Horizontal pull seam baffle structure
By setting baffles at the edge of the horizontal seam plate and using a combination of vertical and horizontal ribs, the problem of poor concrete filling quality is solved, and the building quality and material economy are improved.
Patent Information
- Application Number
- CN202420607084.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-27
- Publication Date
- 2024-11-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In traditional buildings, the quality of concrete filling of horizontal joint slab bottoms cannot be guaranteed, which often requires rework and repair, affecting the building quality.
The structure includes prefabricated shear wall, vertical seam pulling plate, horizontal seam pulling plate, baffle, vertical bar and horizontal bar, and the combination design of horizontal seam pulling plate is fixed through baffle, and the vertical bar and horizontal bar is ensured to ensure the quality of concrete molding.
It effectively prevents horizontal joint plates from shifting during concrete pouring, improves concrete density, reduces the need for rework and repair, and the materials are easy to obtain and economical.
Smart Images

Figure CN222009230U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of wall seam pulling, in particular to a horizontal seam pulling baffle structure. Background Art
[0002] The external structure of traditional civil buildings is mainly constructed by combining masonry walls and shear walls. Over time, various masonry exterior walls are prone to quality problems such as hollowing, cracking, and falling off, especially in areas with large seasonal temperature differences and monsoon climates. Due to the different thermal expansion coefficients of different materials, shrinkage cracks are easily generated between concrete and masonry walls, and between exterior wall masonry and exterior wall plastering. In order to solve the above problems, researchers have developed a fully cast-in-place concrete system for exterior walls, which can effectively improve the lateral bearing capacity and seismic performance of shear walls through structural seam materials (wall structural seam plates). However, when filling concrete at the bottom of the horizontal seam plate, the quality of concrete molding cannot be guaranteed, and subsequent rework and repairs are often required. Utility Model Content
[0003] The utility model aims to provide a horizontal pull-joint baffle structure, which aims to solve the technical problems that the filling quality of the bottom concrete of the horizontal pull-joint plate cannot be guaranteed, resulting in frequent rework and repair.
[0004] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0005] The utility model provides a horizontal seam baffle structure, comprising a prefabricated shear wall, a vertical seam plate, a horizontal seam plate, a baffle, vertical ribs and transverse ribs; the vertical seam plate is arranged against the side of the prefabricated shear wall, the horizontal seam plate is arranged on the side of the vertical seam plate away from the prefabricated shear wall and is tightly arranged with the bottom of the vertical seam plate; the baffle is L-shaped and is arranged at intervals on the edges of a group of long sides of the horizontal seam plate; the vertical part of the baffle is against the side of the long side of the horizontal seam plate, and the transverse part of the baffle is against the lower end surface of the horizontal seam plate; the vertical ribs are arranged on the surface of the horizontal seam plate, close to the long sides on both sides, and are arranged in two rows at intervals along the length direction of the horizontal seam plate, and the lower ends of the vertical ribs pass through the horizontal seam plate; the transverse ribs are cross-staggered and overlapped, and are arranged at intervals in the length direction of the vertical ribs.
[0006] Preferably, the plate body of the vertical seam plate is a square tube with a long cross-section, and a first inner rib plate of full length is arranged at intervals inside the plate body, and two first outer rib plates of full length are arranged on the side of the plate body; the two plate surfaces of the plate body are respectively provided with two L-shaped strips, and the L-shaped strips are arranged in the length direction of the plate surface, with their horizontal parts parallel to the plate surface and facing the edge of the plate surface, and the vertical parts are perpendicular to the plate surface.
[0007] Preferably, a plurality of baffles located on the long sides of the horizontal seam plates are connected and fixed by strip connecting plates, and the strip connecting plates are arranged on the lower end surfaces of the transverse portions of the baffles.
[0008] Preferably, the transverse portion of the L-shaped strip on one side of the vertical seam plate is tightly arranged against the wall surface of the prefabricated shear wall, and the transverse portion edge of the L-shaped strip on the other side is overlapped with the transverse reinforcement.
[0009] Preferably, the plate body of the horizontal seam plate is a square tube with an elongated cross section, and the inside of the plate body is provided with full-length second inner ribs at intervals, and two full-length second outer ribs are provided on the side of the plate body.
[0010] Preferably, the number of the second inner ribs is greater than the number of the first inner ribs; wherein at least four first inner ribs are provided, and at least five second inner ribs are provided.
[0011] Preferably, at least seven vertical ribs are provided, and the number of transverse ribs is the same as that of the vertical ribs.
[0012] Preferably, the transverse reinforcement and the vertical reinforcement are fixed by steel bar binding.
[0013] The beneficial effects of the utility model are embodied in:
[0014] The utility model provides a horizontal seam baffle structure, which fixes the horizontal seam plate by arranging a plurality of baffles at intervals on the edge of the horizontal seam plate, thereby solving the problem that the horizontal seam plate is offset during concrete pouring, resulting in loose concrete at the bottom of the plate and affecting the quality of concrete molding; the baffles are connected in series by strip connecting plates, which is easy to install; the steel bars or leftovers on the construction site can be used for processing, the materials are easy to obtain and have good economy.
[0015] Other features and advantages of the utility model will be described in the following description, and partly become apparent from the description, or understood by implementing the utility model. The main purpose and other advantages of the utility model can be realized and obtained by the solutions particularly pointed out in the description. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The utility model is further described in detail below in conjunction with the accompanying drawings.
[0017] Figure 1 It is a stereogram of the utility model.
[0018] Figure 2 It is a bottom view of the utility model.
[0019] Figure 3 It is a partial enlargement of the utility model. Figure 1 .
[0020] Figure 4 It is a partial enlargement of the utility model. Figure 2 .
[0021] Figure numerals: 1-prefabricated shear wall, 2-vertical seam plate, 3-horizontal seam plate, 4-baffle, 5-vertical reinforcement, 6-transverse reinforcement, 7-strip connecting plate, 21-first inner rib, 22-first outer rib, 23-L-shaped strip, 31-second inner rib, 32-second outer rib. DETAILED DESCRIPTION
[0022] The technical solution of the present invention is described in detail below through embodiments. The following embodiments are merely exemplary and can only be used to explain and illustrate the technical solution of the present invention, but cannot be interpreted as limiting the technical solution of the present invention.
[0023] Reference Figure 1 The utility model provides a horizontal joint baffle structure, comprising a prefabricated shear wall 1, a vertical joint plate 2, a horizontal joint plate 3, a baffle 4, a vertical rib 5 and a transverse rib 6; the vertical joint plate 2 is arranged close to the side of the prefabricated shear wall 1, the horizontal joint plate 3 is arranged on the side of the vertical joint plate 2 away from the prefabricated shear wall 1 and is tightly arranged with the bottom of the vertical joint plate 2; the baffle 4 is L-shaped and is arranged at intervals on the edges of a group of long sides of the horizontal joint plate 3; the vertical part of the baffle 4 is close to the water On the side of the long side of the horizontal seam plate 3, the transverse part of the baffle 4 is against the lower end surface of the horizontal seam plate 3; the vertical ribs 5 are arranged on the surface of the horizontal seam plate 3, close to the long sides on both sides, and are arranged in two rows at intervals along the length direction of the horizontal seam plate 3, and the lower ends of the vertical ribs 5 pass through the horizontal seam plate 3; the transverse ribs 6 are cross-staggered and overlapped with the transverse ribs 6, and are arranged at intervals in the length direction of the vertical ribs 5, wherein at least seven vertical ribs 5 are arranged, and the number of transverse ribs 6 is the same as that of the vertical ribs 5, and the transverse ribs 6 and the vertical ribs 5 are fixed by steel bar binding.
[0024] Reference Figure 2 The multiple baffles 4 located on the long side of the horizontal seam plate 3 are connected and fixed by a strip connecting plate 7, and the strip connecting plate 7 is arranged on the lower end surface of the transverse part of the baffle 4 to connect the single baffle 4 into a whole, thereby enhancing stability and making operation more convenient.
[0025] Reference Figure 3-4The plate body of the vertical seam plate 2 is a square tube with a long cross section, and a first inner rib plate 21 with a full length is arranged at intervals inside the plate body, and two first outer rib plates 22 with a full length are arranged on the side of the plate body; two plate surfaces of the plate body are respectively provided with two L-shaped strips 23, and the L-shaped strips 23 are arranged in the long direction of the plate surface, and their transverse parts are parallel to the plate surface and face the edge of the plate surface, and the vertical parts are perpendicular to the plate surface; the transverse part of the L-shaped strip plate 23 on one side of the plate surface of the vertical seam plate 2 is tightly arranged against the wall surface of the prefabricated shear wall 1, and the transverse part edge of the L-shaped strip plate 23 on the other side of the plate surface is overlapped with the transverse reinforcement 6; the plate body of the horizontal seam plate 3 is a square tube with a long cross section, and a second inner rib plate 31 with a full length is arranged at intervals inside the plate body, and two second outer rib plates 32 with a full length are arranged on the side of the plate body; the number of the second inner rib plates 31 is greater than the number of the first inner rib plates 21, wherein at least four first inner rib plates 21 are arranged, and at least five second inner rib plates 31 are arranged.
[0026] Furthermore, the working principle of the utility model is as follows: first pour concrete, press the horizontal seam plate 3 into the concrete before the concrete initially sets, and insert the vertical reinforcement 5 downward through the horizontal seam plate 3 before the concrete finally sets; then install the baffle plate 4 on the two long sides of the horizontal seam plate 3, and use the baffle plate 4 to clamp and fix the horizontal seam plate 3 to prevent the horizontal seam plate 3 from displacement or angular deviation during subsequent operations; then install the vertical seam plate 2 and the transverse reinforcement 6 and tie them up to fix them.
[0027] The above description is only a preferred specific implementation of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that a technician familiar with the technical field thinks of within the technical scope disclosed in the present invention should be included in the protection scope of the present invention.
Claims
1. A horizontally pulled seam baffle structure, Features: It comprises a prefabricated shear wall (1), a vertical seam plate (2), a horizontal seam plate (3), a baffle (4), vertical reinforcement (5) and transverse reinforcement (6); The vertical seam plate (2) is arranged close to the side of the prefabricated shear wall (1), and the horizontal seam plate (3) is arranged on the side of the vertical seam plate (2) away from the prefabricated shear wall (1) and is arranged close to the bottom of the vertical seam plate (2); the baffle plate (4) is L-shaped and is arranged at intervals on the edges of a group of long sides of the horizontal seam plate (3); the vertical part of the baffle plate (4) is close to the side of the long side of the horizontal seam plate (3), and the horizontal part of the baffle plate (4) is close to the lower end surface of the horizontal seam plate (3); the vertical ribs (5) are arranged on the plate surface of the horizontal seam plate (3) and close to the long sides on both sides, and are arranged in two rows at intervals along the longitudinal direction of the horizontal seam plate (3), and the lower ends of the vertical ribs (5) pass through the horizontal seam plate (3); the transverse ribs (6) are cross-staggered and overlapped with the transverse ribs (6) and are arranged at intervals in the longitudinal direction of the vertical ribs (5).
2. A horizontally pulled seam baffle structure as claimed in claim 1, It is characterized in that The plate body of the vertical seam plate (2) is a square tube with a long strip cross section, and a first inner rib plate (21) is arranged at intervals inside the plate body, and two first outer rib plates (22) are arranged on the side of the plate body; two plate surfaces of the plate body are respectively provided with two L-shaped strip plates (23), and the L-shaped strip plates (23) are arranged in the length direction of the plate surface, with their horizontal parts parallel to the plate surface and facing the edge of the plate surface, and their vertical parts are perpendicular to the plate surface.
3. A horizontally pulled seam baffle structure as claimed in claim 1, It is characterized in that A plurality of baffles (4) located on the long sides of the horizontal seam-drawing plate (3) are connected and fixed via a strip-shaped connecting plate (7), and the strip-shaped connecting plate (7) is arranged on the lower end surface of the transverse portion of the baffle (4).
4. A horizontally pulled seam baffle structure as claimed in claim 2, It is characterized in that The transverse portion of the L-shaped strip (23) on one side of the vertical seam plate (2) is tightly arranged against the wall surface of the prefabricated shear wall (1), and the transverse portion edge of the L-shaped strip (23) on the other side of the plate overlaps the transverse reinforcement (6).
5. A horizontally pulled seam baffle structure as claimed in claim 1, It is characterized in that The plate body of the horizontal seam plate (3) is a square tube with a long strip cross section, and the plate body is provided with a continuous second inner rib plate (31) at intervals, and the side surface of the plate body is provided with two continuous second outer rib plates (32).
6. A horizontally pulled seam baffle structure as claimed in claim 5, It is characterized in that The number of the second inner ribs (31) is greater than the number of the first inner ribs (21); wherein at least four first inner ribs (21) are provided, and at least five second inner ribs (31) are provided.
7. A horizontally pulled seam baffle structure as claimed in claim 3, It is characterized in that At least seven vertical bars (5) are provided, and the number of transverse bars (6) is the same as that of the vertical bars (5).
8. A horizontally pulled seam baffle structure as claimed in claim 3, It is characterized in that The transverse reinforcement (6) and the vertical reinforcement (5) are fixed by steel bar binding.