Hanging post structure for secondary hanging bracket system of steel structure factory building

By designing the connecting structure between the hanging column and the short-section hanging column in the steel structure factory, combined with the setting of stiffeners, the problem of excessive number of hanging rods in the secondary hanging frame system in the existing technology is solved, and construction convenience and accuracy are achieved Improvement.

CN221972795UInactive Publication Date: 2024-11-08SURVEY & DESIGN BRANCH OF CHINA RAILWAY 12TH BUREAU GRP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420501466.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-15
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

There are too many hanging rods in the secondary hanging frame system of existing steel structure factories, which leads to inconvenience in construction and affects the construction period.

Method used

Design a structure including a hanging column, a short-section hanging column and a secondary hanging frame system, and connects the first and second bolt components to achieve the fixation of the hanging column with the roof main beam and the secondary hanging frame system, reducing the number of hanging rods , and stiffeners are installed on the main beam of the roof to enhance structural stability.

Benefits of technology

The number of hanging rods above the secondary hanger structure is reduced, the conflict between pipeline layout and hanging rods is avoided, construction convenience and engineering accuracy are improved, and installation time is shortened.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221972795U_ABST
    Figure CN221972795U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of steel structure buildings, and particularly relates to a davit structure for a secondary hanging bracket system of a steel structure factory building. Comprising a davit, a short section davit and a secondary hanging bracket system, the short section davit is fixed on a roof main beam of the steel structure factory building, the top end of the davit is connected with the bottom end of the short section davit through a first bolt assembly, and the bottom end of the davit is connected with the secondary hanging bracket system through a second bolt assembly; the distance between the davits in the plane of the roof girder is large, the span of the davits above the secondary hanging bracket system is large, the number of the davits is small, and the problem that pipeline arrangement in the space above the secondary hanging bracket structure conflicts with hanging rods is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of steel structure buildings, and in particular relates to a hanging column structure used for a secondary hanger system of a steel structure workshop. Background Art

[0002] Steel structure workshops are widely used in industrial workshops due to their fast construction speed, large span and low cost. The single-layer steel structure adopted by industrial workshops has the characteristics of high single-layer height and multiple integrated pipelines. In addition, due to the cleanliness requirements, multi-layer ceilings must be set up. Therefore, a secondary hanger structure is required to reduce the length of pipeline hangers. However, the commonly used secondary hanger structure is connected to the roof steel frame beam through hangers, and the hanger spacing is about 2.5m. This makes the number of hangers above the secondary hanger structure too large, which has a great impact on the pipeline layout in the space above the secondary hanger structure, resulting in inconvenience in construction and affecting the construction period. Utility Model Content

[0003] The utility model aims to reduce the number of suspension rods of the secondary hanger structure and improve the convenience of construction.

[0004] The utility model provides the following technical solutions: a suspension column structure for a secondary hanger system of a steel structure factory building, comprising a suspension column, a short-section suspension column and a secondary hanger system; the short-section suspension column is fixed on the main roof beam of the steel structure factory building, the top end of the suspension column is connected to the bottom end of the short-section suspension column through a first bolt assembly, and the bottom end of the suspension column is connected to the secondary hanger system through a second bolt assembly.

[0005] Furthermore, the secondary hanger system includes a secondary hanger system main beam and a secondary hanger system secondary beam; the secondary hanger system secondary beam is connected to the secondary hanger system main beam; the bottom end of the hanging column is connected to the secondary hanger system main beam and is aligned with the connection node of the secondary hanger system secondary beam.

[0006] Furthermore, a roof main beam stiffening rib is arranged on the roof main beam at the position of the short section suspension column.

[0007] Furthermore, the first bolt assembly includes a first end plate, a third end plate and a second bolt; the first end plate is fixed to the bottom end of the short section suspension column, the third end plate is fixed to the top end of the suspension column, the periphery of the first end plate extends outward relative to the short section suspension column, the periphery of the third end plate extends outward relative to the suspension column, and the second bolt is connected within the extending range of the first end plate and the third end plate.

[0008] Furthermore, the second bolt assembly includes a second end plate and a first bolt. The second end plate is fixed to the bottom end of the suspension column. The periphery of the second end plate extends outward relative to the suspension column. The first bolt connects the extension range of the second end plate to the top surface of the main beam of the secondary hanger system.

[0009] Furthermore, a second stiffening rib is provided between the third end plate and the suspension column, and the second stiffening rib is plate-shaped and arranged in four directions of the suspension column, front, back, left, and right;

[0010] A third stiffening rib is provided between the first end plate and the short section suspension column. The third stiffening rib is in a plate shape and is arranged in four directions of the front, back, left, and right of the short section suspension column.

[0011] The second and third stiffeners are aligned.

[0012] Furthermore, a first stiffening rib is provided between the second end plate and the suspension column. The first stiffening rib is plate-shaped and arranged in four directions of the suspension column, namely, front, back, left, and right.

[0013] Compared with the prior art, the advantages of the present invention are:

[0014] The spacing between the hanging columns in the plane of the roof main beam is large, and the hanging columns above the secondary hanger system have a large span and a small number, which avoids the problem of conflict between the pipeline layout and the hanger rods in the space above the secondary hanger structure.

[0015] The short-section suspenders are manufactured and welded in the steel structure processing plant. The suspenders and short-section suspenders are connected by the first bolt assembly, realizing factory prefabrication and on-site assembly construction, which improves the accuracy of engineering construction. The fixed-length suspenders can be formed in the factory at one time when the main beam is processed, shortening the later installation time. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the structure of the utility model;

[0017] Figure 2 is a structural schematic diagram of a first bolt assembly;

[0018] Figure 3 It is a schematic structural diagram of the second bolt assembly.

[0019] In the figure: 1- suspension column; 2- main roof beam; 3- main beam of secondary hanger system; 4- secondary beam of secondary hanger system; 5- first end plate; 6- second end plate; 7- first stiffening rib; 8- first bolt; 9- main roof beam stiffening rib; 10- second stiffening rib; 11- second bolt; 12- third end plate; 13- short section suspension column; 14- third stiffening rib. DETAILED DESCRIPTION

[0020] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0021] like Figure 1 As shown: a suspension column structure for a secondary hanger system of a steel structure factory building, comprising a suspension column 1, a short-section suspension column 13 and a secondary hanger system; the short-section suspension column 13 is fixed on the main roof beam 2 of the steel structure factory building, the top end of the suspension column 1 is connected to the bottom end of the short-section suspension column 13 through a first bolt assembly, and the bottom end of the suspension column 1 is connected to the secondary hanger system through a second bolt assembly.

[0022] The secondary hanger system includes a secondary hanger system main beam 3 and a secondary hanger system secondary beam 4; the secondary hanger system secondary beam 4 is connected to the secondary hanger system main beam 3; the bottom end of the hanging column 1 is connected to the secondary hanger system main beam 3 and is aligned with the connection node of the secondary hanger system secondary beam 4.

[0023] The spacing between the suspenders 1 in the plane of the roof main beam 2 can reach 6m to 9m. The suspenders 1 above the secondary hanger system have a large span and a small number, thus avoiding the problem of conflict between the pipeline layout and the hanger rods in the space above the secondary hanger structure.

[0024] The roof main beam 2 is provided with a roof main beam stiffening rib 9 at the position of the short section suspension column 13 .

[0025] like Figure 2 As shown: the first bolt assembly includes a first end plate 5, a third end plate 12 and a second bolt 11; the first end plate 5 is fixed to the bottom end of the short-section suspension column 13, the first end plate 5 is welded to the short-section suspension column 13, the third end plate 12 is fixed to the top end of the suspension column 1, the third end plate 12 is welded to the suspension column 1, the periphery of the first end plate 5 extends outward relative to the short-section suspension column 13, the periphery of the third end plate 12 extends outward relative to the suspension column 1, and the second bolt 11 is connected within the extending range of the first end plate 5 and the third end plate 12.

[0026] The short-section suspension column 13 is welded to the roof main beam 2 in the steel structure processing plant, and the short-section suspension column 13 is connected to the suspension column 1 with the third end plate 12 through the second bolt 11, realizing factory prefabrication and on-site assembly construction, thereby improving the accuracy of engineering construction; the suspension column 1 with a fixed length can be formed in the factory at one time when the main beam is processed in advance, thereby shortening the later installation time.

[0027] like Figure 3 As shown: the second bolt assembly includes a second end plate 6 and a first bolt 8, the second end plate 6 is fixed to the bottom end of the suspension column 1, the second end plate 6 is welded to the suspension column 1, the periphery of the second end plate 6 extends outward relative to the suspension column 1, and the first bolt 8 connects the extension range of the second end plate 6 to the top surface of the main beam 3 of the secondary hanger system; the main beam 3 of the secondary hanger system is H-shaped steel, and the first bolt 8 connects the extension range of the second end plate 6 to the top plate of the H-shaped steel.

[0028] A second stiffening rib 10 is arranged between the third end plate 12 and the suspension column 1. The second stiffening rib 10 is plate-shaped and arranged in four directions of the suspension column 1, front, back, left, and right. A third stiffening rib 14 is arranged between the first end plate 5 and the short-section suspension column 13. The third stiffening rib 14 is plate-shaped and arranged in four directions of the short-section suspension column 13. The second stiffening rib 10 and the third stiffening rib 14 are aligned.

[0029] A first stiffening rib 7 is provided between the second end plate 6 and the suspension column 1 . The first stiffening rib 7 is plate-shaped and arranged in four directions of the suspension column 1 , front, back, left, and right.

[0030] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A suspender column structure for a secondary hanger system of a steel structure workshop, characterized in that: The invention comprises a suspension column (1), a short suspension column (13) and a secondary hanger system; the short suspension column (13) is fixed on the main roof beam (2) of the steel structure factory building, the top end of the suspension column (1) is connected to the bottom end of the short suspension column (13) via a first bolt assembly, and the bottom end of the suspension column (1) is connected to the secondary hanger system via a second bolt assembly.

2. The suspender column structure for the secondary hanger system of a steel structure factory building according to claim 1, characterized in that: The secondary hanger system comprises a secondary hanger system main beam (3) and a secondary hanger system secondary beam (4); the secondary hanger system secondary beam (4) is connected to the secondary hanger system main beam (3); the bottom end of the hanging column (1) is connected to the secondary hanger system main beam (3) and is aligned with the connection node of the secondary hanger system secondary beam (4).

3. A suspender column structure for a secondary hanger system of a steel structure factory building according to claim 1 or 2, characterized in that: The roof main beam (2) is provided with a roof main beam stiffening rib (9) at the position of the short section suspension column (13).

4. The suspender column structure for the secondary hanger system of a steel structure factory building according to claim 2, characterized in that: The first bolt assembly comprises a first end plate (5), a third end plate (12) and a second bolt (11); the first end plate (5) is fixed to the bottom end of the short-section suspension column (13), the third end plate (12) is fixed to the top end of the suspension column (1), the periphery of the first end plate (5) protrudes relative to the short-section suspension column (13), the periphery of the third end plate (12) protrudes relative to the suspension column (1), and the second bolt (11) is connected within the protruding range of the first end plate (5) and the third end plate (12).

5. The suspender column structure for the secondary hanger system of a steel structure factory building according to claim 2, characterized in that: The second bolt assembly comprises a second end plate (6) and a first bolt (8); the second end plate (6) is fixed to the bottom end of the suspension column (1); the periphery of the second end plate (6) protrudes relative to the suspension column (1); and the first bolt (8) connects the protruding range of the second end plate (6) to the top surface of the main beam (3) of the secondary hanger system.

6. The suspender column structure for the secondary hanger system of a steel structure factory building according to claim 4, characterized in that: A second stiffening rib (10) is provided between the third end plate (12) and the suspension column (1); the second stiffening rib (10) is plate-shaped and arranged in four directions of the suspension column (1): front, back, left, and right; A third stiffening rib (14) is provided between the first end plate (5) and the short-section suspension column (13); the third stiffening rib (14) is plate-shaped and arranged in four directions of the front, back, left, and right of the short-section suspension column (13); The second stiffening rib (10) and the third stiffening rib (14) are aligned.

7. The suspender column structure for the secondary hanger system of a steel structure factory building according to claim 5, characterized in that: A first stiffening rib (7) is provided between the second end plate (6) and the suspension column (1); the first stiffening rib (7) is plate-shaped and is arranged in four directions of the suspension column (1): front, back, left, and right.