Assembling structure of concrete prefabricated assembly type stand column
By installing hooks between prefabricated concrete columns and using steel sleeves, combined with the pier structure, the problems of insufficient structural strength and construction complexity in the existing technology are solved, and higher structural integrity and construction convenience are achieved , suitable for high-pressure environments such as earthquakes.
Patent Information
- Application Number
- CN202420358937.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-27
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-02-27
AI Technical Summary
The prefabricated splicing structure of existing concrete frame structure columns has insufficient structural strength, especially in natural disasters such as earthquakes, and the construction process is complicated and the quality is difficult to guarantee.
A prefabricated concrete column assembly structure is designed. By installing hooks between the upper and lower columns and locking and adjusting with steel sleeves, prestress is added and combined with the pier structure is combined to improve the splicing strength and convenience.
It improves the overall structural strength and construction convenience of the column, reduces the complexity of steel bar binding, enhances the force-bearing capacity at the splicing, avoids the formation of cold joints, and is suitable for use in high-pressure environments.
Smart Images

Figure CN221989592U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of prefabricated building columns, in particular to an assembly structure of prefabricated concrete assembled columns. Background Art
[0002] At present, the columns of concrete frame structures are usually made of cast-in-place concrete. In the application of prefabricated assembled structures, the longitudinal reinforcement of the frame columns is usually connected by sleeve grouting, but both require on-site concrete pouring. In the above implementation plan, since the beams and columns need to be cast in place, the construction speed is slow, and formwork is required for shaping, which is costly and takes a long time to construct. Grouting is used to connect the longitudinal reinforcement of the columns, which is difficult to operate. When pouring on site, it is difficult to ensure that the reinforcement remains stable during the pouring process, and the construction quality is difficult to guarantee, and quality inspection is also difficult.
[0003] Therefore, in recent years, various construction projects have vigorously promoted the application of prefabricated and assembled structures. Prefabricated buildings have developed rapidly and have been widely used in various types of buildings. However, when conventional columns are overlapped and spliced, the cold joints are obvious and the structural strength is low. Especially when the internal steel bars are tied, there is a lot of ductility, resulting in insufficient restraint of the steel bars on the columns. Especially at the joints of prefabricated columns, there is almost no prestressing of the steel bars, resulting in insufficient structural strength at the joints of the columns, which has become a weak point of the building and affects the overall strength of the building. The impact is obvious. As a result, the structural strength of buildings made of prefabricated parts is not enough to cope with natural disasters such as earthquakes, and can only be used on plains or in a very small range.
[0004] Based on this, the utility model designs an assembly structure of prefabricated concrete columns to solve the above problems. Utility Model Content
[0005] The purpose of the utility model is to provide an assembly structure of prefabricated concrete columns. The device is mainly based on the existing assembled concrete columns, simplifies the structure, makes the construction process simpler, improves the construction convenience, and only needs to install hooks on the steel bars when the columns are spliced together, so that the hooks of the upper and lower columns are hooked together to form prestress, thereby increasing the integrity of the upper and lower columns. The device has high strength, is easy to install, and has a stable structure.
[0006] The utility model is implemented as follows: an assembly structure of a prefabricated concrete column, comprising:
[0007] Upper post, lower post and hook;
[0008] The upper column and the lower column are both vertically arranged concrete columns;
[0009] A buttress is protruding upward from the top of the lower column, and the buttress and the lower column are an integral structure cast with concrete;
[0010] A plurality of upper column bars are pre-buried in the upper column, and the upper column bars extend out of the lower end surface of the upper column; a plurality of lower column bars are pre-buried in the lower column, and the lower column bars extend out of the upper end surface of the lower column, and the number and position of the upper column bars and the lower column bars correspond to each other;
[0011] A hook is locked on each of the upper column reinforcement and the lower column reinforcement; the hooks on the upper column reinforcement and the lower column reinforcement overlap and are tightly connected to each other;
[0012] The hook extends outward from the upper column or the lower column to a height of d, the pier has a height of h, and h>d.
[0013] Furthermore, a steel sleeve is installed on the straight rod end of the hook through a thread, and the hook is locked with the upper column reinforcement or the lower column reinforcement through the steel sleeve;
[0014] The hook is installed on the exposed end of the upper column reinforcement or the lower column reinforcement through a steel bar sleeve so as to be able to adjust the height.
[0015] Furthermore, a plurality of lower column reinforcements are arranged around the pier without contact; the lower end surface of the upper column is a flat surface, and no upper column reinforcement is arranged on the fitting support surface between the upper column and the pier.
[0016] Furthermore, the hook is an integral structure made of stainless steel;
[0017] The upper column reinforcement and the lower column reinforcement are both steel bars.
[0018] The beneficial effects of the utility model are as follows: 1. The utility model can directly assemble the support between the upper column and the lower column by adding a pier, which can facilitate assembly, and at the same time can expose the upper column reinforcement and the lower column reinforcement inside the concrete structure, which is convenient for binding and installing hooks, and the splicing construction is more convenient;
[0019] 2. This device adds a hook, which can be locked and adjusted through the steel bar sleeve, making it easy to connect the hook and install it on the steel bar, increasing the convenience of connecting the steel bars when splicing the upper column and the lower column, without the need for repeated binding, and also increasing the structural strength;
[0020] 3. The hook is an integral structure supported by stainless steel, which is much stronger than the steel bar. The hooks pull each other to produce prestress, and their tensile strength is greater than the binding force of the steel bar, making the overall force resistance between the upper column and the lower column higher;
[0021] 4. When the upper column and the lower column of the device are spliced with each other, the gap outside the pier needs to be filled during on-site construction, so that the splicing seam of the device is not horizontal, but the gap outside the pier. The splicing seam is sleeve-shaped, so that there is no obvious gap in the splicing seam, and the strength of the splicing is better than the horizontal gap. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] The present invention will be further described below in conjunction with the embodiments with reference to the accompanying drawings.
[0023] Figure 1 This is a schematic diagram of the overall structure of the utility model before splicing;
[0024] Figure 2 It is a top view schematic diagram of the top surface structure of the lower column of the utility model;
[0025] Figure 3 It is a schematic diagram of the structure after the upper column and the lower column of the utility model are spliced.
[0026] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0027] 1-upper column, 11-upper column reinforcement, 2-lower column, 21-pier, 22-lower column reinforcement, 3-hook, 31-rebar sleeve. DETAILED DESCRIPTION
[0028] See also Figures 1 to 3 As shown, the utility model provides an assembly structure of prefabricated concrete columns. In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings in the specification and specific implementation methods.
[0029] In a specific embodiment of the technical solution of the utility model:
[0030] It includes an upper column 1, a lower column 2 and a hook 3; the hook 3 is an integral structure made of stainless steel; the upper column reinforcement 11 and the lower column reinforcement 22 are both steel bars. The upper column reinforcement 11 and the lower column reinforcement 22 are both steel bars embedded in the precast concrete column. This embedded steel bar is a conventional structure of a concrete column. Even cast-in-place concrete columns need to be embedded with steel bars to increase their strength. This is a conventional setting of reinforced concrete structures.
[0031] The upper column 1 and the lower column 2 are both vertically arranged concrete columns; the lower end surface of the upper column 1 is a flat surface.
[0032] A buttress 21 is protruded upward from the top of the lower column 2, and the buttress 21 and the lower column 2 are an integral structure cast with concrete;
[0033] When the upper column 1 is precast and poured, a plurality of upper column bars 11 are already pre-buried therein to form a precast concrete upper column, and the upper column bars 11 extend out of the lower end surface of the upper column 1; a plurality of lower column bars 22 are pre-buried inside the lower column 2, and the lower column bars 22 extend out of the upper end surface of the lower column 2, and the number and position of the upper column bars 11 and the lower column bars 22 correspond one to one;
[0034] A hook 3 is locked on each upper column reinforcement 11 and lower column reinforcement 22; the hooks 3 on the upper column reinforcement 11 and lower column reinforcement 22 overlap and are tightly connected to each other;
[0035] The straight rod end of the hook 3 is threadedly installed with a steel sleeve 31, and the hook 3 is locked with the upper column reinforcement 11 or the lower column reinforcement 22 through the steel sleeve 31;
[0036] The hook 3 is installed at the exposed end of the upper column reinforcement 11 or the lower column reinforcement 22 in a height-adjustable manner through the reinforcement sleeve 31 .
[0037] The hook 3 extends out to a height d on the upper column 1 or the lower column 2, and the height h of the buttress 21 is greater than the height d of the hook 3. This allows the hooks 3 of the upper and lower columns to be hooked within the height range of the buttress 21, preventing the hooks 3 from extending out to collide with the upper column 1 and the lower column 2.
[0038] When the upper column 1 and the lower column 2 are spliced, multiple lower column bars 22 are arranged around the pier 21 without contact; the upper column bars 11 are not arranged on the fitting support surface between the upper column 1 and the pier 21, that is, the lower column bars 22 and the upper column bars 11 should avoid the splicing fitting surface between the pier 21 and the lower end of the upper column 1. It is necessary to avoid the lower column bars 22 and the upper column bars 11 from conflicting with the pier 21.
[0039] This device only illustrates the splicing point, and in reality, the upper column 1 and the lower column 2 are described based on the installation position, and are not specifically limited. In actual construction, the upper column 1 and the lower column 2 have the same structure and are both complete columns, except that the top of the column is the lower column 1 structure with a pier 21, and the bottom of the column is the flat lower column 2 structure. The top of the same column has the same structure as the lower column 2, and the bottom has the same structure as the upper column 1.
[0040] Compared with the existing technology, the structure of the embodiment of the utility model has the following differences:
[0041] 1. The existing prefabricated building columns use a steel bar binding method, that is, bending steel bars to form hooks, and then binding them with wires, or using thinner steel bars to bind the supporting steel bars inside the upper and lower spliced columns. This operation and construction method is relatively cumbersome, the construction is difficult, and the construction speed is slow. The device only needs to rotate the hook 3 and the steel sleeve 31, and after adjusting the position, the hooks 3 of the upper column 1 and the lower column 2 are hooked together, and then the steel sleeve 31 is adjusted to tighten the upper and lower hooks 3. The construction method is simple and convenient. The method is simple and the construction speed is fast; 2. The strength of the steel bar binding can only be to bend the steel bar to form a hook shape, and the length cannot be adjusted. The strength of the steel bar hook structure is far less than the tensile strength borne in the axial direction, which reduces the strength of the steel bar hook; 3. Because the steel bar sleeve 31 of the device can adjust the height of the hook 3, the two hooked hooks 3 can be pulled against each other to generate tension, and then after pouring concrete outside the splicing, prestress can be generated at the splicing, so that the pre-buried steel bars in the upper column 1 and the lower column 2 are integrally formed. The force is not only applied to the whole body, but also the steel bars are connected in a line, so the overall force is better; 4. The existing spliced columns have a horizontal gap at the joint, which is easy to form a cold joint, which will seriously affect the structural strength. The splicing of the device is to smooth the outer periphery of the pier 21 through the template. The main force of the support is still in the middle of the upper column 1, the pier 21 and the lower column 2. The peripheral support relies on the hook 3, the upper column reinforcement 11 and the lower column reinforcement 22, instead of relying on the caulking poured on the construction site. This is a very obvious difference. At present, horizontal splicing requires horizontal seams for support. In order to accommodate the steel bars at the splicing, the horizontal seams have a height of about 10-30cm. The pier 21 of the device is directly spliced with the bottom of the upper column 1. The support of the device relies on the pier 21 instead of relying on the splicing seams to bond and support the upper and lower columns. The support is stronger. Prefabricated parts can be made under high pressure environments, while on-site cast parts cannot. The strength of the pier 21 can be due to the splicing seams of on-site construction. The support strength of the device is significantly better.
[0042] When the utility model is used, the steel sleeve 31 and the hook 3 are first installed on the upper column reinforcement 11 and the lower column reinforcement 22. The steel sleeve 31 and the hook 3 can also be pre-fabricated as an integrated unit and do not need to be installed at the construction site. It is sufficient to ensure that the structural strength and tensile strength are sufficient.
[0043] During on-site construction, the upper column 1 is hoisted and directly spliced on the top of the pier 21 of the lower column to align the upper column 1 with the lower column 2, and then the hook 3 of the upper column 1 and the hook 3 of the lower column 2 are hooked one by one, and then the steel sleeve 31 is adjusted to make the upper and lower hooks 3 hooked with each other produce relative tension to form prestress, thereby further enhancing the integrity and strength of the structure. Then, outside the pier 21, concrete is poured to fill and seal the exposed empty grooves where the hook 3 and the upper column reinforcement 11 and the lower column reinforcement 22 are located, and the upper column 1 and the lower column 2 are filled and smoothed. At this time, the assembly is completed, and there is no gap at the assembly point, and it is not easy to form a cold joint. At the same time, the supporting force of the device does not rely on the on-site cast part of the splicing seam, but relies on the upper column 1, the lower column 2 and the pier 21 for complete support. The hook 3 is used to tighten and ensure the integrity of the support force of the steel skeleton.
[0044] Although the specific implementation methods of the present invention are described above, those skilled in the art should understand that the specific embodiments described are only illustrative and are not intended to limit the scope of the present invention. Equivalent modifications and changes made by those skilled in the art in accordance with the spirit of the present invention should be included in the scope of protection of the claims of the present invention.
Claims
1. An assembly structure of prefabricated concrete columns, It is characterized in that include: An upper column (1), a lower column (2) and a hook (3); The upper column (1) and the lower column (2) are both vertically arranged concrete columns; A buttress (21) is protruding upward from the top of the lower column (2), and the buttress (21) and the lower column (2) are an integral structure cast by concrete; A plurality of upper column bars (11) are pre-buried in the upper column (1), and the upper column bars (11) extend out of the lower end surface of the upper column (1); a plurality of lower column bars (22) are pre-buried in the lower column (2), and the lower column bars (22) extend out of the upper end surface of the lower column (2), and the number and position of the upper column bars (11) and the lower column bars (22) correspond one to one; A hook (3) is locked on each of the upper column reinforcement (11) and the lower column reinforcement (22); the hooks (3) on the upper column reinforcement (11) and the lower column reinforcement (22) overlap and are tightly connected to each other; The hook (3) extends out of the upper column (1) or the lower column (2) to a height of d, the pier (21) has a height of h, and h>d.
2. The assembly structure of a prefabricated concrete column according to claim 1, Features: The straight rod end of the hook (3) is threadedly mounted with a steel sleeve (31), and the hook (3) is locked with the upper column reinforcement (11) or the lower column reinforcement (22) through the steel sleeve (31); The hook (3) is installed on the exposed end of the upper column reinforcement (11) or the lower column reinforcement (22) in an adjustable height through a reinforcement sleeve (31).
3. The assembly structure of a prefabricated concrete column according to claim 1, Features: A plurality of lower column reinforcements (22) are arranged around the buttress (21) without contact; the lower end surface of the upper column (1) is a flat surface, and the upper column reinforcement (11) is not arranged on the contact support surface between the upper column (1) and the buttress (21).
4. The assembly structure of a prefabricated concrete column according to claim 1, Features: The curved hook (3) is an integral structure made of stainless steel; The upper column reinforcement (11) and the lower column reinforcement (22) are both steel bars.