Civil engineering foundation pit excavating device
By designing the ejection mechanism and utilizing a stepper motor to drive the lead screw and scraper structure, the civil engineering foundation pit excavation device achieves efficient soil ejection, solving the problem of low efficiency in existing devices and improving convenience and efficiency.
Patent Information
- Application Number
- CN202322953889.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-31
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-10-31
AI Technical Summary
Existing civil engineering foundation pit excavation equipment is inefficient when dumping soil, and cannot quickly push the soil out of the excavation bucket in one go, resulting in poor equipment convenience.
The ejection mechanism includes a stepper motor, a lead screw, a moving block, a guide rod, a push plate, and a scraper. The stepper motor drives the lead screw to rotate, causing the moving block to engage with the lead screw thread. This drives the guide rod to slide along the inner wall of the excavation bucket, and the push plate moves accordingly to eject the soil. The scraper then removes the sticky soil, achieving a one-time ejection.
It improves the efficiency of soil ejection, reduces the time required for flipping and pouring out, enhances the convenience of the device, and prevents soil accumulation.
Smart Images

Figure CN221972524U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of civil construction foundation pits, in particular to a civil construction foundation pit excavation device. Background Art
[0002] Civil engineering is a project, and civil engineering refers to the planning, construction and maintenance of all infrastructure related to water, soil and culture. Current civil engineering projects include housing, roads, water services, canal services, flood control projects and transportation. In the process of digging foundation pits for civil engineering, in order to avoid the low efficiency of manual excavation, it is very necessary to use excavation equipment to dig the foundation pits;
[0003] The above-mentioned existing technical solutions have the following defects: the existing devices have the defect that it is not convenient to quickly push out the soil when in use. When pouring out the soil, the traditional excavating device generally turns over and exports it gradually, which not only increases the pouring time, but also cannot quickly push out the soil in the excavating bucket directly at one time, resulting in a decrease in the efficiency of exporting the soil, thereby reducing the convenience of the device. Utility Model Content
[0005] Technical issues to be solved
[0006] The purpose of the utility model is to provide a civil engineering foundation pit excavation device to solve the problems raised in the above-mentioned background technology. Utility Model Content
[0007] In order to solve the above technical problems, the utility model provides the following technical solutions: a civil engineering foundation pit excavation device, comprising a mechanical arm, an excavation bucket and bucket teeth, the bottom end of the mechanical arm is hinged with a mounting seat, and the bottom end of the mounting seat is fixed with a connecting block, the bottom end of the connecting block is fixed with an excavation bucket, and one side of the excavation bucket is provided with an ejection mechanism, a replacement structure is provided inside one side of the excavation bucket, and one side of the replacement structure is provided with bucket teeth, the ejection mechanism comprises a stepper motor, a screw rod, a moving block, a protective shell, a guide rod, a push plate and a scraper, the protective shell is installed at the top of one side of the excavation bucket, a stepper motor is installed on one side of the protective shell, and a screw rod is installed on one side of the stepper motor, the outer side of the screw rod is threadedly connected with a moving block, and guide rods are fixed at both ends of one side of the moving block, a push plate is fixed on one side of the guide rod, and a scraper is fixed on the top of the push plate.
[0008] The civil engineering foundation pit excavation device using the present technical solution starts the stepper motor to drive the screw to rotate in the forward direction, and then the moving block engages with the rotating screw thread to drive the two sets of guide rods to slide leftward along the inner wall of the excavation bucket for guidance, and then the push plate moves leftward along with the guide rod to push out the soil in the excavation bucket all at once, reducing the time of the flipping and pouring action and improving the efficiency of the export. At the same time, the four sets of scrapers in contact with the inner wall of the excavation bucket move with the push plate to facilitate the scraping of the soil adhering to the inner wall of the excavation bucket and export it together, thereby reducing the accumulation of soil inside the excavation bucket.
[0009] Preferably, the end of the screw rod away from the stepper motor is connected to the bearing on the excavator bucket, and the left end of the screw rod is connected to the bearing, so as to ensure that the screw rod rotates with the stepper motor, and the guide rods are symmetrically distributed on one side of the moving block. The symmetrically distributed guide rods ensure the stability of the moving block and prevent shaking.
[0010] Preferably, an external thread is provided on the outer wall of the screw rod, and an internal thread matching the external thread is provided on the inner wall of the moving block, so that the screw rod rotates with the rotation of the stepper motor, making it convenient for the moving block to engage with the rotating screw rod thread to drive the guide rod to slide along the inner wall of the excavation bucket for guidance.
[0011] Preferably, the push plate forms a sliding structure with the excavation bucket through a guide rod, so that the guide rod slides along the inner wall of the excavation bucket, thereby driving the push plate to move. The scraper blades are provided in four groups, so that the four groups of scraper blades are respectively in contact with the upper, lower, left and right inner walls of the excavation bucket, thereby scraping off the soil adhering to the inner wall of the excavation bucket.
[0012] Preferably, the replacement structure includes a positioning rod, a fixing rod, a fixing pin and a slot, wherein the fixing rod is fixed to one side of the bucket tooth, a slot is provided inside the fixing rod, and a positioning rod is inserted inside the slot, and a fixing pin is inserted inside the bottom end of the fixing rod. The fixing pin is rotated to gradually engage with the thread of the excavation bucket and leave the fixing rod, and then the bucket tooth is pulled to drive the fixing rod to leave the interior of the excavation bucket for separate disassembly, and then a new bucket tooth is taken to drive the fixing rod to be inserted into the excavation bucket, and at the same time, the positioning rod is aligned and inserted into the slot to strengthen the positioning of the fixing rod, and then the fixing pin is taken and inserted into the screw hole of the excavation bucket, and then the fixing pin is rotated in the opposite direction to gradually enter the fixing rod and tighten it to clamp and fix the fixing rod in the excavation bucket, thereby achieving the effect of fixing the replaced bucket tooth.
[0013] Preferably, an external thread is provided on the outer wall of the fixing pin, and an internal thread matching the external thread is provided inside the excavating bucket, so that the fixing pin can flexibly leave or enter the interior of the fixing rod by engaging with the excavating bucket thread, which is convenient for disassembly or fixation.
[0014] Preferably, the diameter of the positioning rod is smaller than the diameter of the slot, so that the positioning rod can be inserted into the slot, which is convenient for enhancing the positioning effect of the fixing rod and preventing shaking. The fixing pin passes through the excavation bucket and enters the fixing rod, so that the fixing pin passes through the excavation bucket and enters the fixing rod, which is convenient for clamping and fixing the fixing rod.
[0015] Beneficial Effects
[0016] Compared with the prior art, the utility model has the following beneficial effects: the civil construction foundation pit excavation device has a reasonable structure and has the following advantages:
[0017] (1) By starting the stepper motor to drive the screw to rotate in the forward direction, the moving block is then engaged with the rotating screw thread to drive the guide rod to slide to the left along the inner wall of the excavation bucket to guide the moving block, and then the push plate moves to the left along with the guide rod to push out the soil in the excavation bucket at one time. At the same time, the four groups of scrapers scrape off the soil adhering to the inner wall of the excavation bucket and guide it together with the movement of the push plate, thereby reducing the accumulation of soil inside the excavation bucket, thereby realizing the easy-to-push function of the device, improving the convenience of the device, reducing the time of the flipping and pouring action, and improving the efficiency of pushing out the soil;
[0018] (2) The fixing pin is rotated to engage with the thread and leave the fixing rod. The damaged bucket tooth is then pulled to drive the fixing rod out of the bucket for quick disassembly. A new bucket tooth is then taken to drive the fixing rod and insert it into the bucket. The positioning rod is inserted into the slot to position the fixing rod. The fixing pin is taken to insert into the bucket and rotated in the opposite direction. The fixing pin enters the fixing rod and is tightened to lock it in place, thereby fixing the replaced bucket tooth. This realizes the individual replacement function of the device, improves the functionality of the device, and facilitates individual replacement of damaged bucket teeth to ensure the excavation effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0020] Figure 1 It is a front view cross-sectional structural schematic diagram of the utility model;
[0021] Figure 2 This is a front view structural schematic diagram of the utility model;
[0022] Figure 3 This is a schematic diagram of the front cross-sectional structure of the ejection mechanism of the utility model;
[0023] Figure 4 For the utility model Figure 1 Schematic diagram of the enlarged structure of the local section at point A in the middle.
[0024] Explanation of the reference numerals in the figure: 1. Robotic arm; 2. Mounting seat; 3. Ejection mechanism; 301. Stepping motor; 302. Screw rod; 303. Moving block; 304. Protective shell; 305. Guide rod; 306. Push plate; 307. Scraper; 4. Digging bucket; 5. Replacement structure; 501. Positioning rod; 502. Fixing rod; 503. Fixing pin; 504. Slot; 6. Bucket tooth; 7. Connecting block. DETAILED DESCRIPTION
[0025] In order to make the purpose, technical solution and advantages of the embodiment of the utility model clearer, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiment of the utility model. Obviously, the described embodiment is a part of the embodiment of the utility model, not all the embodiments. Based on the embodiment of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0026] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0027] Embodiment 1
[0028] See also Figure 1-4The utility model provides a civil engineering foundation pit excavation device, including a mechanical arm 1, an excavating bucket 4 and a bucket tooth 6. The bottom end of the mechanical arm 1 is hinged with a mounting seat 2, and a connecting block 7 is fixed to the bottom end of the mounting seat 2. The excavating bucket 4 is fixed to the bottom end of the connecting block 7, and a push-out mechanism 3 is provided on one side of the excavating bucket 4. A replacement structure 5 is provided inside one side of the excavating bucket 4, and a bucket tooth 6 is provided on one side of the replacement structure 5. The push-out mechanism 3 includes a stepping motor 301, a screw rod 302, a moving block 303, a protective shell 304, a guide rod 305, a push plate 306 and a scraper 307. The protective shell 304 is installed at the top of one side of the excavating bucket 4, and a stepping motor 301 is installed on one side of the protective shell 304. A screw rod 302 is installed on one side of the stepper motor 301, and the outer side of the screw rod 302 is threadedly connected to a moving block 303, and guide rods 305 are fixed at both ends of one side of the moving block 303, a push plate 306 is fixed on one side of the guide rod 305, and a scraper 307 is fixed on the top of the push plate 306, and the end of the screw rod 302 away from the stepper motor 301 is connected to the bearing on the excavator bucket 4, and the guide rods 305 are symmetrically distributed on one side of the moving block 303, an external thread is provided on the outer wall of the screw rod 302, and an internal thread matching the external thread is provided on the inner wall of the moving block 303, the push plate 306 forms a sliding structure with the excavator bucket 4 through the guide rod 305, and four groups of scrapers 307 are provided.
[0029] The working principle of the civil engineering foundation pit excavation device based on the first embodiment is: the mounting seat 2 is connected to the excavation bucket 4 through the connecting block 7, and then the excavation bucket 4 can be installed on the mechanical arm 1 of the excavator through the mounting seat 2, and then the specific installation steps of the excavation bucket 4 and the working principle of excavating the foundation pit are the same as those in the prior art. When the soil excavated in the excavation bucket 4 needs to be discharged during the foundation pit excavation process, the stepping motor 301 protected by the protective shell 304 is started to drive the screw rod 302 to rotate forward, and then the moving block 303 is threadedly engaged with the rotating screw rod 302 to drive the two sets of guide rods 305 to slide to the left along the inner wall of the excavation bucket 4 for guidance, so as to ensure the moving The stability of the moving block 303, and then the push plate 306 moves to the left with the guide rod 305 to push out the soil in the excavation bucket 4 at one time, reducing the time of the flipping and pouring action and improving the efficiency of the export. At the same time, the four groups of scrapers 307 in contact with the inner wall of the excavation bucket 4 are convenient for scraping off the soil adhering to the inner wall of the excavation bucket 4 and exporting them together with the movement of the push plate 306, thereby reducing the accumulation of soil inside the excavation bucket 4. After pushing the soil, the stepper motor 301 is started to drive the screw rod 302 to rotate in the opposite direction, so that the moving block 303 drives the push plate 306 connected to the guide rod 305 to move right through the threaded engagement for reset, which is convenient for the next soil push.
[0030] Embodiment 2
[0031] This embodiment includes: the replacement structure 5 includes a positioning rod 501, a fixing rod 502, a fixing pin 503 and a slot 504, the fixing rod 502 is fixed to one side of the bucket tooth 6, the fixing rod 502 is provided with a slot 504 inside, and the positioning rod 501 is inserted inside the slot 504, the fixing pin 503 is inserted inside the bottom end of the fixing rod 502, an external thread is provided on the outer wall of the fixing pin 503, and the inside of the excavating bucket 4 is provided with an internal thread matching the external thread, the diameter of the positioning rod 501 is smaller than the diameter of the slot 504, and the fixing pin 503 passes through the excavating bucket 4 and enters the fixing rod 502.
[0032] In this embodiment, when the bucket tooth 6 is damaged during excavation, the fixing pin 503 is rotated to engage with the thread of the excavation bucket 4 and gradually leave the interior of the fixing rod 502. Then, the bucket tooth 6 is pulled to drive the fixing rod 502 to leave the interior of the excavation bucket 4 for quick disassembly and replacement. Then, a new bucket tooth 6 is taken to drive the fixing rod 502 to align and insert it into the excavation bucket 4. At the same time, the positioning rod 501 is aligned and inserted into the slot 504 to strengthen the positioning of the fixing rod 502. Then, the fixing pin 503 is taken and inserted into the screw hole of the excavation bucket 4. The fixing pin 503 is rotated in the opposite direction to gradually enter the fixing rod 502 through thread engagement and tighten it, so that the fixing rod 502 is clamped and fixed in the excavation bucket 4, thereby fixing the replaced bucket tooth 6 and ensuring the stability of the bucket tooth 6.
[0033] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0034] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative labor.
[0035] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the utility model.
Claims
1. A civil engineering foundation pit excavation device, comprising a mechanical arm (1), an excavation bucket (4) and bucket teeth (6), characterized in that: The bottom end of the mechanical arm (1) is hingedly connected to a mounting seat (2), and a connecting block (7) is fixed to the bottom end of the mounting seat (2), an excavating bucket (4) is fixed to the bottom end of the connecting block (7), and a pushing mechanism (3) is provided on one side of the excavating bucket (4), a replacement structure (5) is provided inside one side of the excavating bucket (4), and a bucket tooth (6) is provided on one side of the replacement structure (5), and the pushing mechanism (3) comprises a stepping motor (301), a screw rod (302), a moving block (303), a protective shell (304), a guide rod (305), a push plate (306), and a plurality of pushers (307). 06) and a scraper (307), the protective shell (304) is installed at the top of one side of the excavator bucket (4), a stepper motor (301) is installed on one side of the protective shell (304), and a lead screw (302) is installed on one side of the stepper motor (301), the outer side of the lead screw (302) is threadedly connected to a moving block (303), and guide rods (305) are fixed at both ends of one side of the moving block (303), a push plate (306) is fixed on one side of the guide rod (305), and a scraper (307) is fixed on the top of the push plate (306).
2. A civil engineering foundation pit excavation device according to claim 1, characterized in that: One end of the screw rod (302) away from the stepping motor (301) is connected to a bearing on the digging bucket (4), and the guide rods (305) are symmetrically distributed on one side of the moving block (303).
3. A civil engineering foundation pit excavation device according to claim 1, characterized in that: An external thread is provided on the outer wall of the screw rod (302), and an internal thread matching the external thread is provided on the inner wall of the moving block (303).
4. A civil engineering foundation pit excavation device according to claim 1, characterized in that: The push plate (306) forms a sliding structure with the excavating bucket (4) through the guide rod (305), and the scraper blades (307) are provided in four groups.
5. The civil engineering foundation pit excavation device according to claim 1, characterized in that: The replacement structure (5) comprises a positioning rod (501), a fixing rod (502), a fixing pin (503) and a slot (504); the fixing rod (502) is fixed to one side of the bucket tooth (6); the fixing rod (502) is provided with a slot (504) inside, the positioning rod (501) is inserted into the slot (504); and the fixing pin (503) is inserted into the bottom end of the fixing rod (502).
6. A civil engineering foundation pit excavation device according to claim 5, characterized in that: An external thread is provided on the outer wall of the fixing pin (503), and an internal thread matching the external thread is provided inside the excavating bucket (4).
7. A civil construction foundation pit excavation device according to claim 5, characterized in that: The diameter of the positioning rod (501) is smaller than the diameter of the slot (504), and the fixing pin (503) passes through the excavating bucket (4) and enters the fixing rod (502).