Jacking and unloading device for wind power tower drum
By designing the fixed connection between liftable lifting parts and flange ear plates and tower flange, the wear problem caused by multi-point contact between the arc-shaped support platform and the wind power tower is solved, and the stable lifting, unloading and transportation of the tower is achieved. .
Patent Information
- Application Number
- CN202322751035.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-13
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2033-10-13
AI Technical Summary
When the arc-shaped support table of the existing wind power tower unloading device contacts the outer periphery of the tower, it is easy to cause wear on the non-butt working surface.
A wind power tower lifting and unloading device is designed, using liftable lifting parts and flange ear plates, and the tower flange is connected by bolts to achieve stable fixation and lifting of the tower, avoiding multiple points of the arc-shaped support table. touch.
Through the fixed connection between the lifting parts and the flange ear plate, the wear problem caused by the multi-point contact between the arc-shaped support table and the outer periphery of the tower is solved, ensuring the stable lifting, unloading and transportation of the tower.
Smart Images

Figure CN221988067U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a wind power tower lifting and unloading device, belonging to the technical field of wind power construction auxiliary equipment. Background Art
[0002] The wind farm tower with a height of more than 100 meters needs to be produced in the factory in the form of segments and then transported to the construction site by a transport vehicle. The tower segments are then unloaded from the transport vehicle using an unloading device.
[0003] Existing unloading devices, such as the hydraulic lifting device for loading and unloading wind turbine towers with Chinese patent publication number CN208814584U, disclose the following technology: it includes a base, two hydraulic lifting cylinders and an arc-shaped support platform with the same curvature as the wind turbine tower, and both warped ends of the arc-shaped support platform are provided with hinged seats, the top ends of the two hydraulic lifting cylinders are respectively hinged to the two hinged seats, and the bottom ends thereof are fixedly mounted on the base; although the arc-shaped support platform that is in contact with the wind turbine tower is supported at the top of the hydraulic lifting cylinder, the arc-shaped support platform is prone to wear on its own non-joint working surface when it is in contact with the outer periphery of the wind turbine tower at multiple points. Utility Model Content
[0004] In order to solve the above technical problems, the utility model provides a wind power tower lifting and unloading device.
[0005] The utility model is realized through the following technical solutions.
[0006] The utility model provides a wind power tower lifting and unloading device, comprising:
[0007] A lifting member that can be raised and lowered, wherein the lifting members are four and spaced apart in pairs;
[0008] The flange ear plate is fixedly connected to the top of the lifting member, and bolts B are installed on the flange ear plate, which can be screwed and fixed with the tower flange at the tower shaft end.
[0009] The lifting member is a telescopic screw rod, a telescopic gas rod or a telescopic hydraulic rod to achieve lifting.
[0010] The flange ear plate is provided with a plurality of flange holes, and each flange hole on the flange ear plate is screwed with a bolt B which can be screwed and fixed with the tower flange at the tower shaft end.
[0011] The flange ear plate is fixedly connected to the top of the lifting member by bolts A.
[0012] The top of the lifting member is provided with bolt holes distributed linearly at intervals, and the flange ear plate is also provided with bolt holes distributed linearly at intervals. The bolt holes on the top of the lifting member are screwed and fixed with the bolt holes on the flange ear plate by bolts A, so as to realize a fixed connection between the flange ear plate and the top of the lifting member.
[0013] A leg pad is fixed at the bottom of the lifting member to increase the area of the bottom of the lifting member contacting the ground.
[0014] The bottom of the lifting member is welded and fixed to the leg pad.
[0015] The outrigger pads increase the contact area between the bottom of the lifting member and the ground, thereby reducing concentrated load transfer.
[0016] The beneficial effect of the utility model is that the flange ear plate fixed on the top of the lifting member is fixedly connected to the tower flange at the axial end of the wind turbine tower by bolts B, and the four lifting members are raised synchronously to lift the two axial ends of the tower and separate them from the transport vehicle. Since the flange ear plate fixed on the top of the lifting member is fixedly connected to the tower flange at the axial end of the tower, and the tower flange at the axial end of the tower itself is a docking working surface, the problem of easy wear on the non-docking working surface of the arc-shaped support platform when it is supported by multi-point contact with the outer periphery of the wind turbine tower is solved. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a main schematic diagram used in the utility model;
[0018] Figure 2 So Figure 1 A schematic side view based on
[0019] In the figure: 1-leg pad; 2-lifting piece; 3-flange ear plate; 4-tower flange; 5-tower; 61-bolt A; 62-bolt B. DETAILED DESCRIPTION
[0020] The technical solution of the utility model is further described below, but the scope of protection required is not limited to the description.
[0021] like Figure 1 to Figure 2 shown.
[0022] A wind power tower lifting and unloading device of the present application comprises:
[0023] The lift member 2 is composed of a telescopic screw rod, a telescopic gas rod, a telescopic hydraulic rod, etc., and the lift members 2 are four and are spaced apart in pairs.
[0024] A flange ear plate 3 is provided with a plurality of flange holes, and the flange ear plate 3 is fixedly connected to the top of the lifting member 2 by means of bolts A61. The top of the lifting member 2 is provided with bolt through holes which are linearly spaced apart, and the flange ear plate 3 is also provided with bolt through holes which are linearly spaced apart. The bolt through holes at the top of the lifting member 2 are screwed together and fixed with the bolt through holes of the flange ear plate 3 by means of bolts A61, so as to realize the fixed connection between the flange ear plate 3 and the top of the lifting member 2; each flange hole on the flange ear plate 3 is screwed together and installed with bolts B62, and when in use, the flange ear plate 3 is screwed together and fixed with the flange hole of the tower flange 4 at the axial end of the wind power tower 5 by means of bolts B62.
[0025] A leg pad 1 is welded and fixed to the bottom of the lifting member 2, and the leg pad 1 increases the contact area of the bottom of the lifting member 2 with the ground to reduce concentrated load transfer.
[0026] The four lifting members 2 are distributed in pairs at intervals on the outside of the tower flange 4 at the axial ends of the tower 5. The flange ear plate 3 fixed on the top of the lifting member 2 is fixedly connected to the tower flange 4 at the axial end of the wind turbine tower 5 by bolts B62. The four lifting members 2 are raised synchronously to lift the two axial ends of the tower 5 and separate them from the transport vehicle. After the vehicle withdraws, the four lifting members 2 are controlled to support the tower 5 to complete the unloading process of lifting the wind turbine tower. Since the flange ear plate 3 fixed on the top of the lifting member 2 is fixedly connected to the tower flange 4 at the axial end of the tower 5, and the tower flange 4 at the axial end of the tower 5 itself is a docking working surface, the problem that the arc-shaped support platform is prone to wear on the non-docked working surface when it is supported by multiple points of contact with the outer periphery of the wind turbine tower is solved.
Claims
1. A wind power tower lifting and unloading device, characterized in that: include: A lifting member (2) that can be lifted and lowered, wherein the lifting members (2) are four and spaced apart in pairs; A flange ear plate (3), the flange ear plate (3) is fixedly connected to the top of the lifting member (2), and bolts B (62) are installed on the flange ear plate (3) and can be screwed and fixed with the tower flange (4) at the axial end of the tower (5); The flange ear plate (3) is provided with a plurality of flange holes, and each flange hole on the flange ear plate (3) is screwed with a bolt B (62) that can be screwed and fixed with the tower flange (4) at the axial end of the tower (5); The top of the lifting member (2) is provided with bolt through holes distributed linearly at intervals, and the flange ear plate (3) is also provided with bolt through holes distributed linearly at intervals. The bolt through holes on the top of the lifting member (2) are screwed and fixed with the bolt through holes on the flange ear plate (3) by means of bolts A (61), thereby realizing a fixed connection between the flange ear plate (3) and the top of the lifting member (2).
2. The wind turbine tower lifting and unloading device according to claim 1, characterized in that: The lifting member (2) is a telescopic screw rod, a telescopic gas rod or a telescopic hydraulic rod to achieve lifting.
3. The wind turbine tower lifting and unloading device according to claim 1, characterized in that: A leg pad (1) is fixed to the bottom of the lifting member (2) to increase the area of the bottom of the lifting member (2) contacting the ground.
4. The wind turbine tower lifting and unloading device according to claim 3, characterized in that: The bottom of the lifting member (2) is fixed to the leg pad (1) by welding.
