Adjustable climbing frame for building construction
By designing an adjustable building construction climbing frame, the problem that the existing technology cannot adapt to non-vertical building bodies is solved, the flexible installation and stable support of the climbing frame is achieved, and the convenience and safety of construction are improved.
Patent Information
- Application Number
- CN202420573109.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-22
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-03-22
AI Technical Summary
The existing building construction climbing frame cannot be suitable for non-vertical plane building bodies, especially inclined buildings, which leads to inconvenience in construction.
A climbing frame for adjustable construction is designed. Through the combination of frame body and connecting structure, the length and angle of frame body are adjusted, and a support mechanism is equipped to provide three-point support to adapt to the installation of different building surfaces.
It improves the applicability and stability of the climbing frame, making it easier for construction personnel to climb on the outside of buildings of different heights and shapes, ensuring construction safety and efficiency.
Smart Images

Figure CN222010082U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building equipment, in particular to an adjustable climbing frame for building construction. Background Art
[0002] During the construction process, construction workers need to work at different heights, so reliable support and working platforms are required. Traditional scaffolding or climbing frames are usually fixed in height and cannot meet the construction needs of different heights. The emergence of adjustable climbing frames for construction solves this problem. It can adjust the height according to actual needs and is suitable for buildings of various irregular heights, which improves the flexibility and efficiency of construction. However, during the use of existing construction climbing frames, most of them are erected vertically and the height is adjusted and fixed. The installation angle of the climbing frame cannot be adjusted, resulting in the construction climbing frame being unable to be applied to the exterior walls of buildings that are not vertical planes. If the facade of the building is inclined, the existing construction climbing frame can only expand outward and fit the inclined surface of the building after the support foundation is erected on the outside of the building, so that construction workers can climb to the inclined surface of the building, which makes it inconvenient to use. To this end, we propose an adjustable climbing frame for construction. Utility Model Content
[0003] The purpose of the utility model is to provide an adjustable climbing frame for building construction to solve the problems raised in the above-mentioned background technology.
[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an adjustable climbing frame for construction, comprising a frame body, the frame body is arranged into several groups, two adjacent groups of frame bodies are connected by a connecting structure, the frame body comprises a vertical rod and a cross rod, the vertical rod is arranged into two groups and is distributed in parallel, and a plurality of groups of cross rods which are linearly distributed at equal distances are connected between the two groups of vertical rods, the connecting structure comprises a fixing sleeve which is sleeved on the surface of the vertical rod, the surface of the fixing sleeve is provided with a threaded hole and a limiting bolt A is inserted in the threaded hole, the upper end surface of the fixing sleeve is fixedly connected with a hinge table, the surface of the hinge table is inserted with a hinge shaft, the surface of the hinge shaft is fixedly connected with a hinge block, the upper end surface of the hinge block is fixedly connected with a connecting sleeve, the inner diameter of the connecting sleeve is matched with the outer diameter of the vertical rod, the surface of the connecting sleeve is provided with a threaded hole and a limiting bolt B is inserted in the threaded hole, the surface of the hinge table is provided with a threaded hole which is connected with the hinge hole of the hinge shaft, and a limiting bolt C is inserted in the threaded hole on the surface of the hinge table.
[0005] Preferably, both end surfaces of the vertical rod are provided with bayonet holes, and the limiting bolt A, limiting bolt B and the bayonet holes are matched with each other.
[0006] Preferably, a supporting mechanism is also installed between two adjacent groups of the frames, and the supporting mechanism includes a mounting sleeve which is sleeved on the surface of the vertical rod, the surface of the mounting sleeve is provided with a threaded hole, and a limiting bolt D is inserted in the threaded hole, the mounting sleeve is provided in two groups, and the two groups of mounting sleeves are adaptively sleeved on the two adjacent groups of vertical rods, the surface of the mounting sleeve is provided with a protrusion A, and a damping shaft A is inserted in the inside of the protrusion A, and a connecting rod is fixedly connected to the surface of the damping shaft A, and the other ends of the two groups of connecting rods are hinged to the hinge rod through the damping shaft B, the hinge rod is provided in a "T" shape, one end of the hinge rod is hinged with a protrusion B, the surface of the protrusion B is fixedly connected to an adjusting rod, the surface of the adjusting rod is sleeved with a sleeve, and the other end of the sleeve is fixedly connected to a fixing plate.
[0007] Preferably, a threaded hole is provided on the surface of the sleeve and a limiting bolt E is inserted into the threaded hole.
[0008] Preferably, the damping shaft A, the damping shaft B and the bump B are all provided with torsion springs inside.
[0009] Preferably, the surface of the crossbar is provided with evenly distributed textures.
[0010] Compared with the prior art, the beneficial effects of the utility model are:
[0011] 1. This solution uses the structural setting of the frame and the connecting structure, and the frames are connected by the connecting structure, so that multiple sets of frames can be linearly connected in sequence through multiple sets of connecting structures, and the overall length of the frame can be further adjusted, which is convenient for different building construction heights. In addition, the angles of two adjacent sets of frames can be adjusted through the connecting structure, and different angles can be formed between the two sets of frames, so that the device can be adaptively adjusted during the installation process on the outside of the building to fit the exterior facades of the building with different shapes, which is convenient for construction workers to climb and improves the applicability of the device;
[0012] 2. This scheme uses the structural setting of the frame and the supporting mechanism so that after the supporting mechanism is installed between two adjacent groups of frames, one end of the supporting mechanism is supported on the building to support the two adjacent groups of frames, and further form a three-point support between the two adjacent groups of frames and the building, so that the supporting force can be evenly distributed at different positions, thereby ensuring the balance and stability of the entire climbing frame system, and the adjustable structure of the supporting mechanism can support the surfaces of buildings at different intervals, further increasing the adaptability of the device. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a schematic diagram of the structure of the utility model;
[0014] Figure 2This is a schematic diagram of the frame structure connection of the utility model;
[0015] Figure 3 This is a schematic diagram of the connection structure of the utility model;
[0016] Figure 4 This is a schematic diagram of the support mechanism structure of the utility model.
[0017] In the figure: 1. frame; 101. vertical rod; 102. horizontal rod; 103. bayonet; 2. connection structure; 201. fixing sleeve; 202. limiting bolt A; 203. hinged table; 204. hinged shaft; 205. hinged block; 206. connecting sleeve; 207. limiting bolt B; 208. limiting bolt C; 3. supporting mechanism; 301. mounting sleeve; 302. limiting bolt D; 303. protrusion A; 304. damping shaft A; 305. connecting rod; 306. hinged rod; 307. damping shaft B; 308. protrusion B; 309. adjusting rod; 310. sleeve; 311. fixing plate; 312. limiting bolt E. DETAILED DESCRIPTION
[0018] Example
[0019] See also Figure 1-4 , the utility model provides a technical solution:
[0020] An adjustable climbing frame for construction, wherein the frames 1 are connected by a connecting structure 2, and further, multiple sets of frames 1 can be linearly connected in sequence by multiple sets of connecting structures 2, and the overall length of the frames 1 can be further adjusted, so as to be conveniently applicable to different construction heights. Furthermore, the angle between two adjacent sets of frames 1 can be adjusted by the connecting structure 2, and different angles can be formed between the two sets of frames 1, so that the device can be adaptively adjusted to fit the exterior facades of buildings of different shapes during installation outside the building, so as to facilitate the climbing of construction personnel and improve the applicability of the device.
[0021] The frame 1 includes a vertical rod 101 and a horizontal rod 102. The vertical rods 101 are arranged in two groups and are distributed in parallel. A plurality of horizontal rods 102 are installed between the two groups of vertical rods 101 and are distributed linearly at equal distances. After the frame 1 is installed, the upper end of the frame 1 is set on the surface of the building, and the construction workers climb through the horizontal rods 102, so that the construction workers can climb up. In addition, the surface of the horizontal rod 102 is provided with evenly distributed textures, which further increases the friction during climbing and prevents the construction workers from slipping and stepping on empty space.
[0022] The connection structure 2 includes a fixing sleeve 201 which is sleeved on the surface of the vertical rod 101. The surface of the fixing sleeve 201 is provided with a threaded hole and a limiting bolt A202 is inserted into the threaded hole. After the fixing sleeve 201 is sleeved on the surface of the vertical rod 101, the limiting bolt A202 is tightened in the threaded hole to further achieve a stable connection between the frame 1 and the connection structure 2. In addition, the surfaces of both ends of the vertical rod 101 are provided with bayonet holes 103. When the fixing sleeve 201 is installed on the vertical rod 101 to the fitting position, the threaded hole on the surface of the fixing sleeve 201 is just aligned with the bayonet hole 103, so that the limiting bolt A202 will be inserted into the bayonet hole 103 after being tightened, thereby achieving a firm connection between the fixing sleeve 201 and the vertical rod 101. The upper end surface of the fixed sleeve 201 is fixedly connected with a hinged platform 203, the surface of the hinged platform 203 is inserted with a hinged shaft 204, the surface of the hinged shaft 204 is fixedly connected with a hinged block 205, and the upper end surface of the hinged block 205 is fixedly connected with a connecting sleeve 206. The inner diameter of the connecting sleeve 206 is adapted to the outer diameter of the vertical rod 101, so that after the two sets of frame bodies 1 are connected, one set of vertical rods 101 is inserted into the connecting sleeve 206, and the linear connection between the two sets of vertical rods 101 is further realized. The surface of the connecting sleeve 206 is provided with a threaded hole and a limiting bolt B207 is inserted into the threaded hole. When the vertical rod 101 is inserted into the connecting sleeve 206, the limiting bolt B207 is controlled to be inserted into the bayonet 103 set on the surface of the vertical rod 101, and the vertical rod 101 is further fixed in the connecting sleeve 206, and the fixed connection of the two sets of frame bodies 1 is realized. The hinge block 205 is connected to the hinge shaft 204 for rotation, and the inclination angle of the connecting sleeve 206 on the hinge platform 203 can be further adjusted, so that the angle between the two adjacent groups of vertical rods 101 can be adjusted, and the device can be further controlled to be installed with different line segment structures to be suitable for buildings with different facade shapes, which is convenient for construction workers to climb. In addition, the surface of the hinge platform 203 is provided with a threaded hole that is connected to the hinge hole of the hinge shaft 204, and a limiting bolt C208 is inserted in the threaded hole on the surface of the hinge platform 203. After the hinge shaft 204 is rotated to a suitable angle, the limiting bolt C208 is tightened in the threaded hole and abuts against the surface of the hinge shaft 204, which can increase the friction of the hinge shaft 204 rotation, and further limit and fix the hinge shaft 204, so as to achieve adjustment and fixation between the two adjacent groups of frames 1, and improve the device firmness and personnel safety when construction workers climb.
[0023] A support mechanism 3 is also installed between two adjacent groups of frames 1. The support mechanism 3 can maintain the same distance between the frames 1 and the surface of the building, and further control the frames 1 to be stably installed on the facade of the building and reduce direct contact with the facade, further avoiding damage to the facade of the building. At the same time, the support mechanism 3 can support the frames 1, so that the construction workers can improve the stability of the frames 1 through the support mechanism 3 during the climbing process, and avoid the frames 1 from tilting and collapsing during the climbing process. In addition, the support mechanism 3 can support two groups of frames 1 with different angles, further ensuring the firmness of the two groups of frames 1 after adjustment, so as to improve the stability and safety of the device.
[0024] The support mechanism 3 includes a mounting sleeve 301 sleeved on the surface of the vertical rod 101, and a threaded hole is provided on the surface of the mounting sleeve 301 and a limiting bolt D302 is inserted in the threaded hole. The mounting sleeve 301 can slide on the surface of the vertical rod 101, and further the limiting bolt D302 is tightened in the threaded hole and abuts against the surface of the vertical rod 101, so that the mounting sleeve 301 can be fixedly connected to the surface of the vertical rod 101. In addition, the mounting sleeve 301 is provided in two groups, and the two groups of mounting sleeves 301 are adapted to be sleeved on the two groups of vertical rods 101 in the two adjacent groups of frames 1, so as to further realize the installation of the support mechanism 3 between the two adjacent groups of frames 1. A convex block A303 is provided on the surface of the mounting sleeve 301, and a damping shaft A304 is inserted in the inside of the convex block A303. A connecting rod 305 is fixedly connected to the surface of the damping shaft A304, and the other ends of the two groups of connecting rods 305 are hinged to the hinge rod 306 through the damping shaft B307. Further, by controlling the connecting rod 305 to rotate on the damping shaft A304, the angle of the hinged rod 306 can be adjusted. After the two sets of mounting sleeves 301 are installed on the two adjacent sets of frames 1, the hinged rod 306 can adjust the position to further adjust the installation position of the support mechanism 3. The hinged rod 306 is set to a "T" shape, and a protrusion B308 is hinged at one end of the hinged rod 306. The surface of the protrusion B308 is fixedly connected to an adjustment rod 309. The surface of the adjustment rod 309 is sleeved with a sleeve 310, and the other end of the sleeve 310 is fixedly connected to a fixing plate 311. When the support mechanism 3 is installed on the two adjacent sets of frames 1, by controlling the protrusion B308 to rotate on the hinged rod 306, the adjustment rod 309 is further controlled to be perpendicular to the outer facade of the building, and slides on the surface of the adjustment rod 309 through the sleeve 310, and the fixing plate 311 is controlled to contact the surface of the building. After one end of the support mechanism 3 is supported on the building, the two adjacent groups of frames 1 are supported. In addition, a threaded hole is provided on the surface of the sleeve 310 and a limit bolt E312 is inserted into the threaded hole, so that the overall length of the adjustment rod 309 and the sleeve 310 can be fixed after adjustment, which is convenient for supporting the surfaces of buildings with different spacings. At the same time, torsion springs are provided inside the damping shaft A304, the damping shaft B307, and the protrusion B308, so that after the support mechanism 3 is installed, a three-point support is formed between the two adjacent groups of frames 1 and the building, so that the supporting force can be evenly distributed at different positions, thereby ensuring the balance and stability of the entire climbing frame system. In addition, the adjustable structure of the support mechanism 3 further increases the adaptability of the device.
Claims
1. An adjustable climbing frame for construction, comprising a frame body (1), characterized in that: The frame (1) is arranged into a plurality of groups, and two adjacent groups of frame (1) are connected via a connecting structure (2). The frame (1) comprises a vertical rod (101) and a horizontal rod (102). The vertical rod (101) is arranged into two groups and is distributed in parallel. A plurality of horizontal rods (102) that are linearly distributed at equal distances are connected between the two groups of vertical rods (101). The connecting structure (2) comprises a fixing sleeve (201) sleeved on the surface of the vertical rod (101). The surface of the fixing sleeve (201) is provided with a threaded hole, and a limiting bolt A (202) is inserted into the threaded hole. The upper end surface of the fixing sleeve (201) is fixedly connected with a hinged platform (203). A hinge shaft (204) is inserted on the surface of the hinge platform (203), a hinge block (205) is fixedly connected to the surface of the hinge shaft (204), a connecting sleeve (206) is fixedly connected to the upper end surface of the hinge block (205), the inner diameter of the connecting sleeve (206) is matched with the outer diameter of the vertical rod (101), a threaded hole is provided on the surface of the connecting sleeve (206) and a limiting bolt B (207) is inserted in the threaded hole, a threaded hole is provided on the surface of the hinge platform (203) and is connected to the hinge hole of the hinge shaft (204), and a limiting bolt C (208) is inserted in the threaded hole on the surface of the hinge platform (203).
2. The adjustable climbing frame for construction according to claim 1, characterized in that: The surfaces at both ends of the vertical rod (101) are provided with bayonet holes (103), and the limiting bolt A (202), the limiting bolt B (207) and the bayonet holes (103) are adapted to each other.
3. The adjustable climbing frame for construction according to claim 1, characterized in that: A support mechanism (3) is also installed between two adjacent groups of the frame bodies (1), and the support mechanism (3) includes a mounting sleeve (301) sleeved on the surface of the vertical rod (101), the surface of the mounting sleeve (301) is provided with a threaded hole, and a limiting bolt D (302) is inserted into the threaded hole, and the mounting sleeve (301) is provided in two groups, and the two groups of the mounting sleeves (301) are adapted to be sleeved on the two adjacent groups of vertical rods (101), and the surface of the mounting sleeve (301) is provided with a convex block A (303), and a damping shaft A (302) is inserted into the interior of the convex block A (303). 04), the surface of the damping shaft A (304) is fixedly connected with a connecting rod (305), the other ends of the two groups of connecting rods (305) are hinged on a hinge rod (306) through a damping shaft B (307), the hinge rod (306) is configured as a "T" shape, one end of the hinge rod (306) is hinged with a protrusion B (308), the surface of the protrusion B (308) is fixedly connected with an adjusting rod (309), the surface of the adjusting rod (309) is sleeved with a sleeve (310), and the other end of the sleeve (310) is fixedly connected with a fixing plate (311).
4. The adjustable climbing frame for construction according to claim 3 is characterized in that: The surface of the sleeve (310) is provided with a threaded hole and a limiting bolt E (312) is inserted into the threaded hole.
5. The adjustable climbing frame for construction according to claim 3, characterized in that: Torsion springs are arranged inside the damping shaft A (304), the damping shaft B (307) and the bump B (308).
6. The adjustable climbing frame for construction according to claim 1, characterized in that: The surface of the crossbar (102) is provided with evenly distributed textures.