Automatic driving system of tower crane
Through the tower crane automatic driving system, the central control system, mobile control terminals and hook sensors are used to realize the automatic driving of the tower crane and the avoidance of obstacles, solving the problem of large errors in the traditional tower crane safety sensors and reducing safety Risk and improve operational efficiency.
Patent Information
- Application Number
- CN202420114419.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-17
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-01-17
AI Technical Summary
The traditional safety protection sensor of tower crane equipment is connected to the control system in the form of switches, and cannot be continuously measured, resulting in large errors, large safety hazards, and risks of high-altitude operations.
A tower crane autonomous driving system was designed, including a tower crane central control system, mobile control terminal, handheld microcontroller and hook sensor. Through wireless and network connection, it uses lidar, high-definition camera, and a variety of sensors for real-time use. Data collection and processing to realize autonomous driving and obstacle avoidance, and reduce safety risks.
The tower crane operation has been changed from high altitude operation to ground operation, reducing safety hazards and actively preventing and avoiding safety accidents. The tower crane operation is more stable and improves safety and efficiency.
Smart Images

Figure CN221971091U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of tower crane equipment, and specifically relates to an automatic driving system for a tower crane. Background Art
[0002] Tower cranes are usually operated manually. The tower crane driver is a special equipment operator who works in the tower crane cab and works at high altitudes, which poses safety risks. Since the torque, weight and other safety protection sensors of traditional tower cranes are connected to the tower crane control system in the form of switch quantities, they cannot be measured continuously, resulting in a large error range and great safety hazards. Utility Model Content
[0003] The utility model aims at solving the problems in the prior art and provides an automatic driving system for a tower crane, comprising: a central control system for a tower crane, wherein the central control system for the tower crane is connected with a mobile control terminal, a handheld micro controller, a hook sensor and a tower crane management cloud platform;
[0004] The hook sensor is used to detect obstacles in the hook's running path and send the obstacle information to the tower crane central control system, which processes the information and sends a control signal.
[0005] The mobile control terminal exchanges information with the tower crane central control system through the network to manage the automatic driving of the tower crane;
[0006] The handheld micro controller is connected to the tower crane central control system and mobile control terminal via wireless, and sends hook movement commands to the tower crane main control;
[0007] The tower crane management cloud platform is connected to the tower crane central control system and exchanges information to store and display tower crane operation information.
[0008] Furthermore, the central control system of the tower crane includes a main controller, a control signal processor and various sensors. The main controller includes a power module and a microcontroller, the control signal processor includes a microcontroller and a relay, and each sensor is connected to the main controller through a wire; various signals of the tower crane detected by each sensor are summarized in the main controller, and the main controller sends various control signals to the tower crane.
[0009] Furthermore, the micro-controller is connected to the main controller and the mobile control terminal via wireless, and can send hook movement commands to the main controller. The micro-controller must accept the management of the mobile control terminal. Only when the mobile control terminal authorizes the micro-controller can the micro-controller control the movement of the hook.
[0010] Furthermore, the hook sensor is equipped with a laser radar and a high-definition camera, which are connected to the main control via wireless and exchange information; the hook sensor detects obstacles in the hook's operating path and sends the obstacle information to the main control, so that obstacles can be avoided during automatic operation, thereby ensuring the safety of automatic operation of the tower crane.
[0011] Furthermore, the tower crane management cloud platform adopts a smart construction site management platform system.
[0012] Furthermore, the sensors include surveying and obstacle avoidance sensors, positioning sensors, structure detection sensors, load detection sensors and environment mapping sensors. The surveying and obstacle avoidance sensors include cameras and lidars. The positioning sensors include amplitude sensors, rotation sensors, height sensors and inertial sensors IMU. The structure detection sensors include tilt sensors. The load detection sensors include weight sensors. The environment detection sensors include wind speed sensors. The main controller controls the lidar to detect the direction of travel, and the camera integrates the received data into an image and feeds it back to the control signal processor connected to the main controller. The main controller changes direction to avoid obstacles or perform environment mapping based on the feedback information.
[0013] Furthermore, the mobile control terminal is equipped with a positioning module and a wireless data transmission module to send the location of the loading point and the unloading point to the tower crane and manage the automatic driving of the tower crane.
[0014] Compared with the prior art, the advantages and positive effects of the utility model are:
[0015] The tower crane automatic driving system provided by the utility model can not only enable the tower crane operator to change from high-altitude operation to ground operation, but also change the working environment of the tower crane driver, and at the same time reduce the potential safety hazards to the minimum, and change the safety of the tower crane work from the past passive protection to active prevention to avoid the occurrence of safety accidents. Due to the application of advanced intelligent fuzzy control in the control of the tower crane in the tower crane automatic control system, the tower crane can run more smoothly. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0017] Figure 1 It is a structural schematic diagram of the automatic driving system of a tower crane of the utility model;
[0018] Figure 2A circuit diagram of the microcontroller of the utility model connected with a flash chip and a Darlington array;
[0019] Figure 3 This is a schematic diagram of the circuit connection of the voltage conversion chip of the utility model;
[0020] Figure 4 The utility model is a circuit diagram of the microcontroller connected to the wireless data transmission module. DETAILED DESCRIPTION
[0021] In order to more clearly understand the above-mentioned purpose, features and advantages of the utility model, the utility model is further described below in conjunction with the accompanying drawings and embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.
[0022] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways than those described herein. Therefore, the present invention is not limited to the specific embodiments of the following disclosure.
[0023] Embodiment 1, as Figure 1 to Figure 4 As shown, the present application provides a tower crane automatic driving system, including: a tower crane central control system, a mobile control terminal, a handheld micro controller, a hook sensor and a tower crane management cloud platform; the tower crane central control system includes a main controller, a control signal processor and various sensors, the main controller includes a power module and a micro controller, the control signal processor includes a micro controller and a relay, and each sensor is connected to the main controller by wire; various signals of the tower crane detected by each sensor are summarized to the main controller, and the main controller sends various control signals to the tower crane; mobile control terminal: the mobile control terminal is connected to the main control by wireless, and exchanges information with the central controller through the network. The mobile control terminal is equipped with a positioning module and a wireless data transmission module, which can send the location of the loading point and the drop point to the tower crane. And manage the automatic driving of the tower crane; micro controller: connected to the tower crane main control and the mobile control terminal by wireless, it can send a hook movement command to the tower crane main control, and the micro controller must accept the management of the mobile control terminal. Only when the mobile control terminal authorizes the micro controller can the micro controller control the movement of the hook. The microcontroller is connected to the flash chip, the microcontroller is also connected to the Darlington array, the microcontroller is connected to the wireless data transmission module, and the wireless data transmission module includes an RS485 transceiver chip, a CAN transceiver chip and a wireless communication module. The microcontroller is also connected to the positioning module, the transmitting circuit of the positioning module is connected to the electronic device, and the IN line of the positioning module is connected to the voltage conversion chip. The specific connection circuit diagram is as follows Figure 2-Figure 4 shown.
[0024] The sensors include mapping obstacle avoidance sensors, positioning sensors, structure detection sensors, load detection sensors and environment mapping sensors. The mapping obstacle avoidance sensors include cameras and laser radars. The positioning sensors include amplitude sensors, rotation sensors, height sensors and inertial sensors IMU. The structure detection sensors include tilt sensors. The load detection sensors include weight sensors. The environment detection sensors include wind speed sensors. The main controller controls the laser radar to detect the forward direction. The camera integrates the received data into an image and feeds it back to the control signal processor connected to the main controller. The main controller changes direction to avoid obstacles or perform environment mapping according to the feedback information.
[0025] The amplitude, height and absolute angle data of the current tower crane hook are collected through amplitude sensors, rotation sensors, height sensors and inertial sensors. After processing by the main controller, they are compared with the pre-collected target position data. The human-computer interaction interface issues control instructions to assist in the material lifting operation and ensure positioning accuracy. The inclination sensor is installed on the side of the tower crane. When the inclination angle of the structure connected to the inclination sensor exceeds the limited range, it can be buffered and warned in time to effectively prevent the structure from exceeding the inclination limit angle. The wind speed sensor is used to detect the wind speed to assist the tower crane action. When the wind speed exceeds the set threshold, the tower crane will reduce the speed or stop running when performing the set action and wait for the wind speed to reach the requirement before operating again. The weight sensor is installed at the hook to detect the weight of the item. It can be used for overload detection and mounting detection. It can also prevent the hook from running beyond the set range during operation, which will cause the load to increase and increase the risk of tower crane operation.
[0026] Hook sensor: The hook sensor is equipped with laser radar and high-definition camera, which is connected to the main control via wireless and exchanges information. The hook sensor detects obstacles in the hook's running path and sends the obstacle information to the main control, so that obstacles can be avoided during automatic operation, ensuring the safety of the tower crane's automatic operation.
[0027] The tower crane control cloud platform is a multi-user platform with tower crane monitoring and management capabilities, and has the function of tower crane operation information storage and display. It can realize three-dimensional information display and playback. The tower crane control cloud platform can adopt the existing smart construction site management platform system. The system can realize real-name management, attendance management, safety education management, video surveillance management, salary supervision, logistics management, and various business-based statistical analysis.
[0028] The development of tower crane automatic driving system will generate extensive social and economic benefits, not only improving the safety precautions at construction sites and reducing accidents, but also reducing labor costs.
[0029] The automatic driving system of tower cranes can not only change the working environment of tower crane operators from high-altitude operations to ground operations, but also reduce potential safety hazards to a minimum, and change the safety of tower crane operations from passive protection to active prevention to avoid accidents. In the automatic control system of tower cranes, the application of advanced intelligent fuzzy control in the control of tower cranes makes the operation of tower cranes more stable. The difference between the automatic driving system of tower cranes and traditional tower cranes is that the tower crane driver operates on the tower crane, and the tower crane manager can use the terminal controller to control and manage the tower crane, and one person can manage multiple tower cranes, which can save labor costs.
[0030] The above description is only a preferred embodiment of the present invention and does not limit the present invention in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes and apply it to other fields. However, any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the protection scope of the technical solution of the present invention.
Claims
1. A tower crane automatic driving system, characterized in that: include: The tower crane central control system is connected with the mobile control terminal, handheld micro controller, hook sensor and tower crane management cloud platform; The hook sensor is used to detect obstacles in the hook's running path and send the obstacle information to the tower crane central control system, which processes the information and sends a control signal. The mobile control terminal exchanges information with the tower crane central control system through the network to manage the automatic driving of the tower crane; The handheld micro controller is connected to the tower crane central control system and mobile control terminal via wireless, and sends hook movement commands to the tower crane main control; The tower crane management cloud platform is connected to the tower crane central control system and exchanges information to store and display tower crane operation information.
2. The tower crane automatic driving system according to claim 1, characterized in that: The central control system of the tower crane includes a main controller, a control signal processor and various sensors. The main controller includes a power module and a microcontroller, the control signal processor includes a microcontroller and a relay, and each sensor is connected to the main controller through a wire. Various signals of the tower crane detected by each sensor are summarized in the main controller, and the main controller sends various control signals to the tower crane.
3. The tower crane automatic driving system according to claim 2, characterized in that: The micro-controller is connected to the main controller and the mobile control terminal via wireless, and can send hook movement commands to the main controller. The micro-controller must accept the management of the mobile control terminal. Only when the mobile control terminal authorizes the micro-controller can the micro-controller control the movement of the hook.
4. The automatic driving system for a tower crane according to claim 2, characterized in that: The hook sensor is equipped with a laser radar and a high-definition camera, which is connected to the main control via wireless and exchanges information; the hook sensor detects obstacles in the hook's running path and sends the obstacle information to the main control, so that obstacles can be avoided during automatic operation, thereby ensuring the safety of automatic operation of the tower crane.
5. The tower crane automatic driving system according to claim 2, characterized in that: The tower crane management cloud platform adopts a smart construction site management platform system.
6. The automatic driving system for tower crane according to claim 2, characterized in that: The sensors include mapping obstacle avoidance sensors, positioning sensors, structure detection sensors, load detection sensors and environment mapping sensors. The mapping obstacle avoidance sensors include cameras and laser radars. The positioning sensors include amplitude sensors, rotation sensors, height sensors and inertial sensors IMU. The structure detection sensors include tilt sensors. The load detection sensors include weight sensors. The environment detection sensors include wind speed sensors. The main controller controls the laser radar to detect the forward direction. The camera integrates the received data into an image and feeds it back to the control signal processor connected to the main controller. The main controller changes direction to avoid obstacles or perform environment mapping according to the feedback information.
7. The tower crane automatic driving system according to claim 2, characterized in that: The mobile control terminal is equipped with a positioning module and a wireless data transmission module, which sends the positions of the loading point and the unloading point to the tower crane and manages the automatic driving of the tower crane.