Hydraulic engineering construction device
By combining a base plate, a water-receiving plate, and a water-blocking plate, and utilizing the impact force of water flow and the design of a water storage tank, the problem of unstable installation of hydraulic engineering construction equipment in river channels was solved, achieving stable installation and pressure reduction.
Patent Information
- Application Number
- CN202323661056.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-29
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2033-12-29
AI Technical Summary
Existing water conservancy construction equipment cannot effectively block and buffer rising water flow in river channels, resulting in unstable equipment installation.
The device employs a combination structure of a grounding plate, a water-receiving plate, and a water-blocking plate. It utilizes the impact force of the water flow to increase the contact force between the device and the ground, and enhances the stability of the device by setting a passageway and a water storage tank on the water-receiving plate to divert and store the water flow.
By converting and storing the kinetic energy of the water flow, the installation stability of the construction device is improved, ensuring that the device is not easily washed away under the impact of the water flow, and reducing the pressure on the device.
Smart Images

Figure CN221989216U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of water conservancy engineering technology, and in particular to a water conservancy engineering construction device. Background Art
[0002] At present, water conservancy projects are projects built to eliminate water disasters and develop and utilize water resources. By building water conservancy projects to control water flow, flood disasters can be effectively prevented. In seasons with heavy rainfall, the water level in the river rises, which will cause certain erosion on the river bank. Therefore, a water conservancy project construction device is needed to block the rising water in the river. Utility Model Content
[0003] In order to block the rising water in the river channel to a certain extent, the present application provides a water conservancy project construction device.
[0004] The present application provides a water conservancy project construction device that adopts the following technical solution:
[0005] A water conservancy project construction device includes a grounding plate, a water receiving plate and a water retaining plate, wherein one end of the water receiving plate is connected to one end of the grounding plate; one end of the water retaining plate is connected to one end of the water receiving plate away from the grounding plate, and the other end is connected to one end of the grounding plate away from the water receiving plate.
[0006] By adopting the above technical scheme, when the water level in the river channel rises, the water flow hits the water receiving plate, and the water receiving plate forms a certain barrier and buffer to the water flow; since the water receiving plate is arranged at an angle, the water flow will exert downward pressure on the construction device when hitting the water receiving plate, thereby increasing the contact force between the construction device and the ground, ensuring the installation stability of the construction device; in addition, a relatively stable triangular structure is formed by connecting the grounding plate, the water receiving plate and the water retaining plate, further ensuring the installation stability of the construction device.
[0007] Optionally, the water receiving plate is provided with a plurality of through openings, and the plurality of through openings are evenly distributed on the water receiving plate.
[0008] By adopting the above technical solution, after the water flow hits the water receiving plate, part of the water flow is blocked by the water receiving plate, and the other part of the water flow falls to the grounding plate through the through hole, colliding with the grounding plate, further increasing the contact force between the grounding plate and the ground.
[0009] Optionally, the water receiving plate is arranged in an arc shape.
[0010] By adopting the above-mentioned technical scheme, it is convenient to guide and buffer the water flow that impacts the water receiving plate; in addition, the water receiving plate with an arc-shaped structure will have a larger contact area with the water flow. On the one hand, the kinetic energy of the water flow is consumed to a certain extent through friction, and on the other hand, the residence time of the water flow on the water receiving plate is prolonged, so that more water flows fall to the ground plate.
[0011] Optionally, a plurality of fixing members are evenly arranged on the surface of the grounding plate facing the ground, and the fixing members are used to connect the grounding plate to the ground.
[0012] By adopting the above technical solution, a connection is established between the grounding plate and the ground using fixings, thereby further improving the installation stability of the construction device.
[0013] Optionally, the fixing member is a rod-shaped structure with a pointed end.
[0014] By adopting the above technical solution, when installing the grounding plate, the fixing piece is nailed into the ground from the grounding plate, which has a simple structure, simple operation and stable connection.
[0015] Optionally, a plurality of spikes are arranged on the peripheral side of the fixing member, the spikes are arranged obliquely relative to the fixing member, and the distance between the spikes and the fixing member gradually decreases from one end away from the grounding plate to the other end.
[0016] By adopting the above technical solution, it is easier to nail the fixing piece, and at the same time, the connection strength and connection stability between the grounding plate and the ground are further enhanced.
[0017] Optionally, the grounding plate is provided with a water storage tank.
[0018] By adopting the above technical solution, the water flow falling from the through-port is stored in the water storage tank to a certain extent, so as to reduce the pressure on the water-bearing plate and the construction device.
[0019] Optionally, a drain pipe is provided in the water storage tank, and a water pump is connected to the circumference of the drain pipe.
[0020] By adopting the above technical solution, when the amount of water stored in the water storage tank is large, the water in the water storage tank is pumped out by a water pump to reduce the water-bearing pressure of the construction device.
[0021] In summary, the present application includes at least one of the following beneficial technical effects:
[0022] 1. By setting the grounding plate, water-bearing plate and water-retaining plate, the water flow is blocked to a certain extent, and the contact force between the grounding plate and the ground is strengthened by the water flow, so that the construction device can be installed more stably while blocking the water flow;
[0023] 2. By opening a through hole in the water receiving plate, part of the water flow hitting the water receiving plate is blocked and returned to the river channel, and the other part falls to the grounding plate through the through hole, further strengthening the contact force between the grounding plate and the ground;
[0024] 3. By setting a water storage tank on the grounding plate, the water that falls to the grounding plate is stored in the water storage tank, thereby further improving the contact force between the grounding plate and the ground. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application.
[0026] Explanation of the reference numerals: 1. grounding plate; 11. water storage tank; 12. drainage pipe; 13. water pump; 2. water receiving plate; 21. through-port; 3. water retaining plate; 4. fixing member; 41. spike. DETAILED DESCRIPTION
[0027] The following is combined with Figure 1 This application is described in further detail.
[0028] The present application embodiment discloses a water conservancy project construction device. Figure 1 A water conservancy project construction device includes a grounding plate 1, a water receiving plate 2 and a water retaining plate 3, one end of the water receiving plate 2 is connected to one end of the grounding plate 1, and the water receiving plate 2 is inclined relative to the grounding plate 1. One end of the water retaining plate 3 is connected to one end of the water receiving plate 2 away from the grounding plate 1, and the other end is connected to one end of the grounding plate 1 away from the water receiving plate 2. When the water level in the river rises, the water flow hits the water receiving plate 2, and the water receiving plate 2 forms a certain obstruction and buffer to the water flow; since the water receiving plate 2 is inclined, the water flow will exert downward pressure on the construction device when hitting the water receiving plate 2, thereby increasing the contact force between the construction device and the ground, ensuring the installation stability of the construction device; in addition, a relatively stable triangular structure is formed by the connection of the grounding plate 1, the water receiving plate 2 and the water retaining plate 3, further ensuring the installation stability of the construction device.
[0029] Furthermore, the water receiving plate 2 is provided with a plurality of through holes 21, which are evenly distributed on the water receiving plate 2. With this design, after the water flow hits the water receiving plate 2, a part of the water flow is blocked by the water receiving plate 2, and the other part of the water flow falls to the grounding plate 1 through the through holes 21, and hits the grounding plate 1, thereby further increasing the contact force between the grounding plate 1 and the ground.
[0030] In this embodiment, the water receiving plate 2 is arranged in an arc shape so as to guide and buffer the water flow impacting the water receiving plate 2; in addition, the water receiving plate 2 with an arc structure has a larger contact area with the water flow. On the one hand, the kinetic energy of the water flow is consumed to a certain extent through friction, and on the other hand, the residence time of the water flow on the water receiving plate 2 is prolonged, so that more water flows fall to the grounding plate 1.
[0031] Furthermore, a plurality of fixing members 4 are evenly arranged on the surface of the grounding plate 1 facing the ground, and the fixing members 4 are used to connect the grounding plate 1 to the ground, so as to further improve the installation stability of the construction device.
[0032] In this embodiment, the fixing member 4 is a rod-shaped structure with a pointed end. When installing the grounding plate 1, the fixing member 4 is nailed into the ground from the grounding plate 1. The structure is simple, the operation is simple and the connection is stable.
[0033] Furthermore, a plurality of spikes 41 are provided on the peripheral side of the fixing member 4. The spikes 41 are inclined relative to the fixing member 4. The distance between the spikes 41 and the fixing member 4 gradually decreases from one end away from the grounding plate 1 to the other end, so that it is easier to nail the fixing member 4, while further enhancing the connection strength and stability between the grounding plate 1 and the ground.
[0034] Furthermore, the grounding plate 1 is provided with a water storage tank 11, so that the water flow falling from the through-port 21 can be stored in the water storage tank 11 to a certain extent, so as to reduce the pressure on the water-bearing plate 2 and the construction device.
[0035] Furthermore, in this embodiment, a drain pipe 12 is provided in the water tank 11, and a water pump 13 is connected to the peripheral side of the drain pipe 12. When the amount of water stored in the water tank 11 is large, the water pump 13 is used to pump out the water in the water tank 11 to reduce the water-bearing pressure of the construction device.
[0036] The implementation principle of a water conservancy project construction device in an embodiment of the present application is: when installing the construction device, first use the fixing part 4 to install the ground plate 1 on the ground; when the water level in the river channel rises, the water flow hits the water receiving plate 2, and part of the water flow returns to the river channel under the obstruction of the water receiving plate 2, and the other part falls to the ground plate 1 through the through port 21 and is stored in the water storage tank 11, thereby utilizing the impact force of the water flow and gravity to increase the contact force between the construction device and the ground, further strengthening the connection strength between the construction device and the ground, and at the same time utilizing the water receiving plate 2 and the water retaining plate 3 to block the water flow.
[0037] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A water conservancy project construction device, characterized in that: The invention comprises a grounding plate (1), a water receiving plate (2) and a water baffle plate (3), wherein one end of the water receiving plate (2) is connected to one end of the grounding plate (1), and the water receiving plate (2) is arranged obliquely relative to the grounding plate (1); one end of the water baffle plate (3) is connected to one end of the water receiving plate (2) away from the grounding plate (1), and the other end is connected to one end of the grounding plate (1) away from the water receiving plate (2).
2. A water conservancy project construction device according to claim 1, characterized in that: The water receiving plate (2) is provided with a plurality of through openings (21) extending therethrough, and the plurality of through openings (21) are evenly distributed on the water receiving plate (2).
3. A water conservancy project construction device according to claim 1 or 2, characterized in that: The water receiving plate (2) is arranged in an arc shape.
4. A water conservancy project construction device according to claim 1, characterized in that: A plurality of fixing members (4) are evenly arranged on the surface of the grounding plate (1) facing the ground, and the fixing members (4) are used to connect the grounding plate (1) to the ground.
5. A water conservancy project construction device according to claim 4, characterized in that: The fixing member (4) is a rod-shaped structure with a pointed end.
6. A water conservancy project construction device according to claim 5, characterized in that: A plurality of spikes (41) are arranged on the peripheral side of the fixing member (4), the spikes (41) are arranged obliquely relative to the fixing member (4), and the distance between the spikes (41) and the fixing member (4) gradually decreases from one end away from the grounding plate (1) to the other end.
7. A water conservancy project construction device according to claim 1, characterized in that: The grounding plate (1) is provided with a water storage tank (11).
8. A water conservancy project construction device according to claim 7, characterized in that: A drainage pipe (12) is provided in the water storage tank (11), and a water pump (13) is connected to the circumference of the drainage pipe (12).