Movable concrete mixing plant

Through the articulated metering module and folding maintenance platform, the problem of insufficient passability of the mobile concrete mixing station is solved, and efficient transfer transportation without disassembly is achieved, cost and workload are reduced, and transportation standards are met.

CN222021911UActive Publication Date: 2024-11-19HUNAN ZOOMLION CONCRETE MASCH STATION EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420066150.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-11
Publication Date
2024-11-19
Estimated Expiration
2034-01-11

AI Technical Summary

Technical Problem

The specifications and sizes of the mobile concrete mixing station exceed the restrictions on the transportation road, resulting in insufficient passability, and the metering scale and maintenance table need to be dismantled for separate transportation, which is large in work and high in cost.

Method used

A hinged-mounted metering module and folding maintenance platform are designed, which can switch positions in working and drag states, reduce the height of the metering scale and the width of the maintenance platform, meet transportation standards, and eliminate the need for additional disassembly and reinstallation.

Benefits of technology

It improves the overall passability and transition operation efficiency of the mobile concrete mixing station, reduces loading and unloading and transportation costs, and complies with the relevant vehicle height and vehicle width standards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222021911U_ABST
    Figure CN222021911U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of concrete mixing plants, and discloses a movable concrete mixing plant. The mobile concrete mixing plant comprises a mobile vehicle body, the stirring main machine assembly is mounted above the movable vehicle body; the metering module is integrally hinged to the stirring main machine assembly; wherein the metering module can be switched between a working pivoting position or a dragging pivoting position, a metering scale of the metering module can feed materials to the stirring main machine assembly at the working pivoting position, the metering module deflects downwards towards the moving vehicle body at the dragging pivoting position, and the vertex height of the metering scale is lower than that of the stirring main machine assembly. The overall trafficability of the movable concrete mixing plant can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the field of concrete mixing stations, and in particular, relates to a mobile concrete mixing station. Background Art

[0002] Concrete mixing plants are important devices for preparing concrete. According to whether they can be transported to other sites to meet the diverse needs of engineering construction, concrete mixing plants can be divided into fixed concrete mixing plants and mobile concrete mixing plants. At present, the specifications and dimensions of mobile concrete mixing plants are getting larger and larger, and the overall height and width exceed the restriction standards of transportation roads, resulting in insufficient overall passability. Therefore, at least the metering scale and maintenance platform need to be disassembled, and then packaged and transported, which will inevitably lead to a large workload of assembly and disassembly and high transfer costs. Summary of the invention

[0003] The purpose of the present application is to provide a mobile concrete mixing station to improve the overall trafficability of the mobile concrete mixing station and reduce the transfer cost.

[0004] The present application provides a mobile concrete mixing station, which includes:

[0005] A stirring main unit component, which is installed on the top of the moving vehicle body;

[0006] The metering module is integrally hingedly mounted on the mixing host assembly;

[0007] Among them, the metering module can be switched to a working pivot position or a towing pivot position. In the working pivot position, the metering scale of the metering module can feed materials into the mixing main unit assembly. In the towing pivot position, the metering module swings downward toward the mobile body, and the top height of the metering scale is lower than the top height of the mixing main unit assembly.

[0008] In some embodiments, the metering module includes:

[0009] The supporting frame has a measuring scale installation space formed inside the supporting frame, the measuring scale is installed in the measuring scale installation space, and the supporting frame is pivotally installed on the stirring main unit assembly.

[0010] In some embodiments, in the towing pivot position, the top height of the metering scale is lower than the top height of the mixing main unit assembly and both are less than 4.3 meters.

[0011] In some embodiments, the stirring host assembly further comprises:

[0012] A main frame, wherein an installation space is formed inside the main frame;

[0013] The mixing main body is installed in the installation space and is used for receiving feeding.

[0014] In some embodiments, the main frame includes a top bracket, which is arranged at the top of the main frame, and the support frame includes a side bracket, which is arranged at one side of the support frame, and the side bracket is hingedly connected to the top bracket.

[0015] In some embodiments, the mobile concrete mixing plant further comprises a locking mechanism, which is disposed on the main frame and is used to limit the rotation of the metering module when it is in the towing pivot position.

[0016] In some embodiments, the mobile concrete mixing plant further comprises:

[0017] The foldable inspection platform is pivotally mounted on the peripheral side of the mixing main unit assembly and can be switched between a folded pivot position and an unfolded pivot position. In the folded pivot position, the foldable inspection platform is folded and retracted to the side of the mixing main unit assembly. In the unfolded pivot position, the foldable inspection platform is unfolded toward the side of the mixing main unit assembly.

[0018] In some embodiments, in the folded pivot position of the folding maintenance platform, the overall width of the mobile concrete mixing plant is the platform width between the folded maintenance platforms on both sides and is less than 2.45 meters.

[0019] In some embodiments, there are multiple folding maintenance platforms.

[0020] In some embodiments, in the unfolded pivot position, the unfolded width of the foldable maintenance platform toward the side of the mixing main unit assembly is not less than 0.75 meters.

[0021] In some embodiments, the mobile concrete mixing plant further comprises:

[0022] Aggregate bin, used for feeding the mixing main body of the mixing main assembly;

[0023] The conveying mechanism is used to transport materials between the main mixing machine and the aggregate bin.

[0024] In the technical solution of the present application, when the mobile concrete mixing station completes the transfer transportation and starts working, the metering module can be pivoted to the working pivot position, that is, the position where the material can be fed to the mixing main unit assembly; when the mobile concrete mixing station finishes working and starts the transfer transportation, the metering module can be pivoted to the towing pivot position first, and the top height of the metering scale can be lowered until it is below the top height of the mixing main unit assembly, and then the mobile vehicle body can be used for rapid transfer operation. Compared with the existing method of disassembling the metering scale and the inspection platform before transportation, the present application can improve the overall passability of the mobile concrete mixing station without the need for additional disassembly and reinstallation operations, thereby improving the transfer operation efficiency of the mobile concrete mixing station.

[0025] Other features and advantages of the embodiments of the present application will be described in detail in the subsequent detailed description. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] The accompanying drawings are used to provide a further understanding of the embodiments of the present application and constitute a part of the specification. Together with the following specific embodiments, they are used to explain the embodiments of the present application, but do not constitute a limitation on the embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without creative work. In the drawings:

[0027] Figure 1 It is a structural schematic diagram of a mobile concrete mixing plant according to a specific implementation method of the present application;

[0028] Figure 2 for Figure 1 The structural schematic diagram of the mobile concrete mixing plant shown is in a towing state;

[0029] Figure 3 for Figure 2 A partial enlarged view of the middle A;

[0030] Figure 4 It is a schematic structural diagram of a foldable maintenance platform of a mobile concrete mixing plant in some embodiments when it is in an unfolded pivot position;

[0031] Figure 5 for Figure 4 Schematic diagram of the structure of the folding maintenance platform when it is in the folded pivot position.

[0032] 100 Mobile body 320 Support frame

[0033] 200 Mixing main unit assembly 321 Side bracket

[0034] 210 Main frame 400 Locking mechanism

[0035] 211 Top support 500 Folding inspection platform

[0036] 220 Mixing machine body 600 Aggregate silo

[0037] 300 Metering module 700 Conveying mechanism

[0038] 310 weighing scale DETAILED DESCRIPTION

[0039] The specific implementation of the present application is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the present application, and is not used to limit the present application.

[0040] The mobile concrete mixing plant according to the present application is described below with reference to the accompanying drawings.

[0041] The present application discloses a novel mobile concrete mixing station, such as Figure 1 As shown, a mobile concrete mixing station in a specific embodiment includes:

[0042] A stirring main unit component 200, which is installed above the mobile vehicle body 100;

[0043] The metering module 300 is integrally hingedly mounted on the stirring main unit assembly 200;

[0044] Among them, the metering module 300 can be switched to a working pivot position or a towing pivot position. In the working pivot position, the metering scale 310 of the metering module 300 can feed materials to the mixing main unit assembly 200. In the towing pivot position, the metering module 300 swings downward toward the mobile body 100, and the top height of the metering scale 310 is lower than the top height of the mixing main unit assembly 200.

[0045] Specifically, when the mobile concrete mixing plant is in working condition, the metering template is in the working pivot position. Figure 1 At this time, the metering module 300 is in the working position, and the feeding port of the metering scale 310 can be connected with the feeding port of the mixing main unit assembly 200, and the mixing main unit assembly 200 can be fed normally; when the mobile concrete mixing station finishes working and moves to another site by moving the vehicle body 100, the metering module 300 can be pivoted to the towing pivot position, see Figure 2 and Figure 3 At this time, the vertex height of the metering scale 310 of the metering module 300 is lower than the vertex height of the mixing main unit assembly 200, so the overall height of the mobile concrete mixing station can be reduced to meet the road standard of the semi-trailer without the need for additional disassembly and transportation of the metering scale 310. Therefore, the present application improves the passability of the mobile concrete mixing station and improves the efficiency of the transfer operation.

[0046] To realize the hinged installation of the metering module 300, as Figure 1 As shown, as an example, the metering module 300 may include:

[0047] The support frame 320 has a weighing scale installation space formed inside the support frame 320 . The weighing scale 310 is installed in the weighing scale installation space. The support frame 320 can be pivotally installed on the mixing host assembly 200 .

[0048] Specifically, see Figure 2 , Figure 3 , Figure 4 and Figure 5The metering scale 310 is installed in the supporting frame 320. Due to the overall fixing effect of the supporting frame 320 on the metering scale 310, the metering scale 310 can be reliably switched between the working pivot position and the towing pivot position through the pivoting of the supporting frame 320, thereby reducing the impact of adverse factors such as vibration on the metering scale 310 and ensuring the accurate docking between the feeding port of the metering scale 310 and the feeding port of the mixing main unit assembly 200.

[0049] Among them, the pivotal installation structure of the support frame 320 on the main mixer assembly 200 includes a multi-point hinged installation and locking by a locking pin, etc. These pivotal installation methods and structures are well known to those skilled in the art and will not be elaborated in detail here. Considering the large size and weight of the concrete mixing plant, the hinged structures at each point are all large in size, and the insertion and removal of the pin shaft and the lifting of the metering module 300 all require the use of tools such as electric push rods, oil cylinders, or chain lifting equipment. However, the workload of this pivotal disassembly and assembly method is much lower than the workload of complete disassembly and reloading for transportation.

[0050] It should be noted that the installation method of the metering module 300 on the mixing station main unit assembly 200 is not limited to the above-mentioned hinged installation. For example, the metering module 300 can also be slidably installed on the mixing station main unit assembly 200, that is, vertical guide rails are arranged on the mixing station main unit assembly 200, etc. These should also fall within the scope of protection of this application.

[0051] like Figure 2 and Figure 3 As shown, in the towing pivot position, the top height of the metering scale 310 should be lower than the top height of the mixing host assembly 200 and both can be less than 4.3 meters to meet the transportation standard requirements.

[0052] In this embodiment, when the metering scale 310 is in the towing pivot position, the overall height of the mobile concrete mixing plant is less than 4.3 meters, thereby meeting the vehicle height standards of relevant regulations without the need to go through additional approval procedures.

[0053] In this embodiment, if Figure 1 As shown, the stirring host assembly 200 may also include:

[0054] A main frame 210, wherein an installation space is formed inside the main frame 210;

[0055] The mixing main body 220 is installed in the installation space and is used for receiving feeding.

[0056] Specifically, see Figure 1The main frame 210 is composed of a plurality of brackets, in which a mounting space for mounting the mixing main body 220 is formed. Due to the fixing effect of the plurality of brackets on the mixing main body 220, the mixing main body 220 can be reduced from the adverse effects of the working vibration and the like, and the feeding port of the metering scale 310 can be accurately docked with the feeding port of the mixing main body 220 when the metering scale 310 is in the working pivot position.

[0057] In addition, if Figure 1 , Figure 2 and Figure 3 As shown, the main frame 210 may include a top bracket 211, which is disposed at the top of the main frame 210, and the support frame 320 includes a side bracket 321, which is disposed at one side of the support frame 320, and the side bracket 321 is hingedly connected to the top bracket 211. In this way, the pivotal installation of the metering module 300 on the mixing host assembly 200 can be simply and reliably achieved, and at the same time, the adverse factors caused by working vibration on the metering scale 310 and the mixing host body 220 can be reduced, and the accuracy of the docking between the feeding port of the metering scale 310 and the feeding port of the mixing host body 220 can be improved.

[0058] Those skilled in the art will appreciate that the pivotal mounting method of the metering module 300 on the mixing main unit assembly 200 is not limited to the above-mentioned hinged connection method between the side bracket 321 and the top bracket 211, and may also be a structural form in which the metering module 300 and the mixing main unit assembly 200 are slidably connected.

[0059] On the basis of the hinged connection between the side bracket 321 and the top bracket 211, as shown in FIG. Figure 2 and Figure 3 As shown, the mobile concrete mixing plant further includes a locking mechanism 400 , which may be disposed on the main frame 210 . The locking mechanism 400 may be used to limit the rotation of the metering module 300 when the metering module 300 is in the towing pivot position.

[0060] Specifically, the locking mechanism 400 is disposed on the top bracket 211. When the metering module 300 is in the towing pivot position, the side bracket 321 abuts against the top bracket 211, and the locking mechanism 400 can limit the side bracket 321, thereby limiting the rotation of the metering module 300. The locking mechanism 400 can limit the rotation of the side bracket 321 by means of bolts, pins, and other structures, and of course, other appropriate methods can also be used, which will not be described in detail here.

[0061] In this embodiment, if Figure 4 and Figure 5 As shown, the mobile concrete mixing plant also includes:

[0062] The folding inspection platform 500 can be pivotally mounted on the peripheral side of the mixing main unit assembly 200 and can be switched between a folding pivot position and an unfolding pivot position. In the folding pivot position, the folding inspection platform 500 is folded and retracted to the side of the mixing main unit assembly 200. In the unfolding pivot position, the folding inspection platform 500 is unfolded toward the side of the mixing main unit assembly 200.

[0063] Specifically, when the mobile concrete mixing plant is in operation, the foldable inspection platform 500 is in an unfolded pivot position, see Figure 4 The foldable maintenance platform 500 is unfolded toward the side of the mixing main unit assembly 200 to facilitate the operator to stand and operate the mixing main unit assembly 200. When the mobile concrete mixing station finishes work and needs to be transferred to another site, the foldable maintenance platform 500 can be tilted to the folded pivot position, see Figure 5 At this time, the overall width of the mobile concrete mixing plant is reduced, and can meet the road standard of a semi-trailer, without the need for additional disassembly and transportation of the folding maintenance platform 500. Therefore, the pivoting installation of the folding maintenance platform 500 improves the passability of the mobile concrete mixing plant and improves the efficiency of the transfer operation.

[0064] Among them, Figure 5 As shown, in the folded pivot position of the foldable inspection platform 500, the overall width of the mobile concrete mixing plant is the platform width between the folded inspection platforms 500 on both sides and is less than 2.45 meters. In this way, the vehicle width standard of relevant regulations can be met without the need for additional approval procedures.

[0065] On the basis of meeting the vehicle width standards stipulated in relevant regulations, there can be multiple foldable inspection platforms 500.

[0066] Specifically, see Figure 4 and Figure 5 As an example, two folding inspection platforms 500 are symmetrically arranged on both sides of the mixing main unit assembly 200, so that the operator can more conveniently operate the mixing main unit assembly 200. Of course, the folding inspection platform 500 is not limited to the two shown in the figure, and more can be arranged.

[0067] In addition, in the unfolded pivot position, the unfolded width of the foldable inspection platform 500 toward the side of the mixing main unit assembly 200 is not less than 0.75 meters.

[0068] Specifically, the unfolded width of the foldable maintenance platform 500 toward the side of the mixing main unit assembly 200 should be greater than 0.75 meters to ensure that the foldable maintenance platform 500 has enough space, thereby ensuring that the operator can safely operate the mixing main unit assembly 200.

[0069] like Figure 1As shown, as an example, the mobile concrete mixing plant also includes:

[0070] Aggregate bin 600, used for feeding materials into the mixing main body 220 of the mixing main body assembly 200;

[0071] The conveying mechanism 700 is used for conveying materials between the mixing main body 220 and the aggregate bin 600.

[0072] Specifically, when the mobile concrete mixing station is in working condition, while the material stored in the aggregate bin 600 is transported to the main mixing machine body 220 through the conveying mechanism 700, the metering scale 310 can simultaneously deliver ingredients corresponding to the proportion of the material to the main mixing machine body 220, and mix them in the main mixing machine body 220, so that the mobile concrete mixing station can start producing concrete.

[0073] In the description of the present application, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of the present application, "plurality" means at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0074] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0075] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

Claims

1. A mobile concrete mixing plant, comprising a mobile vehicle body (100), characterized in that: The mobile concrete mixing station comprises: A stirring main machine component (200), wherein the stirring main machine component (200) is installed above the mobile vehicle body (100); A metering module (300) is integrally hingedly mounted on the stirring main unit assembly (200); The metering module (300) can be switched to a working pivot position or a towing pivot position. In the working pivot position, the metering scale (310) of the metering module (300) can feed materials to the stirring main unit component (200). In the towing pivot position, the metering module (300) swings downward toward the mobile vehicle body (100), and the top height of the metering scale (310) is lower than the top height of the stirring main unit component (200).

2. The mobile concrete mixing station according to claim 1, characterized in that: The metering module (300) comprises: A support frame (320), wherein a measuring scale installation space is formed inside the support frame (320), the measuring scale (310) is installed in the measuring scale installation space, and the support frame (320) is pivotally installed on the stirring main unit assembly (200).

3. The mobile concrete mixing station according to claim 2, characterized in that: In the towing pivot position, the top height of the metering scale (310) is lower than the top height of the stirring main unit assembly (200) and both are less than 4.3 meters.

4. The mobile concrete mixing station according to claim 2, characterized in that: The stirring main unit component (200) further comprises: A main frame (210), wherein an installation space is formed inside the main frame (210); A stirring main body (220), wherein the stirring main body (220) is installed in the installation space and is used for receiving the feeding material.

5. The mobile concrete mixing station according to claim 4, characterized in that: The main frame (210) comprises a top bracket (211), wherein the top bracket (211) is arranged at the top end of the main frame (210); the support frame (320) comprises a side bracket (321), wherein the side bracket (321) is arranged at one side of the support frame (320); and the side bracket (321) is hingedly connected to the top bracket (211).

6. The mobile concrete mixing station according to claim 5, characterized in that: The mobile concrete mixing station also includes a locking mechanism (400), which is arranged on the main frame (210) and is used to limit the rotation of the metering module (300) when it is in the towing pivot position.

7. The mobile concrete mixing station according to claim 6, characterized in that: The mobile concrete mixing plant also includes: A foldable inspection platform (500) is pivotally mounted on the peripheral side of the mixing main unit component (200) and can be switched between a foldable pivot position and an unfolded pivot position. In the foldable pivot position, the foldable inspection platform (500) is folded and retracted to the side of the mixing main unit component (200). In the unfolded pivot position, the foldable inspection platform (500) is unfolded toward the side of the mixing main unit component (200).

8. The mobile concrete mixing station according to claim 7, characterized in that: At the folded pivot position of the foldable maintenance platform (500), the overall width of the mobile concrete mixing plant is the platform width between the folded maintenance platforms (500) on both sides and is less than 2.45 meters.

9. The mobile concrete mixing station according to claim 8, characterized in that: There are multiple foldable maintenance platforms (500).

10. The mobile concrete mixing plant according to any one of claims 7 to 9, characterized in that: In the unfolded pivot position, the unfolded width of the foldable inspection platform (500) unfolded toward the side of the mixing main unit assembly (200) is not less than 0.75 meters.

11. The mobile concrete mixing station according to claim 10, characterized in that: The mobile concrete mixing plant also includes: An aggregate bin (600) for feeding materials into the mixing main body (220) of the mixing main body assembly (200); The conveying mechanism (700) is used for conveying materials between the mixing main body (220) and the aggregate bin (600).