Concrete vibration isolation pedestal without accurate positioning and secondary grouting

By introducing bolt grooves and bolt locking components into the concrete vibration isolation platform, the problems of accurate positioning and secondary grouting required in the existing technology are solved, enabling equipment installation without accurate positioning and secondary grouting, thus simplifying the on-site workload.

CN221974697UActive Publication Date: 2024-11-08SHAANXI SITUO MECHANICAL & ELECTRICAL ENG CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202420671105.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-02
Publication Date
2024-11-08
Estimated Expiration
2034-04-02

AI Technical Summary

Technical Problem

The installation of existing vibration damping platforms requires accurate positioning and secondary grouting, which increases the workload on site.

Method used

A concrete vibration isolation platform that eliminates the need for precise positioning and secondary grouting is designed. It employs bolt grooves and bolt locking assemblies, using bolts, pressure plates, and lock nuts within the bolt grooves to secure the equipment, reducing on-site drilling and grouting steps.

Benefits of technology

This makes equipment installation convenient, reduces on-site installation work, and simplifies the process of fixing the equipment base.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221974697U_ABST
    Figure CN221974697U_ABST
Patent Text Reader

Abstract

The utility model discloses a concrete vibration isolation pedestal without accurate positioning and secondary grouting, which comprises a die cavity formed by a concrete guard plate, reinforced concrete is poured in the die cavity, a plurality of spring shock absorbers are arranged on the front side wall and the rear side wall of the concrete guard plate, and the spring shock absorbers are arranged on an installation plane. The bottom surface of the reinforced concrete is suspended on the mounting plane, four bolt grooves penetrating through the reinforced concrete are pre-buried in the reinforced concrete, the four bolt grooves are distributed in a matrix, bolt locking assemblies are mounted in the bolt grooves, each bolt locking assembly comprises a screw rod, a pressing plate and a locking nut, the screw rod penetrates through the corresponding bolt groove from bottom to top, and the pressing plate is fixedly connected with the locking nut. And a pressing plate and a locking nut are mounted on the screw rod penetrating through the bolt groove. The vibration isolation pedestal has the advantages that the pressing plate, the bolt groove and the bolt locking assembly are arranged, accurate positioning and secondary grouting are not needed when the vibration isolation pedestal is installed, and the workload of on-site installation of the equipment pedestal is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a vibration-damping pedestal, in particular to a concrete vibration-damping pedestal which does not require accurate positioning and secondary grouting. Background Art

[0002] The shock-absorbing pedestal, also known as the vibration-absorbing pedestal, inertia fastener, and vibration-absorbing support, exists to reduce the center of gravity of the equipment and increase the stability of the equipment.

[0003] Currently, the equipment with the most shock-absorbing bases on the market is the water pump. The low-frequency vibration of the water pump itself can cause certain harm to people. The building codes also clearly stipulate that water pumps need to be installed with shock-absorbing bases.

[0004] The vibration isolation pedestal is commonly a hybrid of steel structure and reinforced concrete. The vibration isolation pedestal is welded by channel steel on all sides, and reinforced concrete is laid in the middle. The equipment base has bolt holes. According to the location of the bolt holes on the equipment base, anchor bolts are pre-buried or anchor bolt holes are reserved on the concrete vibration isolation pedestal, or holes are drilled during on-site installation. The equipment is fixed by anchor bolts. However, whether it is pre-buried anchor bolts, reserved anchor bolt holes, or holes are drilled on the installation site, the accurate positioning of the equipment base is required, and the reserved anchor bolt holes or on-site drilling require secondary grouting of concrete, which increases the installation workload on site. Utility Model Content

[0005] The utility model aims to overcome the shortcomings of the prior art and provide a concrete vibration isolation pedestal which does not require accurate positioning and secondary grouting.

[0006] The purpose of the utility model is achieved through the following technical solutions: a concrete vibration isolation pedestal that does not require accurate positioning and secondary grouting, including a mold cavity composed of a concrete guard plate, reinforced concrete is poured in the mold cavity, and a plurality of spring shock absorbers are installed on the front and rear side walls of the concrete guard plate, the spring shock absorbers are placed on a mounting plane, and the bottom surface of the reinforced concrete is suspended above the mounting plane, and bolt grooves that penetrate the reinforced concrete are embedded in the reinforced concrete, there are four bolt grooves, and the four bolt grooves are distributed in a matrix, a bolt locking assembly is installed in the bolt groove, the bolt locking assembly includes a screw rod, a pressure plate, and a locking nut, the screw rod passes through the corresponding bolt groove from bottom to top, and a pressure plate and a locking nut are installed on the screw rod passing through the bolt groove.

[0007] Optionally, four bolt grooves are distributed at four corners of the reinforced concrete.

[0008] Optionally, mold cavity plates are embedded on the four corners of the reinforced concrete, and the cavities of the mold cavity plates are bolt grooves.

[0009] Optionally, the concrete guard plate is a channel steel.

[0010] Optionally, the pressing plate is a steel plate, and a strip hole is provided on the steel plate for the screw rod to pass through.

[0011] The utility model has the following advantages: the concrete vibration isolation pedestal of the utility model is provided with a pressure plate, a bolt groove and a bolt locking assembly, so that when the vibration isolation pedestal is installed, accurate positioning and secondary grouting are not required, thereby reducing the workload of on-site installation of the equipment base. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic diagram of the structure of the utility model;

[0013] Figure 2 This is a schematic diagram of the distribution of bolt slots on reinforced concrete;

[0014] Figure 3 It is a structural schematic diagram of the bolt locking assembly installed in the bolt groove;

[0015] Figure 4 for Figure 3 The enlarged schematic diagram of point A in the middle;

[0016] In the figure, 1-spring shock absorber, 2-concrete guard plate, 3-reinforced concrete, 4-bolt locking assembly, 5-equipment base, 6-pressure plate, 7-bolt slot, 8-mold cavity plate. DETAILED DESCRIPTION

[0017] In order to make the purpose, technical scheme and advantages of the embodiments of the present invention clearer, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. The components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0018] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present invention.

[0019] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features thereof may be combined with each other.

[0020] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0021] In the description of the present utility model, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the utility model product is usually placed when in use, or the positions or positional relationships commonly understood by those skilled in the art, which are only for the convenience of describing the present utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model. In addition, the terms "first", "second", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0022] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0023] like Figure 1 and Figure 2 As shown, a concrete vibration isolation pedestal that does not require accurate positioning and secondary grouting includes a mold cavity composed of a concrete guard plate 2, and reinforced concrete 3 is poured in the mold cavity. In this embodiment, the concrete guard plate 2 is a channel steel, that is, the four sides of the vibration isolation pedestal are welded by channel steel, and the reinforced concrete 3 is poured in the middle. Furthermore, a plurality of spring shock absorbers 1 are installed on the front and rear side walls of the concrete guard plate 2. The spring shock absorber 1 is placed on a mounting plane, and the bottom surface of the reinforced concrete 3 is suspended on the mounting plane. The spring shock absorber 1 is a commercially available product, and the installation of the spring shock absorber 1 and the concrete guard plate 2 belongs to the prior art, which is the same as the installation structure of the spring shock absorber 1 of the existing vibration isolation pedestal. Therefore, the structure of the spring shock absorber 1 and its installation structure will not be described in detail.

[0024] In this embodiment, if Figure 2 and Figure 3As shown, a bolt groove 7 penetrating the reinforced concrete 3 is embedded in the reinforced concrete 3, and there are four bolt grooves 7, which are arranged in a matrix. A bolt locking assembly 4 is installed in the bolt groove 7, and the bolt locking assembly 4 includes a screw rod, a pressure plate 6, and a locking nut. The screw rod passes through the corresponding bolt groove 7 from bottom to top, and a pressure plate 6 and a locking nut are installed on the screw rod passing through the bolt groove 7. During installation, the equipment base 5 is placed in the installation area at the top of the reinforced concrete 3. The equipment base 5 is also surrounded by channel steel. Then, the screw rod is inserted from the bottom of the bolt groove 7, and the top of the screw rod passes through the top of the bolt groove 7, and then the pressure plate 6 is installed on the top of the screw rod, as shown in FIG. Figure 4 As shown, one end of the pressure plate 6 is placed on the flange of the channel steel, and the other end of the pressure plate 6 is placed on the reinforced concrete 3. When the locking nut is tightened, one end of the pressure plate 6 presses the corresponding channel steel flange, and the other end of the pressure plate 6 is supported by the reinforced concrete 3. At this time, the pressure plate 6 is in an inclined state. In the present embodiment, the pressure plate 6 is a steel plate, and a strip hole for the screw to pass through is opened on the steel plate. Through the strip hole, the pressure plate 6 can be placed at an angle, which can ensure that one end of the pressure plate 6 and the channel steel flange structure and the other end of the pressure plate 6 are supported by the reinforced concrete 3. Furthermore, an elastic gasket is also installed on the screw between the locking nut and the pressure plate 6 to ensure the locking force of the locking nut. Furthermore, the bolt locking group 4 in the front and rear directions can share one pressure plate 6.

[0025] In this embodiment, if Figure 2 As shown, the equipment base 5 is of a rectangular structure, and therefore, four bolt grooves 7 are distributed at the four corners of the reinforced concrete 3. Furthermore, in order to facilitate the pouring of concrete and the forming of the bolt grooves 7, mold cavity plates 8 are buried on the four corners of the reinforced concrete 3, and the cavities of the mold cavity plates 8 are the bolt grooves 7. That is to say, when pouring concrete, the template cavity is placed at the corresponding position. When the concrete pouring is completed, the template cavity is buried in the reinforced concrete 3, thereby forming the bolt grooves 7.

[0026] The working process of the utility model is as follows: after the bolt groove 7 is embedded in the reinforced concrete 3 and the spring shock absorber 1 is installed on the concrete guard plate 2, the equipment base 5 is placed in the installation area at the top of the reinforced concrete 3, and then the screw is inserted from the bottom of the bolt groove 7, and the top of the screw passes through the top of the bolt groove 7, and then the pressure plate 6 is installed on the top of the screw, one end of the pressure plate 6 is placed on the flange of the channel steel, and the other end of the pressure plate 6 is placed on the reinforced concrete 3, the locking nut is locked, and one end of the pressure plate 6 presses the corresponding flange of the channel steel, and the other end of the pressure plate 6 is fixed by the steel bar. The concrete 3 supports, because the pressure plate 6 presses the equipment base 5, and then after the equipment on the equipment base 5 vibrates, the vibration can be transmitted to the spring shock absorber 1, thereby ensuring the smooth operation of the equipment, and when disassembling, it is only necessary to loosen the locking nut and remove the pressure plate 6 to realize the disassembly of the equipment base 5, thereby making it convenient to disassemble and assemble the base equipment, and there is no need for on-site drilling, secondary grouting, and opening holes on the flange of the equipment base 5, which requires the equipment base 5 to be accurately positioned, and it is only necessary to ensure that the pressure plate 6 can press the flange of the channel steel, thereby reducing the workload of on-site installation of the equipment base 5.

[0027] Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments, or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A concrete vibration isolation pedestal that does not require accurate positioning and secondary grouting, comprising a mold cavity composed of a concrete guard plate, reinforced concrete is poured in the mold cavity, a plurality of spring shock absorbers are installed on the front and rear side walls of the concrete guard plate, the spring shock absorbers are placed on a mounting plane, and the bottom surface of the reinforced concrete is suspended on the mounting plane, characterized in that: Bolt grooves penetrating the reinforced concrete are embedded in the reinforced concrete, there are four bolt grooves, and the four bolt grooves are distributed in a matrix, a bolt locking assembly is installed in the bolt groove, the bolt locking assembly includes a screw rod, a pressure plate, and a locking nut, the screw rod passes through the corresponding bolt groove from bottom to top, and the pressure plate and the locking nut are installed on the screw rod passing through the bolt groove.

2. The concrete vibration isolation pedestal that does not require accurate positioning and secondary grouting according to claim 1 is characterized in that: The four bolt grooves are distributed at four corners of the reinforced concrete.

3. The concrete vibration isolation pedestal that does not require accurate positioning and secondary grouting according to claim 2 is characterized in that: Cavity plates are embedded on the four corners of the reinforced concrete, and the cavities of the cavity plates are the bolt grooves.

4. A concrete vibration isolation pedestal that does not require accurate positioning and secondary grouting according to any one of claims 1 to 3, characterized in that: The concrete guard plate is a channel steel.

5. A concrete vibration isolation pedestal that does not require accurate positioning and secondary grouting according to any one of claims 1 to 3, characterized in that: The pressing plate is a steel plate, and a strip hole is provided on the steel plate for the screw rod to pass through.

Citation Information

Cited By

  • Energy-saving, environment-friendly and reusable highway precast concrete member mold

    CN120481067A

  • Energy-saving, environment-friendly and reusable highway precast concrete component mold

    CN120481067B