Bridge incremental launching construction monitoring equipment

By using real-time monitoring equipment that monitors deviations in bridge overhead construction and rotating cameras to clean up dust, the problem of untimely detection of deviations during construction is solved, and construction efficiency and equipment use effect are improved.

CN222014649UActive Publication Date: 2024-11-15SHAANXI TRAFFIC CONTROL TONGYU TRAFFIC RES CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420327363.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-21
Publication Date
2024-11-15
Estimated Expiration
2034-02-21

AI Technical Summary

Technical Problem

During the bridge overhead construction, due to the limited fixed position of the surveillance camera and the accumulation of dust, the deviation is not discovered in time, which affects the construction efficiency and cost.

Method used

Design a bridge overhead construction monitoring equipment, including displacement sensors, data acquisition modules, data storage modules, data transmission modules and monitoring management platform, use displacement sensors to monitor deviations in real time, and provide warning prompts through LED display screens and speakers. The surveillance camera rotates and adjusts the angle and comes with a sponge cleaning block to clean up dust.

Benefits of technology

Real-time monitoring and early warning are realized, reducing the workload of correction and adjustment, and improving the monitoring area and equipment use effect of the surveillance camera.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222014649U_ABST
    Figure CN222014649U_ABST
Patent Text Reader

Abstract

The utility model discloses bridge incremental launching construction monitoring equipment, which comprises a single chip microcomputer, a displacement sensor, a data acquisition module, a data storage module, a data transmission module, a monitoring management platform and a monitoring device, and is characterized in that the displacement sensor is connected with the data acquisition module through a signal amplification device; the displacement sensor is used for measuring displacement generated in the bridge incremental launching construction process; the data acquisition module is connected with the single-chip microcomputer and used for acquiring displacement generated in the incremental launching construction process. Compared with a traditional deviation correction method, the bridge incremental launching construction monitoring device can track and monitor deviation conditions occurring in the bridge incremental launching construction process in real time, and when the incremental launching deviation exceeds a preset threshold value, early warning display and broadcast reminding can be conducted in time; and the constructors can timely rectify and adjust the deviation after finding the deviation, so that the workload of subsequent deviation rectification and adjustment can be effectively reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge construction, in particular to a bridge jacking construction monitoring device. Background Art

[0002] The top-pushing construction method is one of the commonly used and important construction methods in bridge construction. The principle of the top-pushing construction method is to set up a prefabrication site in the backstage along the longitudinal axis of the bridge axis, prefabricate the beam in stages, and then hoist it into place. The slider is stopped at the starting position, and the vertical jack and the horizontal jack are used to synchronously lift and apply force. With the help of the slide device, the beam is pushed forward section by section, and finally the beam is dropped into place. The horizontal jack returns to the starting position, thus completing a cycle process. The next cycle of top-pushing construction is carried out later until the top-pushing is in place, and finally the formal bearing is replaced. The bridge top-pushing construction is divided into single-point top-pushing method and multi-point top-pushing method according to the top-pushing force device. The beam body may deviate during the top-pushing process because the single stroke walking line is a straight line, and the accuracy problem in operation may cause deviation. There are three types of deviations that may occur: the first is that both the front and rear ends deviate to one side; the second is that one end does not deviate and the other end deviates to one side; the third is that the two ends deviate to different sides, that is, the front end deviates to the left and the rear end deviates to the right, or the front end deviates to the right and the rear end deviates to the left. In the past, if there was deviation or the deviation was too large during a jacking cycle, the construction staff would spend a lot of time, manpower and material resources to correct the deviation when it reached a large extent due to the delayed discovery during construction. This greatly reduced the work efficiency and was not allowed in terms of cost and construction period.

[0003] Existing surveillance cameras are generally fixed at one location on the construction site, resulting in a limited monitoring area for each surveillance camera. At the same time, dust and mud are inevitable during bridge construction. Long-term accumulation of dust will block the lens of the surveillance camera, thereby affecting the use effect of the surveillance equipment. Utility Model Content

[0004] The utility model aims to provide a bridge jacking construction monitoring device to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a bridge jacking construction monitoring device, comprising a single-chip microcomputer, a displacement sensor, a data acquisition module, a data storage module, a data transmission module, a monitoring management platform, and a monitoring device, characterized in that: the displacement sensor is connected to the data acquisition module through a signal amplification device, and is used to measure the displacement occurring during the bridge jacking construction process;

[0006] The data acquisition module is connected to the single chip microcomputer and is used to collect the displacement occurring during the jacking construction process;

[0007] The data storage module implements storage management on the collected displacement;

[0008] The data transmission module is connected to the monitoring management platform and is used to transmit the collection results to the monitoring management platform;

[0009] The monitoring and management platform mainly includes an LED display screen, an early warning device, and a speaker;

[0010] The monitoring device comprises a monitoring camera and a pier column for monitoring the bridge jacking construction.

[0011] Preferably, the LED display screen is connected to an alarm device and a loudspeaker respectively. When the displacement transmitted to the monitoring management platform exceeds a preset threshold, the early warning device activates an early warning response, and the loudspeaker broadcasts in real time to remind the monitoring personnel that the pushing deviation exceeds the preset threshold, and to stop pushing and implement correction adjustments.

[0012] Preferably, a support seat is provided on one side of the pier column, and fixing plates are provided on both sides of the top of the support seat.

[0013] Preferably, shielding blocks are arranged on the top of the two fixed plates, the shielding blocks are in a conical table structure, and transmission shafts are rotatably arranged on the two fixed plates.

[0014] Preferably, a rotating block is provided on the transmission shaft, and the monitoring camera is mounted on the end of the rotating block.

[0015] Preferably, a mounting box is provided on one side of the fixing plate, a driving motor is provided inside the mounting box, and an output end of the driving motor is fixedly connected to the end of the transmission shaft.

[0016] Preferably, a sponge cleaning block is provided at the bottom of the shielding block, and both sides of the sponge cleaning block are in arc edge structure and abut against the surveillance camera.

[0017] Compared with the prior art, the beneficial effects of the utility model are:

[0018] 1. The utility model provides a bridge jacking construction monitoring device. Compared with the traditional correction method, the monitoring device can track and monitor the deviation of the bridge jacking construction process in real time. When the jacking deviation exceeds a preset threshold, it can timely warn and display and broadcast reminders. After the construction personnel find out, they can make corrections and adjustments in time, which can effectively reduce the workload of subsequent corrections and adjustments.

[0019] 2. The utility model provides a bridge jacking construction monitoring device, which can rotate and adjust the angle of the monitoring camera, thereby increasing the monitoring area range of each monitoring camera. At the same time, when not in use, the rotation of the monitoring camera and the friction between the sponge cleaning block can clean the dust on the monitoring camera, which is beneficial to the subsequent use of the monitoring equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a structural schematic diagram of the control of the bridge jacking construction monitoring equipment of the utility model.

[0021] Figure 2 It is a schematic diagram of a signal amplifying device in the bridge jacking construction monitoring equipment of the utility model.

[0022] Figure 3 It is a schematic diagram of the structure of the monitoring device of the utility model.

[0023] Figure 4 This is a schematic diagram of the structure of the monitoring device of the utility model when viewed from above.

[0024] In the figure: pier 1; support base 2; fixing plate 3; shielding block 4; installation box 5; transmission shaft 6; rotating block 7; monitoring camera 8; sponge cleaning block 9. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0026] See also Figures 1 to 4 The utility model provides a technical solution: a bridge jacking construction monitoring device, including a single-chip microcomputer, a displacement sensor, a data acquisition module, a data storage module, a data transmission module, a monitoring management platform, and a monitoring device. The model of the single-chip microcomputer is an AT89C51 single-chip microcomputer. The AT89C51 single-chip microcomputer has a 4K-byte memory, a high-performance, low-power 8-bit microprocessor, a 512-byte EEPROM that can be erased and written 10,000 times, and a 4-channel PWM; its operating frequency is set to 18MHz, which can perform statistical processing on the signal transmitted by the displacement sensor in real time, and output an early warning signal to the monitoring management platform.

[0027] The displacement sensor is connected to the data acquisition module through a signal amplification device to measure the displacement occurring during the bridge jacking construction process; the data acquisition module is connected to the single-chip microcomputer to collect the displacement occurring during the jacking construction process; the data storage module implements storage management for the collected displacement; the data transmission module is connected to the monitoring and management platform to transmit the collected results to the monitoring and management platform; the monitoring and management platform mainly includes an LED display screen, an early warning device, and a speaker; the monitoring device includes a monitoring camera 8 and a pier 1 for monitoring the bridge jacking construction.

[0028] The displacement sensor is a non-contact sensor, consisting of a Hall switch and a highly attractive magnet. It has a long service life, strong anti-interference ability, and is waterproof and corrosion-resistant. The working principle is to install the Hall switch and the magnet on the side of the jacking bridge respectively. During the jacking and moving process of the bridge, the attraction of the magnet enables the signal generated by the Hall switch to directly enter the counter of the single-chip microcomputer and can be used as the pulse signal of the counter.

[0029] The monitoring and management platform is a visual intelligent platform integrated with an LED display, an early warning device, and a loudspeaker. The LED display is connected to the data transmission module to display and read the displacement information fed back by the transmission module in real time. The early warning device is connected to the LED display to respond to the displacement value exceeding the preset threshold in real time. The loudspeaker is also connected to the LED display to broadcast reminders when the displacement value exceeds the preset threshold. Both the early warning device and the loudspeaker can warn and remind construction personnel.

[0030] A support base 2 is fixedly installed on one side of the pier 1, and fixed plates 3 are fixed on both sides of the top of the support base 2. Shielding blocks 4 are welded on the tops of the two fixed plates 3. The shielding blocks 4 are conical table structures. The two fixed plates 3 are rotatably connected to a transmission shaft 6, and a rotating block 7 is fixed on the transmission shaft 6. A monitoring camera 8 is installed on the end of the rotating block 7.

[0031] An installation box 5 is fixedly installed on one side of the fixed plate 3, and a driving motor is installed inside the installation box 5. The output end of the driving motor is fixedly connected to the end of the transmission shaft 6. The driving motor starts to control the rotation of the transmission shaft 6, driving the rotating block 7 and the monitoring camera 8 to rotate, thereby adjusting the monitoring angle of the monitoring camera 8 and increasing the monitoring area range of each monitoring camera 8.

[0032] A sponge cleaning block 9 is bonded to the bottom of the shielding block 4. The bonding of the sponge cleaning block 9 facilitates replacement at a later time. The two sides of the sponge cleaning block 9 are in an arc edge structure and abut against the monitoring camera 8. When the monitoring camera 8 rotates, the monitoring camera 8 squeezes the arc edge of the sponge cleaning block 9, and then rubs and fits with the sponge cleaning block 9, which can clean the dust on the monitoring camera, thereby being beneficial to the subsequent use of the monitoring equipment.

[0033] In summary, the utility model provides a bridge jacking construction monitoring device. Compared with the traditional correction method, the monitoring device can track and monitor the deviation occurring during the bridge jacking construction process in real time. When the jacking deviation exceeds a preset threshold, it can promptly display an early warning and broadcast a reminder. After the construction personnel discover the deviation, they can promptly correct the deviation and adjust it, which can effectively reduce the workload of subsequent correction and adjustment.

[0034] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A bridge jacking construction monitoring device, comprising a single chip microcomputer, a displacement sensor, a data acquisition module, a data storage module, a data transmission module, a monitoring management platform, and a monitoring device, characterized in that: The displacement sensor is connected to the data acquisition module through a signal amplification device and is used to measure the displacement occurring during the bridge jacking construction process; The data acquisition module is connected to the single chip microcomputer and is used to collect the displacement occurring during the jacking construction process; The data storage module implements storage management on the collected displacement; The data transmission module is connected to the monitoring management platform and is used to transmit the collection results to the monitoring management platform; The monitoring and management platform mainly includes an LED display screen, an early warning device, and a speaker; The monitoring device comprises a monitoring camera (8) and a pier (1) for monitoring bridge jacking construction.

2. A bridge jacking construction monitoring device according to claim 1, characterized in that: The LED display screen is connected to the alarm device and the loudspeaker respectively. When the displacement transmitted to the monitoring management platform exceeds a preset threshold, the early warning device starts an early warning response, and the loudspeaker broadcasts in real time to remind the monitoring personnel that the pushing deviation exceeds the preset threshold, and stops pushing and implements correction adjustments.

3. The bridge jacking construction monitoring equipment according to claim 1 is characterized by: A support seat (2) is provided on one side of the pier column (1), and fixing plates (3) are provided on both sides of the top of the support seat (2).

4. The bridge jacking construction monitoring equipment according to claim 3 is characterized by: A shielding block (4) is arranged on the top of the two fixed plates (3), and the shielding block (4) is a conical platform structure. A transmission shaft (6) is rotatably arranged on the two fixed plates (3).

5. The bridge jacking construction monitoring equipment according to claim 4 is characterized by: A rotating block (7) is provided on the transmission shaft (6), and a monitoring camera (8) is mounted on the end of the rotating block (7).

6. The bridge jacking construction monitoring equipment according to claim 3 is characterized by: A mounting box (5) is provided on one side of the fixing plate (3), a driving motor is provided inside the mounting box (5), and an output end of the driving motor is fixedly connected to the end of the transmission shaft (6).

7. The bridge jacking construction monitoring equipment according to claim 4 is characterized by: A sponge cleaning block (9) is provided at the bottom of the shielding block (4); both sides of the sponge cleaning block (9) are in arc-shaped edge structures and are in contact with the monitoring camera (8).