger 20 and the balance heat exchanger 40 can be adjusted to achieve but not limited to the switching of the above three working modes, and the overall operation is simple and convenient. In the heating mode, since the port D of the second three-way valve 62 is not connected to the port E, the refrigerant does not need to pass through the cold water side heat exchanger 30, thereby avoiding the cold water temperature being too low; and such a setting can prevent the refrigerant from migrating into the cold water side heat exchanger 30, resulting in excessive refrigerant entering the compressor 10 when restarting, causing liquid hammer. In the full heat recovery mode, since the ports A and B of the first three-way valve 61 are not connected, and the ports D and F of the second three-way valve 62 are not connected, the refrigerant does not need to pass through the balance heat exchanger 40, ensuring the refrigerant amount between the cold water side heat exchanger 30 and the hot water side heat exchanger 20, thereby ensuring the energy efficiency of the unit. In the cooling mode, since the port A and the port C of the first three-way valve 61 are not connected, the refrigerant does not need to pass through the hot water side heat exchanger 20, thereby avoiding causing the hot water temperature to be too high.

[0042] like Figure 5 and Figure 6As shown, in some embodiments, the four-pipe cooling and heating unit also has a partial heat recovery mode and a partial cold recovery mode. In the partial heat recovery mode, the first three-way valve 61 adjusts the hot water side heat exchanger 20 and the balance heat exchanger 40 to be connected to the exhaust port of the compressor 10, that is, port A is connected to port B, and port A is connected to port C; and the second three-way valve 62 adjusts the suction port of the compressor 10 to be connected to the cold water side heat exchanger 30, that is, port D is connected to port E, and port D is not connected to port F; at this time, the full heat recovery circuit and the refrigeration circuit are both connected. In the partial cold recovery mode, the first three-way valve 61 adjusts the exhaust port of the compressor 10 to communicate with the hot water side heat exchanger 20, that is, port A is connected with port C, and port A is not connected with port B; and the second three-way valve 62 adjusts the balance heat exchanger 40 and the cold water side heat exchanger 30 to communicate with the air intake port of the compressor 10, that is, port D is connected with port E, and port D is connected with port F. At this time, the full heat recovery circuit and the heating circuit are both connected.

[0043] Specifically, in the partial heat recovery mode, a part of the gaseous refrigerant sent out through the exhaust port of the compressor 10 flows to the hot water side heat exchanger 20 to condense and release heat, and flows along the first pipeline to the first expansion valve 73 for expansion before flowing to the cold water side heat exchanger 30; at the same time, another part of the gaseous refrigerant sent out through the exhaust port flows to the balancing heat exchanger 40 to condense and release heat, and then flows along the second pipeline to the first expansion valve 73 for expansion before flowing to the cold water side heat exchanger 30; the refrigerant flowing to the cold water side heat exchanger 30 evaporates and absorbs heat before flowing to the air intake port of the compressor 10. That is, the hot water side heat exchanger 20 and the balancing heat exchanger 40 are both used as condensers, and the cold water side heat exchanger 30 is used as an evaporator. In the partial cold recovery mode, the gaseous refrigerant sent out from the exhaust port of the compressor 10 flows to the hot water side heat exchanger 20 to condense and release heat, a part of the refrigerant flows along the third pipeline through the second expansion valve 74 to expand and then flows to the balance heat exchanger 40 to evaporate and absorb heat, and then flows to the air intake of the compressor 10; at the same time, another part of the refrigerant flows along the first pipeline through the first expansion valve 73 to expand and then flows to the cold water side heat exchanger 30 to evaporate and absorb heat, and then flows to the air intake of the compressor 10. That is, the hot water side heat exchanger 20 is used as a condenser, and the balance heat exchanger 40 and the cold water side heat exchanger 30 are both used as evaporators.

[0044] That is to say, in the partial heat recovery mode, part of the heat can be recovered to the hot water side heat exchanger 20, and the other part of the heat can be discharged to the outside through the balancing heat exchanger 40; and in the partial cold water recovery mode, the cold capacity is distributed between the cold water side heat exchanger 30 and the balancing heat exchanger 40. In this way, the stepless regulation of partial cold recovery and partial heat recovery is met, thereby ensuring the stable water temperature regulation of the terminal water-using equipment when the cold and hot loads change.

[0045] In summary, the four-tube cooling and heat unit provided in this embodiment can adjust the connection state between the cold water side heat exchanger 30, the hot water side heat exchanger 20 and the balance heat exchanger 40 by using the setting of the first three-way valve 61 and the second three-way valve 62, so that the four-tube cooling and heat unit has the above-mentioned multiple working mode switching. Specifically, in the cooling mode, the first three-way valve 61 is adjusted to switch to the partial heat recovery mode; in the heating mode, the second three-way valve 62 is adjusted to switch to the partial cold recovery mode; in the full heat recovery mode, the first three-way valve 61 or the second three-way valve 62 is adjusted to switch to the partial heat recovery mode or the partial cold recovery mode. The specific switching method will be described in detail below, and it is only used as an example here.

[0046] In some specific embodiments, the balanced heat exchanger 40 uses an air heat exchanger, which can dissipate heat into the environment or absorb heat from the environment, and its evaporation pressure will vary greatly with changes in ambient temperature. The evaporation pressure of the refrigerant in the cold water side heat exchanger 30 is relatively stable. When the water temperature is controlled at a certain temperature, the evaporation pressure of the cold water side heat exchanger 30 will vary within a smaller range according to the load size. Therefore, when there is a difference between the evaporation pressure in the balanced heat exchanger 40 and the evaporation pressure in the cold water side heat exchanger 30, the setting of the second three-way valve 62 can perform secondary throttling (i.e., proportional regulation) on the side with higher evaporation pressure, thereby ensuring the effectiveness of the regulation and further preventing the cold water side heat exchanger 30 from freezing and cracking and the compressor 10 from liquid hammer damage.

[0047] Furthermore, both the first three-way valve 61 and the second three-way valve 62 can adopt proportional regulating valves, which can satisfy the switching between cooling mode, heating mode and full heat recovery mode, partial heat recovery mode and partial cold recovery mode. Taking the first three-way valve 61 as an example, when the opening of port A and port B changes, the opening of port A and port C will also change. For example, if the opening of port A and port B decreases, the opening of port A and port C increases; conversely, if the opening of port A and port B increases, the opening of port A and port C decreases. The working mode of the second three-way valve 62 is basically similar to that of the first three-way valve 62, and a similar description will be made in combination with the actual situation below, so it will not be repeated here.

[0048] In a replaceable embodiment, two branches may be connected in parallel at the exhaust port of the compressor 10, respectively connected to the hot water side heat exchanger 20 and the balancing heat exchanger 40, and a second two-way valve may be provided on each branch; at the same time, two branches may be connected in parallel at the intake port, respectively connected to the cold water side heat exchanger 30 and the balancing heat exchanger 40, and a third two-way valve may be provided on each branch.

[0049] like Figures 1 to 7As shown, in an optional embodiment, a fourth pipeline is further provided between the air intake of the compressor 10 and the hot water side heat exchanger 20, and a first two-way valve 76 is provided on the fourth pipeline; and a fifth pipeline is further provided between the hot water side heat exchanger 20 and the balance heat exchanger 40, the fifth pipeline is connected in parallel with the third pipeline, and the two flow directions are opposite, and a third expansion valve 75 is provided on the fifth pipeline. At this time, the four-pipe cooling and heating unit also has a defrosting mode.

[0050] like Figure 7 As shown, in the defrost mode, the first three-way valve 61 adjusts the exhaust port of the compressor 10 to communicate with the balancing heat exchanger 40, that is, port A is connected to port B, and port A is not connected to port C; and the second three-way valve 62 is configured so that at least port D and port F are not connected, and the second three-way valve 62 and the first expansion valve 73 work together to prevent the refrigerant from passing through the second three-way valve 62. The first two-way valve 76 on the fourth pipeline is configured to be in an open state, and the compressor 10, the balancing heat exchanger 40, the fifth pipeline, the third expansion valve 75, the hot water side heat exchanger 20 and the fourth pipeline are connected to form a defrost circuit. The defrost circuit can use the heat of the hot water side heat exchanger 20 to defrost the balancing heat exchanger 40 in winter, and at this time the entire four-pipe refrigeration and heating unit has no cooling load. Since the balancing heat exchanger 40 is an air heat exchanger, in an environment with a low ambient temperature such as winter, moisture in the air around the balancing heat exchanger 40 will condense into frost and adhere to the outer side of the balancing heat exchanger 40, thereby affecting the heat exchange performance. Therefore, it is necessary to defrost the balancing heat exchanger 40 to melt the frost on its surface.

[0051] In actual use, the gaseous refrigerant outputted from the exhaust port of the compressor 10 flows to the balanced heat exchanger 40 to exchange heat with the cold air and condense and release heat, then flows along the fifth pipeline through the third expansion valve 75 to expand and then flows to the hot water side heat exchanger 20 to evaporate and absorb heat, and then flows along the fourth pipeline to the air intake port of the compressor 10; the heat released by the condensation of the refrigerant in the balanced heat exchanger 40 can act on the balanced heat exchanger 40 for defrosting. In addition, in the above-mentioned cooling mode, the heat released by the gaseous refrigerant sent by the compressor 10 through the balanced heat exchanger 40 can also be used to defrost the balanced heat exchanger 40.

[0052] It is understandable that defrosting mostly occurs in a low-temperature environment. In the cooling mode, the balanced heat exchanger 40 is used as a condenser so that the refrigerant can condense and release heat, and after expansion through the first expansion valve 73, it flows to the cold water side heat exchanger 30 to evaporate and absorb heat. In this process, the heat released by the balanced heat exchanger 40 can be used for defrosting. However, since the ambient temperature itself is too low at this time, it will also affect the cold water temperature of the terminal water-using equipment. If the cooling mode is used for defrosting, the cold water will be overcooled. Therefore, the setting of the above-mentioned defrost circuit can meet the condensation heat release of the balanced heat exchanger 40 in a low-temperature environment without passing through the cold water side heat exchanger 30, realize defrosting, and reduce the impact of the defrosting process on the cold water temperature; and, such a setting can also ensure the hot water temperature of the terminal water-using equipment in a low-temperature environment, and reduce the impact of the ambient temperature on the hot water temperature.

[0053] like Figures 1 to 7 As shown, in an optional embodiment, the four-pipe cooling and heating unit further includes a liquid reservoir 50, the inlet of the liquid reservoir 50 is connected in parallel with a first branch and a second branch, and the outlet of the liquid reservoir 50 is connected in parallel with a third branch and a fourth branch. One end of the first branch is connected to the hot water side heat exchanger 20, one end of the third branch is connected to the cold water side heat exchanger 30, a first check valve 71 is provided on the first branch, a first expansion valve 73 is provided on the third branch, the first branch, the liquid reservoir 50 and the third branch are connected to define a first pipeline together, which is used to connect the hot water side heat exchanger 20 and the cold water side heat exchanger 30, so as to achieve the purpose of the refrigerant flowing from the hot water side heat exchanger 20 to the cold water side heat exchanger 30. One end of the second branch is connected to the balanced heat exchanger 40, the second one-way valve 72 is arranged on the second branch, the second branch, the liquid reservoir 50 and the third branch are connected to define a second pipeline, which is used to connect the balanced heat exchanger 40 and the cold water side heat exchanger 30, so as to achieve the purpose of the refrigerant flowing from the balanced heat exchanger 40 to the cold water side heat exchanger 30. One end of the fourth branch is connected to the balanced heat exchanger 40, the second expansion valve 74 is arranged on the fourth branch, the first branch, the liquid reservoir 50 and the fourth branch are connected to define a third pipeline, which is used to connect the hot water side heat exchanger 20 and the balanced heat exchanger 40, so as to achieve the purpose of the refrigerant flowing from the hot water side heat exchanger 20 to the balanced heat exchanger 40.

[0054] The intersection of the first branch and the second branch at the inlet of the liquid reservoir 50 can be used as the first parallel point of the first pipeline and the second pipeline, and the intersection of the third branch and the fourth branch at the outlet of the liquid reservoir 50 can be used as the second parallel point of the first pipeline and the third pipeline. The first one-way valve 71 is used to guide the fluid from the hot water side heat exchanger 20 to the inlet of the liquid reservoir 50, and the second one-way valve 72 is used to guide the fluid from the balancing heat exchanger 40 to the inlet of the liquid reservoir 50. The inlet of the first expansion valve 73 is toward the outlet of the liquid reservoir 50, which is used to reduce the pressure of the refrigerant in the refrigeration circuit and the total heat recovery circuit, and the opening is adjusted according to the evaporation pressure at the cold water side heat exchanger 30. The inlet of the second expansion valve 74 is toward the outlet of the liquid reservoir 50, which is used to reduce the pressure of the refrigerant in the heating circuit, and the opening is adjusted according to the evaporation pressure at the balancing heat exchanger 40. Specifically, a pressure sensor 81 may be provided at one end of the cold water side heat exchanger 30 facing the compressor 10 to obtain the flow pressure of the cold water side heat exchanger 30 and further obtain the evaporation pressure.

[0055] Furthermore, a fifth branch is connected in parallel at the outlet of the liquid storage device 50, the fifth branch is connected to the hot water side heat exchanger 20, the third expansion valve 75 is arranged on the fifth branch, the second branch, the liquid storage device 50 and the fifth branch are connected to define a fifth pipeline together, so that the refrigerant flows from the balancing heat exchanger 40 to the hot water side heat exchanger 20. The inlet of the third expansion valve 75 faces the outlet of the liquid storage device 50, and is used to reduce the pressure of the refrigerant in the defrosting circuit, and the opening is adjusted according to the evaporation pressure at the hot water side heat exchanger 20.

[0056] The arrangement of the liquid storage device 50 enables the refrigerant flowing through the first pipeline, the second pipeline, the third pipeline and the fifth pipeline to be in a fully liquid state.

[0057] In summary, in cooling mode, port A and port B of the first three-way valve 61 are connected, port D and port E of the second three-way valve 62 are connected, the first expansion valve 73 is in operation, and the second expansion valve 74 and the third expansion valve 75 are closed. In heating mode, port A and port C of the first three-way valve 61 are in operation, port D and port F of the second three-way valve 62 are in operation, the second expansion valve 74 is in operation, and the first expansion valve 73 and the third expansion valve 75 are closed. In full heat recovery mode, port A and port C of the first three-way valve 61 are in operation, port D and port E of the second three-way valve 62 are in operation, the first expansion valve 73 is in operation, and the second expansion valve 74 and the third expansion valve 75 are closed. In partial heat recovery mode, port A of the first three-way valve 61 is in operation with both port C and port B, port D and port E of the second three-way valve 62 are in operation, the first expansion valve 73 is in operation, and the second expansion valve 74 and the third expansion valve 75 are closed. In the partial cold recovery mode, the port A of the first three-way valve 61 is connected to the port C, the port D of the second three-way valve 62 is connected to the ports E and F, the first expansion valve 73 and the second expansion valve 74 are in operation, and the third expansion valve 75 is closed. In the defrosting mode, the port A of the first three-way valve 61 is in communication with the port B, the third expansion valve 75 is in operation, and the first two-way valve 76 is open.

[0058] In actual use, the cold water side heat exchanger 30 and the hot water side heat exchanger 20 respectively have a delivery pipe for connecting the terminal water equipment, and the first temperature sensor is arranged on each corresponding delivery pipe, and the first three-way valve 61 and the second three-way valve 62 can adjust the opening according to the temperature signal detected by each first temperature sensor, thereby realizing the switching of each working mode. At the same time, when the balanced heat exchanger 40 adopts an air heat exchanger, the balanced heat exchanger 40 is provided with a second temperature sensor for detecting the ambient temperature. Therefore, when the four-tube refrigeration and heat unit switches from the full heat recovery mode to the partial cold recovery mode, the second three-way valve 62 adjusts the opening according to the detection signal of the second temperature sensor. In addition, it is precisely because of the difference in evaporation pressure between the balanced heat exchanger 40 and the cold water side heat exchanger 30 that a pressure sensor 81 is arranged at one end of the cold water side heat exchanger 30 facing the compressor 10, so that when the four-tube refrigeration and heat unit switches to the partial cold recovery mode, the second three-way valve 62 can adjust the opening according to the detection signal of the pressure sensor 81. The specific switching control process is as follows:

[0059] like Figures 1 to 8 As shown, in some embodiments, the actual cold water temperature (T 冷测 ) and the actual hot water temperature (T 热测 );

[0060] The actual cold water temperature and the set cold water loading temperature (T 冷加载 ) to compare the actual hot water temperature with the set hot water loading temperature (T热加载 ) for comparison;

[0061] When the actual cold water temperature is greater than the set cold water loading temperature, and the actual hot water temperature is not less than the set hot water loading temperature, the four-pipe cooling and heating unit starts or switches to cooling mode;

[0062] When the actual cold water temperature is not greater than the set cold water loading temperature, and the actual hot water temperature is less than the set hot water loading temperature, the four-pipe cooling and heating unit starts or switches to cooling mode;

[0063] When the actual cold water temperature is greater than the set cold water loading temperature and the actual hot water temperature is less than the set hot water loading temperature, the four-pipe cooling and heating unit starts or switches to full heat recovery mode.

[0064] The actual cold water temperature may be the temperature at the cold water inlet where the cold water side heat exchanger 30 is connected to the terminal water-using equipment, and the actual hot water temperature may be the temperature at the hot water inlet where the hot water side heat exchanger 20 is connected to the terminal water-using equipment. In actual use, temperature sensors may be installed at both the cold water inlet of the cold water side heat exchanger 30 and the hot water inlet of the hot water side heat exchanger 20 to monitor the actual cold water temperature and the actual hot water temperature in real time. Setting the cold water loading temperature refers to the preset temperature at which the cooling capacity needs to be increased, and setting the hot water loading temperature refers to the preset temperature at which the heat needs to be increased.

[0065] When the actual cold water temperature at the cold water inlet is greater than the set cold water loading temperature, and the actual hot water temperature is not less than the set hot water loading temperature, it means that the cold water temperature of the terminal water-using equipment (hereinafter referred to as the terminal) is high, but the terminal hot water temperature is in a normal state. At this time, the cold water cooling capacity needs to be increased. Therefore, it is necessary to switch the four-tube cooling and heating unit to the cooling mode to increase the cold water cooling capacity. When the actual cold water temperature is not greater than the set cold water loading temperature, and the actual hot water temperature is less than the set hot water loading temperature, it means that the terminal hot water heat is insufficient, but the terminal cold water temperature is in a normal state. At this time, the hot water heat needs to be increased. Therefore, the four-tube cooling and heating unit can be switched to the heating mode to increase the hot water heat. When the actual cold water temperature is greater than the set cold water loading temperature, and the actual hot water temperature is less than the set hot water loading temperature, it means that the terminal cold water temperature is too high and the terminal hot water temperature is too low. At this time, not only the cold water cooling capacity needs to be increased, but also the hot water heat needs to be increased. Therefore, the four-tube cooling and heating unit needs to be switched to the full heat recovery mode to increase the heat exchange of the entire unit.

[0066] Among them, not less than means greater than or equal to, and not greater than means less than or equal to.

[0067] In cooling mode, the refrigerant circulates between the compressor 10, the balancing heat exchanger 40, the accumulator 50, the first expansion valve 73 and the cold water side heat exchanger 30. Therefore, the opening of the first expansion valve 73 can be adjusted according to the superheat at the cold water side heat exchanger 30. If the superheat here is too large, the evaporation pressure is too large, and the refrigerant flow rate needs to be increased, that is, the opening of the first expansion valve 73 needs to be increased; if the superheat here is too small, the evaporation pressure is too small, and the refrigerant flow rate needs to be reduced, that is, the opening of the first expansion valve 73 needs to be reduced. In heating mode, the refrigerant circulates between the compressor 10, the hot water side heat exchanger 20, the accumulator 50, the second expansion valve 74 and the balancing heat exchanger 40. The opening of the second expansion valve 74 can be adjusted according to the superheat at the balancing heat exchanger 40. The specific adjustment principle is basically similar to that of the first expansion valve 73, so it is not repeated.

[0068] like Figures 1 to 8 As shown, in an optional embodiment, the four-pipe cooling and heating unit still monitors the actual cold water temperature and the actual hot water temperature in real time during the cooling mode operation cycle, and compares them with the corresponding set cold water loading temperature and the set hot water loading temperature. It should be noted that after loading cold or heat for a period of time, it will need to be unloaded, otherwise the terminal cold water may be too cold or the terminal hot water may be too hot. At this time, it is also necessary to compare the actual cold water temperature with the set cold water unloading temperature (T in the figure). 冷卸载 ), actual hot water temperature and set hot water unloading temperature (T 热卸载 ) for comparison. The cold water unloading temperature is set to be less than the cold water loading temperature, and the hot water unloading temperature is set to be greater than the hot water loading temperature. It is worth noting that the loading of the compressor 10 mentioned here may be to increase the power of the compressor 10, and the unloading of the compressor 10 may be to reduce the power of the compressor 10, which is an example here.

[0069] Since the hot water side heat exchanger 20 does not participate in heat exchange in the cooling mode, the four-tube cooling and heating unit will cause the hot water temperature to drop over time during the cooling mode operation cycle. Therefore, when the actual hot water temperature is less than the set hot water loading temperature, it is necessary to increase the hot water heat. At this time, the four-tube cooling and heating unit switches to the partial heat recovery mode so that part of the refrigerant passes through the hot water side heat exchanger 20, and then releases heat to increase the terminal hot water temperature. If the four-tube cooling and heating unit detects that the actual hot water temperature is not less than the set hot water loading temperature during the cooling mode operation cycle, the terminal hot water temperature is in a normal state. At this time, if the actual cold water temperature is greater than the set cold water loading temperature, it means that the cold water temperature is too high and the cooling capacity needs to be increased, so the compressor 10 is loaded; if the actual cold water temperature is less than the set cold water unloading temperature, it means that the cold water temperature meets the requirements, which can prompt the compressor 10 to unload to prevent the water temperature from being too low due to excessive cooling capacity; if the actual cold water temperature is equal to the set cold water loading temperature, the cooling mode is maintained, and the comparison is continued after a certain period of time, and the adjustment can be made according to the above steps.

[0070] like Figures 1 to 8 As shown, in an optional embodiment, the four-tube cooling and heating unit still monitors the actual cold water temperature and the actual hot water temperature in real time during the heating mode operation cycle, and compares them with the corresponding set cold water loading temperature, set cold water unloading temperature, set hot water loading temperature and set hot water unloading temperature. Since the cold water side heat exchanger 30 does not participate in heat exchange in the heating mode, the cold water temperature will rise over time during the operation of the four-tube cooling and heating unit in the heating mode. When the actual cold water temperature is greater than the set cold water loading temperature, it means that the cooling capacity needs to be increased to reduce the water temperature, and the four-tube cooling and heating unit switches to the partial cold recovery mode, so that the cold water side heat exchanger 30 is added to the heat exchange, so that part of the refrigerant evaporates and absorbs heat through the cold water side heat exchanger 30 to reduce the terminal cold water temperature. If the four-tube cooling and heating unit detects that the actual cold water temperature is not greater than the set cold water loading temperature during the heating mode operation cycle, it means that the terminal cold water temperature is in a normal state. At this time, if the actual hot water temperature is lower than the set hot water loading temperature, it means that the hot water temperature is too low and the heat needs to be increased, so the compressor 10 is loaded; if the actual hot water temperature is higher than the set hot water unloading temperature, it means that the hot water temperature meets the demand, which can prompt the compressor 10 to unload to prevent excessive heat from causing the water temperature to be too high; if the actual hot water temperature is equal to the set hot water loading temperature, keep running in heating mode, continue to compare after a certain period of time, and adjust according to the above steps.

[0071] like Figures 1 to 8As shown, in an optional embodiment, the four-tube cooling and heating unit still monitors the actual cold water temperature and the actual hot water temperature in real time during the operation cycle of the full heat recovery mode, and compares them with the corresponding set cold water loading temperature, set cold water unloading temperature, set hot water loading temperature and set hot water unloading temperature. It should be noted that since the heat exchange amount is large in the full heat recovery mode, the impact on the water temperature is also large, so the actual operation time of the full heat recovery mode needs to be considered. At this time, the actual operation time also needs to be compared with the set operation time. The details are as follows:

[0072] Get the actual running time of the full heat recovery mode and compare the actual running time with the set running time (τ min ) for comparison. Among them, the set running time can be used as the minimum running time requirement of the unit. Such a setting is equivalent to reserving a safe running time for the unit, which effectively avoids the unit from switching arbitrarily between the partial cold recovery mode, the full heat recovery mode and the partial heat recovery mode, thereby preventing the balanced heat exchanger 40 from being continuously connected to the high-pressure side and the low-pressure side (that is, it acts as a condenser for a while and an evaporator for a while) and causing damage, thereby improving the control reliability of the unit. Therefore, it can be judged according to the actual running time whether it is necessary to switch to the partial heat recovery mode or the partial cold recovery mode, or whether it is necessary to load or unload the compressor 10.

[0073] In some specific embodiments, the set running time may be between 1s and 600s. Further, it may be between 10s and 500s. For example, the set running time may be 1s, 90s, 250s, 300s, 450s or 600s.

[0074] When the actual hot water temperature is greater than the set hot water unloading temperature, the actual cold water temperature is not less than the set cold water unloading temperature, and the actual operating time is not less than the set operating time, it means that the full heat recovery mode has been running for a period of time and meets the minimum operating time requirement, and the terminal hot water temperature meets the requirement, but because the cold water unloading temperature is lower than the cold water loading temperature, the terminal cold water temperature may still be lower than the set cold water loading temperature, that is, the terminal cold water temperature is low. Therefore, it is necessary to switch the four-tube cooling and heating unit to the partial heat recovery mode to introduce the balancing heat exchanger 40 into the heat exchange to increase the heat exchange capacity of the cold water side heat exchanger 30, thereby ensuring that the terminal cold water temperature meets the requirements. At the same time, the setting of the balancing heat exchanger 40 can also dissipate part of the heat exchange capacity into the air, avoiding the excessive heat exchange capacity of the hot water side heat exchanger 20 and causing the terminal hot water temperature to overheat, thereby ensuring the stability of the terminal cold water temperature and the terminal hot water temperature.

[0075] When the actual hot water temperature is not greater than the set hot water unloading temperature, the actual cold water temperature is less than the set cold water unloading temperature, and the actual operating time is not less than the set operating time, it means that the full heat recovery mode has been running for a period of time and meets the minimum operating time requirement, and the terminal cold water temperature meets the requirement, but because the set hot water unloading temperature is greater than the set hot water loading temperature, the actual hot water temperature may still be less than the set hot water loading temperature, that is, the terminal hot water temperature is low. Therefore, it is necessary to switch the four-pipe cooling and heating unit to the partial cold recovery mode to introduce the balance heat exchanger 40 into the heat exchange, thereby increasing the heat exchange capacity of the hot water side heat exchanger 20, and thus ensuring that the terminal hot water temperature meets the requirements.

[0076] When the actual hot water temperature is greater than the set hot water unloading temperature, the actual cold water temperature is less than the set cold water unloading temperature, and the actual operating time is less than the set operating time, it means that the operating time of the four-pipe refrigeration and heat unit in the full heat recovery mode is short and does not meet the shortest operating time requirement, and the terminal hot water temperature and the terminal cold water temperature both meet their respective needs. At this time, the compressor 10 can be adjusted to unload to avoid overheating or overcooling.

[0077] When the actual hot water temperature is lower than the set hot water loading temperature, the actual cold water temperature is higher than the set cold water unloading temperature, and the actual running time is lower than the set running time, it indicates that the running time of the four-pipe refrigeration and heat unit in the full heat recovery mode is short and does not meet the shortest running time requirement, and the terminal hot water temperature is low and the terminal cold water temperature is high, then it is necessary to adjust the loading of the compressor 10. In an alternative embodiment, it may also be that when the actual cold water temperature is higher than the set cold water loading temperature, the actual hot water temperature is lower than the set hot water unloading temperature, and the actual running time is lower than the set running time, it indicates that the running time of the four-pipe refrigeration and heat unit in the full heat recovery mode does not meet the shortest running time requirement, and the terminal hot water temperature is low and the terminal cold water temperature is high, then it is also necessary to adjust the loading of the compressor 10.

[0078] In addition, when the actual hot water temperature is equal to the hot water unloading temperature, the actual cold water temperature is equal to the cold water unloading temperature, and the actual operating time is less than the set operating time, the full heat recovery mode is maintained, and the comparison is continued after a certain period of time, and adjustments can be made according to the above steps.

[0079] In actual use, you can define the target temperature, that is, the temperature that meets the use requirements. Among them, cold water corresponds to the cold water target temperature, and hot water corresponds to the hot water target temperature. Then, the cold water loading temperature > cold water target temperature > cold water unloading temperature, and the hot water loading temperature < hot water target temperature < hot water unloading temperature. Among them, the cold water target temperature can be set to 7℃, the cold water unloading temperature to 6.7℃, the cold water loading temperature to 7.7℃, the hot water target temperature to 45℃, the hot water unloading temperature to 45.3℃, and the hot water loading temperature to 44.7℃.

[0080] The switching of each mode is described in detail below in combination with the specific control of the first three-way valve 61 and the second three-way valve 62 .

[0081] like Figures 1 to 6 ,and Fig. 9 As shown, in an optional embodiment, when the four-tube cooling and heating unit is switched to the partial heat recovery mode, it is necessary to adjust the connection between the port A and the port B, and the port A and the port C of the first three-way valve 61. Therefore, when switching from the cooling mode or the full heat recovery mode to the partial heat recovery mode, it is necessary to adjust the opening of the port A and the port C. Specifically, when switching from the cooling mode to the partial heat recovery mode, since the port A is connected to the port B in the cooling mode, and the port A is not connected to the port C (that is, the opening is equal to 0), it is necessary to increase the opening of the port A and the port C, so as to meet the connection between the port B and the port C; when switching from the full heat recovery mode to the partial heat recovery mode, since the port A is connected to the port C in the full heat recovery mode, and the port A is not connected to the port B, it is necessary to reduce the opening of the port A and the port C, so as to increase the opening of the port A and the port B, so as to achieve the connection between the port B and the port C and the port A.

[0082] During the adjustment process, if the openings of ports A and C of the first three-way valve 61 are adjusted to 0, then ports A of the first three-way valve 61 are connected to port B and the opening is 100%, and the four-pipe cooling and heating unit switches to the cooling mode; if the openings of ports A and C of the first three-way valve 61 are adjusted to 100%, then ports A and B are not connected, and the four-pipe cooling and heating unit switches to the full heat recovery mode. It is worth noting that at this time, the second three-way valve 62 remains unchanged, and ports D and E are connected.

[0083] If the ports A and B, and the ports A and C of the first three-way valve 61 are both connected, the four-pipe cooling and heating unit switches to the partial heat recovery mode. During the operation cycle of the partial heat recovery mode:

[0084] When the actual hot water temperature is lower than the set hot water loading temperature and the actual running time is longer than the set running time (τ 设定 ), it means that the partial heat recovery mode has been running for a period of time and meets the minimum running time requirement, but the terminal hot water heat is insufficient, so the opening of port A and port C is increased, while the opening of port A and port B is reduced, thereby increasing the amount of refrigerant flowing to the hot water side heat exchanger 20, reducing the amount of refrigerant flowing to the balance heat exchanger 40, and increasing the heat exchange capacity of the hot water side heat exchanger 20.

[0085] When the actual hot water temperature is greater than the set hot water unloading temperature and the actual operating time is greater than the set operating time, it means that the terminal hot water heat is sufficient. At this time, the openings of ports A and C can be reduced to increase the openings of ports A and B, thereby reducing the amount of refrigerant flowing to the hot water side heat exchanger 20 and increasing the amount of refrigerant flowing to the balancing heat exchanger 40, so that the excess heat can be dissipated through the balancing heat exchanger 40 and air heat dissipation.

[0086] When the actual operation time is less than the set operation time, and the actual cold water temperature is greater than the set cold water loading temperature, it means that the partial heat recovery mode has not yet met the minimum operation time requirement, but the terminal cold water temperature is high, which prompts the compressor 10 to load. At the same time, when the actual cold water temperature is less than the set cold water unloading temperature, and the actual operation time is less than the set operation time, that is, the terminal cold water temperature meets the requirements, but in order to prevent excessive cooling, the compressor 10 is prompted to unload. In addition, when the actual cold water temperature is equal to the set cold water loading temperature, or the actual cold water temperature is equal to the set cold water unloading temperature, and the actual operation time is less than the set operation time, the unit is kept in the current operation state for a period of time and then compared again.

[0087] That is, in the partial heat recovery mode, it is possible to first determine whether the actual hot water temperature meets the requirement, and when the actual hot water temperature meets the requirement, it is then determined whether the actual operating time meets the requirement, and when the actual operating time does not meet the requirement, it is determined whether the actual cold water temperature meets the requirement, so as to load or unload the compressor 10. In addition, when the actual hot water temperature does not meet the requirement, it is possible to directly determine whether the actual cold water temperature meets the requirement, so as to load and unload the compressor 10.

[0088] In some specific embodiments, when switching from the cooling mode to the partial heat recovery mode, the openings of the ports A and C are adjusted to increase by a first gear; when switching from the full heat recovery mode to the partial heat recovery mode, the openings of the ports A and C are adjusted to decrease by a second gear. The first gear and the second gear can be between 0.5% and 20%, for example, the first gear and the second gear are both 2%, and of course, can also be 0.5%, 10%, 15% or 20%. The specific adjustment gear can be calculated based on the water temperature difference. Specifically, when switching from the cooling mode to the partial heat recovery mode, the openings of the ports A and C are adjusted to increase by 2%; when switching from the full heat recovery mode to the partial heat recovery mode, the openings of the ports A and C are adjusted to decrease by 2%.

[0089] like Figures 1 to 6 ,and Fig.10As shown, in an optional embodiment, when the four-pipe cooling and heating unit is switched to the partial cold recovery mode, it is necessary to adjust the connection between the port D and the port E, and the port D and the port F of the second three-way valve 62. Therefore, when switching from the heating mode or the full heat recovery mode to the partial cold recovery mode, it is necessary to adjust the opening of the port D and the port E.

[0090] When switching from the heating mode to the partial cold recovery mode, since the ports D and F are connected in the heating mode, but the ports D and E are not connected, the openings of the ports D and E need to be increased to the third level, so that the ports E and F are connected to the port D. The third level is between 0.5% and 20%, such as 0.5%, 2%, 10% or 20%. Specifically, the openings of the ports D and E can be increased by 2%.

[0091] When switching from full heat recovery mode to partial cold recovery mode, since port D is connected to channel E in full heat recovery mode, but port D is not connected to port F, it is necessary to increase the opening of port D and port F (that is, reduce the opening of port D and port E) to ensure that both port E and port F are connected to port D. In partial cold recovery mode, the balanced heat exchanger 40 is used as an evaporator for evaporation and heat absorption; and since the balanced heat exchanger 40 is an air heat exchanger, the refrigerant flowing through the balanced heat exchanger 40 is used for heat exchange with air for heat absorption and evaporation, so the ambient temperature will affect the evaporation pressure of the balanced heat exchanger 40. Therefore, it is necessary to consider the actual ambient temperature of the balanced heat exchanger 40, and then adjust the opening of port D and port E to meet the adjustment of the amount of refrigerant flowing through the balanced heat exchanger 40.

[0092] Exemplarily, when the four-pipe refrigeration and heating unit switches from full heat recovery mode to partial cold recovery mode:

[0093] Get the actual ambient temperature (T 环温测 ) and set the ambient temperature (T 设定环温 ) for comparison;

[0094] When the actual ambient temperature is greater than the set ambient temperature, reduce the opening between port D and port E;

[0095] When the actual ambient temperature is not higher than the set ambient temperature, the opening between port D and port E is increased.

[0096] When the actual ambient temperature is higher than the set ambient temperature, it means that the temperature around the balanced heat exchanger 40 is high, resulting in an increase in the evaporation pressure of the balanced heat exchanger 40. At this time, it is necessary to increase the amount of refrigerant flowing through the balanced heat exchanger 40 to ensure that sufficient refrigerant flows to the balanced heat exchanger 40. Therefore, the opening of the port D and the port E can be reduced to the first opening, so that the port D and the port E and the port F are all connected, and the first opening is greater than the opening of the port D and the port F. In this way, it can be ensured that the balanced heat exchanger 40 and the cold water side heat exchanger 30 have heat exchange capacity to meet the heat exchange requirements of the hot water side heat exchanger 20. Moreover, since it is still necessary to ensure that the refrigerant of the cold water side heat exchanger 30 meets the terminal cold water load, the opening of the port D and the port E cannot be too small. For example, the 100% opening of the port D and the port E can be reduced by 2% (i.e., the fourth gear), so that the first opening is 98%. In addition, because the evaporation pressure of the balancing heat exchanger is too large and greater than the evaporation pressure of the cold water side heat exchanger, the openings of ports D and F need to be smaller than those of ports D and E to achieve a secondary throttling effect.

[0097] The first opening can be between 80% and 99.5%. When the openings of the corresponding ports D and E are 100%, the fourth gear needs to be reduced. The fourth gear is between 0.5% and 20%, such as 0.5%, 2%, 10% or 20%.

[0098] When the actual ambient temperature is not greater than the set ambient temperature, it means that the temperature around the balanced heat exchanger 40 is low and can be fully used for evaporative heat exchange. Therefore, the opening of ports D and E can be reduced to the second opening, and the opening of ports D and F can be made greater than the second opening. At this time, the balanced heat exchanger 40 can be fully utilized for heat exchange, and the cold water side heat exchanger 30 can be maintained without causing the terminal cold water temperature to be too low. For example, the opening of ports D and E can be adjusted to 30%, and the opening of ports D and F reaches 70%. Among them, 30% can also be used as the initial opening when opening. The second opening can be in the range of 5%-50%, for example, it can be 5%, 30%, 45% or 50%.

[0099] In some specific embodiments, the ambient temperature is set to a range value, with an upper limit temperature and a lower limit temperature. The upper limit temperature may be the ambient temperature corresponding to a certain value of the evaporation pressure in the balance heat exchanger 40 being higher than the evaporation pressure in the cold water side heat exchanger 30, and the lower limit temperature may be the ambient temperature corresponding to a certain value of the evaporation pressure in the balance heat exchanger 40 being lower than the evaporation pressure in the cold water side heat exchanger 30. At the same time, when the refrigerant in the four-tube cooling and heating unit is water, the ambient temperature may be set to 10°C when the outlet water temperature is controlled at 7°C.

[0100] During the adjustment process, if the openings of the ports D and E of the second three-way valve 62 are adjusted to 0, the ports D and F of the second three-way valve 62 are fully connected and the four-pipe cooling and heating unit is switched to the heating mode; if the openings of the ports D and E of the second three-way valve 62 are adjusted to 100%, the four-pipe cooling and heating unit is switched to the full heat recovery mode. It is worth noting that at this time, the first three-way valve 61 remains unchanged and is in a state where the ports A and B are connected.

[0101] If the ports D and E, and the ports D and F of the second three-way valve 62 are both connected, the four-pipe cooling and heating unit switches to the partial cold recovery mode. During the operation cycle of the partial cold recovery mode:

[0102] Compare the actual cold water temperature with the set cold water cut-in temperature (T 冷切入 ), when the actual cold water temperature is greater than the set cold water cut-in temperature, the terminal cold water temperature is too high, and the cooling capacity needs to be increased. Therefore, the opening of ports D and E needs to be increased to 100%, so that the four-pipe cooling and heating unit switches from partial cold recovery mode to full heat recovery mode. Among them, the set cold water cut-in temperature refers to the temperature when cold water needs to be added.

[0103] When the evaporation pressure of the cold water side heat exchanger 30 is less than the set evaporation pressure, it is necessary to reduce the opening of ports D and E to reduce the cooling capacity; and when the actual cold water temperature is greater than the set cold water loading temperature, it is necessary to increase the opening of ports D and E to increase the cooling capacity. However, since the evaporation pressure has a higher priority on the cold water side heat exchanger, after the amount of refrigerant flowing through the cold water side heat exchanger 30 is reduced, the actual cold water temperature will be higher than the set cold water cut-in temperature after the partial cold recovery mode has been running for a period of time. At this time, it is necessary to switch the partial cold recovery mode to the full heat recovery mode to ensure the amount of refrigerant flowing through the cold water side heat exchanger 30.

[0104] If the actual cold water temperature is not greater than the set cold water cut-in temperature: obtain the actual pressure on the cold water side and convert the actual pressure on the cold water side (P 冷侧 ) and the cold water side set pressure (i.e. the set evaporation pressure mentioned above, P in the figure 冷设定min) for comparison; when the actual pressure on the cold water side is less than the set pressure on the cold water side, reduce the opening of port D and port E. Among them, the actual pressure on the cold water side refers to the evaporation pressure of the refrigerant in the cold water side heat exchanger 30, and the set pressure on the cold water side is the minimum evaporation pressure of the refrigerant in the cold water side heat exchanger 30. If the evaporation pressure of the cold water side heat exchanger 30 is too small, it is necessary to reduce the flow area between port D and port E to increase the evaporation pressure. It is understandable that there may be risks in long-term operation because the actual pressure on the cold water side is too small. Therefore, in order to ensure the safety and reliability of the four-pipe refrigeration and heat unit, it is necessary to reduce the opening of port D and port E to form secondary throttling on the cold water side heat exchanger to ensure that the evaporation pressure of the refrigerant in the cold water side heat exchanger 30 is within a safe range.

[0105] In some specific embodiments, the openings of the ports D and E can be reduced to a fifth gear, which is between 5% and 25%, for example, 5%, 10%, 20% or 25%.

[0106] When the actual pressure on the cold water side is not less than the set pressure on the cold water side, it means that the evaporation pressure of the cold water side heat exchanger 30 meets the requirements, and the actual cold water temperature and the operating time of the four-pipe refrigeration and heat unit in the partial cold recovery mode can be judged.

[0107] When the actual cold water temperature is greater than the set cold water loading temperature, and the actual running time is greater than the set running time (τ 设定 ), it means that the partial cold recovery mode has been running for a period of time and meets the minimum running time requirement, but the terminal cold water temperature is high, so it is necessary to increase the opening of port D and port E to the third gear (for example, increase by 2%), and reduce the opening of port D and port F, thereby increasing the amount of refrigerant flowing through the cold water side heat exchanger 30 and reducing the amount of refrigerant flowing through the balancing heat exchanger 40; and, such a setting can reduce the evaporation pressure of the cold water side heat exchanger 30, thereby reducing the superheat of the cold water side heat exchanger 30.

[0108] When the actual cold water temperature is lower than the set cold water unloading temperature and the actual operating time is longer than the set operating time, it means that the terminal cold water cooling capacity is sufficient. At this time, the opening of port D and port E can be reduced to the fourth level (for example, it can be reduced by 2%), and the opening of port D and port F can be increased, thereby increasing the refrigerant amount of the balanced heat exchanger 40 so that the heat can be dissipated through the balanced heat exchanger 40.

[0109] When the actual hot water temperature is lower than the set hot water loading temperature, and the actual running time is lower than the set running time, it means that the terminal hot water temperature is low before the running time is reached, and the compressor 10 needs to be loaded. At the same time, when the actual hot water temperature is higher than the set hot water unloading temperature, and the actual running time is lower than the set running time, it means that the hot water temperature of the terminal water-using equipment is too high, and the compressor 10 needs to be unloaded. In addition, when the actual hot water temperature is equal to the set hot water loading temperature or the actual hot water temperature is equal to the set hot water unloading temperature, and the actual running time is lower than the set running time, the unit is kept in the current running state for a period of time and then compared again.

[0110] That is, in the partial cold recovery mode, it is possible to first determine whether the actual cold water temperature meets the requirement, and when the actual cold water temperature meets the requirement, it is then determined whether the actual operating time meets the requirement, and when the actual operating time does not meet the requirement, it is determined whether the actual hot water temperature meets the requirement, so as to load or unload the compressor 10. In addition, when the actual cold water temperature does not meet the requirement, it is possible to directly determine whether the actual hot water temperature meets the requirement, so as to load and unload the compressor 10.

[0111] Among them, the above-mentioned compressor is shut down when it is unloaded to the minimum, and is fully loaded when it is loaded to the maximum.

[0112] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0113] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the patent application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the scope of patent protection of the present application shall be subject to the attached claims.

Claims

1. A four-tube refrigeration and heating unit, characterized in that: The four-tube refrigeration and heating unit includes a compressor, a cold water side heat exchanger, a hot water side heat exchanger and a balance heat exchanger; The compressor has an exhaust port and an air intake port, the exhaust port is provided with a first three-way valve, the air intake port is provided with a second three-way valve, the first three-way valve is connected to one end of the hot water side heat exchanger and one end of the balancing heat exchanger, and the second three-way valve is connected to one end of the cold water side heat exchanger and one end of the balancing heat exchanger; The other end of the cold water side heat exchanger is connected to the other end of the hot water side heat exchanger through a first pipeline, the other end of the cold water side heat exchanger is connected to the other end of the balancing heat exchanger through a second pipeline, and the other end of the hot water side heat exchanger is connected to the other end of the balancing heat exchanger through a third pipeline; The first pipeline and the second pipeline are connected in parallel to form a first parallel point, the first pipeline and the third pipeline are connected in parallel to form a second parallel point, and the first parallel point is located upstream of the second parallel point; The first pipeline is provided with a first one-way valve and a first expansion valve, and the first one-way valve is located upstream of the first parallel point, and the first expansion valve is located downstream of the second parallel point, the second pipeline is provided with a second one-way valve, and the third pipeline is provided with a second expansion valve, the second one-way valve is located upstream of the first parallel point, and the second expansion valve is located downstream of the second parallel point; The four-pipe cooling and heating unit has at least a cooling mode, a heating mode and a full heat recovery mode, and the four-pipe cooling and heating unit is configured to switch the cooling mode, the heating mode and the full heat recovery mode in response to the adjustment states of the first three-way valve and the second three-way valve.

2. The four-tube refrigeration and heat unit according to claim 1, characterized in that: In the cooling mode, the first three-way valve adjusts the exhaust port of the compressor to communicate with the balanced heat exchanger, and the second three-way valve adjusts the suction port of the compressor to communicate with the cold water side heat exchanger, and the compressor, the balanced heat exchanger, the second pipeline, the first expansion valve and the cold water side heat exchanger are connected to form a refrigeration circuit; In the heating mode, the first three-way valve adjusts the exhaust port of the compressor to communicate with the hot water side heat exchanger, the second three-way valve adjusts the suction port of the compressor to communicate with the balancing heat exchanger, and the compressor, the hot water side heat exchanger, the third pipeline, the second expansion valve and the balancing heat exchanger are connected to form a heating circuit; In the full heat recovery mode, the first three-way valve adjusts the exhaust port of the compressor to be connected to the hot water side heat exchanger, and the second three-way valve adjusts the intake port of the compressor to be connected to the cold water side heat exchanger. The compressor, the hot water side heat exchanger, the first pipeline, the first expansion valve and the cold water side heat exchanger are connected to form a full heat recovery loop.

3. The four-tube refrigeration and heat unit according to claim 2, characterized in that: The four-tube refrigeration and heating unit also has a partial heat recovery mode and a partial cold recovery mode; In the partial heat recovery mode, the first three-way valve adjusts the hot water side heat exchanger and the balance heat exchanger to communicate with the exhaust port of the compressor, the second three-way valve adjusts the suction port of the compressor to communicate with the cold water side heat exchanger, and the full heat recovery circuit and the refrigeration circuit are both connected; In the partial cold recovery mode, the first three-way valve adjusts the exhaust port of the compressor to be connected to the hot water side heat exchanger, the second three-way valve adjusts the balancing heat exchanger and the cold water side heat exchanger to be connected to the suction port of the compressor, and the full heat recovery circuit and the heating circuit are both connected.

4. The four-tube refrigeration and heating unit according to claim 1, characterized in that: A fourth pipeline is further provided between the air intake port of the compressor and one end of the hot water side heat exchanger, and a first two-way valve is provided on the fourth pipeline; A fifth pipeline is also provided between the other end of the hot water side heat exchanger and the other end of the balancing heat exchanger. The fifth pipeline is connected in parallel with the third pipeline and has an opposite flow direction. A third expansion valve is provided on the fifth pipeline.

5. The four-tube refrigeration and heating unit according to claim 4 is characterized in that: The four-tube refrigeration and heating unit also has a defrost mode; In the defrost mode, the first three-way valve adjusts the exhaust port of the compressor to be connected to the balancing heat exchanger, the first two-way valve is configured to be in an open state, and the compressor, the balancing heat exchanger, the fifth pipeline, the third expansion valve, the hot water side heat exchanger and the fourth pipeline are connected to form a defrost circuit.

6. The four-tube refrigeration and heat unit according to claim 4, characterized in that: The four-tube refrigeration and heating unit also includes a liquid reservoir, the inlet of the liquid reservoir is connected in parallel with a first branch and a second branch, and the outlet of the liquid reservoir is connected in parallel with a third branch and a fourth branch; The first branch is connected to the hot water side heat exchanger, the third branch is connected to the cold water side heat exchanger, the first one-way valve is arranged on the first branch, the first expansion valve is arranged on the third branch, and the first branch and the third branch are connected to define the first pipeline together; The second branch is connected to the balancing heat exchanger, the second one-way valve is arranged on the second branch, and the second branch is connected to the third branch to jointly define the second pipeline; The fourth branch is connected to the balancing heat exchanger, the second expansion valve is arranged on the fourth branch, and the first branch and the fourth branch are connected to jointly define the third pipeline.

7. The four-tube refrigeration and heat unit according to claim 6, characterized in that: The outlet of the liquid storage device is also connected in parallel with a fifth branch, the fifth branch is connected to the hot water side heat exchanger, the third expansion valve is arranged on the fifth branch, and the second branch is connected to the fifth branch to jointly define the fifth pipeline.

8. The four-tube refrigeration and heating unit according to claim 3 is characterized in that: The cold water side heat exchanger and the hot water side heat exchanger respectively have a delivery pipe for connecting to the terminal water-using equipment, and the delivery pipe is provided with a first temperature sensor; the first three-way valve and the second three-way valve are both configured to adjust the opening degree in response to the detection signal of the first temperature sensor corresponding to each other.

9. The four-tube refrigeration and heating unit according to claim 8, characterized in that: The balanced heat exchanger adopts an air heat exchanger, and the balanced heat exchanger is provided with a second temperature sensor, and the second temperature sensor is used to detect the ambient temperature; When the four-pipe refrigeration and heating unit is switched from the full heat recovery mode to the partial cold recovery mode, the second three-way valve is configured to adjust the opening degree in response to the detection signal of the second temperature sensor.

10. The four-tube refrigeration and heat unit according to claim 9, characterized in that: At least one end of the cold water side heat exchanger facing the compressor is provided with a pressure sensor; When the four-pipe cooling and heating unit is switched to the partial cold recovery mode, the second three-way valve is configured to adjust the opening degree in response to the detection signal of the pressure sensor.

11. The four-tube refrigeration and heat unit according to claim 1, characterized in that: The exhaust port and the suction port of the compressor are respectively connected in parallel with a sixth branch and a seventh branch; At the exhaust port, the corresponding sixth branch and the seventh branch are respectively connected to the hot water side heat exchanger and the balancing heat exchanger, and are respectively provided with a second two-way valve; At the air intake port, the corresponding sixth branch and the seventh branch are respectively connected to the cold water side heat exchanger and the balancing heat exchanger, and are respectively provided with a third two-way valve.

Citation Information

Cited By

  • Heat recovery type heat pump system and control method thereof

    CN119309345A