Soil layer settlement detection equipment for engineering construction

By designing soil layer settlement detection equipment, using pressure sensors and data calculators, the problem of large detection errors in soil layer small settlement in the existing technology has been solved, and accurate detection of soil layer settlement has been achieved, and the safety of buildings has been improved. .

CN222013091UActive Publication Date: 2024-11-15THE FIRST COMPARY OF CHINA EIGHTH ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420023308.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-03
Publication Date
2024-11-15
Estimated Expiration
2034-01-03

AI Technical Summary

Technical Problem

The existing soil layer measurement method uses measuring rods, making it difficult to accurately detect small settlement, resulting in large measurement errors, making it impossible to understand the trend of foundation settlement in a timely manner, affecting the safety of the building.

Method used

A soil layer settlement detection equipment for engineering construction is designed, including a roof cover, settlement top plate, detection guide column, contact hammer, pressing spring, pressure sensor and data calculator to detect soil layer settlement through pressure sensor, and data calculator calculates settlement height , reduce errors and improve measurement accuracy.

Benefits of technology

Accurate detection of soil layer settlement is achieved, measurement errors are reduced, and the change trend of soil layer settlement is achieved in a timely manner, which improves the safety of buildings.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222013091U_ABST
    Figure CN222013091U_ABST
Patent Text Reader

Abstract

The utility model discloses soil layer settlement detection equipment for engineering construction, relates to the technical field of soil layer settlement detection equipment, and adopts the technical scheme that the soil layer settlement detection equipment comprises a top cover, an equipment shell is arranged at the top end of the top cover, a settlement top plate is arranged in the equipment shell, a detection guide column is arranged at the bottom end of the settlement top plate, and a contact hammer is arranged at one end of the detection guide column; and pressing springs are symmetrically and fixedly connected to the two sides of the bottom end of the sedimentation top plate and fixedly connected with a pressing base table, and a pressure sensor is arranged at the bottom end of the pressing base table. The device has the beneficial effects that the settlement condition of a soil layer in a foundation pit can be accurately monitored through the settlement top plate on the top cover and the detection guide column and the contact hammer which are arranged at the bottom end of the settlement top plate; the data calculator at the top end of the settlement top plate receives data of the pressure sensor and displays the data through the detection panel on the side face of the equipment shell, and a user can quickly know whether the soil layer is settled or not and know the settlement height of the soil layer by clicking a button on the panel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of soil layer settlement detection equipment, in particular to soil layer settlement detection equipment for engineering construction. Background Art

[0002] The foundation will settle under the action of building load. If the foundation settlement, especially differential settlement, exceeds the allowable range of the building, it will affect the normal use of the building at the least, and may cause house cracking and tilting, roadbed subsidence, dam collapse, etc. In order to timely understand the settlement of the foundation under the action of building load and the trend of settlement changes, so as to take effective measures in advance to prevent accidents, many projects need to set up settlement observation.

[0003] However, most of the existing soil layer measurement methods use measuring rods for detection. This results in the inability to measure the settlement height when the soil layer settles slightly, resulting in large measurement errors and inaccurate measurement data.

[0004] How to solve the above problems is the research topic of this program. Utility Model Content

[0005] In order to achieve the above-mentioned purpose of the utility model and to solve the above-mentioned technical problems, the utility model provides a soil settlement detection device for engineering construction.

[0006] The technical solution is as follows, including a top cover, a device shell is arranged on the top of the top cover, a sinking top plate is arranged inside the device shell, a detection guide column is arranged in the middle of the bottom end of the sinking top plate, a contact hammer is arranged at the end of the detection guide column away from the top cover, pressing springs are symmetrically fixedly connected on both sides of the bottom end of the sinking top plate, the bottom end of the pressing spring is fixedly connected to a pressing base, a pressure sensor is arranged at the bottom end of the pressing base, and the pressure sensor is arranged at the top end of the top cover.

[0007] A data calculator is disposed on the top of the settling top plate, and the data calculator is electrically connected to the pressure sensor.

[0008] A battery cover is arranged at the top end of the top cover, a battery is arranged inside the battery cover, and the battery cover is arranged outside the device housing.

[0009] The top end of the top cover is symmetrically fixedly connected with a fixed slide bar, through holes matching the fixed slide bar are opened at both ends of the subsidence top plate, and the subsidence top plate is slidably connected to the outer side of the fixed slide bar.

[0010] Handles are symmetrically arranged at both ends of the upper surface of the top cover, and a detection panel is arranged on one side of the device housing, and the detection panel is electrically connected to the data calculator.

[0011] The data calculator and the pressure sensor are both electrically connected to the battery.

[0012] A foundation pit is arranged at the bottom end of the top cover, and the contact hammer is arranged at the inner bottom end of the foundation pit.

[0013] The parts not involved in the device are the same as those in the prior art or can be implemented by using the prior art.

[0014] The beneficial effects of the technical solution provided by the embodiment of the utility model are as follows: This solution provides a soil settlement detection device for engineering construction, and the beneficial effects are mainly reflected in the following aspects:

[0015] (1) A settlement top plate is arranged above the top cover, a reset spring is arranged between the settlement top plate and the top cover, the settlement top plate is slidably connected to the outside of the fixed slide rod, a detection guide column and a contact hammer are arranged in the middle of the bottom end of the settlement top plate, the contact hammer is located at the inner bottom end of the foundation pit and contacts the inner bottom end of the foundation pit, if the detection guide column and the contact hammer detect soil layer settlement inside the foundation pit, the reset spring will be compressed, a pressing spring is symmetrically fixedly connected to the bottom end of the settlement top plate, the other end of the pressing spring is fixedly connected to a pressing base, the pressing spring will be compressed, and the pressing base can be pressed against the pressure sensor, so that the pressure sensor generates a pressure value, thereby achieving the effect of detecting soil layer settlement;

[0016] (2) Through the data calculator set on the top of the settlement top plate, the data calculator can receive the pressure data detected by the pressure sensor. A detection panel is set on one side of the device shell. If you want to know whether the current soil layer has settled and the settlement height, click the detection button on the side of the detection panel, and then the data calculator will collect whether the current pressure sensor generates pressure data. If it does, the soil layer of the current foundation pit has settled. If the pressure value is zero, settlement has occurred. In this way, it can accurately detect whether the soil layer has settled and reduce errors;

[0017] (3) The utility model uses a data calculator set on the top of the settlement top plate, and the soil layer settlement height calculation formula is H=1 / 2gt2, H is the settlement height, g is the gravity constant, and t is the total settlement time. In this way, the height of the contact hammer following the soil layer settlement can be accurately calculated, thereby reducing errors and improving measurement accuracy;

[0018] The utility model has a scientific and reasonable structure, is safe and convenient to use, and provides great help to people. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the utility model.

[0020] Figure 2It is a schematic diagram of the equipment structure inside the foundation pit of an embodiment of the utility model.

[0021] Figure 3 It is a schematic diagram of the structure inside the device housing of an embodiment of the utility model.

[0022] Figure 4 It is a schematic diagram of the local structure of an embodiment of the utility model.

[0023] Among them, the figure markings are: 1. foundation pit; 2. equipment housing; 3. battery cover; 4. detection panel; 5. top cover; 6. handle; 7. detection guide column; 8. contact hammer; 9. settlement top plate; 10. pressing base; 11. data calculator; 12. fixed slide rod; 13. reset spring; 14. pressing spring; 15. pressure sensor. DETAILED DESCRIPTION

[0024] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. Of course, the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.

[0025] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other.

[0026] In the description of the invention of the present utility model, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the invention of the utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the invention of the utility model. In addition, the terms "first", "second", etc. are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, features defined as "first", "second", etc. may explicitly or implicitly include one or more of the features. In the description of the invention of the present utility model, unless otherwise specified, "multiple" means two or more.

[0027] In the description of the invention of the utility model, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the invention of the utility model can be understood according to specific circumstances.

[0028] Example 1

[0029] See also Figures 1 to 4 The utility model provides a soil layer settlement detection device for engineering construction, including a top cover 5, a device housing 2 is arranged on the top of the top cover 5, a settlement top plate 9 is arranged inside the device housing 2, a detection guide column 7 is arranged in the middle of the bottom end of the settlement top plate 9, a contact hammer 8 is arranged at the end of the detection guide column 7 away from the top cover 5, and pressing springs 14 are symmetrically fixedly connected to the two sides of the bottom end of the settlement top plate 9, and the bottom end of the pressing spring 14 is fixedly connected to a pressing base 10, and a pressure sensor 15 is arranged at the bottom end of the pressing base 10, and the pressure sensor 15 is arranged at the top end of the top cover 5.

[0030] A data calculator 11 is provided at the top of the settlement top plate 9, and the data calculator 11 is electrically connected to the pressure sensor 15. In this way, the data calculator 11 can collect the pressure data received by the pressure sensor 15, and when the pressure data changes, it indicates that the soil layer begins to settle.

[0031] A battery cover 3 is disposed at the top of the top cover 5 , and batteries are disposed inside the battery cover 3 . The battery cover 3 is disposed outside the device housing 2 to facilitate power supply.

[0032] The top of the top cover 5 is symmetrically fixedly connected with a fixed slide rod 12, and through holes matching the fixed slide rod 12 are opened at both ends of the sinking top plate 9. The sinking top plate 9 is slidably connected to the outer side of the fixed slide rod 12, so that the sinking top plate 9 is more stable during the descent process.

[0033] Handles 6 are symmetrically arranged at both ends of the upper surface of the top cover 5, and a detection panel 4 is arranged on one side of the equipment housing 2. The detection panel 4 is electrically connected to the data calculator 11. The top cover 5 can be picked up by the handle 6 or placed on the top of the foundation pit 1, parallel to the top plane of the foundation pit 1, so as to achieve the effect of measuring settlement. The data calculated by the data calculator 11 can be displayed on one side of the detection panel 4.

[0034] The data calculator 11 and the pressure sensor 15 are both electrically connected to a battery, and the battery provides power for the data calculator 11 and the pressure sensor 15 .

[0035] A foundation pit 1 is arranged at the bottom end of the top cover 5, and a contact hammer 8 is arranged at the inner bottom end of the foundation pit 1. The contact hammer 8 can descend along with the settlement of the soil layer at the inner bottom end of the foundation pit 1, so as to facilitate the detection of the settlement of the soil layer.

[0036] When the utility model is used, a foundation pit 1 is dug at the position where measurement is required, and then the top cover 5 is placed on the top of the foundation pit 1, so that the detection guide column 7 and the contact hammer 8 will be located inside the foundation pit 1, and a settlement top plate 9 is arranged above the top cover 5, and the settlement top plate 9 and the top cover 5 are fixedly connected by a reset spring 13, and a fixed slide bar 12 is symmetrically fixedly connected at the top of the top cover 5, and the settlement top plate 9 is slidably connected to the outside of the fixed slide bar 12, and a detection guide column 7 is arranged in the middle of the bottom end of the settlement top plate 9, and a contact hammer 8 is arranged at the other end of the detection guide column 7. The contact hammer 8 is located at the inner bottom end of the foundation pit 1 and contacts with the inner bottom end of the foundation pit 1. If the detection guide column 7 and the contact hammer 8 detect soil layer settlement inside the foundation pit 1, the reset spring 13 will be compressed, and a pressing spring 14 is symmetrically fixedly connected to the bottom end of the settlement top plate 9, and the other end of the pressing spring 14 is fixedly connected to a pressing base 10, and the pressing spring 14 will be compressed, and the pressing base 10 can be pressed toward the pressure sensor 15. The pressure sensor 15 generates a pressure value. A data calculator 11 is arranged on the top of the settlement top plate 9. The data calculator 11 can receive the pressure data detected by the pressure sensor 15. A device housing 2 is arranged on the top of the top cover 5. A detection panel 4 is arranged on one side of the device housing 2. If you want to know whether the current soil layer has settled and the height of the settlement, click the detection button on the side of the detection panel 4, and then the data calculator 11 will collect whether the current pressure sensor 15 generates pressure data. If it has, the soil layer of the current foundation pit 1 has settled. If the pressure value is zero, settlement has occurred. In this way, it can be accurately found whether the soil layer has settled. The data calculator 11 calculates the height of the soil layer according to the soil layer settlement height calculation formula H=1 / 2gt2, where H is the settlement height, g is the gravity constant, and t is the total settlement time. In this way, the height of the contact hammer 8 following the settlement of the soil layer can be accurately calculated, and then displayed on one side of the detection panel 4. This can reduce errors and improve measurement accuracy.

[0037] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A soil settlement detection device for engineering construction, characterized in that: The device comprises a top cover (5), wherein a device housing (2) is arranged at the top of the top cover (5), a sinking top plate (9) is arranged inside the device housing (2), a detection guide column (7) is arranged in the middle of the bottom end of the sinking top plate (9), a contact hammer (8) is arranged at the end of the detection guide column (7) away from the top cover (5), pressing springs (14) are symmetrically fixedly connected to the two sides of the bottom end of the sinking top plate (9), the bottom end of the pressing spring (14) is fixedly connected to a pressing base (10), a pressure sensor (15) is arranged at the bottom end of the pressing base (10), and the pressure sensor (15) is arranged at the top end of the top cover (5).

2. The soil settlement detection equipment for engineering construction according to claim 1 is characterized in that: A data calculator (11) is provided at the top of the sedimentation top plate (9), and the data calculator (11) is electrically connected to the pressure sensor (15).

3. The soil settlement detection equipment for engineering construction according to claim 2 is characterized in that: A battery cover (3) is arranged at the top end of the top cover (5), a battery is arranged inside the battery cover (3), and the battery cover (3) is arranged on the outside of the device housing (2).

4. The soil settlement detection equipment for engineering construction according to claim 1, characterized in that: The top end of the top cover (5) is symmetrically fixedly connected with a fixed slide bar (12), and through holes matching the fixed slide bar (12) are opened at both ends of the sinking top plate (9), and the sinking top plate (9) is slidably connected to the outer side of the fixed slide bar (12).

5. The soil settlement detection equipment for engineering construction according to claim 2, characterized in that: Handles (6) are symmetrically arranged at both ends of the upper surface of the top cover (5), and a detection panel (4) is arranged on one side of the device housing (2), and the detection panel (4) is electrically connected to the data calculator (11).

6. The soil settlement detection equipment for engineering construction according to claim 3, characterized in that: The data calculator (11) and the pressure sensor (15) are both electrically connected to the battery.

7. The soil settlement detection equipment for engineering construction according to claim 1, characterized in that: A foundation pit (1) is provided at the bottom end of the top cover (5), and the contact hammer (8) is arranged at the inner bottom end of the foundation pit (1).