Bridge with bus station
By designing a bridge with bus stops in the rapid bus system, the red light waiting and congestion problems are solved, and the bus gets on and off the bridge is realized, which improves the operation efficiency and visual space, and solves the problem of passengers passing by the road. question.
Patent Information
- Application Number
- CN202322657608.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-28
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-09-28
AI Technical Summary
When setting up a bus stop, the existing rapid bus system failed to effectively solve the problem of congestion caused by waste of road surfaces waiting for red lights, picking up passengers, turning and changing lanes, and passengers need to cross the road when getting on and off the bus, causing long-distance detours. Impacts operational efficiency.
Design a bridge with a bus stop, with a bridge span structure, support frame, guide bridge, waiting area and staircase on the bridge. The support frame is designed with columns and inclined columns. The bridge deck includes reinforcement ribs and a heatable plastic layer, waiting area It has guardrails and awnings, and the stairs can be selected as escalators to enable passengers to get on and off the bus on the bridge, improving visual space and operating efficiency.
The bus is fully carried out on the bus exclusively on the bus overpass, which greatly improves the operation efficiency of the bus system and maximizes the visual environment under the overpass. By heating the bridge deck, the anti-slip and anti-ice of passengers is optimized for passengers and pedestrians. Crossroads pass through.
Smart Images

Figure CN221972064U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to a bridge with a bus station, belonging to the field of transportation. Background Art
[0002] With the increase of urban population and cars, urban traffic problems are becoming increasingly prominent. In many large cities, due to excessive cars, traffic jams often occur, traffic accidents are frequent, and the atmosphere is polluted. Traffic problems have had a serious impact on urban social and economic development. In order to solve traffic problems, some cities have adopted bus rapid transit systems. The bus rapid transit system is a large-capacity, convenient, and fast public transportation method that operates on public transportation dedicated roads, maintains the characteristics of rail transit, and has the flexibility of ordinary buses. There are currently two main ways to build a bus rapid transit system: one is to build a fully enclosed bus rapid transit lane. The other is to mark out a bus rapid transit lane on an existing road. These two methods do not solve the problem of wasted road surface waiting at red lights and mixed traffic jams with social vehicles when picking up passengers and turning and changing lanes.
[0003] The applicant proposed a simple bridge in Chinese patent 201910473417.2. The construction cost of this bridge is low, and the special flyover is built entirely with standard parts. Each component can be prefabricated for rapid construction or disassembly. The above-mentioned technical problems are solved.
[0004] Since many bus stops in the public transportation system are located at intersections, if the bus stops can be directly set up on simple bridges, passengers can get on and off the bus completely on the dedicated bus overpass, and avoid long detours caused by passengers crossing the road when getting on and off the bus. This will greatly improve the operating efficiency of the public transportation system.
[0005] In addition, in order to improve the visual space under the simple bridge of the original patent that is affected by the columns, the applicant proposed an improved bridge structure with a bus stop in this application. Utility Model Content
[0006] The purpose of the utility model is to provide a bridge with a bus stop to solve the above problems.
[0007] A bridge with a bus stop, comprising a bridge span structure, both ends of which are connected to support frames respectively; each support frame is connected to an approach bridge, and the bottom of the approach bridge is connected to a road;
[0008] The bridge span structure comprises two parallel supporting beams, which are fixed on the supporting frame; a bridge deck is laid between the supporting beams, and one end of the bridge deck extends to the outside of the inner supporting beam to form an extension;
[0009] The portion of the bridge deck between the two supporting beams forms the bridge deck, and the extended portion forms a waiting area;
[0010] The approach bridge comprises two approach bridge support beams arranged in parallel, the approach bridge support beams are used to support the approach bridge deck, and the uppermost ends of the approach bridge support beams are fixed on the support frames.
[0011] Optionally, the waiting area is provided with stairs connected to the ground.
[0012] Optionally, the staircase is an escalator.
[0013] Optionally, the bridge span structure and the waiting area are both provided with guardrails, and the waiting area is provided with a sunshade.
[0014] Optionally, the bridge with the bus station has two or more approach bridges; each support frame connects one approach bridge and two bridge span structures; each support frame includes two upright columns and one inclined column; a support column is provided in the middle and lower part of the inclined column to support the inclined column;
[0015] Each upright column supports a supporting crossbeam and a bridge approach supporting beam intersecting on the adjacent side respectively; the inclined columns support the two intersecting supporting crossbeams.
[0016] Optionally, the inclined column and the two upright columns are connected to each other through connecting beams to form a triangular structure.
[0017] Optionally, the middle part of the stairs includes a platform, and the escalator side where the platform is connected to the ground is connected to the ground through platform pillars; the escalator side where the platform is connected to the waiting area is connected to the supporting beam through connecting columns to ensure that the platform is sturdy and the escalator is installed.
[0018] Optionally, the bottom of the bridge deck is provided with reinforcing ribs. By providing the reinforcing ribs, the thickness and weight of the bridge deck can be reduced while ensuring the strength of the bridge deck.
[0019] Optionally, the bridge deck comprises a hard portion and a heatable plastic layer disposed on the hard portion.
[0020] Optionally, the bottom of the supporting frame of the bridge is fixed to the ground by bolts; and the bolt holes for bolt fixing at the bottom of at least one supporting frame of the bridge are long holes.
[0021] The beneficial effects of this application include:
[0022] 1. Setting up a dedicated BRT station on a dedicated bus overpass, so that passengers can get on and off the bus completely on the dedicated bus overpass, can greatly improve the operating efficiency of the bus system.
[0023] 2. The support frame adopts a design of vertical columns and inclined columns, which maximizes the visual environment under the overpass.
[0024] 3. The entrance of the stairs is set below the approach bridge. Passengers walk along the zebra crossing on the road to the entrance of the stairs and enter the rear vehicle area along the stairs. This allows passengers and pedestrians to share the pedestrian zebra crossing at the intersection. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 This is a schematic diagram of a four-way interchange;
[0026] Figure 2 This is a schematic diagram of the connection between beams and columns;
[0027] Figure 3 It is the side view of the connection between beam and column;
[0028] Figure 4 This is a schematic diagram of the stairs;
[0029] Figure 5 This is the bridge deck structure diagram;
[0030] Figure 6 Side view of the installation plate for the bridge deck;
[0031] Figure 7 This is a schematic diagram of the long hole at the bottom of the column;
[0032] Figure 8 This is a schematic diagram of a three-way bridge;
[0033] Fig. 9 This is a schematic diagram of the overpass. DETAILED DESCRIPTION
[0034] The present application is described in detail below with reference to embodiments, but the present application is not limited to these embodiments.
[0035] A bridge with a bus stop as shown in the attached drawings comprises a bridge span structure 1, both ends of which are connected to support frames; each support frame is connected to an approach bridge 2, and the bottom of the approach bridge is connected to the road;
[0036] like Figure 5 and Figure 6 As shown, the bridge span structure comprises two parallel supporting beams 11 and 12, which are fixed on a supporting frame; a bridge deck 14 is laid between the supporting beams 11, and one end of the bridge deck extends to the outside of the inner supporting beam to form an extension;
[0037] The bridge deck between the two supporting beams forms the bridge deck, and the bridge deck at the extended portion forms a waiting area 3; there is a staircase 4 on the waiting area 3. By providing the reinforcing ribs 141, the thickness and weight of the bridge deck can be reduced while ensuring the strength of the bridge deck.
[0038] The bridge deck 14 includes a steel hard part at the bottom and a plastic part 142 arranged on the hard part. A heating wire can be embedded in the plastic part to achieve heating of the bridge deck, and the plastic bridge deck can play a role of anti-skid and anti-icing. In order to facilitate installation, the bridge deck 14 can be set as a standard part with uniform length, which is convenient for production and use. In this embodiment, the bridge deck 14 is set as a standard part with a length of 9m and a width of 1m (the bridge deck part is 7m long and the waiting area is 2m long).
[0039] The approach bridge comprises two parallel approach bridge support beams 21, which are used to support the approach bridge deck, and the uppermost ends of the approach bridge support beams are fixed on the support frame. In this embodiment, the paving structure of the approach bridge deck is the same as the road surface of the bridge span structure.
[0040] like Figure 1 and Figure 2 As shown, each support frame connects an approach bridge and two bridge span structures; each support frame includes two upright columns 5 and an inclined column 6; an inclined beam support column 61 is provided at the bottom of the inclined column 6.
[0041] Each upright column 5 supports a supporting beam 11 and a bridge approach supporting beam 21 intersecting on the adjacent side, and the inclined column 6 supports the two intersecting supporting beams 11. The inclined column 6 can prevent the sight of the vehicle from being affected after it passes under the bridge.
[0042] In addition, in order to ensure the stability of the inclined columns, the inclined columns 6 of each support frame and the two upright columns 5 are fixed to each other through a connecting beam 13 to form a triangular stable structure. The upright columns 5, the inclined columns 6, the approach bridge support beam 21, the bridge deck beams 11, 12, and the connecting beam 13 are all made of I-beams.
[0043] The waiting area is provided with stairs 7, and the stairs 7 are connected to the ground. The middle part of the stairs includes a platform 71, and the side of the escalator connected to the ground is connected to the ground through a platform pillar; the side of the escalator connecting the platform to the waiting area is connected to the supporting beam through a connecting column. The entrance of the stairs is located outside the crosswalk at the intersection. The height of the platform is about 2.5m, and the zebra crossing is below the platform to facilitate the passage of pedestrians getting on and off the bus and crossing the road. The entrance of the stairs is set at the support frame below the approach bridge. Passengers getting on and off the bus walk along the zebra crossing on the road to the entrance of the stairs and enter the rear vehicle area along the stairs. Bus stops and ground signs can be installed on the platform to guide passengers to board the bus.
[0044] As a further improvement, the staircase is an escalator.
[0045] like Figure 5 As shown, the bridge span structure and the waiting area are both provided with guardrails 15, and the waiting area is provided with a sunshade 31.
[0046] All the above-mentioned components are connected by bolts, which makes them easy to install and removable.
[0047] All the above beams and pillars are made of steel, and the bottom of the bridge support frame is fixed to the ground by bolts. In order to prevent thermal expansion and contraction, the bolt holes for bolt fixing at the bottom of at least one support frame of the bridge are long holes. Figure 7 The garden screw hole 51 of the left figure, and the long screw hole 52 of the right figure are adopted for the support frame of the left and right road intersections. In this way, certain deformation can be tolerated during thermal expansion and contraction.
[0048] If the bus routes at the intersection only involve 3 or 2 directions, there is no need to set up a four-way overpass. Figure 8 A three-way interchange or Fig. 9 The overpass in the middle is sufficient. Each approach bridge and bridge deck structure is set up with two lanes up and down, and the waiting area is about 2m wide. The bridge deck of the overpass is set 2m wider than the approach bridge to accommodate the space required for the waiting area and escalator.
[0049] The above are only a few embodiments of the present application and do not constitute any form of limitation to the present application. Although the present application is disclosed as above with preferred embodiments, it is not intended to limit the present application. Any technician familiar with the profession, without departing from the scope of the technical solution of the present application, using the technical content disclosed above to make slight changes or modifications are equivalent to equivalent implementation cases and fall within the scope of the technical solution.
Claims
1. A bridge with a bus stop, comprising a bridge span structure, It is characterized in that The two ends of the bridge span structure are respectively connected to support frames; each support frame is connected to an approach bridge, and the bottom of the approach bridge is connected to the road; The bridge span structure comprises two parallel supporting beams, which are fixed on the supporting frame; a bridge deck is laid between the supporting beams, and one end of the bridge deck extends to the outside of the inner supporting beam to form an extension; The portion of the bridge deck between the two supporting beams forms the bridge deck, and the extended portion forms a waiting area; The approach bridge comprises two approach bridge support beams arranged in parallel, the approach bridge support beams are used to support the approach bridge deck, and the uppermost ends of the approach bridge support beams are fixed on the support frames.
2. The bridge with a bus stop according to claim 1, It is characterized in that The waiting area is provided with stairs, and the stairs are connected to the ground.
3. The bridge with a bus stop according to claim 2, It is characterized in that The staircase is an escalator.
4. The bridge with a bus stop according to claim 1, It is characterized in that The bridge span structure and the waiting area are both provided with guardrails, and the waiting area is provided with a sunshade.
5. The bridge with a bus stop according to claim 1, It is characterized in that The bridge with a bus stop has two or more approach bridges; each support frame connects an approach bridge and two bridge span structures; each support frame includes two upright columns and one inclined column; a support column is provided in the middle and lower part of the inclined column to support the inclined column; each upright column supports a supporting beam and an approach bridge support beam intersecting on the adjacent side; the inclined column supports two intersecting supporting beams.
6. The bridge with a bus stop according to claim 5, It is characterized in that The inclined columns and the two upright columns are connected to each other through connecting beams to form a triangular structure.
7. The bridge with a bus stop according to claim 2, It is characterized in that The middle part of the staircase includes a platform, and the escalator side connected to the platform is connected to the ground through the platform pillar; the escalator side connected to the platform and the waiting area is connected to the supporting beam through a connecting column to ensure that the platform is solid and the escalator is installed.
8. The bridge with a bus stop according to claim 1, It is characterized in that The bottom of the bridge deck is provided with reinforcing ribs.
9. The bridge with a bus stop according to claim 1, It is characterized in that The bridge deck comprises a hard part and a heatable plastic layer arranged on the hard part.
10. The bridge with a bus stop according to claim 1, It is characterized in that The bottom of the support frame of the bridge is fixed to the ground by bolts; the bolt holes for bolt fixing at the bottom of at least one support frame of the bridge are long holes.