Erecting structure of steel supporting beam and top beam

By using hanging plates and hanging parts in the connection between steel support beams and crown beams, combined with the design of pads and bolts, the problem of inconvenient connection between steel support beams and crown beams is solved, and fast, simple construction and uniform construction are achieved Axial force transmission, suitable for foundation pit support structures.

CN222008933UActive Publication Date: 2024-11-15SHENZHEN MUNICIPAL ENG CORP +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420549059.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-18
Publication Date
2024-11-15
Estimated Expiration
2034-03-18

AI Technical Summary

Technical Problem

In the prior art, the connection between the steel support beam and the crown beam is complicated and inconvenient during the construction process due to the center of the embedded steel plates being not in the same straight line or the construction period is limited, which affects the construction of the foundation pit support structure.

Method used

The connection and hanging part of the hanging plate and the steel support beam are bent and arranged through the pad plate on the top of the crown beam to ensure that the center line of the steel support beam is on the same straight line, and the connection and the outer end surface are fixed by bolts to achieve Adjustable connection structure simplifies construction process.

Benefits of technology

It ensures rapid erection of steel support beams, simple structure, convenient construction, low cost, and can effectively solve the connection problem when the embedded steel plate is misaligned or missed, ensuring uniform axial force transmission.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222008933U_ABST
    Figure CN222008933U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of steel support beams, and discloses a steel support beam and crown beam erection structure, which comprises a crown beam arranged at the tops of a plurality of support piles and a steel support beam, the end part of the steel support beam is connected with two hanging plates, the lower parts of the hanging plates are connected with the end part of the steel support beam to form a connecting part, and the top part of the connecting part is arranged in a bending manner. A hanging part is formed, and the hanging part and the connecting part are arranged in a bent mode; a base plate is arranged at the top of the crown beam, and the hanging part abuts against the base plate from top to bottom; when the embedded steel plate arranged in the top beam is staggered or even omitted, the connecting part of the hanging plate is connected with the steel supporting beam, the hanging part of the hanging plate is erected on the base plate at the top of the top beam, it can be ensured that the steel support can be erected, and the center line of the steel supporting beam is located on the same straight line by adjusting the thickness of the base plate; the steel support beam is simple in structure, convenient to construct, low in cost and capable of ensuring rapid erection of the steel support beam.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model patent relates to the technical field of steel support beams, and specifically, to the erection structure of steel support beams and crown beams. Background Art

[0002] With the continuous development of society, subway construction has become a key construction project in many cities. 90% of subway construction is located in the city center. Due to space limitations, foundation pit excavation mostly adopts open excavation construction. In order to ensure the safety of construction and the surrounding environment of the foundation pit, support, reinforcement and protection measures are needed for the side walls of the foundation pit and the surrounding environment.

[0003] The supporting structure of the foundation pit includes a plurality of supporting piles arranged on the periphery of the foundation pit, a cap beam is provided on the plurality of supporting piles, and a plurality of steel support beams are arranged above the foundation pit, the ends of the steel support beams are connected to the cap beams, and the plurality of steel support beams are arranged in a truss shape. Since the steel support beams can be reused, they are widely used in foundation pit support.

[0004] In the prior art, in order to achieve the connection between the crown beam and the steel support beam, an embedded steel plate is generally arranged on the inner side of the crown beam, and the centers of the two embedded steel plates are ensured to be in the same straight line. When the steel support beam is erected, a welding bracket is arranged at the bottom of the embedded steel plate, and then the end of the steel support beam is erected on the welding bracket, and axial force is applied to fix it.

[0005] However, since the embedded steel plates are embedded in advance when constructing the crown beam, it often happens that the centers of the two embedded steel plates are not in the same straight line due to various restrictions during the construction process. In some projects, due to time constraints, the construction link of the embedded steel plates will be omitted, resulting in the inability to complete the erection of the steel support beam, or the erection structure between the steel support beam and the crown beam is complicated, the construction is inconvenient, and the construction of the entire support structure is affected. Utility Model Content

[0006] The utility model aims to provide a steel support beam and a crown beam erection structure, aiming to solve the problem of inconvenience in construction of the steel support beam and the crown beam erection structure in the prior art.

[0007] The utility model is implemented as follows: the erection structure of a steel support beam and a crown beam comprises a crown beam and a steel support beam arranged on the top of a plurality of support piles, the ends of the steel support beam are connected to two hanging plates, the lower parts of the hanging plates are connected to the ends of the steel support beam to form a connecting part, the top of the connecting part is bent to form a hanging part, and the hanging part and the connecting part are bent; a pad is provided on the top of the crown beam, and the hanging part is pressed against the pad from top to bottom.

[0008] Furthermore, the connecting portion is arranged longitudinally.

[0009] Furthermore, the hanging portion is arranged horizontally, and the hanging portion and the connecting portion are bent at a right angle.

[0010] Furthermore, a bending position is formed between the hanging portion and the connecting portion, and a diagonal support plate is provided at the bending position, the top of the diagonal support plate is butted against the bottom of the hanging portion, and the side of the diagonal support plate is butted against the connecting portion.

[0011] Furthermore, both sides of the end of the steel support beam respectively have outer end surfaces arranged outward, and the two connecting parts are respectively connected to the two outer end surfaces and arranged in parallel.

[0012] Furthermore, the connection part is arranged in a flat plate shape, the connection part is attached to the outer end surface, and the connection part is relatively fixed to the outer end surface by bolts passing through the connection part and the outer end surface.

[0013] Furthermore, the backing plate is fixed to the top of the crown beam by bolts, and the top of the backing plate is recessed downward to form a groove, and the hanging part is embedded in the groove.

[0014] Furthermore, the end of the steel support beam has a docking flange, the docking flange is connected to an end portion, the end portion abuts against the inner side of the crown beam, and both sides of the docking flange respectively form the outer end faces.

[0015] Furthermore, the groove is formed in the middle of the pad, and connecting sides are formed on both sides of the pad respectively. A plurality of bolts are passed through the connecting sides, and the plurality of bolts fix the pad to the crown beam; the plurality of bolts on the connecting sides are staggered along the length direction of the groove.

[0016] Furthermore, the strip groove passes through the outer end of the pad to form an outer end opening, and the hanging part is inserted into the strip groove through the outer end opening; the inner end of the strip groove forms an inner end wall, and the inner end wall extends toward the hanging part to form an upper pressing plate, and the upper pressing plate is located above the strip groove;

[0017] A slot is formed between the upper pressing plate and the strip groove, the hanging part is inserted into the slot and arranged with a spacing between the inner end wall, and the upper pressing plate presses against the hanging part from top to bottom.

[0018] Compared with the prior art, the erection structure of the steel support beam and the crown beam provided by the utility model can ensure that the steel support can be erected by utilizing the connection between the connecting part of the hanging plate and the steel support beam when the embedded steel plate arranged inside the crown beam is misplaced or even missed. The hanging part of the hanging plate is erected on the pad at the top of the crown beam, which can ensure that the steel support can be erected. By adjusting the thickness of the pad, it can ensure that the center lines of the steel support beams are in the same straight line, which facilitates the uniform transmission of the axial force applied by the steel support beam in the later stage. The utility model has a simple structure, convenient construction, low cost, and can ensure the rapid erection of the steel support beam. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the main view of the erection structure of the steel support beam and the crown beam provided by the utility model;

[0020] Figure 2 It is a schematic diagram of the main view of the hanging board provided by the utility model;

[0021] Figure 3 It is a cross-sectional schematic diagram of the cooperation between the hanging part and the pad provided by the utility model. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.

[0023] The implementation of the present utility model is described in detail below in conjunction with specific embodiments.

[0024] The same or similar numbers in the drawings of this embodiment correspond to the same or similar parts; in the description of the present utility model, it should be understood that if the terms "upper", "lower", "left", "right" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the drawings, it is only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and cannot be understood as limitations on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0025] Reference Figure 1-3 As shown, it is a preferred embodiment provided by the utility model.

[0026] The erection structure of the steel support beam and the crown beam includes a crown beam 101 arranged on the top of a plurality of support piles 100 and a steel support beam 400, wherein the plurality of support piles 100 are arranged along the outer periphery of the foundation pit; two hanging plates are connected to the ends of the steel support beam 400, the lower parts of the hanging plates are connected to the ends of the steel support beam 400 to form a connecting portion 401, the top of the connecting portion 401 is bent to form a hanging portion 400, and the hanging portion 400 and the connecting portion 401 are bent; a pad 300 is provided on the top of the crown beam 101, and the hanging portion 400 is pressed against the pad 300 from top to bottom.

[0027] In actual use, the connecting parts 401 of the two hanging plates are first connected to the ends of the steel support beam 400. After the construction of the foundation pit support structure, when the embedded steel plate inside the crown beam 101 is misplaced or missing, the hanging parts 400 of the two hanging plates can be erected on the half point on the top of the crown beam 101, and ensure that the center lines of the steel support beam 400 are in the same straight line, so as to facilitate the uniform transmission of the axial force applied by the steel support beam 400 in the later stage.

[0028] The above-mentioned erection structure of the steel support beam and the crown beam can ensure that the steel support can be erected when the embedded steel plate arranged inside the crown beam 101 is misplaced or even missed by utilizing the connection between the connecting portion 401 of the hanging plate and the steel support beam 400. The hanging portion 400 of the hanging plate is erected on the pad 300 at the top of the crown beam 101. By adjusting the thickness of the pad 300, it can be ensured that the center lines of the steel support beam 400 are in the same straight line, so that the axial force applied by the steel support beam 400 in the later stage is evenly transmitted. The structure is simple, the construction is convenient, the cost is low, and the rapid erection of the steel support beam 400 can be ensured.

[0029] The connection part 401 is arranged longitudinally, so that it is convenient to connect the connection part 401 with the end of the steel support beam 400, and the center line of the steel support beam 400 can be adjusted to be in the same straight line more conveniently.

[0030] The hanging part 400 is arranged horizontally, and is bent at a right angle to the connecting part 401. In this way, the hanging part 400 is conveniently mounted on the pad 300 at the top of the crown beam 101, and it is more advantageous to ensure that the center lines of the steel support beam 400 are in the same straight line.

[0031] In some embodiments, a bending position is formed between the hanging portion 400 and the connecting portion 401, and a diagonal support plate 403 is provided at the bending position, the top of the diagonal support plate 403 is butted against the bottom of the hanging portion 400, and the side of the diagonal support plate 403 is butted against the connecting portion 401. By providing the diagonal support plate 403, the connecting portion 401 and the hanging portion 400 can be made more stable, and the phenomenon of bending angle change during the supporting process can be avoided.

[0032] The two ends of the steel support beam 400 have outer end surfaces facing outwards, and the two connecting parts 401 are respectively connected to the two outer end surfaces and arranged in parallel. In this way, the two connecting parts 401 clamp and fix the ends of the steel support beam 400 to ensure the stability of the connection between the hanging plate and the steel support beam 400.

[0033] In some embodiments, the connection part 401 is arranged in a flat plate shape, and the connection part 401 is attached to the outer end surface. The connection part 401 is relatively fixed to the outer end surface by passing the bolt through the connection part 401 and the outer end surface. In this way, the detachable connection between the hanging plate and the steel support beam 400 is achieved, and the connection area between the connection part 401 and the end of the steel support beam 400 is larger, and the connection is more stable.

[0034] The top of the crown beam 101 to which the backing plate 300 is fixed by bolts, and the top of the backing plate 300 is concave downward to form a groove 405, and the hanging part 400 is embedded in the groove 405. In this way, the position connection of the hanging part 400 on the backing plate 300 is restricted by the groove 405, avoiding the phenomenon of lateral displacement, so that the connection between the hanging part 400 and the backing plate 300 is more stable.

[0035] In some embodiments, the end of the steel support beam 400 has a docking flange 404, the docking flange 404 is connected to an end portion 402, the end portion 402 abuts against the inner side of the crown beam 101, and both sides of the docking flange 404 respectively form the above-mentioned outer end surfaces.

[0036] The groove 405 is formed in the middle of the pad 300 , and the two sides of the pad 300 form connecting sides respectively. A plurality of bolts are passed through the connecting sides, and the plurality of bolts fix the pad 300 to the crown beam 101 ; the plurality of bolts on the connecting sides are staggeredly arranged along the length direction of the groove 405 .

[0037] By arranging multiple bolts on the connection side in a staggered arrangement, multiple position staggered connections can be achieved, so that the pad 300 is more firmly connected to the top of the crown beam 101 . The groove 405 is located between the two connection sides, which facilitates the hanging part 400 to be inserted into the groove 405 .

[0038] In some embodiments, the strip groove 405 passes through the outer end of the pad 300 to form an outer end opening, and the hanging part 400 is inserted into the strip groove 405 through the outer end opening; the inner end of the strip groove 405 forms an inner end wall, and the inner end wall extends toward the hanging part 400 to form an upper pressing plate 301, and the upper pressing plate 301 is located above the strip groove 405;

[0039] A slot is formed between the upper pressing plate 301 and the strip groove 405 , and the hanging portion 400 is inserted into the slot and arranged with a spacing between the upper pressing plate 301 and the inner end wall. The upper pressing plate 301 presses against the hanging portion 400 from top to bottom.

[0040] There is a gap between the hanging part 400 and the inner end wall to facilitate the hanging part 400 to adjust the insertion depth in the strip groove 405, etc. By pressing the hanging part 400 from top to bottom with the upper pressure plate 301, the hanging part 400 can be clamped upward and downward so that the hanging part 400 can be more firmly placed in the strip groove 405.

[0041] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. The erection structure of steel support beams and crown beams is characterized in that: It includes a crown beam and a steel support beam arranged on the top of multiple supporting piles, two hanging plates are connected to the ends of the steel support beam, the lower part of the hanging plate is connected to the end of the steel support beam to form a connecting part, the top of the connecting part is bent to form a hanging part, and the hanging part and the connecting part are bent; a pad is provided on the top of the crown beam, and the hanging part is pressed against the pad from top to bottom.

2. The steel support beam and crown beam erection structure according to claim 1, characterized in that: The connecting portion is arranged longitudinally.

3. The steel support beam and crown beam erection structure according to claim 2, characterized in that: The hanging portion is arranged in a transverse direction, and the hanging portion and the connecting portion are bent in a right angle.

4. The steel support beam and crown beam erection structure according to claim 3, characterized in that: A bending position is formed between the hanging portion and the connecting portion, and a diagonal support plate is provided at the bending position. The top of the diagonal support plate is butted against the bottom of the hanging portion, and the side of the diagonal support plate is butted against the connecting portion.

5. The steel support beam and crown beam erection structure according to any one of claims 1 to 4, characterized in that: Both sides of the end of the steel support beam respectively have outer end surfaces arranged outward, and the two connecting parts are respectively connected to the two outer end surfaces and are arranged in parallel.

6. The steel support beam and crown beam erection structure according to claim 5, characterized in that: The connecting part is arranged in a flat plate shape, and the connecting part is attached to the outer end surface. The connecting part is relatively fixed to the outer end surface by bolts passing through the connecting part and the outer end surface.

7. The steel support beam and crown beam erection structure according to claim 6, characterized in that: The backing plate is fixed to the top of the crown beam by bolts, and the top of the backing plate is recessed downward to form a groove, and the hanging part is embedded in the groove.

8. The steel support beam and crown beam erection structure according to claim 7, characterized in that: The end of the steel support beam is provided with a butt flange, the butt flange is connected with an end head, the end head abuts against the inner side of the crown beam, and the two sides of the butt flange respectively form the outer end faces.

9. The steel support beam and crown beam erection structure according to claim 7, characterized in that: The strip groove is formed in the middle of the pad, and two sides of the pad form connecting sides respectively. A plurality of bolts are passed through the connecting sides, and the plurality of bolts fix the pad to the crown beam; the plurality of bolts on the connecting sides are staggeredly arranged along the length direction of the strip groove.

10. The steel support beam and crown beam erection structure according to claim 9, characterized in that: The strip groove passes through the outer end of the pad to form an outer end opening, and the hanging part is inserted into the strip groove through the outer end opening; the inner end of the strip groove forms an inner end wall, and the inner end wall extends toward the hanging part to form an upper pressing plate, and the upper pressing plate is located above the strip groove; A slot is formed between the upper pressing plate and the strip groove, the hanging portion is inserted into the slot and is spaced apart from the inner end wall, and the upper pressing plate presses against the hanging portion from top to bottom.