Pile-column integrated frame structure waterfront trestle

Through the pile-column integrated frame structure, the problems of poor integrity and low construction efficiency in the construction of traditional waterfront trests are solved, efficient and stable waterfront trest construction is achieved, and the seismic performance and adaptability of the structure are enhanced.

CN222008619UActive Publication Date: 2024-11-15CHINA WATER RESOURCES BEIFANG INVESTIGATION DESIGN & RES CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202323342311.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-08
Publication Date
2024-11-15
Estimated Expiration
2033-12-08

AI Technical Summary

Technical Problem

In the traditional waterfront trest construction method, the separated structure leads to poor integrity, and the supporting platform and pile foundation connecting beams need to be installed, resulting in many construction processes and slow progress, and it is easy to damage the upper beam slab when the flood is overflowing.

Method used

The integrated pile and column frame structure is adopted, and the integral rigid structure system is formed through reinforced concrete cast-infused piles and frame columns. The frame column is embedded in the cast-infused piles, and the frame beams and columns are rigidly connected, eliminating the bearing and connecting beams, and the pile and columns are integrated. Pouring molding enhances structural stability and seismic resistance.

Benefits of technology

It improves construction efficiency, enhances the overall stability and seismic resistance of the structure, has strong adaptability, reduces construction process and material consumption, reduces water flow resistance, and ensures the safety and aesthetics of the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222008619U_ABST
    Figure CN222008619U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of buildings, in particular to a waterfront trestle with a pile-column integrated frame structure. Comprising reinforced concrete cast-in-place piles, frame columns, frame beams and trestle plates, reinforced concrete cast-in-place pile foundations are fixedly embedded in a foundation, the frame columns are directly fixedly embedded in the reinforced concrete cast-in-place piles on the lower portion by controlling the rigidity ratio of the sections of the piles to form a pile-column integrated structure, and the diameter of the frame columns is smaller than 0.5 times that of the reinforced concrete cast-in-place piles; frame column steel bars extend into the piles and are anchored to the reinforced concrete cast-in-place piles, the frame beams and the frame columns are poured together through reserved steel bars, the frame beams and the frame columns are rigidly connected to form a frame structure system, and trestle plates are fixed to the frame beams. According to the waterfront trestle, arrangement of a pile top bearing platform and a pile foundation connecting beam is omitted in the construction stage of the waterfront trestle, meanwhile, the piles can be integrally formed in a pouring mode, secondary pouring is avoided, and therefore construction procedures are reduced, and construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction, in particular to a waterfront trestle with a pile-column integrated frame structure. Background Art

[0002] The waterfront trestle is a common patrol and maintenance facility for rivers, lakes and other waters. It also has the functions of convenience, leisure, water-friendliness and landscape. It is not only practical, but also has a high ornamental value, lighting up the landscape of rivers, lakes and other waters. The waterfront trestle is usually located on the edge of a river, lake or ocean. It can effectively connect the traffic on both sides and facilitate people's travel. At the same time, it can also serve as an important channel for sightseeing and tourism, allowing tourists to enjoy the waterscape up close. The construction of the waterfront trestle can protect the ecological environment of rivers, lakes or oceans, prevent human activities from damaging them, and provide patrol and maintenance functions. In addition, some cities also hold various cultural activities on the trestle, such as concerts, art exhibitions, etc. The waterfront trestle is an important part of the urban landscape, and its existence can enhance the beauty and quality of the city. The design of the trestle usually incorporates local cultural and historical elements, making it a landmark building in the city. However, since the conventional method of constructing the bridge beam and the lower supporting structure of the waterfront trestle is often to use a separate structure by setting bearings, which is not an integral structure, the flood can easily damage the upper beam and slab; and it is necessary to set a cap and a pile foundation connecting beam transition at the top of the pile, and the cap and connecting beam must be cast separately, and the cap and connecting beam must reach a certain strength before the upper structure can be constructed. Therefore, the construction of the waterfront trestle project has many procedures, and the progress is slow, which cannot give full play to the advantages of the rapid construction of the waterfront trestle. Therefore, how to ensure the safety of the flood-overflowing bridge structure and improve the construction efficiency of the waterfront trestle under the premise of ensuring safety is an important direction for the design of waterfront trestle in the future. Utility Model Content

[0003] The purpose of the utility model is to provide a pile-column integrated frame structure waterfront trestle to solve the problem that the integrity of the waterfront trestle is poor. In the traditional construction method, it is necessary to set a pedestal and a pile foundation connecting beam at the top of the pile, and the pedestal and the connecting beam must reach a certain strength before the construction of the upper structure can be carried out. This traditional construction method leads to the problem that the waterfront trestle project has many construction processes and slow progress.

[0004] In order to solve the above technical problems, the utility model specifically provides the following technical solutions:

[0005] A pile-column integrated frame structure waterfront trestle comprises reinforced concrete bored piles, frame columns, frame beams and trestle plates, wherein the reinforced concrete bored piles are embedded in the foundation, the lower parts of the frame columns are directly embedded in the reinforced concrete bored piles to form a pile-column integrated structure, and the diameter of the frame columns is less than 0.5 times the diameter of the reinforced concrete bored piles, satisfying the cross-sectional stiffness ratio of the reinforced concrete bored piles and the frame columns, the two ends of the frame beams are fixed on two frame columns, the frame beams and the frame columns are rigidly connected to form a frame structure, the frame structure and the pile-column integrated structure form an overall rigid frame system, and the two ends of the trestle plate are fixed on two adjacent frame beams.

[0006] Furthermore, anchoring steel bars are provided at the lower part of the frame column, and the frame column is fixed to the internal steel bars of the reinforced concrete pile through the anchoring steel bars, and the reinforced concrete pile and the frame column are cast in one piece.

[0007] Furthermore, reserved steel bars are provided on the upper part of the frame columns, and the frame beams are cast together with the frame columns through the reserved steel bars, so that the frame beams and the frame columns form a frame structure.

[0008] Furthermore, the frame columns and the frame beams are prefabricated structures or cast-in-place structures.

[0009] Furthermore, the trestle board is made of prefabricated or cast-in-place reinforced concrete slabs, tempered laminated glass, and anti-corrosion wooden boards.

[0010] Furthermore, railings are provided on both sides of the trestle board.

[0011] Furthermore, a decorative layer is provided on the upper portion of the trestle board.

[0012] Compared with the prior art, the utility model has the following beneficial effects:

[0013] (1) High construction efficiency: The pile-column integrated frame structure waterfront pier eliminates the need for abutments and connecting beams by directly embedding the frame columns into the lower reinforced concrete piles. At the same time, the piles and columns can be cast in one piece, avoiding secondary casting, thereby greatly reducing the construction process and improving construction efficiency.

[0014] (2) Good structural stability: The frame columns and frame beams are connected by reserved steel bars and cast together to form a frame structure system. At the same time, the steel bars of the frame columns are extended into the piles and anchored in the reinforced concrete piles to form an integrated pile-column structure. The reinforced concrete piles, frame columns and frame beams of the waterfront pier are connected as a whole, which enhances the overall stability and seismic performance of the structure and improves the stability of the structure.

[0015] (3) Strong adaptability: The foundation adopts reinforced concrete cast-in-place piles, which can adapt to various geological conditions and solve the problem of large foundation scouring depth. At the same time, since the diameter of the frame column of the pile-column integrated frame structure waterfront trestle is smaller than that of the traditional bridge column, it has the characteristics of flexible layout and small water blocking effect, and has strong adaptability. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the implementation of the utility model or the technical solution in the prior art, the following is a brief introduction to the drawings required for the implementation or the prior art description. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.

[0017] Figure 1 It is a three-dimensional view of a waterfront trestle with a pile-column integrated frame structure according to the utility model;

[0018] Figure 2 It is a side sectional view of a waterfront trestle with a pile-column integrated frame structure according to the utility model;

[0019] Figure 3 This is a cross-sectional structural diagram of the connection between the frame column and the reinforced concrete cast-in-place pile of the utility model.

[0020] The numbers in the figure represent the following: 1. reinforced concrete cast-in-place piles; 2. frame columns; 3. frame beams; 4. trestle plates; 5. railings; 6. decorative layers; 7. anchoring steel bars. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0022] like Figures 1 to 3 As shown, the utility model provides a pile-column integrated frame structure waterfront trestle, comprising reinforced concrete cast-in-place piles 1, frame columns 2, frame beams 3 and trestle boards 4. The waterfront trestle eliminates the need for a pile top cap and a pile foundation connecting beam by directly embedding the frame columns 2 into the lower reinforced concrete cast-in-place piles 1. At the same time, the pile columns can be integrally cast to avoid secondary casting, thereby greatly reducing construction procedures and improving construction efficiency.

[0023] In the present invention, the reinforced concrete pile 1 is embedded in a solid foundation. This ensures the stability and bearing capacity of the trestle. Figure 2 As shown, the lower part of the frame column 2 is provided with an anchoring steel bar 7 extending into the reinforced concrete pile 1, and the frame column 2 is fixed to the internal steel bars of the reinforced concrete pile 1 through the anchoring steel bar 7. In this way, the connection strength between the frame column 2 and the reinforced concrete pile 1 can be enhanced, and the stability of the entire structure can be improved.

[0024] The two ends of the frame beam 3 are fixed on two frame columns 2, and the two ends of the trestle board 4 are fixed on two adjacent frame beams 3. In this way, the overall stability and bearing capacity of the trestle can be ensured. In order to further improve the stability and bearing capacity of the structure, the frame columns 2 and the frame beams 3 of the utility model are rigidly connected to form a frame structure.

[0025] First, the reinforced concrete piles 1 and the frame columns 2 are cast as one piece. This ensures the connection strength between the reinforced concrete piles 1 and the frame columns 2 and improves the stability of the entire structure. At the same time, this integrated design can also reduce construction procedures and improve construction efficiency. The reinforced concrete piles 1 and the frame columns 2 are cast as one piece and can also reduce the number of connection nodes and the complexity of the nodes, thereby reducing the construction difficulty and quality risks of the nodes. This integrated design can also improve the seismic performance of the structure, because the cast-in-place piles and the frame columns 2 can bear the load together and deform synergistically under the action of an earthquake, thereby enhancing the toughness and seismic resistance of the overall structure.

[0026] Secondly, the diameter of the frame column 2 is less than 0.5 times the diameter of the reinforced concrete pile 1. In the design, in order to ensure the embedded effect of the reinforced concrete pile 1 on the frame column 2 and the overall performance and stability of the structure, it is necessary to ensure that the stiffness ratio between adjacent components meets the requirements. For the frame structure, the stiffness of the reinforced concrete pile 1 is required to be greater than the stiffness of the frame column 2. Generally, the stiffness ratio can be controlled at about 10 times. By controlling the cross-sectional diameters of the reinforced concrete pile 1 and the frame column 2, their cross-sectional area and cross-sectional moment of inertia can be adjusted to control their stiffness. Specifically, the diameter of the frame column 2 is less than 0.5 times the diameter of the reinforced concrete pile 1, which means that the cross-sectional area, cross-sectional moment of inertia and stiffness of the frame column 2 are relatively small. The purpose of this design is to ensure that the stiffness ratio of the frame column 2 to the reinforced concrete pile 1 is less than 1 / 10, so that the reinforced concrete pile 1 has sufficient embedded effect on the frame column, and the frame column 2 can withstand the corresponding load and remain stable at the connection with the reinforced concrete pile 1. This design can not only reduce material consumption, but also reduce water flow resistance and improve the stability and seismic performance of the structure. When the frame column 2 is embedded in the reinforced concrete pile 1, the reinforced concrete pile 1 can provide greater anti-overturning ability, bending moment resistance and shear resistance, thereby reducing the calculated height of the frame column 2. A smaller frame column 2 height can reduce the total height of the structure and reduce the lateral displacement of the structure. At the same time, due to the reduction in the calculated height of the frame column 2, the force on the upper structure column will also be reduced accordingly. Therefore, a smaller cross-sectional size of the frame column 2 can be used to meet the load-bearing requirements of the structure.

[0027] By controlling the pile-column stiffness ratio to achieve the condition that the frame column 2 is completely embedded in the lower reinforced concrete pile 1, the economy and aesthetics of the structure can be achieved under the premise of ensuring the safety of the structure. In addition, this design can also simplify the construction process and improve construction efficiency. Setting the diameter of the frame column 2 to be less than 0.5 times the diameter of the reinforced concrete pile 1 can achieve the purpose of material saving and design flexibility under the premise of meeting the structural stability and functional requirements. This design can not only reduce material consumption and water flow resistance, but also improve the stability and seismic performance of the structure and improve construction efficiency. By controlling the pile-column stiffness ratio to achieve the condition that the frame column 2 is completely embedded in the lower reinforced concrete pile 1 base, the economy and aesthetics of the structure can be achieved under the premise of ensuring the safety of the structure.

[0028] Finally, a reserved steel bar is provided on the upper part of the frame column 2, and the frame beam 3 is cast together with the frame column 2 through the reserved steel bar, so that the frame beam 3 and the frame column 2 form a frame structure. During the construction process, the frame beam 3, the integral structure frame column 2 and the reinforced concrete cast-in-place pile 1 are cast together as a whole, further enhancing the integrity and stability of the waterfront trestle and improving the earthquake resistance.

[0029] Specifically, the trestle board 4 has various forms, and different materials and structures can be selected according to actual needs and scenarios. Common materials for the trestle board 4 include prefabricated or cast-in-place reinforced concrete slabs, tempered laminated glass, anti-corrosion wood boards, etc. These materials have good bearing capacity and durability, and can meet the use requirements of the trestle.

[0030] Specifically, railings 5 ​​are provided on both sides of the trestle board 4. There are many types of railings 5, and different types of railings 5 ​​can be selected according to different design styles and preferences. Common types of railings 5 ​​include stone railings 5, imitation wood railings 5, stainless steel railings 5, etc. These railings 5 ​​can not only play a decorative role, but also provide certain safety protection functions.

[0031] Specifically, a decorative layer 6 is provided on the upper part of the trestle board 4, and the selection of the decorative layer 6 can be carried out according to different scenes, requirements and construction effects. Common decorative surface materials include antiseptic wood surface layer, marble surface layer, colored concrete surface layer, etc. These decorative surface layers can increase the aesthetics of the trestle, coordinate with the surrounding environment, and enhance the overall landscape effect.

[0032] Specifically, the utility model can also adopt prefabricated frame columns 2 and frame beams 3, but a connection end connected to the upper frame column 2 must be reserved at the upper end of the reinforced concrete pile 1 to facilitate the connection between the prefabricated frame column 2 and the reinforced concrete pile 1, and a connection end must also be set at the connection between the prefabricated frame column 2 and the frame beam 3.

[0033] In summary, the utility model provides a pile-column integrated frame structure waterfront trestle, which has the characteristics of high construction efficiency, good structural stability and strong adaptability. By directly embedding the frame column 2 into the lower reinforced concrete cast-in-place pile 1, the setting of the pedestal and the connecting beam is eliminated, and the pile column can be cast in one piece, avoiding secondary casting, thereby greatly reducing the construction process and improving the construction efficiency. At the same time, by providing anchor steel bars 7, reserved steel bars and other measures, the stability and seismic resistance of the structure are enhanced. In addition, the utility model also has the characteristics of flexible layout, small water blocking effect, and small impact on flood discharge, and has strong adaptability.

[0034] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, ordinary technicians in the field should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model.

Claims

1. A pile-column integrated frame structure waterfront trestle, characterized in that: The invention comprises reinforced concrete bored piles (1), frame columns (2), frame beams (3) and a trestle board (4), wherein the reinforced concrete bored piles (1) are embedded in the foundation, the lower part of the frame column (2) is directly embedded in the reinforced concrete bored piles (1) to form a pile-column integrated structure, and the diameter of the frame column (2) is less than 0.5 times the diameter of the reinforced concrete bored pile (1), the two ends of the frame beam (3) are fixed on two frame columns (2), the frame beam (3) and the frame column (2) are rigidly connected to form a frame structure, the frame structure and the pile-column integrated structure form an overall rigid frame system, and the two ends of the trestle board (4) are fixed on two adjacent frame beams (3).

2. The pile-column integrated frame structure waterfront trestle according to claim 1, characterized in that: Anchor steel bars (7) are provided at the bottom of the frame column (2), and the frame column (2) is fixed to the internal steel bars of the reinforced concrete cast-in-place pile (1) via the anchor steel bars (7), and the reinforced concrete cast-in-place pile (1) and the frame column (2) are cast in one piece.

3. The pile-column integrated frame structure waterfront trestle according to claim 1, characterized in that: The upper part of the frame column (2) is provided with reserved steel bars, and the frame beam (3) is cast together with the frame column (2) via the reserved steel bars, so that the frame beam (3) and the frame column (2) form a frame structure.

4. The pile-column integrated frame structure waterfront trestle according to claim 1, characterized in that: The frame columns (2) and the frame beams (3) are prefabricated structures or cast-in-place structures.

5. The pile-column integrated frame structure waterfront trestle according to claim 1, characterized in that: The trestle board (4) is composed of a prefabricated or cast-in-place reinforced concrete board, tempered laminated glass and an anti-corrosion wooden board.

6. The pile-column integrated frame structure waterfront trestle according to claim 1, characterized in that: Railings (5) are provided on both sides of the trestle board (4).

7. The pile-column integrated frame structure waterfront trestle according to claim 1, characterized in that: A decorative layer (6) is provided on the upper part of the trestle board (4).

Citation Information

Cited By

  • Water passing road structure suitable for underneath passing high-speed railway in shoal area

    CN122485153A

  • A water crossing road structure suitable for crossing under a high-speed railway in a shallow area

    CN122485153B