Assembly type shaft

By designing prefabricated steel beam units, the parts error and accuracy problems in wellbore equipment installation are solved, construction efficiency and wellbore quality are improved, steel is saved, and the stability and efficient installation of the wellbore is achieved.

CN221989390UActive Publication Date: 2024-11-12CINF ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420022263.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-03
Publication Date
2024-11-12
Estimated Expiration
2034-01-03

AI Technical Summary

Technical Problem

The production and installation of existing wellbore equipment has problems such as part processing errors, limited installation accuracy, slow construction progress, and large steel consumption, which affects the operating quality of the wellbore.

Method used

The steel beam unit is designed as a prefabricated structure, and the overall prefabricated and unloaded correction is carried out in the factory, so as to reduce parts lifting and error correction on site, and form an overall structure through the connection of tank passages and anchors, improving installation stability and efficiency.

Benefits of technology

The construction period is shortened, the assembly efficiency and wellbore operation quality are improved, the amount of steel is saved, and the stability and stress balance of the structure are achieved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221989390U_ABST
    Figure CN221989390U_ABST
Patent Text Reader

Abstract

The utility model provides an assembly type shaft. The assembly type shaft comprises a shaft wall and a plurality of steel beam units arranged in the height direction of the shaft wall at intervals, every two adjacent steel beam units are connected through a shaft guide, and stairs are further arranged between the multiple steel beam units. The steel beam unit comprises a ring beam and a plurality of cage guide beams connected into the ring beam, the interior of the ring beam is divided into a middle area, a first side area and a second side area, the first side area and the second side area are arranged at the two ends of the middle area respectively, a plurality of anchor rods are evenly distributed on the periphery of the ring beam, and the anchor rods stretch into the cylinder wall; the cage guide beams in the plurality of steel beam units are connected through the cage guide; and the staircase is arranged in the first side area. According to the utility model, the workload of on-site assembly error correction is greatly reduced, the stability of the mounting structure is ensured, and the shaft operation quality is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of shaft construction, in particular to an assembled shaft. Background Art

[0002] The current manufacturing and installation process of shaft equipment is as follows: the manufacturer processes the parts (brackets, tankway beams, ladder beams, tankways and ladders), which are then transported in bulk to the site and assembled one by one.

[0003] This installation method has the following problems: (i) There are errors when the parts are processed in the factory. During on-site assembly, the errors make it impossible to assemble them. The parts can only be corrected on-site to meet the assembly requirements. However, on-site correction has limitations and is difficult to handle. (ii) Affected by the processing technology and the construction and installation technology, the installation accuracy of the tankway beam and the tankway is limited, which affects the operation quality of the shaft. (iii) Multiple parts are hoisted and assembled one by one, the construction progress is slow, and the construction period is long. (iv) In order to ensure the stability of the connecting structure of each part in the shaft, the steel consumption is large. Utility Model Content

[0004] The utility model aims to provide an assembled shaft with more convenient construction and more reasonable structure.

[0005] The technical solution of the utility model is: an assembled shaft, comprising a shaft wall, a plurality of steel beam units arranged at intervals in the height direction of the shaft wall, two adjacent steel beam units are connected by a tankway, and stairs are also arranged between the plurality of steel beam units; the steel beam unit comprises a ring beam and a plurality of tankway beams connected to the ring beam, the plurality of tankway beams divide the interior of the ring beam into a middle area and a first side area and a second side area respectively arranged at both ends of the middle area, a plurality of anchor rods are evenly distributed on the outer periphery of the ring beam, and the anchor rods extend into the shaft wall; the tankway connects the tankway beams in the plurality of steel beam units; the stairs are arranged in the first side area.

[0006] In the above scheme, the steel beam unit is designed to form a whole and can be prefabricated in the factory. During on-site assembly, the number of on-site parts hoisting is greatly reduced, the construction period is shortened and the assembly efficiency is improved. In addition, the steel beam unit is a prefabricated structure, and the cutting errors of the various parts set inside it can be corrected in the factory, which greatly reduces the workload of on-site assembly error correction, ensures the stability of the installation structure, and improves the quality of wellbore operation.

[0007] Preferably, the steel beam unit also includes a ladder beam; the ring beam has a first center line and a second center line that are perpendicular to each other, and the tankway beam includes a first beam body parallel to the first center line and a second beam body parallel to the second center line; two first beam bodies are symmetrically arranged along the first center line, and two second beam bodies are symmetrically arranged along the second center line, and the second side area is formed between the two second beam bodies, the second beam body connects the ring beam and one of the first beam bodies, and a ladder beam for fixing stairs is connected between the other first beam body and the ring beam, and at least two ladder beams are arranged on both sides of the second center line, and a first side area is formed between at least two of the ladder beams.

[0008] Preferably, the first beam body of one of the steel beam units is butted up and down with the first beam body of another of the steel beam units and connected via connecting bolts, and the tank channel is connected to the first beam body via connecting bolts.

[0009] Preferably, three ladder beams are arranged at intervals, the staircase is installed between the first and second ladder beams, a floor slab is arranged between the second and third ladder beams, and the floor slab is connected to the staircase.

[0010] Preferably, a connecting plate corresponding to the position of the tankway beam of each steel beam unit is provided on the tankway, and the connecting plate is connected to the tankway beam via connecting bolts.

[0011] Preferably, the plurality of tank channels are respectively connected to a side surface of the tank channel beam close to the middle area or the second side area.

[0012] Preferably, the ring beam and the tankway beam are both channel steels.

[0013] Compared with the related art, the beneficial effects of the utility model are:

[0014] 1. The steel beam unit of the assembled shaft design can be formed into a whole and prefabricated in the factory. During on-site assembly, the number of parts hoisted on site is greatly reduced, the construction period is shortened and the assembly efficiency is improved;

[0015] Second, the assembled shaft uses the steel beam unit as a prefabricated structure, and the cutting errors of the parts arranged inside it can be corrected in the factory, which greatly reduces the workload of on-site assembly error correction, ensures the stability of the installation structure, and improves the operation quality of the shaft;

[0016] 3. The assembled shaft has the steel beam unit as a prefabricated module structure, which can realize reasonable design of the force balance of the steel beam unit and save steel consumption. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 A schematic diagram of the planar structure of the assembled shaft provided by the utility model;

[0018] Figure 2 For along Figure 1 AA cross-sectional structure diagram in;

[0019] Figure 3 along Figure 1 BB cross-sectional structure diagram;

[0020] Figure 4 It is a schematic diagram of the installation of the tankway and the first beam body;

[0021] Figure 5 This is a schematic diagram of the installation of the tankway and the second beam.

[0022] In the attached drawings: 1. ring beam; 11. cylinder wall; 101. middle area; 102. first side area; 103. second side area; 104. first center line; 105. second center line; 2. anchor rod; 3. tankway beam; 31. first beam body; 32. second beam body; 4. ladder beam; 5. floor slab; 6. stairs; 7. partition net; 8. connecting bolt; 9. tankway; 91. connecting plate; 10. steel beam unit. DETAILED DESCRIPTION

[0023] The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict. For the convenience of description, if the words "upper", "lower", "left" and "right" appear in the following text, they only indicate that the upper, lower, left and right directions are consistent with the drawings themselves, and do not limit the structure.

[0024] like Figure 1 , Figure 2 , Figure 3 As shown, the present embodiment provides an assembled shaft including a shaft wall 11 and a plurality of steel beam units 10 spaced apart in the height direction of the shaft wall 11 .

[0025] The steel beam unit 10 includes a ring beam 1, a tank beam 3 and a ladder beam 4. The ring beam 1 is a ring-shaped structure adapted to the inner surface of the cylinder wall 11, and is a channel steel having a plurality of anchor rods 2 arranged circumferentially thereon. The ring beam 1 is fixed to the cylinder wall 11 via the anchor rods 2. The ring beam 1 has a first center line 104 and a second center line 105 which are perpendicular to each other. The tank beam 3 is a channel steel, and includes a first beam body 31 parallel to the first center line 104 and a second beam body 32 parallel to the second center line 105. Two first beam bodies 31 are symmetrically arranged along the first center line 104, and an intermediate area 101 is formed between the two first beam bodies 31. Figure 4As shown, when a plurality of steel beam units 10 are butt-jointed and installed, the first beam body 31 of one steel beam unit 10 is butt-jointed with the first beam body 31 of another steel beam unit 10 up and down and connected by connecting bolts 8. Two adjacent steel beam units 10 are connected by a tank channel 9. The tank channel 9 is provided with a connecting plate 91 corresponding to the position of the first beam body 31, and the connecting plate 91 is connected to the first beam body 31 by connecting bolts 8.

[0026] like Figure 1 As shown, the tank channel 9 is respectively connected to one side surface of the tank channel beam 3 close to the middle area 101, and the tank channel 9 is located on the outside of the second beam body 32 and the ladder beam 4 (the side away from the second center line 105).

[0027] Two second beam bodies 32 are symmetrically arranged along the second center line 105, and the second side area 103 is formed between the two second beam bodies 32. The second beam body 32 connects the ring beam 1 and one of the first beam bodies 31, and a ladder beam 4 for fixing the stairs 6 is connected between the other first beam body 31 and the ring beam 1. Figure 5 As shown, the tank channel 9 is provided with a connecting plate 91 corresponding to the position of the second beam body 32, and the connecting plate 91 is connected to the tank channel beam 3 through a connecting bolt 8. The tank channel 9 is connected to a side surface of the tank channel beam 3 close to the second side area 103. One second beam body 32 is connected to one tank channel 9, and the center lines of the two tank channels 9 on the second side area 103 form the center line of the counterweight.

[0028] Three ladder beams 4 are arranged at intervals on both sides of the second center line 105, and a first side area 102 is formed between the three ladder beams 4. Among the three ladder beams 4, a staircase 6 is installed between the first and second ladder beams 4, and a floor slab 5 is arranged between the second and third ladder beams 4, and the floor slab 5 is connected to the staircase 6.

[0029] Before the shaft construction, the steel beam unit 10 is first welded into a whole in the factory, and then the whole is coated with an anti-corrosion coating. All parts inside the steel beam unit 10 are on the same plane for easy transportation. Then the steel beam unit 10, tank channel 9, and staircase 6 are transported to the site. First, the tank channel 9 is used as a vertical support at the wellhead to connect the upper and lower steel beam units 10 to form a standard floor unit. Then the floor slab 5, staircase 6 and partition net 7 are installed on the standard floor unit in sequence. Then the standard floor unit is hoisted to the corresponding position underground, and the anchor rod 2 is installed to fix it, completing the installation of a standard floor unit. Then follow the above steps to complete the installation of other standard units from bottom to top. The anchor rod 2 can be adjusted at will at the same elevation according to the site conditions, and the installation accuracy of the standard floor unit is not affected by the installation accuracy of the anchor rod.

[0030] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. An assembled wellbore, comprising a wellbore wall (11), characterized in that: It also comprises a plurality of steel beam units (10) arranged at intervals in the height direction of the cylinder wall (11), two adjacent steel beam units (10) are connected by a tankway (9), and stairs (6) are provided between the plurality of steel beam units (10); the steel beam unit (10) comprises a ring beam (1) and a plurality of tankway beams (3) connected to the ring beam (1), the plurality of tankway beams (3) dividing the interior of the ring beam (1) into a middle area (101) and a first side area (102) and a second side area (103) respectively arranged at both ends of the middle area (101), a plurality of anchor rods (2) are evenly distributed on the outer periphery of the ring beam (1), the anchor rods (2) extend into the cylinder wall (11); the tankway (9) connects the tankway beams (3) in the plurality of steel beam units (10); and the stairs (6) are arranged in the first side area (102).

2. The assembled wellbore according to claim 1, characterized in that: The steel beam unit (10) further comprises a ladder beam (4); the ring beam (1) has a first center line (104) and a second center line (105) which are perpendicular to each other; the tankway beam (3) comprises a first beam body (31) parallel to the first center line (104) and a second beam body (32) parallel to the second center line (105); two first beam bodies (31) are symmetrically arranged along the first center line (104); two second beam bodies (32) are symmetrically arranged along the second center line (105); a second side area (103) is formed between the two second beam bodies (32); the second beam body (32) connects the ring beam (1) and one of the first beam bodies (31); a ladder beam (4) for fixing a staircase (6) is connected between the other first beam body (31) and the ring beam (1); at least two ladder beams (4) are arranged on both sides of the second center line (105); a first side area (102) is formed between at least two ladder beams (4).

3. The assembled wellbore according to claim 2, characterized in that: The first beam body (31) of one of the steel beam units (10) is butted up and down with the first beam body (31) of another of the steel beam units (10) and connected via connecting bolts (8); the tank channel (9) is connected to the first beam body (31) via connecting bolts (8).

4. The assembled wellbore according to claim 2, characterized in that: The ladder beams (4) are arranged at intervals of three, the staircase (6) is installed between the first and second ladder beams (4), and a floor slab (5) is arranged between the second and third ladder beams (4), and the floor slab (5) is connected to the staircase (6).

5. The assembled wellbore according to claim 1, characterized in that: The tankway (9) is provided with a connecting plate (91) corresponding to the position of the tankway beam (3) of each steel beam unit (10), and the connecting plate (91) is connected to the tankway beam (3) via connecting bolts (8).

6. The assembled wellbore according to claim 1, characterized in that: The plurality of tank channels (9) are respectively connected to a side surface of the tank channel beam (3) close to the middle area (101) or the second side area (103).

7. The assembled wellbore according to claim 1, characterized in that: The ring beam (1) and the tankway beam (3) are both channel steels.