Effect raising system for replacing high-order steam extraction with flue gas waste heat composite low-order steam extraction

By designing a system for flue gas waste heat composite low-order steam extraction to replace high-order steam extraction, using flue gas waste heat to heat air and water, replacing high-grade steam extraction, the problem of poor coal saving effect in bituminous coal coal units is solved, and the Significant energy-saving effect.

CN222011968UActive Publication Date: 2024-11-15NORTH CHINA POWER ENG
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202420685381.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-03
Publication Date
2024-11-15
Estimated Expiration
2034-04-03

AI Technical Summary

Technical Problem

The existing flue gas waste heat utilization technology has poor coal saving effect in bituminous coal units. Investment has increased but the increase in coal saving is limited, so it is impossible to effectively utilize low-grade flue gas waste heat.

Method used

Design an efficiency improvement system for flue gas waste heat composite low-order steam extraction replacement high-order steam extraction. Through primary fans, secondary fans, boilers and steam turbine heating and cooling air is heated by using flue gas waste heat to heat the air preheater inlet cold air. And heat high-pressure feed water and high-temperature condensate through bypass flue gas to replace high-grade steam extraction and improve the functional power of the unit.

Benefits of technology

With the unit's heat consumption unchanged, the coal saving amount is significantly increased, and the coal saving amount in the BMCR operating condition of the bituminous coal unit has increased from 1g/kWh of the conventional plan to 3.18g/kWh, which significantly improves the energy saving effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222011968U_ABST
    Figure CN222011968U_ABST
Patent Text Reader

Abstract

The utility model discloses an efficiency increasing system for replacing high-order steam extraction with flue gas waste heat composite low-order steam extraction. A flue gas outlet of a boiler is sequentially connected with a temperature adjusting flue gas cooler, a heating medium water flue gas cooler and a dust remover. An air preheater and a bypass flue are arranged between a smoke outlet of the boiler and the temperature adjusting smoke cooler in parallel. The primary fan is connected with the air preheater after passing through the first primary air heater and the first secondary air heater in sequence; the secondary fan is connected with the air preheater after sequentially passing through the second primary air heater and the second secondary air heater; heat exchange pipelines in the first primary air heater and the second primary air heater are connected with a heat exchange pipeline in the heat medium water smoke cooler; a condensate pipe is led out from an outlet of an eighth low-pressure heater or a lower-stage heater in the steam turbine regenerative steam extraction system, and the condensate pipe is connected with heat exchange pipelines in the first second-stage air heater and the second second-stage air heater. The scheme is particularly suitable for bituminous coal units, and compared with an existing scheme, the coal saving amount efficiency is remarkably improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of coal-fired power generation units, and specifically relates to an efficiency-enhancing system for replacing high-order extraction steam with flue gas waste heat composite low-order extraction steam. Background Art

[0002] At present, the exhaust temperature of lignite units is high. A flue gas waste heat cascade utilization system with air preheater bypass is used to heat the cold air, bypass the air preheater flue gas, heat the feed water and high-order condensate, and squeeze out the high-grade extraction steam, so as to achieve low-grade heat replacement of high-grade heat, and achieve significant energy-saving effect. Taking the Beijing Energy Wujianfang Power Plant as an example, it uses lignite from the West No. 1 Mine in the Wujianfang Mining Area. The boiler exhaust temperature (air preheater outlet) is about 145°C. The flue gas waste heat is not only high-grade, but also high in heat. The flue gas waste heat cascade utilization system with air preheater bypass is used. The BMCR working condition reduces the standard coal consumption of power generation by about 5g / kwh (if the existing conventional flue gas waste heat utilization technology is used, the coal saving level is 2.5g / kWh).

[0003] As for bituminous coal, the exhaust temperature of bituminous coal units is low, generally below 120℃, and the flue gas waste heat is not only of low grade, but also of small heat. If a flue gas waste heat cascade utilization system with air preheater bypass is adopted, due to the low exhaust temperature, the mass share of flue gas out of the bypass is low (generally around 6%), compared with the conventional flue gas waste heat utilization scheme, the investment is much increased, but the coal saving effect is limited.

[0004] Bituminous coal units are the mainstream of my country's coal-fired power plants. Therefore, it is necessary to combine the waste heat of flue gas to develop an efficiency improvement system that is more suitable for bituminous coal units, which will be more practical for energy conservation and carbon reduction in my country's coal-fired power plants. Utility Model Content

[0005] The technical problem to be solved by the utility model is to provide an efficiency improvement system for replacing high-order extraction steam with flue gas waste heat and low-grade extraction steam, so as to solve the problem that the existing scheme has poor coal saving level when used for bituminous coal units, and to utilize flue gas waste heat and low-grade extraction steam to heat the cold air at the air preheater inlet, and the high-temperature flue gas bypassed to heat the high-pressure feed water and high-temperature condensate to replace the high-grade extraction steam. In this way, the work capacity of the unit is increased while the heat consumption of the unit remains unchanged, thereby significantly improving the amount of coal saving.

[0006] According to the technical scheme of the utility model, the utility model provides an efficiency-improving system for replacing high-order extraction steam with flue gas waste heat composite low-order extraction steam, including a primary fan, a secondary fan, a boiler and a steam turbine heat recovery extraction system; the flue gas outlet of the boiler is connected to a temperature-regulating flue gas cooler, a heat medium water flue gas cooler and a dust collector in sequence through a flue; an air preheater and a bypass flue are arranged in parallel between the flue gas outlet of the boiler and the temperature-regulating flue gas cooler; the primary fan is connected to the air preheater after passing through the first primary air heater and the first and second secondary air heaters in sequence; the secondary fan is connected to the air preheater after passing through the second primary air heater and the second and second secondary air heaters in sequence; the first primary air heater The heat exchange pipelines in the first-stage and second-stage heaters are connected to the heat exchange pipelines in the heat medium water smoke cooler; a condensate pipe is led out from the outlet of the No. 8 low-pressure heater or the lower-stage heater in the turbine heat recovery and extraction system, and the condensate pipe is connected to the heat exchange pipelines in the first-stage and second-stage heaters and the second-stage and second-stage heaters; a feed water heat exchanger for heating part of the feed water in the turbine heat recovery and extraction system, and a high-temperature condensate heat exchanger for heating part of the condensate in the turbine heat recovery and extraction system are provided in the bypass flue; a temperature regulating water pipe is led out from the outlet of the low-pressure heater in the turbine heat recovery and extraction system, and the temperature regulating water pipe is connected to the heat exchange pipeline in the temperature regulating smoke cooler.

[0007] Furthermore, the condensate pipe is arranged at the outlet of the No. 8 low-pressure heater; the output ends of the heat exchange pipelines in the first and second-level air heaters and the second and second-level air heaters are connected to the inlet of the No. 8 low-pressure heater.

[0008] Furthermore, a variable frequency booster pump is provided in the condensate water pipe.

[0009] Furthermore, an adjusting baffle for adjusting the flue gas flow rate is provided in the bypass flue.

[0010] Furthermore, the feed water heat exchanger and the high-temperature condensate water heat exchanger are arranged in sequence along the flue gas flow direction.

[0011] Furthermore, the steam turbine heat recovery extraction system includes a No. 9 low-pressure heater, a No. 8 low-pressure heater, a No. 7 low-pressure heater, a No. 6 low-pressure heater, a No. 5 low-pressure heater, a deaerator, a feed water pump, a No. 3 high-pressure heater, a No. 2 high-pressure heater and a No. 1 high-pressure heater, which are connected in sequence.

[0012] Furthermore, the input end of the heat exchange pipeline in the feed water heat exchanger is connected to the pipeline at the inlet of the No. 3 high-pressure heater, and the output end of the heat exchange pipeline in the feed water heat exchanger is connected to the pipeline at the outlet of the No. 1 high-pressure heater.

[0013] Furthermore, the input end of the heat exchange pipeline in the high-temperature condensate heat exchanger is connected to the pipeline at the inlet of the No. 5 low-pressure heater, and the output end of the heat exchange pipeline in the high-temperature condensate heat exchanger is connected to the pipeline at the outlet of the No. 5 low-pressure heater.

[0014] Furthermore, the input end of the heat exchange pipeline in the thermostatic smoke cooler is connected to the pipeline at the inlet of the No. 6 low-pressure heater, and the output end of the heat exchange pipeline in the thermostatic smoke cooler is connected to the pipeline at the outlet of the No. 6 low-pressure heater.

[0015] Furthermore, the smoke outlet of the dust collector is connected to the induced draft fan, the flue gas desulfurization device and the chimney in sequence.

[0016] Compared with the prior art, the beneficial technical effects of the utility model are as follows:

[0017] The utility model's flue gas waste heat composite low-order extraction steam replacement high-order extraction steam efficiency improvement system combines flue gas waste heat, is particularly suitable for bituminous coal units, and has great significance for energy conservation and carbon reduction in my country's coal-fired power plants. Taking a 1000MW bituminous coal unit as an example, assuming that the exhaust gas temperature at the air preheater outlet is 120°C and the dust collector inlet flue gas temperature is controlled at 90°C; using this efficiency improvement system, the coal saving under BMCR conditions is 3.18g / kwh; if the conventional flue gas waste heat utilization scheme is adopted, the coal saving under BMCR conditions is 1g / kwh, and the efficiency is significantly improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the system structure according to an embodiment of the utility model.

[0019] Description of reference numerals in the accompanying drawings:

[0020] 1. Primary fan; 11. First-stage air heater; 12. First-stage and second-stage air heaters; 2. Secondary fan; 21. Second-stage air heater; 22. Second-stage and second-stage air heaters; 3. Boiler; 41. Air preheater; 42. Bypass flue; 43. Feedwater heat exchanger; 44. High-temperature condensate heat exchanger; 45. Adjustment damper; 5. Temperature-controlled smoke cooler; 61. Heat medium water smoke cooler; 62. Condensate pipe; 63. Variable frequency booster pump; 7. Dust collector; 81. Feedwater pump; 82. Deaerator; 91. Draft fan; 92. Flue gas desulfurization device; 93. Chimney. DETAILED DESCRIPTION

[0021] The utility model provides an efficiency-enhancing system that uses flue gas waste heat and low-grade extraction steam to replace high-grade extraction steam, solving the problem that the existing solution has a poor coal-saving level when used in bituminous coal units. The main inventive concept of this solution is to use flue gas waste heat and low-grade extraction steam to heat the cold air at the inlet of the air preheater, and the high-temperature flue gas bypassed to heat the high-pressure feed water and high-temperature condensate to replace high-grade extraction steam. In this way, the unit's work capacity is increased while the unit's heat consumption remains unchanged, thereby significantly improving the amount of coal saved.

[0022] See also Figure 1, an efficiency-enhancing system of a flue gas waste heat composite low-order steam extraction replacing high-order steam extraction in one embodiment of the utility model is applied to a coal-fired power generation unit. Similar to the existing coal-fired power generation unit, it includes a primary fan 1, a secondary fan 2, an air preheater 41 (referred to as air preheater), a boiler 3 and a steam turbine heat recovery steam extraction system. The primary fan 1 and the secondary fan 2 are respectively connected to the pulverized coal burner of the boiler 3 through the air supply duct (and the air preheater 41). The boiler 3 is connected to the steam turbine and the steam turbine heat recovery steam extraction system. The steam turbine heat recovery steam extraction system includes one or more high-pressure heaters (referred to as high-pressure heaters) and one or more low-pressure heaters (referred to as low-pressure heaters). These structures (not further clearly defined in the embodiments of the utility model) can use the existing technology and will not be elaborated here.

[0023] One of the main improvements of the utility model is that the first-stage heater and the second-stage heater are used to heat the cold air at the inlet of the air preheater. Among them, the first-stage heater uses the waste heat of the flue gas to heat the cold air; the second-stage heater uses the condensate at the outlet of the No. 8 low-pressure heater or a lower-order heater to heat the air, and heats the air temperature at the inlet of the air preheater to, for example, 90°C, and the condensate after cooling is returned to, for example, the inlet of the No. 8 low-pressure heater. With the above measures, the mass share of the flue gas bypassed can reach more than 10%.

[0024] More specifically, the primary air fan 1 is connected to the air preheater 41 after passing through the first primary air heater 11 and the first secondary air heater 12 in sequence. The secondary air fan 2 is connected to the air preheater 41 after passing through the second primary air heater 21 and the second secondary air heater 22 in sequence. The heat exchange pipelines in the first primary air heater 11 and the second primary air heater 21 are connected to the heat exchange pipelines in the heat medium water smoke cooler 61, for example, the first primary air heater 11 and the second primary air heater 21 are in parallel. A condensate pipe 62 is led out from the outlet of the No. 8 low-pressure heater or a lower-order heater in the turbine heat recovery extraction system, and the condensate pipe 62 is connected to the heat exchange pipelines in the first secondary air heater 12 and the second secondary air heater 22, for example, the first secondary air heater 12 and the second secondary air heater 22 are in parallel.

[0025] The first-stage air heater (the first first-stage air heater 11, the second first-stage air heater 21) is a flue gas waste heat air heater, and the first-stage air heater is arranged on the outlet air duct of the fan (primary fan 1, secondary fan 2). Corresponding to the first-stage air heater, a heat medium water smoke cooler 61 is provided, which is arranged on the flue between the outlet of the air preheater 41 and the inlet of the dust collector 7, and transfers the heat of the flue gas to the first-stage air heater through the heat medium water. For example, under the control requirements of the dust collector operation, the exhaust temperature is reduced from 120°C to 90°C; the air temperature is heated from 23°C to about 50°C.

[0026] The secondary air heater (the first secondary air heater 12, the second secondary air heater 22) is a condensate water heater, and the secondary air heater is arranged in the air duct downstream of the first stage air heater. A variable frequency booster pump 63 is provided in the condensate water pipe 62. The condensate water pipe 62 is, for example, arranged at the outlet of the No. 8 low-pressure heater; the output ends of the heat exchange pipelines in the first secondary air heater 12 and the second secondary air heater 22 are connected to the inlet of the No. 8 low-pressure heater to form a loop. In this way, part of the condensate water is extracted from the outlet of the No. 8 low-pressure heater and led to the secondary air heater, and the cooled condensate water returns to the inlet of the No. 8 low-pressure heater (tentative), and the air temperature is heated from 50°C at the outlet of the first stage air heater to 90°C (tentative).

[0027] The flue gas outlet of the boiler 3 is connected to the temperature-regulating flue gas cooler 5, the heat medium water flue gas cooler 61 and the dust collector 7 in sequence through the flue. An air preheater 41 and a bypass flue 42 are arranged in parallel (or in parallel) between the flue gas outlet of the boiler 3 and the temperature-regulating flue gas cooler 5. Since the air is heated by the heater, the function of the air preheater is partially replaced, which is manifested in that the temperature of the cold air entering the cold end of the air preheater is increased from 23°C to 90°C. When the hot air temperature at the hot end of the air preheater remains unchanged, part of the flue gas does not enter the air preheater 41, but is introduced into the bypass flue 42. The bypass flue 42 is provided with a feed water heat exchanger 43 for heating part of the feed water in the steam turbine heat recovery extraction system, and a high-temperature condensate water heat exchanger 44 for heating part of the condensate in the steam turbine heat recovery extraction system. In other words, the feedwater heat exchanger 43 and the high-temperature condensate heat exchanger 44 arranged in the bypass flue 42 heat part of the high-pressure feedwater and the high-temperature condensate respectively to displace the corresponding high-pressure extraction steam; the end of the bypass flue 42 merges into the outlet flue of the air preheater 41. The feedwater heat exchanger 43 and the high-temperature condensate heat exchanger 44 are arranged in sequence along the flue gas flow direction to achieve step-by-step heat exchange.

[0028] As the air temperature at the cold end of the air preheater increases, the exhaust gas temperature at the outlet of the air preheater increases due to the control of the cold end temperature difference. Therefore, a temperature-controlled smoke cooler 5 is provided, and a temperature-controlled water pipe is led out from the outlet of the low-pressure heater in the steam turbine heat recovery extraction system, and the temperature-controlled water pipe is connected to the heat exchange pipeline in the temperature-controlled smoke cooler 5; the cold source uses high-temperature condensed water with a temperature difference matching, and the outlet smoke temperature of the temperature-controlled smoke cooler 5 is the same as the original exhaust gas temperature of the air preheater 41. In this way, the heat balance between the tail two-stage smoke cooler (temperature-controlled smoke cooler 5 and heat medium water smoke cooler 61) and the two-stage heater and the stable operation of the system are ensured.

[0029] Furthermore, an adjusting damper 45 (eg an electrically controlled adjusting flue gas damper) for adjusting the flue gas flow rate is provided in the bypass flue duct 42 to ensure that the bypass flue gas flow rate and the air preheater flue gas flow rate are within the design values.

[0030] In a specific embodiment, the steam turbine heat recovery extraction system includes a No. 9 low pressure heater, a No. 8 low pressure heater, a No. 7 low pressure heater, a No. 6 low pressure heater, a No. 5 low pressure heater, a deaerator 82, a feed water pump 81, a No. 3 high pressure heater, a No. 2 high pressure heater, and a No. 1 high pressure heater. The above-mentioned high pressure / low pressure heaters are connected in sequence. Figure 1 Indicated by #1 to #9. The input end of the heat exchange pipeline in the feed water heat exchanger 43 is connected to the pipeline at the inlet of the No. 3 high-pressure heater, and the output end of the heat exchange pipeline in the feed water heat exchanger 43 is connected to the pipeline at the outlet of the No. 1 high-pressure heater, thus forming a loop. The input end of the heat exchange pipeline in the high-temperature condensate heat exchanger 44 is connected to the pipeline at the inlet of the No. 5 low-pressure heater, and the output end of the heat exchange pipeline in the high-temperature condensate heat exchanger 44 is connected to the pipeline at the outlet of the No. 5 low-pressure heater, thus forming a loop. The input end of the heat exchange pipeline in the thermostatic smoke cooler 5 is connected to the pipeline at the inlet of the No. 6 low-pressure heater (through the thermostatic water pipe), and the output end of the heat exchange pipeline in the thermostatic smoke cooler 5 is connected to the pipeline at the outlet of the No. 6 low-pressure heater (through the thermostatic water pipe), thus forming a loop.

[0031] The smoke outlet of the dust collector 7 is connected to the induced draft fan 91, the flue gas desulfurization device 92 (FGD) and the chimney 93 in sequence.

[0032] It is understandable that each pipeline / pipeline may be provided with valves, pumps and / or temperature detection devices, pressure monitoring devices, etc. as required, which will not be elaborated here.

[0033] As a supplementary explanation, when the efficiency-enhancing system of the utility model is working, the main means of the control strategy are: adjusting the water side flow rate through the variable frequency pump speed regulation of the heat medium water system (first-stage heater) and the variable frequency condensate booster pump speed regulation (secondary heater) to ensure that the flue gas temperature at the dust collector inlet is, for example, 90°C. The auxiliary means of the control strategy are: flue gas side bypass regulation to control the flue gas flow rate, bypass water side regulation to control the water side flow rate, etc.

[0034] The main concept and beneficial technical effects of the utility model are as follows.

[0035] The main technical idea of ​​this scheme is to use the flue gas waste heat and low-grade extraction steam to heat the cold air at the air preheater inlet, and the high-temperature flue gas from the bypass to heat the high-pressure feed water and high-temperature condensate to replace the high-grade extraction steam, thereby increasing the unit's work capacity while keeping the unit's heat consumption unchanged.

[0036] Furthermore, the feasibility of using steam turbine extraction steam to heat the secondary air heater is as follows:

[0037] If low-stage steam extraction is used, there is a problem that the steam drain cannot flow back within the full load range, considering the steam extraction port pressure, pipeline pressure drop and other issues. In order to ensure that the steam drain flows back to the condenser within the full load range, a higher steam extraction pressure is required, such as 5-stage steam extraction.

[0038] If 5-stage extraction steam is used, by comparing the heat balance diagrams of multiple projects (data as shown in the table below), it can be seen that in terms of enthalpy value, the 5-stage extraction steam is equivalent to the extraction steam of each high-pressure heater, and the work capacity is equivalent. Therefore, it is impossible to achieve the purpose of replacing and squeezing out the high-pressure extraction steam to do more work.

[0039] Enthalpy tables of multiple engineering heat balance diagrams

[0040] Steam Turbine Plant Project Name 1 segment 2nd paragraph 3 sections 4 paragraphs 5th paragraph 6 segments Dongqi (kJ / kg) Jingneng Chagan Nur 3117 3059.4 3110.4 3217.6 3012 2901 SAIC(kJ / kg) Jingneng Five Rooms 3121.9 3027.5 3016.3 3260.8 3081.1 2973.7 SAIC(kJ / kg) A million-dollar project 2975.2 3339.4 3095.9 3372.2 3269.4 3103.2 Steam (kJ / kg) Lujiang Project 3159.2 3056.5 3032.4 3213.2 3012.4 2924.8

[0041] Condensate not only has high pressure and energy grade matching, but is also an indirect use of low-pressure extraction steam and can achieve lower-order extraction steam utilization, making it an ideal heat source for a secondary air heater.

[0042] In summary, bituminous coal units are the mainstream of coal-fired power plants in my country. Combining flue gas waste heat, developing an efficiency improvement system suitable for bituminous coal units is of great significance to energy conservation and carbon reduction in my country's coal-fired power plants. Take a 1000MW bituminous coal unit as an example. Assume that the exhaust gas temperature at the air preheater outlet is 120°C and the flue gas temperature at the dust collector inlet is controlled at 90°C. Using this efficiency improvement system, the coal saving under BMCR operating conditions is 3.18g / kwh. If the conventional flue gas waste heat utilization solution is adopted, the coal saving under BMCR operating conditions is 1g / kwh, and the efficiency is significantly improved.

Claims

1. A flue gas waste heat composite low-order extraction steam replacement high-order extraction steam efficiency improvement system, comprising a primary fan (1), a secondary fan (2), a boiler (3) and a turbine heat recovery extraction system; characterized in that: The flue gas outlet of the boiler (3) is connected in sequence to a temperature-regulating flue gas cooler (5), a heat medium water flue gas cooler (61) and a dust collector (7) through a flue; an air preheater (41) and a bypass flue (42) are arranged in parallel between the flue gas outlet of the boiler (3) and the temperature-regulating flue gas cooler (5); The primary air fan (1) is connected to the air preheater (41) after passing through the first primary air heater (11) and the first secondary air heater (12) in sequence; the secondary air fan (2) is connected to the air preheater (41) after passing through the second primary air heater (21) and the second secondary air heater (22) in sequence; the heat exchange pipelines in the first primary air heater (11) and the second primary air heater (21) are connected to the heat exchange pipelines in the heat medium water smoke cooler (61); a condensate pipe (62) is led out from the outlet of the No. 8 low-pressure heater or a lower-order heater in the steam turbine heat recovery extraction system, and the condensate pipe (62) is connected to the heat exchange pipelines in the first secondary air heater (12) and the second secondary air heater (22); A feed water heat exchanger (43) for heating part of the feed water in the steam turbine heat recovery extraction system and a high temperature condensate heat exchanger (44) for heating part of the condensate in the steam turbine heat recovery extraction system are provided in the bypass flue (42); A temperature regulating water pipe is led out from the outlet of the low-pressure heater in the steam turbine heat recovery extraction system, and the temperature regulating water pipe is connected to the heat exchange pipeline in the temperature regulating smoke cooler (5).

2. The efficiency improvement system of flue gas waste heat combined with low-order extraction steam to replace high-order extraction steam according to claim 1 is characterized in that: The condensate pipe (62) is arranged at the outlet of the No. 8 low-pressure heater; the output ends of the heat exchange pipelines in the first and second-stage heaters (12) and the second and second-stage heaters (22) are connected to the inlet of the No. 8 low-pressure heater.

3. The efficiency improvement system of flue gas waste heat combined with low-order extraction steam to replace high-order extraction steam according to claim 1 is characterized in that: A variable frequency booster pump (63) is provided in the condensate water pipe (62).

4. The efficiency improvement system of flue gas waste heat combined with low-order extraction steam to replace high-order extraction steam according to claim 1 is characterized in that: An adjusting baffle (45) for adjusting the flue gas flow rate is arranged in the bypass flue (42).

5. The efficiency improvement system of flue gas waste heat combined with low-order extraction steam to replace high-order extraction steam according to claim 1 is characterized in that: The feed water heat exchanger (43) and the high-temperature condensate heat exchanger (44) are arranged in sequence along the flue gas flow direction.

6. The efficiency improvement system of flue gas waste heat combined with low-order extraction steam to replace high-order extraction steam according to any one of claims 1 to 5, characterized in that: The steam turbine heat recovery extraction system includes a No. 9 low-pressure heater, a No. 8 low-pressure heater, a No. 7 low-pressure heater, a No. 6 low-pressure heater, a No. 5 low-pressure heater, a deaerator (82), a feed water pump (81), a No. 3 high-pressure heater, a No. 2 high-pressure heater and a No. 1 high-pressure heater which are connected in sequence.

7. The efficiency improvement system of flue gas waste heat combined with low-order extraction steam to replace high-order extraction steam according to claim 6 is characterized in that: The input end of the heat exchange pipeline in the feed water heat exchanger (43) is connected to the pipeline at the inlet of the No. 3 high-pressure heater, and the output end of the heat exchange pipeline in the feed water heat exchanger (43) is connected to the pipeline at the outlet of the No. 1 high-pressure heater.

8. The efficiency improvement system of flue gas waste heat combined with low-order extraction steam to replace high-order extraction steam according to claim 6 is characterized in that: The input end of the heat exchange pipeline in the high-temperature condensate heat exchanger (44) is connected to the pipeline at the inlet of the No. 5 low-pressure heater, and the output end of the heat exchange pipeline in the high-temperature condensate heat exchanger (44) is connected to the pipeline at the outlet of the No. 5 low-pressure heater.

9. The efficiency improvement system of flue gas waste heat combined with low-order extraction steam to replace high-order extraction steam according to claim 6 is characterized in that: The input end of the heat exchange pipeline in the temperature-regulating smoke cooler (5) is connected to the pipeline at the inlet of the No. 6 low-pressure heater, and the output end of the heat exchange pipeline in the temperature-regulating smoke cooler (5) is connected to the pipeline at the outlet of the No. 6 low-pressure heater.

10. The system for improving the efficiency of flue gas waste heat combined with low-order extraction steam to replace high-order extraction steam according to any one of claims 1 to 5, characterized in that: The smoke outlet of the dust collector (7) is sequentially connected to an induced draft fan (91), a flue gas desulfurization device (92) and a chimney (93).

Citation Information

Cited By

  • Construction method and system of power station boiler flue gas waste heat deep regenerative system

    CN120008060A

  • Construction method and system for deep recuperation of waste heat in flue gas of utility boiler