Hoop supporting device for overwater construction platform

By designing a semi-circular clamping plate, connecting plate, stiffening rib plate, bolt holes, mounting base, and adjustable support bracket for the water construction platform clamping support device, the problems of difficult installation of bolted connections and insufficient load-bearing capacity in the existing technology have been solved, realizing efficient and safe installation of water construction platforms.

CN221989265UActive Publication Date: 2024-11-12CCCC THIRD HARBOR ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420616100.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-27
Publication Date
2024-11-12
Estimated Expiration
2034-03-27

AI Technical Summary

Technical Problem

Existing steel clamp devices are difficult to install properly in water construction due to the bolted connection of the connecting plate, which limits the load-bearing capacity and affects safety. In addition, the main beam is large and the installation position is limited.

Method used

It adopts a design with two semi-circular retaining plates, connecting plates, stiffening ribs, bolt holes, mounting bases, angle adjustment components and adjustable support brackets. The support brackets are set separately, with fewer bolts and adjustable support angles, making it suitable for pile foundations with different inclinations.

Benefits of technology

It is easy to install, highly stable, and offers high construction safety and efficiency. It is adaptable to pile foundations with different inclinations, reduces the number of bolts, and improves the convenience and safety of installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221989265U_ABST
    Figure CN221989265U_ABST
Patent Text Reader

Abstract

The utility model discloses a hoop supporting device for an overwater construction platform. Comprising two semicircular embracing plates, connecting plates arranged at the two ends of the two embracing plates, a plurality of triangular stiffening rib plates connected between the embracing plates and the connecting plates, and a plurality of bolt holes formed in the connecting plates, wherein connecting bolts are inserted into the bolt holes to connect the two embracing plates together; the mounting base is arranged on the vertical center line of the outer side of the holding plate, the angle adjusting assembly is arranged on the mounting base, and the length-adjustable supporting bracket is mounted on the mounting base through the angle adjusting assembly. The supporting bracket is easy and convenient to install, reasonable in structural stress, high in installation stability, capable of adjusting the length of the supporting bracket, capable of providing enough installation space for a main beam of a construction platform, high in construction safety and high in efficiency; and the included angle between the supporting bracket and the steel hoop can be adjusted, so that the device is suitable for pile foundations with different gradients.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of installation of water construction platforms, in particular to a hoop support device for a water construction platform. Background Art

[0002] The high-pile wharf is characterized by being located high in the water. The erection of the water construction platform for the beams or piers below it is the key to its construction. The water construction platform support system can be divided into two methods: the clamp method and the reverse hanging method. The clamp method has a more stable structure and better safety. It is the most commonly used water construction platform support device for the beams and piers under the high-pile wharf.

[0003] The pile foundation of high-pile docks is mainly made of concrete piles or steel pipe piles, usually circular piles. The upper structure of the pile foundation is a lower beam or pier. The dock is located in the water and there is a slope protection structure with a certain slope underneath, so there is no condition for setting up ground supports.

[0004] In order to solve the problem of supporting the construction platform on the water and ensure the construction safety of the beams or piers under the dock, some steel clamp devices have gradually appeared, among which the device disclosed in the Chinese patent application (CN 202519621 U) is the most representative (such as Figure 1 As shown in the figure, this device is suitable for the suspended support system of the lower beam structure, which consists of two semicircular steel sleeves arranged opposite to each other. The support system is set up on the load-bearing wing plates on both sides of the hoop to form a suspended support system. This structure can set up a support system to provide a safe construction platform for the construction of the crossbeam or pier under the dock. The two semicircular steel sleeves of this steel hoop device are connected by bolts. The connecting plate is the weakest part of the steel hoop device, and the load-bearing wing plate is welded on the top of the connecting plate, which affects the safety of the device; and due to the load-bearing load, the size of the main beam of the support system is relatively large. In order to meet the requirement that the main beam of the construction platform has enough installation space, the wing plate must be lengthened, and the corresponding connecting plate must be lengthened, so the number of bolts fixing the connecting plate increases. The construction conditions on the water are limited, and the bolts are not easy to install in place. The force performance of the steel hoop is limited, and the safety is affected, which greatly limits the use of the steel hoop. Summary of the invention

[0005] In view of this, the utility model provides a hoop support device for an above-water construction platform, which has the characteristics of simple and convenient installation, high stability, high construction safety and high efficacy.

[0006] The utility model solves the above problems through the following technical means:

[0007] The utility model discloses a hoop support device for a water construction platform, comprising two semicircular holding plates, connecting plates arranged at both ends of the two holding plates, a plurality of triangular stiffening ribs connected between the holding plates and the connecting plates, a plurality of bolt holes arranged on the connecting plates for inserting connecting bolts to connect the two holding plates together, a mounting seat arranged on the vertical center line of the outer side of the holding plates, an angle adjustment component arranged on the mounting seat, and a length-adjustable support bracket installed on the mounting seat through the angle adjustment component.

[0008] As a preferred implementation of the above technical solution, the mounting seat includes an arc-shaped plate fixed closely to the holding plate, side plates located at both ends of the arc-shaped plate, and a flat plate arranged between the two side plates for fixing the supporting corbel.

[0009] As a further improvement of the above technical solution, a plurality of intermediate ribs are provided between the arc-shaped plate and the flat plate.

[0010] As a further improvement of the above technical solution, the supporting corbel includes a top plate as a supporting plane, a plurality of ribs arranged perpendicularly below the top plate, and a back plate arranged at the end of the top plate.

[0011] Preferably, there are at least three bolt holes, and the multiple bolt holes are evenly arranged in a single row along the height direction of the holding plate.

[0012] Preferably, the circumference of the circle formed by the two holding plates being installed together is 10-30 cm smaller than the circumference of the pile foundation.

[0013] Preferably, the angle adjustment assembly includes an arc-shaped adjustment hole opened on the mounting seat, a center bolt provided on the supporting corbel and fixed to the mounting seat, and an adjustment bolt provided on the supporting corbel and installed in the arc-shaped adjustment hole.

[0014] Preferably, the supporting corbel is a sleeve telescopic structure or a folding structure.

[0015] It can be seen from the above technical solution that the utility model has the following beneficial effects:

[0016] The utility model discloses a water construction platform clamp support device, which is divided into two semicircular clamp plates, which can be hoisted by lifting equipment or installed by hand winches and other devices. The number of connecting bolts is small, and the installation is simple and convenient. Moreover, the supporting corbel is separately arranged and is not associated with the connecting plate. The structure has reasonable force and high installation stability. The length of the supporting corbel can be adjusted, which also provides sufficient installation space for the main beam of the construction platform, and the construction safety and efficiency are high. Moreover, the angle between the supporting corbel and the steel clamp is adjustable, which is suitable for pile foundations with different inclinations. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a structural schematic diagram of a clamp device in the prior art;

[0018] Figure 2 A schematic structural diagram of a hoop support device for an above-water construction platform according to the utility model;

[0019] Figure 3 for Figure 2 Bottom view of

[0020] Figure 4 A structural schematic diagram of a mounting seat of a hoop support structure of an above-water construction platform of the utility model;

[0021] Figure 5 A structural schematic diagram of an angle adjustment component of a hoop support structure of an above-water construction platform of the utility model.

[0022] like Figure 2-Figure 5 , holding plate-1, supporting corbel-2, top plate 21, rib plate 22, back plate 23, connecting plate-3, connecting bolts-4, bolt holes-5, stiffening rib plate-6, mounting seat-7, arc plate-71, side plate-72, flat plate-73, middle rib plate-74, angle adjustment assembly 8, arc adjustment hole-81, center bolt-82, adjustment bolt-83. DETAILED DESCRIPTION

[0023] In the description of the present invention, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.

[0024] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, unless otherwise specified, "plurality" means two or more.

[0025] The utility model will be described in detail below with reference to the accompanying drawings. Figure 2 and Figure 3As shown: the hoop support device for the water construction platform described in this embodiment includes two semicircular holding plates 1, connecting plates 3 arranged at both ends of the two holding plates 1, a plurality of triangular stiffening ribs 6 connected between the holding plates 1 and the connecting plates 3, a plurality of bolt holes 5 arranged on the connecting plates 3 for inserting connecting bolts 4 to connect the two holding plates 1 together, a mounting seat 7 arranged on the outer vertical center line of the holding plates 1, an angle adjustment component 8 arranged on the mounting seat 7, and a length-adjustable support bracket 2 installed on the mounting seat 7 through the angle adjustment component 8.

[0026] The water construction platform clamp support device described in this embodiment is divided into two semicircular clamp plates 1, which can be hoisted by lifting equipment or installed by hand winches and other devices. The number of connecting bolts 4 is small, and the installation is simple and convenient; and the supporting corbel 2 is set separately and is not associated with the connecting plate 3. The structure has reasonable force and high installation stability. The length of the supporting corbel 2 can be adjusted, and sufficient installation space is provided for the main beam of the construction platform, so the construction is safe and efficient; and the angle between the supporting corbel 2 and the steel clamp is adjustable, which is suitable for pile foundations with different slopes.

[0027] When installing the hoop support device for the water construction platform described in this embodiment, first, according to the installation position of the hoop device, the two semicircular holding plates 1 are put on the dock pile foundation, and the connecting bolts 4 are passed through the corresponding bolt holes 5 on the two holding plates 1 and tightened. When tightening the bolts, proceed from the middle to the upper and lower sides. At this time, the two semicircular holding plates 1 are forced to shrink and close and dock. After the inner surface of the semicircular steel plate is close to the surface of the dock pile foundation, the hoop device is installed in place, and then the angle and length of the supporting bracket 2 are adjusted according to the inclination angle of the pile foundation. degree, so that the top plates 21 of the two supporting corbels 2 are in the same horizontal plane, and then a construction platform is set up thereon. At this time, the upper ends of the supporting corbels 2 and the connecting plates 3 simultaneously bear the load from the construction platform and transmit it to the holding plate 1. The construction platform is set up through the balance of friction between the holding plate 1 and the pile foundation. When dismantling the hoop support device for the water construction platform described in this embodiment, the connecting bolts 4 are loosened and pulled out from the bolt holes 5 on the connecting plates 3, thereby separating the two semicircular holding plates 1.

[0028] As a preferred implementation of the above technical solution, Figure 4 As shown, the mounting base 7 includes an arc-shaped plate 71 fixed closely against the holding plate 1 , side plates 72 located at both ends of the arc-shaped plate 71 , and a flat plate 73 disposed between the two side plates 72 for fixing the supporting corbel 2 .

[0029] As a further improvement of the above technical solution, Figure 4As shown, a plurality of intermediate ribs 74 are provided between the arc-shaped plate 71 and the flat plate 73 .

[0030] As a preferred implementation of the above technical solution, the supporting corbel 2 includes a top plate 21 as a supporting plane, a plurality of ribs 22 arranged perpendicular to the bottom of the top plate, and a back plate 23 arranged at the end of the top plate 21. This structure has the characteristics of high strength and good stability.

[0031] In order to facilitate installation and fixation, as a preferred implementation of the above technical solution, the number of the bolt holes 5 is at least three, and the plurality of bolt holes 5 are evenly arranged in a single row along the height direction of the holding plate 1 .

[0032] As a preferred implementation of the above technical solution, the circular circumference of the two holding boards 1 installed together is 10-30 cm smaller than the circumference of the pile foundation, which can ensure that when the two holding boards 1 are connected by connecting bolts 4, the inner walls of the two holding boards 1 can be close to the surface of the pile foundation, thereby enhancing the installation strength.

[0033] As a preferred implementation of the above technical solution, Figure 5 As shown, the angle adjustment assembly 8 includes an arc-shaped adjustment hole 81 opened on the flat plate 73, a center bolt 82 provided on the supporting corbel 2 and fixed to the flat plate 73, and an adjustment bolt 83 provided on the supporting corbel 2 and installed in the arc-shaped adjustment hole 81. When adjustment is required, the adjustment bolt 83 is loosened, and then the adjustment bolt 83 is moved in the arc-shaped adjustment hole 81 with the center bolt 82 as the center. After adjusting to the level of the top plate 21 of the supporting corbel 2, the adjustment bolt 83 is tightened to complete.

[0034] As a preferred implementation of the above technical solution, the supporting corbel is a sleeve telescopic structure or a folding structure.

[0035] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the technical solution of the utility model can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the utility model, which should be included in the scope of the claims of the utility model.

Claims

1. A hoop support device for a water construction platform, characterized in that: The invention comprises two semicircular holding plates, connecting plates arranged at both ends of the two holding plates, a plurality of triangular stiffening ribs connected between the holding plates and the connecting plates, a plurality of bolt holes arranged on the connecting plates for inserting connecting bolts to connect the two holding plates together, a mounting seat arranged on the vertical center line of the outer side of the holding plates, an angle adjustment component arranged on the mounting seat, and a length-adjustable supporting bracket installed on the mounting seat through the angle adjustment component.

2. The above-water construction platform clamp support device according to claim 1, characterized in that: The mounting seat comprises an arc-shaped plate fixed closely to the holding plate, side plates located at both ends of the arc-shaped plate, and a flat plate arranged between the two side plates for fixing the supporting corbel.

3. The above-water construction platform clamp support device according to claim 2, characterized in that: A plurality of intermediate ribs are also provided between the arc-shaped plate and the flat plate.

4. The above-water construction platform clamp support device according to claim 1, characterized in that: The supporting corbel comprises a top plate as a supporting plane, a plurality of ribs arranged perpendicularly below the top plate, and a back plate arranged at the end of the top plate.

5. The above-water construction platform clamp support device according to claim 1, characterized in that: The number of the bolt holes is at least three, and the plurality of bolt holes are evenly arranged in a single row along the height direction of the holding plate.

6. The above-water construction platform clamp support device according to claim 1, characterized in that: The circular circumference of the two holding plates installed together is 10-30 cm smaller than the circumference of the pile foundation.

7. The above-water construction platform clamp support device according to claim 1, characterized in that: The angle adjustment assembly includes an arc-shaped adjustment hole opened on the mounting seat, a center bolt arranged on the supporting bracket and fixed to the mounting seat, and an adjustment bolt arranged on the supporting bracket and installed in the arc-shaped adjustment hole.

8. The above-water construction platform clamp support device according to claim 1, characterized in that: The supporting corbel is a sleeve-connected telescopic structure or a folding structure.