Main beam and secondary beam connecting structure and overhanging type discharging platform
By connecting the fastening bolts and locking nuts of the independent connecting components to the secondary beam, the problem of the inability to disassemble the main and secondary beams of the traditional unloading platform cannot be adjusted as a whole, and the rapid disassembly and flexible adjustment of the primary and secondary beams can be achieved, reducing the Construction costs and material waste.
Patent Information
- Application Number
- CN202420118146.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-17
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-01-17
AI Technical Summary
The main beam and secondary beam of the traditional unloading platform are integrally formed, cannot be disassembled, has a large weight and is inconvenient to move, and different projects have different load requirements, so the specifications of the main and secondary beams cannot be adjusted, resulting in waste of materials and increased construction costs.
The secondary beam is connected with independent connecting components, and the primary and secondary beams are disassembled and adjusted by fastening bolts and locking nuts. The secondary beam specifications are selected according to actual needs, and the materials can be recycled, suitable for unloading platforms with different loads.
It realizes rapid disassembly and assembly and flexible adjustment of primary and secondary beams, reduces material waste and construction costs, and improves transportation convenience and applicability.
Smart Images

Figure CN222009647U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of material transportation, in particular to a main-secondary beam connection structure and a cantilevered unloading platform. Background Art
[0002] The unloading platform is a device set at the edge of the building facade for the transportation of construction materials. In traditional technology, the main beam is made of I-beam, and the secondary beam is made of I-beam or channel steel. The main beam and the secondary beam are connected by welding, and the main and secondary beams form a whole;
[0003] Since the main beam and secondary beam are an integral whole and cannot be disassembled during use, they are heavy and inconvenient to move; different projects have different load requirements for the unloading platform, and the main and secondary beams are welded, and the specifications of the main and secondary beams cannot be adjusted, so more unloading platforms can only be invested, which increases investment and construction costs. Utility Model Content
[0004] The purpose of the utility model is to provide a main-secondary beam connection structure and a cantilevered unloading platform to address the above-mentioned deficiencies, thereby solving the problem in the prior art that the main beam and the secondary beam are an integral whole, cannot be disassembled during use, are heavy and inconvenient to move; different projects have different load requirements for the unloading platform, the main and secondary beams are welded, and the specifications of the main and secondary beams cannot be adjusted, so more unloading platforms can only be invested, increasing investment and construction costs.
[0005] The utility model is realized by the following scheme:
[0006] A main-secondary beam connection structure comprises at least a main beam, a connection assembly and a secondary beam; the connection assembly is arranged perpendicular to the length direction of the main beam, and the connection assembly is arranged not exceeding the two side edges of the main beam; the connection assembly is provided with a fastening portion connected to the secondary beam, and a matching portion is provided on the secondary beam at a position corresponding to the connection assembly; the matching portion and the fastening portion cooperate to connect the connection assembly and the secondary beam into an integral structure.
[0007] Based on the above-mentioned main-secondary beam connection structure, the main beam is an I-beam, and the secondary beam is a channel steel; the specification of the channel steel of the secondary beam is selected according to actual conditions, and the specification of the secondary beam channel steel is not greater than the specification of the main beam I-beam.
[0008] Based on the above-mentioned main-secondary beam connection structure, the connection component is a plate-like structure, and the fastening part is a fastening bolt and a locking nut; the side dimension of the connection component in contact with the main beam is not greater than the height of the main beam; a locking hole whose size and shape match the fastening bolt is provided on the connection component; a matching hole matching the locking hole is provided on the secondary beam; the fastening bolt is passed through the locking hole and the matching hole, and the locking nut is connected to the end of the fastening bolt, so that the main beam, the secondary beam and the connection component are connected as one.
[0009] Based on the above-mentioned main-secondary beam connection structure, the connection component is a channel steel, and the fastening part is a fastening bolt and a locking nut; the side dimension of the connection component in contact with the main beam is not greater than the height of the main beam; a locking hole whose size and shape match the fastening bolt is arranged on the connection component; a matching hole matching the locking hole is arranged on the secondary beam; the fastening bolt passes through the locking hole and the matching hole, and the locking nut is connected to the end of the fastening bolt, so that the main beam, the secondary beam and the connection component are connected as one.
[0010] Based on the above-mentioned main-secondary beam connection structure, the connection assembly includes a vertical connection plate and a transverse connection plate; the transverse connection plates are respectively arranged at the two ends of the vertical connection plate, and the transverse connection plate is arranged perpendicular to the vertical connection plate, the vertical connection plate and the transverse connection plate are both embedded in the single-side U-shaped cavity of the main beam, and the contact surface of the vertical connection plate and the transverse connection plate with the main beam is welded;
[0011] Based on the above-mentioned main-secondary beam connection structure, the end surface of the transverse connecting plate and the cavity contact surface of the main beam are welded.
[0012] Based on the above-mentioned main and secondary beam connection structure, the locking holes are arranged along the width direction of the connection component, and at least two locking holes are arranged.
[0013] Based on the above-mentioned main-secondary beam connection structure, the matching holes are evenly arranged along the width direction of the secondary beam, and the number of the matching holes is the same as that of the locking holes.
[0014] Based on the above-mentioned main-secondary beam connection structure, a steel gasket is arranged on the contact portion between the locking nut and the secondary beam.
[0015] The present solution also provides a cantilevered unloading platform, which includes at least a main beam and a secondary beam. A plurality of connecting components are welded in sequence in the length direction of the main beam, and the secondary beam and the connecting components are detachably connected. A bottom plate is arranged between adjacent secondary beams, and a guardrail is arranged above the main beam. A connecting piece is arranged on the secondary beam, and the bottom plate and the connecting piece are connected by bolts.
[0016] In summary, due to the adoption of the above technical solution, the beneficial effects of the utility model are:
[0017] 1. This solution uses independent connecting components to connect with the secondary beam, so that the main and secondary beams can be detachably connected as a whole. The secondary beam can be selected according to the actual needs of the site to avoid waste of materials, making the device more flexible. At the same time, it can realize rapid disassembly and assembly of the main beam and the secondary beam, realize recycling, and facilitate transportation.
[0018] 2. All materials in this solution can be used in a circulated manner, and the materials are easy to carry. All components of the unloading platform are connected by bolts and can be easily disassembled and installed. The specifications of the main and secondary beams can be adjusted according to the construction conditions, which is convenient for transporting large-sized and heavy-weight material components. It has strong applicability, reduces the number of unloading platforms used, and reduces construction costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the overall top view of the embodiment 1 of the utility model;
[0020] Figure 2 This is a schematic diagram of the overall main structure of Embodiment 1 of the present utility model;
[0021] Figure 3 It is a first-view axonometric diagram of the entire embodiment 2 of the utility model;
[0022] Figure 4 It is a second perspective axonometric diagram of the entire embodiment 2 of the utility model;
[0023] Figure 5 It is a schematic diagram of the overall top view of Example 3 of the utility model;
[0024] Description of the drawings: 1. Main beam; 2. Connection assembly; 3. Secondary beam; 4. Fastening bolts; 5. Locking nuts; 6. Locking holes; 7. Matching holes; 8. Vertical connecting plates; 9. Horizontal connecting plates; 10. Steel gaskets; 11. Bottom plates. DETAILED DESCRIPTION
[0025] All features disclosed in this specification, or steps in all methods or processes disclosed, except mutually exclusive features and / or steps, can be combined in any manner.
[0026] Any feature disclosed in this specification (including any additional claims and abstract), unless otherwise stated, may be replaced by other equivalent or alternative features having similar purposes. That is, unless otherwise stated, each feature is only an example of a series of equivalent or similar features.
[0027] In the description of the present invention, it should be understood that the terms "up", "down", "left", "right", etc., indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.
[0028] In addition, the terms "first", "second", etc. are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first", "second", etc. may explicitly or implicitly include one or more of the features.
[0029] Example 1
[0030] like Figure 1 and 2 As shown, the utility model provides a technical solution:
[0031] A main-secondary beam connection structure, which at least includes but is not limited to a main beam 1, a connection component 2 and a secondary beam 3; the connection component 2 is arranged perpendicular to the length direction of the main beam 1, and the connection component 2 is arranged not exceeding the two side edges of the main beam 1; a fastening portion connected to the secondary beam 3 is arranged on the connection component 2, and a matching portion is arranged on the secondary beam 3 at a position corresponding to the connection component 2; the matching portion and the fastening portion cooperate to connect the connection component 2 and the secondary beam 3 into an integral structure.
[0032] Based on the above structure, this solution uses an independent connecting component 2 to connect with the secondary beam 3, so that the main and secondary beams 3 can be detachably connected as a whole. The secondary beam 3 can be selected according to the actual needs of the site to avoid waste of materials, making the device more flexible, and at the same time, it can realize rapid disassembly and assembly of the main beam 1 and the secondary beam 3, realize recycling, and facilitate transportation.
[0033] As an example, the main beam 1 can be an I-beam, and the secondary beam 3 can be a channel steel; the specification of the channel steel of the secondary beam 3 is selected according to actual conditions, and the specification of the channel steel of the secondary beam 3 is not greater than the specification of the I-beam of the main beam 1.
[0034] Based on the above structure, I-beams are selected for the main beam 1 and channel steels are selected for the secondary beam 3, which can effectively reduce the overall preparation cost. The channel steel of the secondary beam 3 is smaller than that of the main beam 1, which can facilitate the secondary beam 3 to be embedded in the I-beam of the main beam 1 for assembly when needed, thereby increasing the stability of the overall structure.
[0035] As an example, the connection component 2 may be a plate-like structure, and the fastening part may be a fastening bolt 4 and a locking nut 5; the side dimension of the connection component 2 in contact with the main beam 1 is not greater than the height of the main beam 1; a locking hole 6 having a size and shape matching the fastening bolt 4 is provided on the connection component 2;
[0036] A matching hole 7 matching with the locking hole 6 is provided on the secondary beam 3; the fastening bolt 4 is set through the locking hole 6 and the matching hole 7, and the locking nut 5 is connected to the end of the fastening bolt 4, so that the main beam 1, the secondary beam 3 and the connecting component 2 are connected as a whole.
[0037] Based on the above structure, in this embodiment, the connection component 2 adopts a sheet plate structure. The sheet plate can be embedded in the interior of the I-beam of the main beam 1. The upper and lower ends of the I-beam can limit and support the two sides of the connection component 2, further increasing the overall stability. At the same time, the plane of the sheet plate structure can be in good contact with the channel steel plane of the secondary beam 3, increasing the contact area between the two. Finally, the fastening bolts 4 and the locking nuts 5 are used to connect the connection component 2 and the secondary beam 3 into an integral structure.
[0038] As an example, the locking holes 6 are arranged along the width direction of the connecting component 2, and there are at least two locking holes 6. The matching holes 7 are evenly arranged along the width direction of the secondary beam 3, and the number of the matching holes 7 is the same as that of the locking holes 6.
[0039] Based on the above structure, by setting at least two locking holes 6 and matching holes 7, at least two fastening points are formed between the connecting component 2 and the secondary beam 3, thereby increasing the connection strength between the connecting component 2 and the secondary beam 3. Multiple fastening points can prevent twisting at the connection.
[0040] As an example, a steel washer 10 may be provided on the contact portion between the locking nut 5 and the secondary beam 3; the steel washer 10 can increase the contact area of the locking portion, prevent the matching hole 7 from being damaged, and also increase the locking strength.
[0041] Example 2
[0042] like Figure 3 and 4 As shown, the utility model provides a technical solution:
[0043] A main-secondary beam 3 connection structure, which at least includes but is not limited to a main beam 1, a connection component 2 and a secondary beam 3; the connection component 2 is arranged perpendicular to the length direction of the main beam 1, and the connection component 2 is arranged not exceeding the two side edges of the main beam 1; a fastening portion connected to the secondary beam 3 is arranged on the connection component 2, and a matching portion is arranged on the secondary beam 3 at a position corresponding to the connection component 2; the matching portion and the fastening portion cooperate to connect the connection component 2 and the secondary beam 3 into an integral structure.
[0044] Based on the above structure, this solution uses an independent connecting component 2 to connect with the secondary beam 3, so that the main and secondary beams 3 can be detachably connected as a whole. The secondary beam 3 can be selected according to the actual needs of the site to avoid waste of materials, making the device more flexible, and at the same time, it can realize rapid disassembly and assembly of the main beam 1 and the secondary beam 3, realize recycling, and facilitate transportation.
[0045] As an example, the main beam 1 can be an I-beam, and the secondary beam 3 can be a channel steel; the specification of the channel steel of the secondary beam 3 is selected according to actual conditions, and the specification of the channel steel of the secondary beam 3 is not greater than the specification of the I-beam of the main beam 1.
[0046] Based on the above structure, I-beams are selected for the main beam 1 and channel steels are selected for the secondary beam 3, which can effectively reduce the overall preparation cost. The channel steel of the secondary beam 3 is smaller than that of the main beam 1, which can facilitate the secondary beam 3 to be embedded in the I-beam of the main beam 1 for assembly when needed, thereby increasing the stability of the overall structure.
[0047] As an example, the connection component 2 may be a channel steel, and the fastening part may be a fastening bolt 4 and a locking nut 5; the side dimension of the connection component 2 in contact with the main beam 1 is not greater than the height of the main beam 1; a locking hole 6 having a size and shape matching the fastening bolt 4 is provided on the connection component 2;
[0048] A matching hole 7 matching with the locking hole 6 is provided on the secondary beam 3; the fastening bolt 4 is set through the locking hole 6 and the matching hole 7, and the locking nut 5 is connected to the end of the fastening bolt 4, so that the main beam 1, the secondary beam 3 and the connecting component 2 are connected as a whole.
[0049] Based on the above structure, in this embodiment, the connection component 2 is made of channel steel, and the end of the channel steel can be embedded in the interior of the I-beam of the main beam 1. The upper and lower ends of the I-beam can limit and support the two sides of the connection component 2, further increasing the overall stability. At the same time, the plane of the channel steel can be in good contact with the channel steel plane of the secondary beam 3, increasing the contact area between the two. Finally, the fastening bolts 4 and the locking nuts 5 are used to connect the connection component 2 and the secondary beam 3 into an integral structure.
[0050] As an example, the connection assembly 2 may include a vertical connection plate 8 and a horizontal connection plate 9; the horizontal connection plate 9 is respectively arranged at the two ends of the vertical connection plate 8, and the horizontal connection plate 9 is arranged perpendicular to the vertical connection plate 8, the vertical connection plate 8 and the horizontal connection plate 9 are both embedded in the single-side U-shaped cavity of the main beam 1, and the contact surface of the vertical connection plate 8 and the horizontal connection plate 9 and the main beam 1 is welded;
[0051] Based on the above structure, the welding area between the connection assembly 2 and the main beam 1 can be increased by providing the transverse connection plate 9, so that the connection strength between the connection assembly 2 and the main beam 1 can be further increased.
[0052] As an example, the end surface of the transverse connecting plate 9 and the cavity contact surface of the main beam 1 are welded; this can further increase the welding area and ensure the connection strength.
[0053] As an example, the locking holes 6 are arranged along the width direction of the connecting component 2, and there are at least two locking holes 6. The matching holes 7 are evenly arranged along the width direction of the secondary beam 3, and the number of the matching holes 7 is the same as that of the locking holes 6.
[0054] Based on the above structure, by setting at least two locking holes 6 and matching holes 7, at least two fastening points are formed between the connecting component 2 and the secondary beam 3, thereby increasing the connection strength between the connecting component 2 and the secondary beam 3. Multiple fastening points can prevent twisting at the connection.
[0055] As an example, a steel washer 10 may be provided on the contact portion between the locking nut 5 and the secondary beam 3; the steel washer 10 can increase the contact area of the locking portion, prevent the matching hole 7 from being damaged, and also increase the locking strength.
[0056] The materials on the construction site floors are transported by construction elevators and unloading platforms. Due to the limited space of the construction elevator, large-sized and heavy-weight material components can only be transported by unloading platforms. At this time, unloading platforms with different loads can be selected according to the actual situation of the construction site. In this solution, the secondary beam 3 connecting parts are welded to the main beam 1, and the secondary beam 3 and the connecting parts are connected by bolts. The use of this technology can not only achieve the purpose of detachable main and secondary beams 3, but also adjust the specifications of the main and secondary beams 3 to be suitable for unloading platforms with different loads.
[0057] For projects without large-sized and heavy-weight material components, a small-sized secondary beam 3 can be selected. If large-sized and heavy-weight material components appear, the small-sized secondary beam 3 can be replaced with a large-sized one, and there is no need to prepare a new unloading platform, which can reduce construction costs.
[0058] Example 3
[0059] like Figure 5 As shown, the utility model provides a technical solution:
[0060] A cantilever unloading platform, which at least includes but is not limited to a main beam 1 and a secondary beam 3, a plurality of connecting components 2 are sequentially welded in the length direction of the main beam 1, and the secondary beam 3 is detachably connected to the connecting components 2; a bottom plate 11 is arranged between adjacent secondary beams 3, and a guardrail is arranged on the main beam 1;
[0061] Based on the above structure, by adopting a detachable structure for the main beam 1 and the secondary beam 3, the entire unloading platform is easier to install and can be recycled for many times.
[0062] As an example, a connecting member (not shown) may be provided on the secondary beam 3, and the bottom plate 11 is connected to the connecting member by bolts.
[0063] In this solution, all materials can be circulated and used, and the materials are easy to carry. All components of the unloading platform are connected by bolts and can be easily disassembled and installed. The specifications of the main and secondary beams can be adjusted according to the construction situation, which is convenient for transporting large-sized and heavy-weight material components. It has strong applicability, reduces the number of unloading platforms used, and reduces construction costs.
[0064] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A main and secondary beam connection structure, characterized in that: It at least includes a main beam, a connecting component and a secondary beam; the connecting component is arranged perpendicular to the length direction of the main beam, and the connecting component is arranged no more than the two side edges of the main beam; the connecting component is provided with a fastening part connected to the secondary beam, and a matching part is provided on the secondary beam at a position corresponding to the connecting component; the matching part and the fastening part cooperate to connect the connecting component and the secondary beam into an integral structure.
2. A primary and secondary beam connection structure as claimed in claim 1, characterized in that: The main beam is an I-beam, and the secondary beam is a channel steel; the specification of the channel steel of the secondary beam is selected according to actual conditions, and the specification of the channel steel of the secondary beam is not greater than the specification of the I-beam of the main beam.
3. A primary and secondary beam connection structure as claimed in claim 2, characterized in that: The connecting component is a plate-like structure, and the fastening part is a fastening bolt and a locking nut; the side dimension of the connecting component in contact with the main beam is not greater than the height of the main beam; a locking hole whose size and shape match the fastening bolt is provided on the connecting component; a matching hole matching the locking hole is provided on the secondary beam; the fastening bolt is passed through the locking hole and the matching hole, and the locking nut is connected to the end of the fastening bolt, so that the main beam, the secondary beam and the connecting component are connected as a whole.
4. A primary and secondary beam connection structure as claimed in claim 2, characterized in that: The connecting component is a channel steel, and the fastening part is a fastening bolt and a locking nut; the side dimension of the connecting component in contact with the main beam is not greater than the height of the main beam; a locking hole whose size and shape match the fastening bolt is arranged on the connecting component; a matching hole matching the locking hole is arranged on the secondary beam; the fastening bolt passes through the locking hole and the matching hole, and the locking nut is connected to the end of the fastening bolt, so that the main beam, the secondary beam and the connecting component are connected as a whole.
5. A primary and secondary beam connection structure as claimed in claim 4, characterized in that: The connecting assembly includes a vertical connecting plate and a transverse connecting plate; the transverse connecting plates are respectively arranged at the two ends of the vertical connecting plates, and the transverse connecting plates are arranged perpendicular to the vertical connecting plates, the vertical connecting plates and the transverse connecting plates are both embedded in the single-side U-shaped cavity of the main beam, and the contact surfaces of the vertical connecting plates and the transverse connecting plates and the main beam are welded.
6. A primary and secondary beam connection structure as claimed in claim 5, characterized in that: The end surface of the transverse connecting plate and the cavity contact surface of the main beam are welded.
7. A primary and secondary beam connection structure as claimed in claim 3 or 4, characterized in that: The locking holes are arranged along the width direction of the connecting component, and at least two locking holes are arranged.
8. A primary and secondary beam connection structure as claimed in claim 7, characterized in that: The matching holes are evenly arranged along the width direction of the secondary beam, and the number of the matching holes is the same as that of the locking holes.
9. A primary and secondary beam connection structure as claimed in claim 8, characterized in that: A steel gasket is arranged on the contact portion between the locking nut and the secondary beam.
10. A cantilever unloading platform, characterized in that: It at least includes a main beam and a secondary beam, wherein a plurality of connection components are welded in sequence in the length direction of the main beam, and the secondary beam and the connection components are detachably connected; a bottom plate is arranged between adjacent secondary beams, and a guardrail is arranged on the main beam; a connection piece is arranged on the secondary beam, and the bottom plate and the connection piece are connected by bolts.