Intelligent gas meter based on Internet of Things

By designing partition assembly structure and networking modules in the gas meter, the problem of inconvenient assembly of gas meter is solved, and the installation efficiency and use stability are improved.

CN222014802UActive Publication Date: 2024-11-15QIXIAN NATURAL GAS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420383738.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-29
Publication Date
2024-11-15
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

Existing gas meters are not convenient for partition assembly and control use, affecting the use effect, and are inefficient in assembly and installation.

Method used

An IoT intelligent gas meter was designed, including U-bend pipes, mechanical metering, assembly housing, maintenance inner housing, processing chamber and power supply chamber. The partition assembly and control processing modules are integrated through electrical connections of wires, and the Wireless, card and wired modules are connected to the network, and the installation of external strips and sliders is combined to facilitate adjustment and assembly, improving installation convenience.

Benefits of technology

It realizes convenient partition assembly and control of gas meter, improves installation efficiency and stability, and makes operation more convenient and efficient.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222014802U_ABST
    Figure CN222014802U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of gas meters, in particular to an internet-of-things intelligent gas meter which comprises a U-shaped bent pipeline, and a mechanical meter is assembled at the butt joint end of the U-shaped bent pipeline. An assembling outer shell is arranged on the outer side of the mechanical meter and the outer side of the U-shaped bent pipeline, a maintenance inner shell is integrally arranged on the inner side of the assembling outer shell, the maintenance inner shell is sequentially provided with an assembling bin, a processing bin and a power supply bin from top to bottom, the mechanical meter and the U-shaped bent pipeline are located in the assembling bin, and an electronic meter is assembled on the right side of the U-shaped bent pipeline. The electronic meter is electrically connected with a control processing module through a wire, the control processing module is assembled in the processing bin, the control processing module is electrically connected with a storage battery through a wire, the storage battery is assembled in the power supply bin, and an assembly back plate is assembled on the back of the assembly shell. According to the utility model, partitioned assembly, control and use are facilitated, and adjustment, assembly and installation are facilitated, so that installation and use are more convenient and stable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of gas meters, in particular to an Internet of Things intelligent gas meter. Background Art

[0002] Subsequently, with the continuous laying and improvement of the gas supply pipeline network and the popularization and application of gas equipment, the use of smart gas meters has become more and more extensive, which has brought great convenience to people's lives and metering control;

[0003] In this regard, China's patent application number: CN202121022921.X discloses a smart gas meter, including an outer shell, an inner shell, a gas meter base and a lithium battery, wherein a waterproof plate is fixedly connected to the top of the front of the outer shell, a flip cover is hingedly connected to the top of the front of the outer shell by a hinge, a small flip cover is hingedly connected to the bottom of the front of the outer shell by a hinge, a first screw hole is opened at the bottom of the small flip cover, a second screw hole is opened at the upper part of the inner shell, a circuit board is arranged in the middle of the inner shell, and a lithium battery is connected to the right side of the middle of the inner shell;

[0004] However, the existing gas meters are inconvenient to zoning and control the use, which affects the use effect. At the same time, it is inconvenient to adjust the assembly and installation, which affects the installation efficiency.

[0005] Therefore, in order to solve the above problems, an Internet of Things smart gas meter is proposed. Utility Model Content

[0006] The purpose of the utility model is to provide an Internet of Things smart gas meter to solve the problems of the existing gas meters mentioned in the above background technology, which are inconvenient for partition assembly and control use, affecting the use effect, and inconvenient for adjustment, assembly and installation, affecting the installation efficiency.

[0007] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an IoT smart gas meter, comprising a U-bend pipe, wherein a mechanical meter is installed at the butt end of the U-bend pipe;

[0008] An assembly shell is arranged on the outside of the mechanical meter and the U-bend pipe, and a maintenance inner shell is integrally arranged on the inside of the assembly shell. The maintenance inner shell is provided with an assembly bin, a processing bin and a power supply bin in sequence from top to bottom, and the mechanical meter and the U-bend pipe are located inside the assembly bin. An electronic meter is arranged on the right side of the U-bend pipe, and the electronic meter is electrically connected to a control processing module through a wire, and the control processing module is assembled inside the processing bin. The control processing module is electrically connected to a battery through a wire, and the battery is assembled inside the power supply bin. An assembly back plate is arranged on the back of the assembly shell, and an installation outer strip is integrally arranged on the back of the assembly back plate, and an installation slide is clamped between the installation outer strip and the assembly back plate.

[0009] Preferably, the control processing module is internally integrated with a wireless module, a card module and a wired module, a transition line is plugged into the right side of the wired module, the transition line is inserted through the maintenance inner shell and the right side wall of the assembly outer shell, the outer end of the transition line is connected to a plug connector, and the plug connector is assembled on the right side wall of the assembly shell.

[0010] Preferably, a limit strip is integrally provided on the outer wall of the plug connector, and the limit strip is clamped inside the right side wall of the assembly shell. A limit groove corresponding to the limit strip is opened on the right side wall of the assembly shell, and an assembly set is provided on the outer wall of the transition line, and the assembly set is clamped on the right side wall of the maintenance inner shell.

[0011] Preferably, a charging module is connected and installed on the right side of the battery, a charging cable is plugged into the right side of the charging module, the charging cable is also plugged into the right side walls of the maintenance inner shell and the assembly outer shell, and a power socket is connected to the right side of the charging cable, and the power socket is installed on the right side of the assembly outer shell.

[0012] Preferably, a solenoid valve symmetrical to the electronic meter is installed on the left side of the U-bend pipe, an electronic flow meter is arranged between the solenoid valve and the electronic meter, the electronic flow meter is assembled and docked in the center of the bottom of the U-bend pipe, the solenoid valve and the electronic flow meter are assembled inside the assembly bin by screws, the upper part of the U-bend pipe is assembled inside the assembly bin by an assembly buckle, and a limit clamp ring is fixed on the surface of the docking end of the U-bend pipe, the limit clamp ring is clamped on the inner wall of the upper end of the assembly shell, and a limit clamp groove corresponding to the limit clamp ring is opened at the upper end of the assembly shell.

[0013] Preferably, a leakage detection head is provided at the lower part of the assembly bin, and the leakage detection head is electrically connected to the control processing module through a wire. The leakage detection head is inserted and installed on the inner wall between the assembly bin and the processing bin, and the inner wall is provided with an assembly groove corresponding to the leakage detection head. A sealing sleeve is provided on the surface of the leakage detection head, and the sealing sleeve is clamped in the assembly groove. The inner wall between the assembly bin and the processing bin, and the inner wall between the processing bin and the power supply bin are both inserted and installed with interlaced docking heads.

[0014] Preferably, fire-resistant filling cotton is filled between the maintenance inner shell and the assembly outer shell, an assembly cover is installed on the front side of the assembly shell, and the interior of the assembly cover is hinged from top to bottom with upper cover doors, inspection doors and auxiliary doors corresponding to the assembly bin, processing bin and power supply bin, and the right sides of the upper cover door, inspection door and auxiliary door and the right side wall of the fire-resistant filling cotton are equipped with corresponding locks, and a visual window is installed on the surface of the upper cover door.

[0015] Preferably, the upper and lower ends of the assembly back plate are integrally provided with assembly top strips, and the assembly top strip is assembled on the back of the assembly shell by assembly screws, mounting holes are provided on both sides of the mounting slide bar, and a fine-adjustment slide groove corresponding to the mounting outer strip is provided on the back of the mounting slide bar, and the overlapping parts of the mounting slide bar, the mounting outer strip and the assembly back plate are assembled by fine-adjustment screws, and fine-adjustment screw holes corresponding to the fine-adjustment screws are provided inside the mounting outer strip and the assembly back plate.

[0016] Compared with the prior art, the utility model has the following beneficial effects: the utility model is convenient for partition assembly and control use, and is convenient for adjusting assembly and installation, making installation and use more convenient and stable;

[0017] 1. The utility model is provided with an assembly shell, a maintenance inner shell, an assembly chamber, a processing chamber and a power supply chamber, so that the electronic meter, the control processing module and the battery can be assembled, which is convenient for partition assembly and use, making the use more stable and safe. Through this design, the convenience and practicality of the Internet of Things smart gas meter are improved.

[0018] 2. The utility model is provided with an assembly back plate, an installation outer strip and an installation slide strip, which makes it easy to adjust and assemble according to needs during assembly and use, making the operation more convenient and efficient, and easy to assemble and install according to needs. Through this design, the convenience and practicality of the Internet of Things smart gas meter are improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of a front cross-section of the structure of the utility model;

[0020] Figure 2 It is a schematic diagram of the structure of the utility model;

[0021] Figure 3 It is a schematic side view of the structure of the utility model;

[0022] Figure 4 This is a rear view schematic diagram of the local structure of the outer strip installed in the utility model;

[0023] Figure 5 For this utility model Figure 1 A schematic diagram of the structure enlargement in the middle;

[0024] Figure 6 For this utility model Figure 4 A magnified schematic diagram of the structure at B in the middle;

[0025] In the figure: 100, U-bend pipe; 101, limit clamp ring; 102, limit clamp slot; 103, assembly buckle; 110, mechanical meter; 200, assembly shell; 201, fire-resistant filling cotton; 202, assembly cover; 203, upper cover door; 204, maintenance door; 205, auxiliary door; 206, lock; 207, visual window; 210, maintenance inner shell; 211, assembly chamber; 212, processing chamber; 213, power supply chamber; 214, insertion joint; 220, electronic meter; 221, electronic flow meter; 222, solenoid valve; 230, control processing module; 231, wireless Module; 232, card module; 233, wired module; 234, transition line; 235, plug connector; 236, limit card strip; 237, limit groove; 238, assembly kit; 240, battery; 241, charging module; 242, charging cable; 243, power socket; 250, leakage detection head; 251, assembly groove; 252, sealing sleeve; 300, assembly back plate; 301, assembly top strip; 302, assembly screw; 310, installation outer strip; 320, installation slide strip; 321, installation hole; 322, fine-tuning slide groove; 323, fine-tuning screw pin; 324, fine-tuning screw hole. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0027] See also Figure 1-6 , an embodiment provided by the utility model:

[0028] An Internet of Things smart gas meter, comprising a U-bend pipe 100, a mechanical meter 110 being installed at the butt end of the U-bend pipe 100;

[0029] An assembly shell 200 is provided on the outside of the mechanical meter 110 and the U-bend pipe 100, and a maintenance inner shell 210 is integrally provided on the inside of the assembly shell 200. The maintenance inner shell 210 is provided with an assembly bin 211, a processing bin 212 and a power supply bin 213 from top to bottom, and the mechanical meter 110 and the U-bend pipe 100 are located inside the assembly bin 211. An electronic meter 220 is provided on the right side of the U-bend pipe 100. The electronic meter 220 is electrically connected to a control processing module 230 through a wire. The control processing module 230 is assembled inside the processing bin 212. The control processing module 230 is electrically connected to a battery 240 through a wire. The battery 240 is assembled inside the power supply bin 213. An assembly back plate 300 is provided on the back of the assembly shell 200. An installation outer strip 310 is integrally provided on the back of the assembly back plate 300. An installation slide bar 320 is clamped between the installation outer strip 310 and the assembly back plate 300.

[0030] Furthermore, the control processing module 230 is internally integrated with a wireless module 231, a card module 232 and a wired module 233. A transition line 234 is plugged into the right side of the wired module 233. The transition line 234 is inserted through the maintenance inner shell 210 and the right side wall of the assembly outer shell 200. The outer end of the transition line 234 is connected to a plug connector 235, which is assembled on the right side wall of the assembly outer shell 200. This design facilitates the integrated assembly and selective control of the control processing module 230, making the operation more convenient.

[0031] Furthermore, a limit clamping strip 236 is integrally provided on the outer wall of the plug connector 235, and the limit clamping strip 236 is clamped inside the right side wall of the assembly shell 200. A limit groove 237 corresponding to the limit clamping strip 236 is opened on the right side wall of the assembly shell 200, and an assembly sleeve 238 is sleeved on the outer wall of the transition line 234, and the assembly sleeve 238 is clamped on the right side wall of the maintenance inner shell 210. Through this design, the assembly and transfer docking of the plug connector 235 and the wired module 233 are facilitated, making the operation and use more convenient;

[0032] Furthermore, a charging module 241 is connected to the right side of the battery 240, a charging cable 242 is plugged into the right side of the charging module 241, and the charging cable 242 is also plugged into the right side wall of the maintenance inner shell 210 and the assembly outer shell 200, and a power socket 243 is connected to the right side of the charging cable 242, and the power socket 243 is assembled on the right side of the assembly outer shell 200. This design facilitates the docking, charging and supply of the battery 240;

[0033] Furthermore, a solenoid valve 222 symmetrical to the electronic meter 220 is installed on the left side of the U-bend pipe 100, an electronic flow meter 221 is arranged between the solenoid valve 222 and the electronic meter 220, and the electronic flow meter 221 is assembled and docked at the bottom center of the U-bend pipe 100, the solenoid valve 222 and the electronic flow meter 221 are assembled inside the assembly bin 211 by screws, the upper part of the U-bend pipe 100 is assembled inside the assembly bin 211 by the assembly buckle 103, and a limit clamping ring 101 is fixed on the surface of the docking end of the U-bend pipe 100, the limit clamping ring 101 is clamped on the inner wall of the upper end of the assembly shell 200, and a limit clamping groove 102 corresponding to the limit clamping ring 101 is opened at the upper end of the assembly shell 200. Through this design, the auxiliary assembly and control of the U-bend pipe 100 are facilitated, making the use and control more convenient;

[0034] Furthermore, a gas leakage detection head 250 is provided at the lower part of the assembly bin 211, and the gas leakage detection head 250 is electrically connected to the control processing module 230 through a wire. The gas leakage detection head 250 is inserted and assembled on the inner wall between the assembly bin 211 and the processing bin 212, and the inner wall is provided with an assembly groove 251 corresponding to the gas leakage detection head 250. A sealing sleeve 252 is sleeved on the surface of the gas leakage detection head 250, and the sealing sleeve 252 is clamped inside the assembly groove 251. The inner wall between the assembly bin 211 and the processing bin 212 and the inner wall between the processing bin 212 and the power supply bin 213 are both inserted and assembled with an interlaced docking head 214. Through this design, it is convenient to monitor whether there is gas leakage inside during assembly and use;

[0035] Furthermore, fire-resistant filling cotton 201 is filled between the maintenance inner shell 210 and the assembly outer shell 200, and an assembly cover 202 is assembled on the front side of the assembly outer shell 200. The assembly cover 202 is hinged from top to bottom with an upper cover door 203, an inspection door 204 and an auxiliary door 205 corresponding to the assembly bin 211, the processing bin 212 and the power supply bin 213, and the right sides of the upper cover door 203, the inspection door 204 and the auxiliary door 205 and the right side wall of the fire-resistant filling cotton 201 are equipped with corresponding locks 206, and a visual window 207 is assembled on the surface of the upper cover door 203. Through this design, auxiliary inspection and operation of the assembly bin 211, the processing bin 212 and the power supply bin 213 are convenient;

[0036] Furthermore, the assembly back plate 300 is integrally provided with an assembly top strip 301 at the upper and lower ends, and the assembly top strip 301 is assembled on the back of the assembly shell 200 by means of assembly screws 302. The installation slide bar 320 is provided with installation holes 321 on both sides, and the back of the installation slide bar 320 is provided with a fine-tuning slide groove 322 corresponding to the installation outer strip 310. The overlapping parts of the installation slide bar 320, the installation outer strip 310 and the assembly back plate 300 are assembled by means of a fine-tuning screw pin 323. The installation outer strip 310 and the assembly back plate 300 are provided with a fine-tuning screw hole 324 corresponding to the fine-tuning screw pin 323. This design facilitates auxiliary installation and assembly.

[0037] Working principle: During operation, the inlet and outlet pipes are docked and assembled with the U-bend pipe 100. According to assembly needs, the fine-tuning slide 322 and the installation outer strip 310 are fine-tuned by the cooperation of the fine-tuning screw pin 323 and the fine-tuning screw hole 324, so that the installation slide strip 320 can be assembled and docked with the cooperation of the installation hole 321, which is convenient for the stable assembly of the assembly shell 200. Through the opening and closing of the lock buckle 206, it is convenient to open the upper cover door 203, the inspection door 204 and the auxiliary door 205, which is convenient for the inspection and maintenance of the assembly compartment 211, the processing compartment 212 and the power supply compartment 213. When in use, according to the use needs, Through the coordinated setting of the wireless module 231, the card module 232 and the wired module 233, the networking is selected, and the wireless network is connected through the wireless module 231, or the Internet of Things card is inserted through the card module 232, or the wired network is connected through the wired module 233 with the cooperation of the transition line 234 and the plug connector 235, which is convenient for subsequent control operations, making it more convenient to use, and convenient for electrical control and reading of relevant data of the electronic meter 220, the electronic flow meter 221 and the solenoid valve 222. When the air leakage detection head 250 is assembled, it is convenient to assist in monitoring whether there is air leakage inside the assembled shell 200, making it safer to use. The operation ends here.

[0038] It should be noted that in the present application, the connection and specific connection structure and the use principle of the electronic meter 220, the electronic flow meter 221, the solenoid valve 222, the control processing module 230, the battery 240 and the air leakage detection head 250 are all prior art, and are common knowledge to those skilled in the art. Different specifications and modes can be realized through a variety of implementation methods, and no other special requirements are made in the present application. It is only necessary that they can realize the functions in the present application, so no specific limitation is made here.

[0039] The above description is only a preferred embodiment of the utility model and does not limit the utility model in any form. Any ordinary technician in the industry can smoothly implement the utility model as shown in the drawings of the specification and described above. However, any equivalent changes, modifications and evolutions made by technicians familiar with the profession without departing from the scope of the technical solution of the utility model using the technical content disclosed above are all equivalent embodiments of the utility model. At the same time, any equivalent changes, modifications and evolutions made to the above embodiments based on the essential technology of the utility model are still within the protection scope of the technical solution of the utility model.

Claims

1. An Internet of Things smart gas meter, comprising a U-bend pipeline (100), wherein a mechanical meter (110) is mounted at a butt end of the U-bend pipeline (100); Features: An assembly shell (200) is arranged outside the mechanical meter (110) and the U-bend pipe (100), and a maintenance inner shell (210) is integrally arranged inside the assembly shell (200). The maintenance inner shell (210) is provided with an assembly chamber (211), a processing chamber (212) and a power supply chamber (213) in sequence from top to bottom. The mechanical meter (110) and the U-bend pipe (100) are located inside the assembly chamber (211). An electronic meter (220) is arranged on the right side of the U-bend pipe (100). The electronic meter (220) is connected to the assembly chamber (211) by a wire. A control processing module (230) is electrically connected, and the control processing module (230) is installed inside the processing chamber (212). The control processing module (230) is electrically connected to a battery (240) through a wire, and the battery (240) is installed inside the power supply chamber (213). The back of the assembly shell (200) is equipped with an assembly back plate (300), and the back of the assembly back plate (300) is integrally provided with an installation outer strip (310), and an installation slide bar (320) is clamped between the installation outer strip (310) and the assembly back plate (300).

2. The IoT smart gas meter according to claim 1, characterized in that: The control processing module (230) is internally integrated with a wireless module (231), a card module (232) and a wired module (233); a transition line (234) is plugged into the right side of the wired module (233); the transition line (234) is inserted through the maintenance inner shell (210) and the right side wall of the assembly outer shell (200); the outer end of the transition line (234) is connected to a plug connector (235); and the plug connector (235) is assembled on the right side wall of the assembly outer shell (200).

3. The IoT smart gas meter according to claim 2, characterized in that: The outer wall of the plug connector (235) is integrally provided with a limit clip (236), and the limit clip (236) is clamped inside the right side wall of the assembly shell (200). The right side wall of the assembly shell (200) is provided with a limit groove (237) corresponding to the limit clip (236). The outer wall of the transition line (234) is sleeved with an assembly sleeve (238), and the assembly sleeve (238) is clamped on the right side wall of the maintenance inner shell (210).

4. The IoT smart gas meter according to claim 1, characterized in that: The right side of the storage battery (240) is connected to a charging module (241), the right side of the charging module (241) is plugged with a charging cable (242), the charging cable (242) is also plugged into the right side wall of the maintenance inner shell (210) and the assembly outer shell (200), and the right side of the charging cable (242) is connected to a power socket (243), and the power socket (243) is assembled on the right side of the assembly outer shell (200).

5. The IoT smart gas meter according to claim 1, characterized in that: The left side of the U-bend pipe (100) is equipped with a solenoid valve (222) symmetrical to the electronic meter (220); an electronic flow meter (221) is arranged between the solenoid valve (222) and the electronic meter (220); the electronic flow meter (221) is assembled and docked at the center of the bottom of the U-bend pipe (100); the solenoid valve (222) and the electronic flow meter (221) are assembled inside the assembly bin (211) by means of screws; the upper part of the U-bend pipe (100) is assembled inside the assembly bin (211) by means of an assembly buckle (103); a limit clamping ring (101) is fixedly arranged on the surface of the docking end of the U-bend pipe (100); the limit clamping ring (101) is clamped on the inner wall of the upper end of the assembly shell (200); and a limit clamping groove (102) corresponding to the limit clamping ring (101) is provided at the upper end of the assembly shell (200).

6. The IoT smart gas meter according to claim 1, characterized in that: A gas leakage detection head (250) is arranged at the lower part of the assembly bin (211), and the gas leakage detection head (250) is electrically connected to the control processing module (230) through a wire. The gas leakage detection head (250) is inserted and assembled on the inner wall between the assembly bin (211) and the processing bin (212), and the inner wall is provided with an assembly groove (251) corresponding to the gas leakage detection head (250). A sealing sleeve (252) is sleeved on the surface of the gas leakage detection head (250), and the sealing sleeve (252) is clamped inside the assembly groove (251). The inner wall between the assembly bin (211) and the processing bin (212) and the inner wall between the processing bin (212) and the power supply bin (213) are both inserted and assembled with an interlaced docking head (214).

7. The IoT smart gas meter according to claim 1, characterized in that: The maintenance inner shell (210) and the assembly outer shell (200) are filled with fire-resistant filling cotton (201), and the front side of the assembly outer shell (200) is equipped with an assembly cover (202). The inside of the assembly cover (202) is hinged with an upper cover door (203), an inspection door (204) and an auxiliary door (205) corresponding to the assembly bin (211), the processing bin (212) and the power supply bin (213) from top to bottom, and the right sides of the upper cover door (203), the inspection door (204) and the auxiliary door (205) and the right side wall of the fire-resistant filling cotton (201) are equipped with corresponding locks (206), and the surface of the upper cover door (203) is equipped with a visual window (207).

8. The IoT smart gas meter according to claim 1, characterized in that: The upper and lower ends of the assembly back plate (300) are integrally provided with assembly top strips (301), and the assembly top strip (301) is assembled on the back of the assembly shell (200) by means of assembly screws (302). The two sides of the installation slide bar (320) are provided with installation holes (321), and the back of the installation slide bar (320) is provided with a fine-tuning slide groove (322) corresponding to the installation outer strip (310). The overlapping part of the installation slide bar (320), the installation outer strip (310) and the assembly back plate (300) is assembled by means of a fine-tuning screw pin (323), and the installation outer strip (310) and the assembly back plate (300) are provided with a fine-tuning screw hole (324) corresponding to the fine-tuning screw pin (323) inside.