Fabricated concrete member construction positioning device

By designing the construction positioning device of prefabricated concrete components, using the coordination of external threaded columns and cone covers, the precise alignment of steel bars and reserved holes is achieved, which solves the problems of low efficiency and large errors in the construction of prefabricated concrete structures, and improves installation accuracy and efficiency.

CN222009660UActive Publication Date: 2024-11-15CHENGDU NO 1 CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420436457.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-07
Publication Date
2024-11-15
Estimated Expiration
2034-03-07

AI Technical Summary

Technical Problem

Due to the difficulty of operation during construction, prefabricated prefabricated concrete structures lead to low construction efficiency and large errors, making it difficult to achieve rapid and accurate assembly.

Method used

A prefabricated concrete component construction positioning device is designed, including four first angle steel, four internal threaded pipes, four external threaded columns and docking components. Through the cooperation of the external threaded column and the cone cover, the steel bar and reserved hole are realized. Accurate alignment and insertion to improve installation accuracy.

Benefits of technology

Through this device, the installation accuracy of concrete components can be improved, construction time can be shortened, construction efficiency can be improved, and the problem of precise alignment during prefabricated components can be solved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009660U_ABST
    Figure CN222009660U_ABST
Patent Text Reader

Abstract

The utility model discloses an assembly type concrete member construction positioning device, and relates to the technical field of prefabricated assembly type concrete member positioning installation. One ends of the four internal threaded pipes are respectively fixed at the diagonal lines of the four pieces of angle steel; and the four external threaded columns are mounted in the four internal threaded pipes through threads correspondingly. The four pieces of first angle steel are attached to the four corners of the bearing table, the four butt joint assemblies are installed at the four corner edges of concrete respectively, the concrete is hoisted through a crane, the external threaded column is rotated, the external threaded column moves along the internal threaded pipe, the external stud is made to be higher than a steel bar, the concrete moves downwards, the external threaded column is inserted into the conical cover, and the concrete is connected with the bearing table. And through the arrangement of the conical cover, the external threaded columns can be conveniently inserted into the positioning holes, and when the external threaded columns are inserted into the positioning holes, the prefabricated holes in the bottom of the concrete are aligned with the steel bars, so that positioning installation is achieved, and the installation accuracy is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of positioning and installing prefabricated assembled concrete components, and in particular to a construction positioning device for assembled concrete components. Background Art

[0002] In recent years, due to the shortage of labor and the increasing attention to environmental protection, my country's construction industry is in a profound transformation and upgrading process. Modern industrialized green buildings represented by prefabricated concrete structures have the advantages of low pollution, high degree of industrialization, energy saving and environmental protection, and have been vigorously promoted in recent years. However, the further promotion and application of prefabricated concrete structures also faces bottlenecks, mainly manifested in the fact that the main components of prefabricated concrete structures are prefabricated in factories and transported to construction sites for assembly. Compared with traditional cast-in-place structures, the construction process has higher requirements for fineness, but the overall professional quality of current construction personnel is not high, lacks technical experience accumulation and summary of prefabricated concrete structures, and lacks a comprehensive and detailed understanding and mastery of the process flow and operation points of prefabricated structures, resulting in low construction efficiency, large construction errors, and even construction errors. Therefore, in order to promote the development of modern industrialized green buildings, promote the smooth implementation of the transformation and upgrading of my country's construction industry, and further promote the application of prefabricated concrete buildings, how to quickly and accurately assemble prefabricated components is a key technical problem that needs to be solved.

[0003] When connecting two prefabricated components, it is necessary to align the multiple steel bars of one of the prefabricated components with the multiple reserved holes of the other prefabricated component and insert them. However, some prefabricated components often weigh several tons and need to be lifted and connected with the help of a crane. When operating the crane, due to factors such as vision and inertia, it is difficult to accurately and quickly align the multiple steel bars with the multiple reserved holes of the other prefabricated component and insert them, which slows down the construction time. Utility Model Content

[0004] The purpose of this application is to provide a utility model to solve the problems raised in the above background technology.

[0005] To achieve the above purpose, the present application provides the following technical solution: a construction positioning device for assembled concrete components, comprising:

[0006] four first angles;

[0007] Four internally threaded pipes, one end of each of which is fixed at the diagonal lines of four angle steels;

[0008] Four external threaded columns, the four external threaded columns are respectively installed in four internal threaded tubes through threads;

[0009] The docking assembly comprises two pairs of second angle steels, each pair of the second angle steels is provided with a moving assembly, the diagonal lines of the second angle steels are provided with positioning holes, and the bottom outer wall of the second angle steels is fixed with a conical cover coaxially arranged with the positioning holes.

[0010] Preferably, one end of the external threaded column is a dome structure.

[0011] Preferably, a second double-section telescopic cylinder is commonly mounted on one of the inner second angle steels of the two pairs of the second angle steels.

[0012] Preferably, the moving assembly comprises a first double-section telescopic cylinder, and both ends of the first double-section telescopic cylinder are fixed to each pair of second angle steels.

[0013] Preferably, the moving assembly further comprises an external threaded rod, a rotation hole is provided on the outer wall of one of the second angle steels in each pair of second angle steels, a threaded hole is provided on the outer wall of the other second angle steel, and the external threaded rod is threadedly installed in the threaded hole.

[0014] In summary, the technical effects and advantages of the utility model are:

[0015] The four first angle steels fit with the four corners of the load-bearing platform, and the four docking components are respectively installed at the four corners of the concrete. The concrete is lifted by a crane, and the external threaded column is rotated. The external threaded column moves along the internal threaded pipe so that the external stud is higher than the steel bar, and the concrete moves downward. The external threaded column is inserted into the conical cover. The setting of the conical cover facilitates the insertion of the external threaded column into the positioning hole. When the external threaded column is inserted into the positioning hole, the prefabricated hole at the bottom of the concrete is aligned with the steel bar, thereby realizing positioning installation and improving the accuracy of installation. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For those skilled in the art, other drawings can be obtained based on these drawings without paying any creative work.

[0017] Figure 1 Schematic diagram of installation in this embodiment;

[0018] Figure 2 is a schematic diagram of the three-dimensional structure of the first angle steel in this embodiment;

[0019] Figure 3 This is a schematic diagram of the three-dimensional structure of the docking assembly in this embodiment from a first perspective;

[0020] Figure 4 Schematic diagram of the stereoscopic structure of the docking assembly in this embodiment from a second viewing angle.

[0021] In the figure: 1. first angle steel; 2. internal threaded pipe; 3. external threaded column; 4. dome structure; 5. docking assembly; 6. second angle steel; 7. external threaded rod; 8. first double-section telescopic cylinder; 9. conical cover; 10. second double-section telescopic cylinder.

[0022] a. Cement floor; b. Load-bearing platform; c. Steel bars. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0024] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the embodiments of the present application and the features therein can be combined with each other without conflict.

[0025] In the description of the present invention, it should be noted that the terms "upper", "lower", "inside", "outside", "top / bottom" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0026] In the description of the present utility model, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "set / connected", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances.

[0027] Example: Reference Figure 1-4 The present invention provides a construction positioning device for assembled concrete components, comprising:

[0028] Four first angle steels 1;

[0029] Four internally threaded tubes 2, one end of each of the four internally threaded tubes 2 is fixed at the diagonal lines of four angle steels;

[0030] Four external threaded columns 3, the four external threaded columns 3 are respectively installed in the four internal threaded tubes 2 through threads;

[0031] The docking assembly 5 includes two pairs of second angle steels 6, each pair of second angle steels 6 is provided with a moving assembly, a positioning hole is opened on the diagonal of the second angle steels 6, and a conical cover 9 coaxially arranged with the positioning hole is fixed to the bottom outer wall of the second angle steels 6;

[0032] Through the above connection relationship, it can be known that the technical solution of the utility model is that the four first angle steels 1 are fitted with the four corners of the load-bearing platform b, and the four docking components 5 are respectively installed at the four corners of the concrete. The concrete is lifted by a crane, and the external threaded column 3 is rotated. The external threaded column 3 moves along the internal threaded pipe 2, so that the external stud is higher than the steel bar c, the concrete moves downward, and the external threaded column 3 is inserted into the conical cover 9. The setting of the conical cover 9 facilitates the insertion of the external threaded column 3 into the positioning hole. When the external threaded column 3 is inserted into the positioning hole, the prefabricated hole at the bottom of the concrete is aligned with the steel bar c, thereby realizing positioning installation and improving the accuracy of installation.

[0033] Specifically, one end of the external threaded column 3 is a dome structure 4;

[0034] It can be seen from the above connection relationship that the dome structure 4 facilitates the external threaded column 3 to be inserted into the conical cover 9 .

[0035] Specifically, one of the inner angle steels 6 of the two pairs of second angle steels 6 is commonly installed with a second double-section telescopic cylinder 10;

[0036] It can be seen from the above connection relationship that the second double-section telescopic cylinder 10 is used to adjust the distance between the two pairs of second angle steels 6 .

[0037] Specifically, the moving assembly includes a first double-section telescopic cylinder 8, both ends of which are fixed on each pair of second angle steels 6, and the moving assembly also includes an external threaded rod 7, a rotation hole is opened on the outer wall of one of the second angle steels 6 in each pair of second angle steels 6, and a threaded hole is opened on the outer wall of the other second angle steel 6, and the external threaded rod 7 is installed in the threaded hole by threading;

[0038] It can be known from the above connection relationship that by rotating the external threaded rod 7, the external threaded rod 7 adjusts the distance between the two second angle steels 6 in each pair of second angle steels 6 through the thread, thereby clamping on the concrete column.

[0039] Specifically, positioning straight notches are provided on the outer walls at both ends of the first angle steel 1 .

[0040] The working principle of the utility model is as follows: the four first angle steels 1 are fitted with the four corners of the load-bearing platform b, the four docking components 5 are respectively installed at the four corners of the concrete, the concrete is lifted by a crane, the external threaded column 3 is rotated, the external threaded column 3 moves along the internal threaded pipe 2, so that the external stud is higher than the steel bar c, the concrete moves downward, and the external threaded column 3 is inserted into the conical cover 9. The setting of the conical cover 9 facilitates the insertion of the external threaded column 3 into the positioning hole. When the external threaded column 3 is inserted into the positioning hole, the prefabricated hole at the bottom of the concrete is aligned with the steel bar c, thereby realizing positioning installation and improving the accuracy of installation.

[0041] Finally, it should be noted that the above is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. Although the present utility model has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present utility model shall be included in the protection scope of the present utility model.

Claims

1. A construction positioning device for assembled concrete components, characterized in that: include: four first angle steels (1); Four internally threaded tubes (2), one end of each of the four internally threaded tubes (2) being fixed at the diagonal lines of four angle steels respectively; Four external threaded columns (3), the four external threaded columns (3) being respectively installed in four internal threaded tubes (2) through threads; A docking assembly (5), the docking assembly (5) comprising two pairs of second angle steels (6), each pair of the second angle steels (6) being provided with a moving assembly, a positioning hole being provided on the diagonal of the second angle steels (6), and a conical cover (9) being fixed on the bottom outer wall of the second angle steels (6) and being arranged coaxially with the positioning hole.

2. The construction positioning device for assembled concrete components according to claim 1, characterized in that: One end of the external threaded column (3) is a dome structure (4).

3. The construction positioning device for assembled concrete components according to claim 1, characterized in that: A second double-section telescopic cylinder (10) is commonly mounted on one of the second angle steels (6) in the two pairs of the second angle steels (6).

4. The construction positioning device for assembled concrete components according to claim 1, characterized in that: The moving assembly comprises a first double-section telescopic cylinder (8), and both ends of the first double-section telescopic cylinder (8) are fixed on each pair of second angle steels (6).

5. The construction positioning device for assembled concrete components according to claim 1, characterized in that: The moving assembly also includes an external threaded rod (7), the outer wall of one of the second angle steels (6) in each pair of second angle steels (6) is provided with a rotation hole, the outer wall of the other second angle steel (6) is provided with a threaded hole, and the external threaded rod (7) is installed in the threaded hole by means of threads.

6. The construction positioning device for assembled concrete components according to claim 1, characterized in that: The outer walls at both ends of the first angle steel (1) are provided with positioning straight notches.