Blade foot used in complex geology land large-diameter open caisson construction process
By using embedded steel bars tied with blades and outsourcing galvanized steel plates in large-diameter caisson construction, the problem of insufficient strength of the existing blade feet is solved, and more stable sinking and more efficient construction is achieved, especially in complex under geological and abundant groundwater conditions.
Patent Information
- Application Number
- CN202420627199.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-28
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-03-28
AI Technical Summary
In the construction of large-diameter caisson under complex geological conditions, the existing blade foot strength is insufficient, resulting in increased construction difficulty, and traditional processes have problems of uneven sinking and difficulty in precipitation.
The blade foot is tied with embedded steel bars, and the galvanized steel plate is outsourced. The bottom of the blade foot is inverted right-angle trapezoid. Combined with mechanical connection and welding technology, the strength and stability of the blade foot is enhanced, the construction process is reduced, and the soil cutting capacity is improved.
It improves the stability and construction efficiency of caisson sinking, reduces construction difficulty, prevents high head erosion, enhances the protective performance of the blade feet, and ensures normal construction under complex geological conditions.
Smart Images

Figure CN222008973U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of caisson construction devices, in particular to a blade foot used in the construction process of large-diameter caissons on land with complex geology, and is suitable for the construction of large-diameter and ultra-deep caissons in complex geological water-rich strata. Background Art
[0002] With the vigorous development of my country's infrastructure, my country's caisson construction has gradually become the world's forefront. Large caissons are more widely used because of their overall structural rigidity, good stability, large bearing capacity, ability to support large loads, and good durability. At the same time, caissons have the characteristics of small construction interference, safety and reliability, small footprint, and little impact on surrounding buildings. Due to the increase in bearing loads, the size of caissons has gradually increased, and the construction of large-diameter caissons has gradually become a trend. However, the construction technology of diameter caissons is still in the development stage, and there are not many research results on the stress characteristics of caissons during the sinking process. Caisson projects have high limitations if they are constructed using traditional techniques. Improper construction can easily lead to problems such as uneven sinking of roads and buildings and difficulties in precipitation in areas with abundant groundwater.
[0003] The supporting pipeline project of the Ash River Sewage Treatment Plant in Harbin City, the main sewage pipeline project through the Ash River section has a total of 4 caissons arranged along the Ash River, numbered 1#-4#, with a depth of about 22.75m-34.05m; 2# and 4# caissons are working wells for jacking construction, and 1# and 3# caissons are receiving wells for jacking construction. The soil in the site is sandy soil and clay, and there is upper stagnant water caused by pipeline and ditch leakage, rainwater infiltration and other factors. The upper stagnant water level is 3.1~8.6m, and the stable water level is 2.2~7.5m. The groundwater is extremely abundant, and the groundwater is connected to the Ash River, which makes precipitation difficult. The caisson needs to pass through the plastic and hard plastic clay layers in the later stage, which greatly increases the difficulty of construction. However, the existing caisson blade foot strength is not enough, and it is not conducive to the sinking of the caisson, which increases the difficulty of construction. Utility Model Content
[0004] In view of this, in order to solve the technical problems mentioned in the above background technology, the utility model aims to propose a blade foot used in the construction process of large-diameter caissons on land with complex geology.
[0005] To achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a blade foot used in the construction process of a large-diameter caisson on land with complex geology, comprising a blade foot body and a steel plate, wherein the blade foot body is formed by binding pre-embedded steel bars, a steel plate is fixed to the outer periphery of the blade foot body, and the bottom of the blade foot body is an inverted right-angled trapezoid.
[0006] Furthermore, the steel plate is a galvanized steel plate.
[0007] Furthermore, the steel plate is 3 mm.
[0008] Furthermore, the steel plate is made of Q235B material.
[0009] Furthermore, the height of the blade body is 1500 mm.
[0010] Furthermore, when the diameter of the embedded steel bars is 22 ≥ d ≥ 18 mm, the stress-bearing steel bar joints are connected by welding or mechanical connection.
[0011] Furthermore, when the diameter of the embedded steel bar d>22mm, the stressed steel bar joints are mechanically connected.
[0012] Furthermore, when the diameter of the embedded steel bars is d≤16mm, the joints of the stress-bearing steel bars and the non-stress-bearing distribution steel bars are overlapped by welding or binding.
[0013] Furthermore, the embedded steel bars include annular steel bars on the inner side of the blade foot, annular steel bars on the outer side of the blade foot, vertical combined steel bars at the blade foot, vertical steel bars on the inner side of the blade foot, annular steel bars on the bottom of the blade foot and a plurality of tension bars. The annular steel bars on the inner side of the blade foot are tied to the inner side of the blade foot body, the annular steel bars on the outer side of the blade foot are tied to the outer side of the blade foot body, and the annular steel bars on the bottom of the blade foot are tied to the bottom of the blade foot body. A plurality of tension bars are horizontally tied between the blade foot bodies. The outer side of the upper end of the blade foot body is tied with the vertical combined steel bars at the blade foot, and the inner side is tied with the vertical steel bars on the inner side of the blade foot.
[0014] Furthermore, the diameter of the annular steel bars on the inner side of the blade foot and the outer side of the blade foot are 28mm, with a spacing of 100cm; the diameter of the vertical combined steel bars at the blade foot and the vertical steel bars on the inner side of the blade foot are 32mm, with a spacing of 100cm; the diameter of the annular steel bars at the bottom of the blade foot is 25mm, and there are 10 of them.
[0015] Compared with the prior art, the blade foot used in the construction process of a large-diameter caisson on land with complex geology described in the utility model has the following beneficial effects:
[0016] (1) The utility model of the caisson blade foot belt is covered with a steel plate, which acts as a template during construction, reduces construction procedures, and saves construction time.
[0017] (2) Compared with the traditional concrete blade foot, the friction between the steel plate of the utility model and the soil layer is small, which is conducive to the sinking of the caisson.
[0018] (3) Compared with the traditional concrete blade foot, the outer steel plate blade foot is stronger and more convenient for cutting soil layers.
[0019] (4) During the sinking process of the caisson, the outer steel plate of the utility model plays a protective role to prevent high water head from scouring the concrete surface. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention.
[0021] Figure 1 This is a flow chart of the construction process of large-diameter caissons on land with complex geology;
[0022] Figure 2 It is a schematic diagram of the structure of the blade foot used in the construction process of a large-diameter caisson on land in complex geological conditions as described in the utility model;
[0023] Figure 3 It is a schematic diagram of the binding of blade feet used in the construction process of large-diameter caisson on land in complex geological conditions as described in the utility model;
[0024] Figure 4 Layout of the caisson for practical applications Figure 1 ;
[0025] Figure 5 Layout of the caisson for practical applications Figure 2 .
[0026] Among them: 1-steel plate, 2-embedded steel bars, 3-blade body, 4-caisson. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely explain the technical solutions in the embodiments of the utility model. It should be noted that the embodiments and features in the embodiments of the utility model can be combined with each other without conflict, and the described embodiments are only part of the embodiments of the utility model, not all of the embodiments.
[0028] See also Figure 1-5 To illustrate the present embodiment, a blade foot used in the construction of a large-diameter caisson on land with complex geology includes a blade foot body 3 and a steel plate 1. The blade foot body 3 is formed by binding pre-embedded steel bars 2. The steel plate 1 is fixed to the periphery of the blade foot body 3. The bottom of the blade foot body 3 is an inverted right-angled trapezoid.
[0029] The steel plate 1 is a galvanized steel plate. The steel plate 1 is 3 mm thick. The steel plate 1 is made of Q235B material.
[0030] The height of the blade foot body 3 is 1500 mm, and the blade foot is located at the bottom end of the caisson wall.
[0031] A method for constructing a large-diameter caisson on land with complex geology, specifically comprising the following steps:
[0032] Step 1: Pit drainage: Set up intercepting ditches around the pit, connect them to the municipal drainage well, build retaining walls around the pit to prevent rainwater from flowing into the pit, and set up a sump in the pit;
[0033] Step 2: Site foundation pit construction: During construction, according to the caisson layout orientation provided by the design, measurement and layout are carried out to determine the scope of the caisson cushion foundation pit excavation, and then excavation is carried out. Before the first section of the caisson is made, the caisson foundation pit needs to be manually leveled and a coarse sand cushion layer is laid at the bottom of the foundation pit;
[0034] Step 3: Formwork support construction: Prepare 1.5m high and 3mm thick Q235B galvanized steel plate for the well wall, weld HRB300 embedded steel bars inside the galvanized steel plate, prepare and install the outer and inner supports of the caisson, and use double-row buckle scaffolding for the inner and outer walls of the well;
[0035] Step 4: Blade foot construction: prepare blade foot steel bars, then process the blade foot steel bars into blade feet, and pour blade foot concrete after the steel bar formwork is fixed and tied;
[0036] Step 5: Shaft wall construction: Shaft wall construction sequence: Tie up the steel bars at the blade foot → Install the formwork → Pour concrete → Sink the caisson → Tie up the steel bars of the next section of the caisson → Install the formwork → Pour concrete → Sink the caisson to the last section of the caisson and pour concrete;
[0037] Step 6: Treatment of the reserved hole of the caisson: A circle of water-stop steel ring plates for the hole gate needs to be embedded at the hole gate of the jacking pipe and cast together with the concrete of the well wall structure. The steel ring of the caisson hole gate is made and installed, and then a hole is reserved at the entrance and exit position of the jacking pipe;
[0038] Step 7: Caisson sinking: The concrete cushion layer is chiseled off, and the caisson is made in sections and sunk in stages. The groundwater level is observed in real time, and the caisson is sunk without drainage. After the blade foot is completely buried in the soil, the mud pump is turned on, and thixotropic mud is injected while the caisson sinks. After the caisson sinks stably, the bottom of the caisson is sealed;
[0039] Step 8: Base plate construction: base plate reinforcement tying and base plate concrete pouring.
[0040] The construction of the blade foot in the large-diameter caisson construction method on land with complex geology is described as follows:
[0041] 1. Blade foot reinforcement construction
[0042] (1) The embedded steel bars 2 of the blade foot are processed into semi-finished products in the steel bar processing plant, and are marked with different specifications and numbers and stacked in the steel bar storage area. The truck crane cooperates with manual labor to move the steel bars to the work surface and tie and connect them according to the design and specification requirements.
[0043] Table 1 Summary of steel bar profile at blade foot
[0044]
[0045] (2) Tie-up form and lap length of steel bars
[0046] When the diameter of the steel bar of the utility model is 22≥d≥18mm, the stress-bearing steel bar joints are connected by welding or mechanical connection, with mechanical connection being preferred; when the diameter d>22mm, the stress-bearing steel bar joints are connected mechanically; when the diameter d≤16mm, the stress-bearing steel bar and non-stress-bearing distribution steel bar joints can be welded or tied and overlapped, with welding connection being preferred.
[0047] The specific connection forms and requirements are as follows:
[0048] ①Welding connection:
[0049] The mechanical connection joints of adjacent longitudinal bars in the same component should be staggered. The length of the connection section of the mechanical connection joint is 35d (d is the smaller diameter of the connected steel bar) and not less than 500mm. The percentage of the joint area of the tensile longitudinal bars in the same connection section should not be greater than 50%, and the longitudinal compressive steel bars may not be restricted. Weld length: 10d for single-sided welding and 5d for double-sided welding. The welding of ribbed steel bars with a diameter greater than 28mm should be determined by test, and residual heat treated steel bars should not be welded.
[0050] ② Mechanical connection:
[0051] The mechanical connection joints of adjacent longitudinal reinforcements in the same component are staggered. The length of the mechanical connection joint connection section is 35d (d is the smaller diameter of the connected reinforcement). The percentage of the tensile longitudinal reinforcement joint area in the same connection section should not be greater than 50%, and the longitudinal compression reinforcement can be unrestricted. The concrete cover thickness of the mechanical connection sleeve meets the requirements for the minimum steel bar cover thickness, and the lateral clearance of the sleeve should not be less than 25mm.
[0052] ③Binding and overlapping:
[0053] The tied lap joints of adjacent longitudinal tension bars in the same component are staggered. The length of the lap joint connection section is 1.3 times the lap length. The percentage of the lap joint area of the tensile reinforcement located in the same connection section: for beams, slabs and walls, it should not be greater than 25%. The minimum lap length of the longitudinal compression reinforcement should not be less than 70% of the lap length of the longitudinal tension reinforcement mentioned above, and should not be less than 200mm.
[0054] ④ The binding form and lap length design of the steel bars of the 4 caisson blades, shaft walls and bottom plates are the same and will not be described later.
[0055] 2. Blade foot concrete construction
[0056] After the steel bar formwork is fixed and tied, the blade foot concrete is poured.
[0057] (1) Casting sequence
[0058] Concrete pouring is carried out by two overhead pumps into the warehouse, and the pouring is symmetrical. After pouring one layer, pouring continues from the starting point of the previous layer. The drop of the concrete of the caisson blade, the wall and the bottom plate is greater than 6m. The concrete pouring method of stringing barrels into the warehouse can be used.
[0059] (2) Casting method
[0060] When pouring concrete at the blade foot, it should be done in layers and continuously, with each layer thickness of 30cm-50cm. The initial setting time of concrete, structural characteristics, and density of steel bars are comprehensively considered and determined. The thickness of each layer is controlled at 30-50cm. The concrete is vibrated by an inserted ZN50 vibrator. When using a vibrating rod, the distance between the vibrating rod and the template should not be greater than 0.5 times the radius of action of the vibrator, and it should not be vibrated close to the template to avoid collision with steel bars, embedded parts, etc. The time for each insertion and vibration is about 20-30 seconds. When vibrating, pay attention to the corners and reserved openings to fully vibrate and compact them. The vibration should be carried out in the order from bottom to top and from corner to middle, and the vibration time should be strictly controlled. When using an inserted vibrator, it should be inserted quickly and pulled out slowly. The insertion points should be evenly arranged, moved point by point, and carried out in sequence without omission to achieve uniform vibration. The moving spacing should not be greater than 1.5 times the radius of action of the vibration (generally 30-40cm). When vibrating the upper layer, the lower layer should be inserted 5-10cm to ensure that the two layers of concrete are firmly combined.
[0061] (3) Blade foot concrete maintenance
[0062] The concrete shall be covered and watered within 12 hours after pouring. The blade foot shall be covered with geotextile and watered for 14 days.
[0063] (4) Analysis of blade foot concrete pouring
[0064] Taking the 1# caisson blade foot as an example, it is calculated that about 697 cubic meters of concrete need to be poured for the caisson blade foot. The pouring construction was completed in one day according to the planned construction period. Each sky pump needs to pour about 29 cubic meters per hour. The working efficiency of each sky pump is 20-40 cubic meters per hour, and two sky pumps meet the construction requirements.
[0065] Application Examples
[0066] 1. Ashi River Sewage Treatment Plant Supporting Pipeline Project (Sewage Trunk Line Project Passing Through Ashi River Section)
[0067] The supporting pipeline project of Ash River Sewage Treatment Plant is located in Daowai District, Harbin City. There are 4 caissons arranged along the Ash River for the sewage trunk line project, numbered 1# (K0+138)-4# (K2+733), with a depth of about 22.75m-34.05m; 2# and 4# caissons are working wells for pipe jacking construction, and 1# and 3# caissons are receiving wells for pipe jacking construction. The concrete strength grade of the working well, receiving well, etc. is C40, the bottom concrete is C30, the impermeability grade is P12, the concrete filling in the structure is C25 (anti-cracking concrete), and the cushion concrete is C20. When the 1# well caisson was constructed, the foundation bearing capacity of the excavated medium sand layer was fa=220kPa, and when the 2# well caisson was constructed, the base was replaced with 2m thick medium-coarse sand with a foundation bearing capacity of fa=220kPa. The base of the 3# caisson is made of medium sand with a foundation bearing capacity of fa=220kPa, and the base of the 4# caisson is made of medium sand with a foundation bearing capacity of fa=220kPa according to geological and hydrological conditions.
[0068] The project will start in April 2022 and be completed in October 2022. The foundation pit is excavated mechanically, coarse sand is laid at the bottom of the foundation pit, and a concrete cushion is poured. The inner wall of the well is pre-buried with an I-beam bracket platform, and the inner wall bracket of the caisson is erected on the I-beam bracket platform. The blade foot steel bars are processed in the steel bar processing yard, and the well wall steel bars are tied and concrete is poured. The caisson adopts the principle of "segmented production and step-by-step sinking", and uses manual pneumatic picks to chisel out the cushion layer. The groundwater level is observed in real time, and non-drainage sinking is taken in time to avoid water and sand gushing. After the blade foot is completely buried in the soil, the mud pump is turned on, and the caisson is injected with thixotropic mud while sinking. The sinking construction is divided into three stages: initial sinking, normal sinking, and final sinking, and corrective control measures are taken respectively. After the caisson sinks stably, the non-drainage vertical conduit method is used to pour underwater bottom concrete. This method ensures the normal construction of large-diameter and ultra-deep caissons under complex geological conditions and abundant groundwater. The construction quality meets the design and relevant quality acceptance specifications. This method is safe and reliable, convenient to construct, fast in construction, safe and environmentally friendly, efficient and energy-saving, good in quality, meets the construction unit's construction period requirements, has significant economic and social benefits, and provides valuable experience for similar engineering construction.
[0069] 2. EPC project of tailwater discharge from Tangxun Lake sewage treatment plant to the river
[0070] The EPC utility model of the tailwater discharge project of Tangxun Lake Sewage Treatment Plant is located in Hongshan District, Wuhan City. There are 4 vertical shafts along the north bank of Tangxun Lake, numbered 1# (K6+514.172)-4# (K10+287.99), with a depth of about 19.4m-25m; 1# and 4# shafts are working shafts for pipe jacking construction, 2# shaft is a receiving shaft for pipe jacking construction, and 3# shaft is both a working shaft and a receiving shaft. The concrete strength grade of the working well, receiving well, etc. is C35, the impermeability grade is S8, and the concrete filling and cushion layer in the structure is C15. A circle of interlocking plain concrete piles are constructed around the foundation pit of the 3# and 4# caissons as a water-stop curtain, and the concrete strength grade is C20. The base of the 1#, 2#, and 3# wells is (5-2) medium-weathered mudstone siltstone foundation with a bearing capacity of fa=1500kPa, and the base of the 4# caisson is (5-1) strongly weathered mudstone siltstone foundation with a bearing capacity of fa=450kPa.
[0071] The project will start in January 2022 and be completed in December 2022. The foundation pit is excavated mechanically, coarse sand is laid at the bottom of the foundation pit, and a concrete cushion is poured. An I-beam bracket platform is embedded in the inner wall of the well, and the inner wall bracket of the caisson is erected on the I-beam bracket platform. The blade foot steel bars are processed in the steel bar processing yard, and the well wall steel bars are tied and concrete is poured. The caisson adopts the principle of "segmented production and step-by-step sinking". The cushion layer is chiseled out by manual pneumatic picks, the groundwater level is observed in real time, and non-drainage sinking is taken in time to avoid water and sand gushing. After the blade foot is completely buried in the soil, the mud pump is turned on, and the caisson is injected with thixotropic mud while sinking. The sinking construction is divided into three stages: initial sinking, normal sinking, and final sinking, and corrective control measures are taken respectively. After the caisson sinks stably, the non-drainage vertical conduit method is used to pour underwater bottom concrete. This method ensures the normal construction of large-diameter and ultra-deep caissons under complex geological conditions and abundant groundwater. The construction quality meets the design and relevant quality acceptance specifications. This method is safe and reliable, convenient to construct, fast in construction, safe and environmentally friendly, efficient and energy-saving, good in quality, meets the construction unit's construction period requirements, has significant economic and social benefits, and provides valuable experience for similar engineering construction.
[0072] The embodiments of the utility model disclosed above are only used to help explain the utility model. The embodiments do not describe all the details in detail, nor do they limit the utility model to the specific implementation methods described. According to the content of this specification, many modifications and changes can be made. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the utility model, so that technicians in the relevant technical field can well understand and use the utility model.
Claims
1. A blade foot used in the construction of large-diameter caissons on land with complex geology, characterized by: It comprises a blade body (3) and a steel plate (1), wherein the blade body (3) is formed by binding pre-buried steel bars (2), a steel plate (1) is fixed to the outer periphery of the blade body (3), and the bottom of the blade body (3) is an inverted right-angled trapezoid.
2. The blade foot used in the construction process of large-diameter caisson on land with complex geology according to claim 1 is characterized by: The steel plate (1) is a galvanized steel plate.
3. The blade foot used in the construction process of large-diameter caisson on land with complex geology according to claim 1 or 2, characterized in that: The steel plate (1) is 3 mm thick.
4. The blade foot used in the construction process of large-diameter caisson on land with complex geology according to claim 1 or 2, characterized in that: The steel plate (1) is made of Q235B material.
5. The blade foot used in the construction process of large-diameter caisson on land with complex geology according to claim 1 or 2, characterized in that: The height of the blade body (3) is 1500 mm.
6. The blade foot used in the construction process of large-diameter caisson on land with complex geology according to claim 1 is characterized by: When the diameter of the embedded steel bar (2) is 22 ≥ d ≥ 18 mm, the joints of the stress-bearing steel bars shall be connected by welding or mechanical means.
7. The blade foot used in the construction of large-diameter caissons on land with complex geology according to claim 6 is characterized by: When the diameter d of the embedded steel bar (2) is greater than 22 mm, the stress-bearing steel bar joints are mechanically connected.
8. The blade foot used in the construction of large-diameter caissons on land with complex geology according to claim 7 is characterized by: When the diameter of the embedded steel bars (2) is d≤16mm, the joints of the stress-bearing steel bars and the non-stress-bearing distribution steel bars shall be welded or tied together.
9. The blade foot used in the construction process of large-diameter caisson on land with complex geology according to claim 1 is characterized by: The embedded steel bars (2) include annular steel bars on the inner side of the blade foot, annular steel bars on the outer side of the blade foot, vertical combined steel bars at the blade foot, vertical steel bars on the inner side of the blade foot, annular steel bars at the bottom of the blade foot, and a plurality of tension bars. The annular steel bars on the inner side of the blade foot are tied to the inner side of the blade foot body (3), the annular steel bars on the outer side of the blade foot are tied to the outer side of the blade foot body (3), and the annular steel bars at the bottom of the blade foot are tied to the bottom of the blade foot body (3). A plurality of tension bars are tied transversely between the blade foot bodies (3). The outer side of the upper end of the blade foot body (3) is tied with vertical combined steel bars at the blade foot, and the inner side is tied with vertical steel bars on the inner side of the blade foot.
10. The blade foot used in the construction process of large-diameter caisson on land with complex geology according to claim 9, characterized in that: The diameter of the annular steel bars on the inner side of the blade foot and the outer side of the blade foot are 28mm, with a spacing of 100cm; the diameter of the vertical combined steel bars at the blade foot and the vertical steel bars on the inner side of the blade foot are 32mm, with a spacing of 100cm; the diameter of the annular steel bars at the bottom of the blade foot is 25mm, and there are 10 of them.