Hazardous waste incineration flue gas treatment system

By setting up a suction chamber and a water vapor recovery tower in the hazardous waste incineration flue gas treatment system, water vapor is recycled and heat recovery is used for waste heat boiler, the problems of increasing air pressure and reducing combustion efficiency caused by water vapor are solved, and efficient heat recovery is achieved .

CN222011919UActive Publication Date: 2024-11-15SHANDONG DONGSHUN ENVIRONMENTAL PROTECTION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323494777.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-21
Publication Date
2024-11-15
Estimated Expiration
2033-12-21

AI Technical Summary

Technical Problem

The existing hazardous waste incineration flue gas treatment system increases the air pressure due to the generation of water vapor during the secondary combustion process, which reduces combustion efficiency and limits heat recovery, resulting in the problem of heat waste.

Method used

A hazardous waste incineration flue gas treatment system is designed, by setting a suction chamber and a water vapor recovery tower at the outlet end of the primary combustion chamber, water vapor recovery tower is used to recover water vapor, and heat is carried out through the first waste heat boiler and the second waste heat boiler. Recycling, preventing water vapor from entering the secondary combustion system, ensuring combustion efficiency and heat recovery.

Benefits of technology

It effectively avoids water vapor entering the flue gas system, ensures the reliability of secondary combustion, and recovers as much heat as possible, reducing heat loss.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222011919U_ABST
    Figure CN222011919U_ABST
Patent Text Reader

Abstract

The utility model provides a hazardous waste incineration flue gas treatment system which comprises a primary combustion chamber, the outlet end of the primary combustion chamber is connected with a gas suction chamber, the residue outlet end of the gas suction chamber is connected with a water vapor recovery tower, the bottom of the water vapor recovery tower is provided with a slag conveyor for receiving waste residues, and the top of the water vapor recovery tower is provided with a cooling layer; the upper part of the suction chamber is connected with a secondary combustion chamber; a second combustor is installed in the secondary combustion chamber, and a first waste heat boiler is connected to the lower portion of the second combustor. A second waste heat boiler is connected to the upper portion of the second combustor and connected with the waste gas treatment system through a flue gas pipeline. The gas suction chamber for collecting flue gas and the water vapor recovery tower are arranged at the outlet end of the primary combustion chamber, water vapor generated by cooling water of the slag conveyor expands and ascends in the water vapor recovery tower and then is liquefied in cold to be recovered, and the water vapor can be prevented from entering a flue gas incineration system through separation of the gas suction chamber; therefore, the reliability of secondary combustion can be ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of hazardous waste incineration treatment, in particular to a hazardous waste incineration smoke treatment system. Background Art

[0002] At present, conventional methods for treating hazardous waste include incineration, especially secondary incineration, which can further reduce the possibility of incomplete combustion. However, secondary incineration requires a large amount of heat, and the flue gas after incineration also carries a large amount of heat. In order to avoid wasting heat, heat exchange is performed before the flue gas is discharged to recover the heat of the flue gas. However, when the temperature of the flue gas is reduced, it will cause the problem of dioxin regeneration, which limits the recovery of flue gas heat and causes the heat to be lost in vain.

[0003] In this regard, the patent with announcement number CN207599713U discloses a hazardous waste incineration system based on flue gas recirculation, which can improve the benefits of heat recovery in flue gas. However, it installs a secondary combustion chamber at the outlet end of the primary combustion chamber, and a slag picker is set at the bottom of the secondary combustion chamber. A second burner is set above the secondary combustion chamber. The space for secondary combustion of flue gas is connected to the cooling water space of the slag picker. This will cause the residue carrying high heat to release a large amount of water vapor instantly when it is quenched by water, causing the air pressure in the secondary combustion chamber to increase sharply, which is not conducive to the smooth operation of the equipment. Secondly, the high water vapor content in the secondary combustion chamber will reduce the efficiency of secondary combustion, resulting in the temperature of secondary combustion failing to meet the requirements, resulting in incomplete combustion of flue gas, or increasing the secondary combustion flame to ensure combustion efficiency, but it will increase more energy consumption. Utility Model Content

[0004] The purpose of this application is to provide a hazardous waste incineration flue gas treatment system, aiming to solve the above-mentioned problems in the prior art.

[0005] An embodiment of the present application provides a hazardous waste incineration flue gas treatment system, including a primary combustion chamber, the outlet end of the primary combustion chamber is connected to an intake chamber, the residue outlet end of the intake chamber is connected to a water vapor recovery tower, a slag scooper for receiving waste residues is provided at the bottom of the water vapor recovery tower, and a cooling layer is provided on the top of the water vapor recovery tower; a gas outlet is opened at the upper part of the intake chamber, and the gas outlet is connected to a secondary combustion chamber; a second burner is installed in the secondary combustion chamber, and the secondary combustion chamber below the second burner is connected to a first waste heat boiler, and the first waste heat boiler is connected to the inlet end of the primary combustion chamber through a flue gas duct; the secondary combustion chamber above the second burner is connected to a second waste heat boiler, and the second waste heat boiler is connected to a waste gas treatment system through a flue gas duct, and the outlet end of the waste gas treatment system is connected to a chimney.

[0006] Furthermore, the primary combustion chamber is an inclined rotary kiln, the high side of the primary combustion chamber is the inlet end, and the low side is the outlet end; the inlet end of the primary combustion chamber is also connected to a discharge machine for feeding.

[0007] Furthermore, a first burner and a gas supply device are installed at the outlet end of the primary combustion chamber, and the gas supply device fills oxygen-rich gas into the primary combustion chamber.

[0008] Furthermore, a conveying device for waste residues is arranged in the air intake chamber to transport the waste residues discharged from the primary combustion chamber to the water vapor recovery tower.

[0009] Furthermore, a first induced draft fan is provided on the flue gas duct at the outlet side of the first waste heat boiler; and a second induced draft fan is provided on the flue gas duct at the outlet side of the second waste heat boiler.

[0010] The beneficial effects of the utility model are as follows: the utility model sets an air suction chamber for collecting flue gas and a water vapor recovery tower at the outlet end of the primary combustion chamber. The water vapor generated by the cooling water of the slag extractor expands and rises in the water vapor recovery tower, and then is cooled and liquefied for recovery. The separation of the air suction chamber can prevent water vapor from entering the flue gas incineration system, thereby ensuring the reliability of secondary combustion. At the same time, the first waste heat boiler can recover as much heat as possible to avoid heat loss. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a schematic diagram of the overall structure of the utility model.

[0012] In the figure:

[0013] 1. Primary combustion chamber; 2. Discharging machine; 3. First burner; 4. Air supply device; 5. Air suction chamber; 6. Water vapor recovery tower; 7. Slag remover; 8. Cooling layer; 9. Secondary combustion chamber; 10. Second burner; 11. First waste heat boiler; 12. Flue gas duct; 13. Second waste heat boiler; 14. Waste gas treatment system; 15. Chimney; 16. First induced draft fan; 17. Second induced draft fan. DETAILED DESCRIPTION

[0014] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0015] like Figure 1A hazardous waste incineration flue gas treatment system shown includes a primary combustion chamber 1, which is an inclined rotary kiln, with the high side of the primary combustion chamber 1 being the inlet end and the low side being the outlet end. The inlet end of the primary combustion chamber 1 is also connected to a discharger 2 for feeding. The discharger 2 transports the hazardous waste to be incinerated to the inlet of the rotary kiln. A first burner 3 and an air supply device 4 are installed at the outlet end of the primary combustion chamber 1, and the air supply device 4 fills the primary combustion chamber 1 with oxygen-rich gas to promote the combustion of the first burner 3. During the rotation of the rotary kiln, the waste moves from the high end to the low end under the action of the rotation thrust and its own gravity, and successively undergoes drying, combustion and burnout stages in the process.

[0016] The outlet end of the primary combustion chamber 1 is connected to the suction chamber 5, the residue outlet end of the suction chamber 5 extends horizontally and is connected to the water vapor recovery tower 6, and a conveying device for waste residues is provided in the suction chamber 5, which can be a conventional conveying device for transporting the waste residues discharged from the primary combustion chamber 1 to the water vapor recovery tower 6. During the transportation process, the waste residues still release smoke and heat, which are gathered in the suction chamber 5 and sucked into the secondary combustion chamber 9. The waste residues enter the water vapor recovery tower 6.

[0017] A slag picker 7 for receiving waste residues is provided at the bottom of the water vapor recovery tower 6. The waste residues are in a molten state at this time, and fall into the slag picker 7 to be quenched and solidified by cooling water. The slag picker 7 is conventionally provided with a horizontal trough section and a lifting section. The horizontal trough section is provided with cooling water for cooling the waste residues into slag, and then the residues are removed and drained through the lifting section. The large amount of heat carried by the waste residues is transferred to the cooling water, so that the liquid water is vaporized in a large amount in a short time to generate water vapor. The water vapor rises to the top in the water vapor recovery tower 6. A cooling layer 8 is provided at the top of the water vapor recovery tower 6. The cooling layer 8 is set at a low temperature. When the water vapor is cooled, it is liquefied into liquid water again and falls back into the slag picker 7, thereby recovering the water vapor, which can prevent a large amount of vaporized water from mixing into the flue gas treatment system.

[0018] A gas outlet is provided at the upper part of the air intake chamber 5, and the gas outlet is connected to the secondary combustion chamber 9, and the flue gas in the air intake chamber 5 enters the secondary combustion chamber 9. A second burner 10 is installed in the secondary combustion chamber 9, and the secondary combustion chamber 9 below the second burner 10 is connected to a first waste heat boiler 11, and the first waste heat boiler 11 is connected to the inlet end of the primary combustion chamber 1 through a flue gas duct 12. A second waste heat boiler 13 is connected to the secondary combustion chamber 9 above the second burner 10, and the second waste heat boiler 13 is connected to an exhaust gas treatment system 14 through a flue gas duct 12, and the outlet end of the exhaust gas treatment system 14 is connected to a chimney 15.

[0019] A first induced draft fan 16 is provided on the flue gas duct 12 at the outlet side of the first waste heat boiler 11, which sucks the flue gas generated by the primary combustion in the secondary combustion chamber 9 into the first waste heat boiler 11 to recover heat. After the flue gas temperature is reduced to 240-500°C, it returns from the flue gas duct 12 to the primary combustion chamber 1 to participate in the incineration. During the process, the gas supply device 4 always provides oxygen-rich gas to the primary combustion chamber 1 to make it fully burned. A second induced draft fan 17 is provided on the flue gas duct 12 at the outlet side of the second waste heat boiler 13. The second induced draft fan 17 is used to draw the flue gas in the secondary combustion chamber 9 through the second burner 10 into the second waste heat boiler 13. During the process, the second burner 10 performs a second combustion on the flue gas to make the combustion of the flue gas more complete. The second waste heat boiler 13 recovers heat to reduce the temperature to 500-600°C, and then enters the waste gas treatment system 14 to remove harmful substances in the flue gas, such as sulfur dioxide, nitrogen oxides, hydrogen chloride, hydrogen fluoride, heavy metals, dust and dioxins, and then discharges them into the atmosphere through the chimney 15 after reaching the standard. In this embodiment, the waste gas treatment system 14 can use conventional devices for removing dangerous gases, such as deacidification tower, denitration tower, alkali washing tower and physical dust filtration device. In addition, since the flue gas entering the first waste heat boiler 11 is not discharged into the atmosphere, the waste heat recovery can recover as much heat as possible without considering the problem of dioxin regeneration.

[0020] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.

Claims

1. A hazardous waste incineration flue gas treatment system, characterized in that: It includes a primary combustion chamber, the outlet end of the primary combustion chamber is connected to an intake chamber, the residue outlet end of the intake chamber is connected to a water vapor recovery tower, a slag scooper for receiving waste residues is provided at the bottom of the water vapor recovery tower, and a cooling layer is provided on the top of the water vapor recovery tower; a gas outlet is provided at the upper part of the intake chamber, and the gas outlet is connected to a secondary combustion chamber; a second burner is installed in the secondary combustion chamber, and the secondary combustion chamber below the second burner is connected to a first waste heat boiler, and the first waste heat boiler is connected to the inlet end of the primary combustion chamber through a flue gas duct; the secondary combustion chamber above the second burner is connected to a second waste heat boiler, and the second waste heat boiler is connected to a waste gas treatment system through a flue gas duct, and the outlet end of the waste gas treatment system is connected to a chimney.

2. The hazardous waste incineration flue gas treatment system according to claim 1 is characterized in that: The primary combustion chamber is an inclined rotary kiln, the high side of the primary combustion chamber is the inlet end, and the low side is the outlet end; the inlet end of the primary combustion chamber is also connected to a discharge machine for feeding.

3. The hazardous waste incineration flue gas treatment system according to claim 2 is characterized in that: The outlet end of the primary combustion chamber is provided with a first burner and a gas supply device, and the gas supply device fills oxygen-rich gas into the primary combustion chamber.

4. The hazardous waste incineration flue gas treatment system according to claim 1, characterized in that: The suction chamber is provided with a conveying device for waste residues, which transports the waste residues discharged from the primary combustion chamber to the water vapor recovery tower.

5. The hazardous waste incineration flue gas treatment system according to claim 1, characterized in that: A first induced draft fan is arranged on the flue gas duct at the outlet side of the first waste heat boiler; a second induced draft fan is arranged on the flue gas duct at the outlet side of the second waste heat boiler.