Auxiliary device for piling construction
By designing pile driving construction auxiliary devices, using parts such as ground anchor insertion rods and hydraulic cylinders, the problems of pile body inclination and safety hazards are solved, and the stable vertical placement and efficient construction of pile body are achieved.
Patent Information
- Application Number
- CN202323507814.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-21
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-12-21
AI Technical Summary
In the existing pile driving construction methods, the pile body is prone to tilt, resulting in unstable pile laying and safety hazards, affecting construction efficiency and safety.
A pile construction auxiliary device is designed, including a first placement ring, a second placement ring, a variable diameter connecting pipe, a correction component and a guide wheel assembly. Through components such as ground anchor insertion rod and hydraulic cylinder, the pile body is ensured during the placement process. Stay vertical and stable, reducing manual intervention and safety risks.
It improves the stability and safety of pile body placement, reduces manual intervention, reduces construction risks, and improves construction efficiency.
Smart Images

Figure CN221972380U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of piling, in particular to a piling construction auxiliary device. Background Art
[0002] As we all know, the foundation of a building must be reinforced before it can support the building. Pile driving is a process of planting piles in a building foundation. It is generally divided into prefabricated piles and cast-in-place piles. Among them, prefabricated piles are piles made in advance. Prefabricated piles need to be inspected on site before piling. After the inspection, if the stratum is soft, it is necessary to drill holes first. Of course, if the stratum is different during the construction of the prefabricated piles, it is also necessary to drill or blast holes before placing the piles. In this case, the prefabricated piles need to be inserted into the holes pre-opened in the foundation during the pile placement construction. When piling, it is necessary to ensure that the pile body is vertically inserted into the hole to ensure the stability of the pile body. At present, this piling construction method is generally to lift the pile body by a crane, and then manually push the bottom of the pile body to align with the hole, and slowly release it into the hole to achieve the piling construction operation of the pile body. However, in this operation method, the pile body is firstly easy to tilt, resulting in a collision between the pile body and the hole, affecting the pile placement operation, and constantly manually straightening the pile body, there are safety hazards, resulting in poor reliability of this pile placement method. In order to solve the above problems, a piling construction auxiliary device is proposed. Utility Model Content
[0003] 1. Technical issues to be resolved
[0004] In view of the deficiencies of the prior art, the utility model provides a piling construction auxiliary device to solve the problems of poor stability and potential safety hazards of the prior art pile placement mentioned in the background technology.
[0005] (II) Technical solution
[0006] In order to achieve the above-mentioned purpose, the utility model provides the following technical solutions: a piling construction auxiliary device, comprising:
[0007] A first placement circle, wherein a plurality of ground anchor rods are arranged on the bottom circumference of the first placement circle;
[0008] a second placement ring, wherein the second placement ring is located above the first placement ring, and an inner diameter of the second placement ring is greater than an inner diameter of the first placement ring;
[0009] A reducing connecting pipe, the reducing connecting pipe being connected between the first placement ring and the second placement ring;
[0010] A correction component, which is arranged on the variable diameter connecting pipe and is used to correct the pile body;
[0011] A guide wheel assembly is installed on the circumferential inner wall of the first placement ring, the circumferential inner wall of the second placement ring and the output end of the correction assembly.
[0012] Further, the correction component includes:
[0013] A plurality of hydraulic cylinders, wherein the hydraulic cylinders are circumferentially mounted on the circumferential outer wall of the variable diameter connecting pipe;
[0014] The output end of the hydraulic cylinder slides and penetrates the outer wall of the variable diameter connecting pipe and points to the inside of the variable diameter connecting pipe.
[0015] Furthermore, the guide wheel assembly comprises:
[0016] A wheel frame, the wheel frame being mounted on the circumferential inner wall of the first placement ring, the circumferential inner wall of the second placement ring and the output end of the correction component;
[0017] A wheel axle is rotatably mounted on the wheel frame.
[0018] Furthermore, barbs are provided on the outer wall of the ground anchor rod.
[0019] Furthermore, four level rulers are installed on the circumference of the outer wall of the variable diameter connecting pipe.
[0020] Furthermore, a plurality of guide wheel assemblies are also arranged on the inner wall of the variable diameter connecting pipe.
[0021] (III) Beneficial effects
[0022] Compared with the prior art, the utility model provides a piling construction auxiliary device, which has the following beneficial effects:
[0023] The utility model inserts a plurality of ground anchor rods into the ground, stabilizes the first placement circle and installs it vertically with the hole, then lifts the pile body by a crane, and first inserts the bottom of the pile body into the second placement circle. Since the inner diameter of the second placement circle is relatively large, it is convenient for the pile body to be inserted, and then slowly inserts it into the reducer connecting pipe under the action of the guide wheel assembly. The reducer connecting pipe gradually becomes smaller, and under the action of the correction assembly, the pile body is corrected to the center position of the first placement circle, and then continuously guided downward and input into the preset hole. Compared with the prior art, human intervention is reduced, risk factors are reduced, and the placement stability of the pile body is improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 This is a schematic diagram of the structure of Embodiment 1 of the present application;
[0025] Figure 2 This is a schematic diagram of the internal structure of Example 1 in this application;
[0026] Figure 3 This is a schematic diagram of the structure of Example 2 in this application;
[0027] Figure 4 This is a schematic diagram of the internal structure of Example 2 in this application.
[0028] In the figure: 1. first placement circle; 2. second placement circle; 3. reducer connecting pipe; 4. hydraulic cylinder; 5. wheel frame; 6. wheel axle; 7. level; 8. iron block; 9. anchor rod; 10. barb. DETAILED DESCRIPTION
[0029] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0030] For example, see Figures 1 to 4 , a pile driving construction auxiliary device, comprising: a first placement ring 1, a second placement ring 2, a reducing connecting pipe 3, a correction component and a guide wheel component, a bottom circumference of the first placement ring 1 is provided with a plurality of ground anchor rods 9, the second placement ring 2 is located above the first placement ring 1, and the inner diameter of the second placement ring 2 is greater than the inner diameter of the first placement ring 1, the reducing connecting pipe 3 is connected between the first placement ring 1 and the second placement ring 2, the correction component is arranged on the reducing connecting pipe 3, and is used to correct the pile body, the circumferential inner wall of the first placement ring 1, the circumferential inner wall of the second placement ring 2 and the output end of the correction component are all installed with a guide wheel assembly, a plurality of ground anchor rods 9 are inserted into the ground, the first placement ring 1 is stably installed and placed vertically with the hole, and then the pile body is hoisted by a crane, the bottom of the pile body is first inserted into the second placement ring 2, and due to the second placement The inner diameter of the circle 2 is relatively large, which is convenient for the insertion of the pile body. Then, under the action of the guide wheel assembly, it is slowly inserted into the reducing connecting pipe 3. Through the gradual reduction of the reducing connecting pipe 3, it is corrected to the center position of the first placement circle 1 under the action of the correction assembly, and then it is continuously guided downward and input into the preset hole. Compared with the prior art, it reduces human intervention, reduces dangerous factors, and improves the placement stability of the pile body. Barbs 10 are provided on the outer wall of the anchor rod 9. The barbs 10 improve the stability of the anchor rod 9 after it is inserted into the ground, and the length of the anchor rod 9 is not limited. When in use, it is sufficient to ensure that the overall construction auxiliary device is stably installed. In order to facilitate the insertion of the anchor rod 9 into the ground, an iron block 8 is welded on the outer wall of the first placement circle. By hitting with a hammer, it is convenient to insert the anchor rod 9 into the ground.
[0031] Correspondingly, the correction component includes: multiple hydraulic cylinders 4, which are circumferentially installed on the circumferential outer wall of the reducer connecting pipe 3. The output end of the hydraulic cylinder 4 slides and penetrates the outer wall of the reducer connecting pipe 3 and points to the inside of the reducer connecting pipe 3. The hydraulic cylinder 4 can push the pile body to the center position of the first prevention circle, and the purpose of using the hydraulic cylinder 4 is to ensure the pushing force on the pile body. When in use, one side of it will be equipped with a corresponding hydraulic pump station system to ensure the use of the hydraulic cylinder 4.
[0032] Furthermore, the guide wheel assembly includes: a wheel frame 5 and a wheel axle 6. The wheel frame 5 is installed on the circumferential inner wall of the first placement circle 1, the circumferential inner wall of the second placement circle 2 and the output end of the correction assembly. The wheel axle 6 is rotatably mounted on the wheel frame 5. The rotation effect of the wheel axle 6 is ensured by the wheel frame 5 and the wheel axle 6. In addition, a plurality of guide wheel assemblies are also arranged on the inner wall of the variable diameter connecting pipe 3 to prevent the pile body from directly hitting the inner wall of the variable diameter connecting pipe 3, thereby improving the rural guiding effect on the pile body.
[0033] In the second embodiment, four level rulers 7 are installed on the circumference of the outer wall of the variable diameter connecting pipe 3 to observe and ensure the placement level of the pile driving construction auxiliary device (so as to determine the verticality with the already drilled hole), and then the pile body is lifted by a crane (because the pile body is tied by a special lifting belt, the pile body is basically in an inclined state after lifting), so that the bottom of the pile body is inserted into the second placement circle 2, and the pile body is guided downward by multiple wheel axles 6. After the pile body passes through the correction component, the hydraulic cylinder 4 is turned on to extend the hydraulic cylinder 4 toward the central axis position of the variable diameter connecting pipe 3, and the pile body is pushed to the axial position of the variable diameter connecting pipe 3, and then the pile body is slowly transported downward by the crane. Among them, the "inner diameter" formed by the multiple guide wheels in the first placement circle 1 is just suitable for the outer diameter of the corresponding pile body. Because prefabricated pile bodies are generally prefabricated in a batch of the same size, in this case, a corresponding pile driving construction auxiliary device can be made. If the prefabricated pile bodies are of many sizes, a set of correction components can also be installed on the upper side of the first placement circle 1. Please refer to Figure 3 and Figure 4 , ensure that the two correcting components cooperate with each other to correct the pile body and transport it downward into the hole.
[0034] To sum up, when using the piling construction auxiliary device, first align the whole with the axis of the pre-opened hole, then hammer the anchor rod 9 into the ground outside the hole, and observe the installation level of the auxiliary device through the level ruler 7. After stable and horizontal installation, lift the corresponding pile body by the crane, slowly release the pile body downward from the second placement circle 2, and cooperate with the correction component to correct it to ensure that the pile body is vertically inserted into the hole.
[0035] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A piling construction auxiliary device, characterized in that: include: A first placement ring (1), wherein a plurality of ground anchor rods (9) are arranged on the bottom circumference of the first placement ring (1); A second placement ring (2), the second placement ring (2) is located above the first placement ring (1), and the inner diameter of the second placement ring (2) is greater than the inner diameter of the first placement ring (1); A reducing connecting pipe (3), wherein the reducing connecting pipe (3) is connected between the first placement ring (1) and the second placement ring (2); A correction component, which is arranged on the variable diameter connecting pipe (3) and is used to correct the pile body; A guide wheel assembly is installed on the circumferential inner wall of the first placement ring (1), the circumferential inner wall of the second placement ring (2) and the output end of the correction assembly.
2. A piling construction auxiliary device according to claim 1, characterized in that: The correction component includes: A plurality of hydraulic cylinders (4), wherein the hydraulic cylinders (4) are circumferentially mounted on the circumferential outer wall of the variable diameter connecting pipe (3); The output end of the hydraulic cylinder (4) slides and penetrates the outer wall of the reducing connecting pipe (3) and points to the inside of the reducing connecting pipe (3).
3. A piling construction auxiliary device according to claim 2, characterized in that: The guide wheel assembly comprises: A wheel frame (5), the wheel frame (5) being mounted on the circumferential inner wall of the first placement ring (1), the circumferential inner wall of the second placement ring (2) and the output end of the correction component; A wheel axle (6) is rotatably mounted on the wheel frame (5).
4. A piling construction auxiliary device according to claim 3, characterized in that: The outer wall of the ground anchor rod (9) is provided with barbs (10).
5. A piling construction auxiliary device according to claim 4, characterized in that: Four level rulers (7) are installed on the circumference of the outer wall of the variable diameter connecting pipe (3).
6. A piling construction auxiliary device according to claim 5, characterized in that: A plurality of guide wheel assemblies are also arranged on the inner wall of the variable diameter connecting pipe (3).