Continuous curing-cracking production line

By designing a continuous curing-cracking production line, using PLC control system and induction device, the automated curing-cracking process of polymer materials is realized, solving the problem of low automation in the prior art, and improving production efficiency and material densification.

CN222022030UActive Publication Date: 2024-11-19FUJIAN LEADASIA NEW MATERIAL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323386466.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-12
Publication Date
2024-11-19
Estimated Expiration
2033-12-12

AI Technical Summary

Technical Problem

The existing polymer impregnation and cracking process has low degree of automation, low production efficiency, and it is difficult to achieve densification of composite materials.

Method used

A continuous curing-cracking production line is designed, including impregnation plates, rotary conveyor belts, gas replacement zones, preheating transition zones, curing zones, cooling zones and high-temperature cracking zones. The PLC control system and induction device are used to realize the automation of impregnated materials. Curing-cracking process.

Benefits of technology

The curing-cracking and cracking automation process of polymer materials is realized, the degree of automation is improved, the production efficiency is improved, the densification of the material is ensured and oxidation is prevented.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222022030U_ABST
    Figure CN222022030U_ABST
Patent Text Reader

Abstract

The utility model discloses a continuous curing-cracking production line. Comprising a dipping plate for placing a dipping material, a rotary conveying belt for conveying the dipping plate, and a feeding area, a first gas replacement area, a first preheating transition area, a low-temperature curing area, a first cooling area, a second gas replacement area, a second preheating transition area and a high-temperature cracking area which are sequentially arranged along the rotary conveying belt, the rotary conveying belt is provided with a plurality of conveying pieces used for pushing the dipping plate to rotate on the rotary conveying belt, the space from the first gas replacement area to the second cooling area is a closed space, and the device further comprises a PLC (programmable logic controller) control system. The continuous curing-cracking production line disclosed by the utility model can realize the automatic curing-cracking process of a polymer material, and is high in automation degree.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of cracking equipment, in particular to a continuous solidification-cracking production line. Background Art

[0002] Polymer impregnation and pyrolysis (PIP) is a composite material preparation process that has developed rapidly in the past decade. f / SiC、SiC f / SiC and Si3N 4f The process of preparing ceramic matrix composite materials such as Si3N4 is to use a fiber preform as a skeleton, remove the air in the preform by vacuum, use an organic polymer solution or melt containing Si in the main chain for impregnation, crosslink and solidify under the protection of inert gas, and then perform high-temperature cracking to convert the precursor polymer into a ceramic matrix such as SiC and Si3N4. Due to the formation of pores by the cracked small molecules and the shrinkage of the matrix after cracking, it is necessary to implement the above-mentioned impregnation cracking process multiple times to achieve the densification of the composite material. The precursor polymers for preparing ceramic composite materials by PIP process mainly include polycarbosilane (PCS), polymethylsilane, polyvinylsilane, hydrogenated polycarbosilane, polysilane, etc. Among them, PCS is currently the most used precursor polymer. By preparing PCS into a solution for impregnation, the requirements for equipment are simpler, and cracking is subsequently performed using a cracking furnace, but the existing process is not highly automated and has low production efficiency. Utility Model Content

[0003] The utility model aims to provide a continuous solidification-cracking production line, which can realize the automated process of solidification-cracking of polymer materials and has a high degree of automation.

[0004] In order to achieve the above purpose, the solution of the utility model is:

[0005] A continuous solidification-cracking production line comprises an impregnation plate for placing impregnation materials, a rotary conveyor belt for conveying the impregnation plate, and a loading area, a first gas replacement area, a first preheating transition area, a low-temperature solidification area, a first cooling area, a second gas replacement area, a second preheating transition area, a high-temperature cracking area, a second cooling area and a unloading area arranged in sequence along the rotary conveyor belt, wherein the rotary conveyor belt is provided with a plurality of conveying members for pushing the impregnation plate to rotate thereon, the first gas replacement area and the second gas replacement area are respectively provided with gas replacement chambers, each of the gas replacement chambers is respectively provided with a vacuum pump and a ventilation system, the first preheating transition area and the second preheating transition area are respectively provided with a ventilation system, the low-temperature solidification area and the high-temperature cracking area are provided with a heating device and a ventilation system, the first cooling area and the second cooling area are respectively provided with a ventilation system, and the second cooling area is provided with a cooling circulation waterway; the first gas replacement area to the second cooling area is a closed space, and further comprises a PLC control system, and each of the vacuum pumps, ventilation systems, heating devices and conveying members is also control-connected to the PLC control system.

[0006] The loading zone, the first cooling zone, the second preheating transition zone and the second cooling zone are respectively arranged at the corners of the rotary conveyor belt.

[0007] It also includes a sensing device, which includes a sensor for sensing the impregnation plate. The sensor is arranged at the corner of the rotary conveyor belt, and the sensor is connected to the PLC control system.

[0008] The conveying member is one of an electric push plate device, an electric roller or a non-electric roller, or a combination of the two.

[0009] The conveying member arranged on the rotary conveyor belt corresponding to the position between the loading zone and the low-temperature solidification zone includes an electric pusher, the conveying member arranged on the rotary conveyor belt corresponding to the position of the low-temperature solidification zone is a non-electric roller, the conveying member arranged on the rotary conveyor belt corresponding to the first cooling zone includes an electric roller, the conveying member arranged on the rotary conveyor belt corresponding to the position between the first cooling zone and the second gas replacement zone is an electric pusher, the conveying member arranged on the rotary conveyor belt corresponding to the position of the second preheating transition zone includes an electric roller and an electric pusher, the conveying member arranged on the rotary conveyor belt corresponding to the position of the high-temperature cracking zone is a non-electric roller, the conveying member arranged on the rotary conveyor belt corresponding to the position of the second cooling zone includes an electric roller and an electric pusher, and the conveying member arranged on the rotary conveyor belt corresponding to the position between the unloading zone and the loading zone is an electric roller.

[0010] The ventilation system comprises an air inlet pipe and an air outlet pipe, and the heating device is a graphene heating device.

[0011] A branch conveyor belt is also arranged between the second preheating transition zone, the high-temperature cracking zone and the second cooling zone. Both ends of the branch conveyor belt are respectively connected to corresponding positions of the rotary conveyor belt. The branch conveyor belt is provided with a plurality of conveying parts for pushing the impregnation plate to rotate thereon.

[0012] The feed inlet and the discharge outlet of the gas replacement chamber are respectively installed with electric isolation doors, the feed inlet and the discharge outlet of the low-temperature solidification zone and the high-temperature cracking zone are respectively installed with electric insulation doors, and the discharge outlet of the second cooling zone is also installed with an electric isolation door, and each of the electric isolation doors and the electric insulation door is also controlled and connected to the PLC control system.

[0013] A third gas replacement zone is further arranged between the second cooling zone and the material unloading zone, and a gas replacement chamber is arranged on the third gas replacement zone.

[0014] After adopting the above structure, the utility model provides a continuous solidification-cracking production line, and its working principle is as follows: the precursor polymer is placed on the impregnation plate after impregnation, enters the rotary conveyor belt through the loading area, and is transported to the first gas exchange area under the control of the PLC control system, stays in the gas exchange chamber, waits for the gas exchange chamber to complete at least one ventilation, enters the first preheating transition area for preheating, then enters the low-temperature solidification area to complete the solidification preheating, then enters the first cooling area for cooling, and then enters the second gas exchange area, waits for the corresponding gas exchange chamber to complete at least one ventilation as needed, enters the second preheating transition area for preheating, and then transports to the high-temperature cracking area for high-temperature cracking under the protection of the protective gas to avoid oxidation, and finally enters the second cooling area for cooling, and is pushed to the unloading area. The utility model provides a continuous solidification-cracking production line, which concentrates the solidification-cracking process of the impregnated material on one assembly line, and can realize the automation process of the solidification-cracking of the polymer material, with a high degree of automation. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a structural schematic diagram of a continuous solidification-cracking production line of the utility model.

[0016] In the figure:

[0017] Dipping plate 1 Rotating conveyor belt 2

[0018] Loading zone 20 First gas replacement zone 21

[0019] First preheating transition zone 22 Low temperature curing zone 23

[0020] First cooling zone 24 Second gas replacement zone 25

[0021] Second preheating transition zone 26 High temperature cracking zone 27

[0022] Second cooling zone 28 Unloading zone 29

[0023] Branch conveyor belt 201 Electric push plate 31

[0024] Motorized roller 32 Non-motorized roller 33

[0025] Sensor 4 Electric isolation door 5

[0026] Vacuum pump 6 Ventilation system 7

[0027] Electric insulation door 8 Heating device 9 DETAILED DESCRIPTION

[0028] In order to further explain the technical solution of the present utility model, the present utility model is described in detail below through specific embodiments.

[0029] A continuous solidification-cracking production line, such as Figure 1 As shown, it includes an impregnation plate 1 for placing impregnation materials, a rotary conveyor belt 2 for conveying the impregnation plate 1, and a loading zone 20, a first gas replacement zone 21, a first preheating transition zone 22, a low-temperature solidification zone 23, a first cooling zone 24, a second gas replacement zone 25, a second preheating transition zone 26, a high-temperature cracking zone 27, a second cooling zone 28 and a unloading zone 29 arranged in sequence along the rotary conveyor belt 2. In this embodiment, the rotary conveyor belt 2 is a square ring-shaped conveyor belt, and the loading zone 20, the first cooling zone 24, the second preheating transition zone 26 and the second cooling zone 28 are respectively arranged at the corners of the rotary conveyor belt 2. The first gas replacement zone 21 to the second cooling zone 28 are closed spaces.

[0030] The rotary conveyor belt 2 is provided with a plurality of conveying members for pushing the impregnation plate 1 to rotate thereon, and the conveying members are one or a combination of an electric plate pusher 31, an electric roller 32 or a non-electric roller 33. Preferably, the conveying members arranged at the position between the feeding area 20 and the low-temperature curing area 23 of the rotary conveyor belt 2 include the electric plate pusher 31, and the conveying members arranged at the position of the rotary conveyor belt 2 corresponding to the low-temperature curing area 23 are non-electric rollers 33, because it is not suitable to use electric equipment in the low-temperature curing area 23.

[0031] The conveying member arranged at the position of the rotary conveyor 2 corresponding to the first cooling zone 24 includes an electric roller 32, the conveying member arranged at the position between the first cooling zone 24 and the second gas replacement zone 25 of the rotary conveyor 2 is an electric pusher 31, and the conveying member arranged at the position of the rotary conveyor 2 corresponding to the second preheating transition zone 26 includes an electric roller 32 and an electric pusher 31. The conveying member arranged at the position of the rotary conveyor 2 corresponding to the high-temperature cracking zone 27 is a non-electric roller 33, because it is not suitable to use electric equipment in the high-temperature cracking zone 27. The conveying member arranged at the position of the rotary conveyor 2 corresponding to the second cooling zone 28 includes an electric roller 32 and an electric pusher 31, and the conveying member arranged at the position between the unloading zone 29 and the loading zone 20 of the rotary conveyor 2 is an electric roller 32.

[0032] It can be found that the electric pushers 31 are arranged at the corners of the rotary conveyor belt 2 .

[0033] The continuous solidification-cracking production line also includes a PLC control system and a sensing device, the sensing device includes four sensors 4 for sensing the impregnation plate 1, each sensor 4 is arranged at the corner of the rotary conveyor belt 2, the sensor 4 is connected to the PLC control system, and the electric pusher 31 and the electric roller 32 are also connected to the PLC control system. When the impregnation plate 1 is transported to a certain corner on the rotary conveyor belt 2, the corresponding sensor 4 senses the position of the impregnation plate 1 and sends a position signal to the PLC control system. After receiving the position signal, the PLC control system controls the corresponding electric pusher 31 to work, completing the transportation of the impregnation plate 1 at the corner.

[0034] The first gas exchange zone 21 and the second gas exchange zone 25 are respectively provided with gas exchange chambers, and the feed port and the discharge port of the gas exchange chamber are respectively installed with electric isolation doors 5, and each gas exchange chamber is respectively provided with a vacuum pump 6 and a ventilation system 7. The first preheating transition zone 22 and the second preheating transition zone 26 are respectively provided with a ventilation system 7, and the feed port and the discharge port of the low-temperature solidification zone 23 and the high-temperature cracking zone 27 are respectively installed with electric insulation doors 8, and the low-temperature solidification zone 23 and the high-temperature cracking zone 27 are provided with a heating device 9 and a ventilation system 7, and the first cooling zone 24 and the second cooling zone 28 are respectively provided with a ventilation system 7, and the second cooling zone 28 is provided with a cooling circulation water circuit, and the discharge port of the second cooling zone 28 is installed with an electric isolation door 5. In this embodiment, the heating device 9 is a graphene heating device. Each electric isolation door 5 and the electric insulation door 8 are also connected to the PLC control system. Each ventilation system 7 includes an air inlet pipe for introducing protective gas and an air outlet pipe for extracting gas, and both the air inlet pipe and the air outlet pipe are provided with electric valves. Each vacuum pump 6, the electric valve of the ventilation system 7 and the heating device 9 are also connected to the PLC control system.

[0035] After adopting the above structure, the working process of the continuous solidification-cracking production line of the utility model is as follows:

[0036] First, the impregnated precursor polymer is placed on the impregnation plate 1 and placed in the loading area 20 via a known grabbing device (such as a manipulator). After the corresponding sensor 4 senses the impregnation plate 1, it sends a position signal to the PLC control system. After the PLC control system receives the position signal, it controls the electric pusher 31 near the loading area 20 to work and push the impregnation plate 1 to the first gas replacement area 21. At this time, the PCL control system controls the electric isolation door 5 of the gas replacement chamber to open, and the impregnation plate 1 enters the gas replacement chamber. The electric isolation door 5 is closed, and the vacuum pump 6 is turned on to evacuate the gas replacement chamber. When the vacuum degree reaches the preset value, the electric valve of the air inlet pipe is opened to introduce protective gas (such as nitrogen). This ventilation is repeated twice. , thereby ensuring that no oxygen enters the subsequent area, and at the same time, each subsequent area is also introduced with protective gas (such as nitrogen) through its own ventilation system 7; then the electric isolation door 5 of the discharge port of the gas replacement chamber is opened, and the impregnation plate 1 is pushed into the first preheating transition zone 22 by the electric pusher 31. The first preheating transition zone 22 does not have an independent heating device, and relies on the residual heat of the low-temperature curing zone 23 to preheat the impregnated body. After preheating, it is pushed into the low-temperature curing zone 23 by the electric pusher 31, and the impregnated body is cured by the heating device 9. When the next impregnation plate 1 enters the low-temperature curing zone 23, the electric insulation door 8 of the low-temperature curing zone 23 is opened, and the impregnation plate 1 that first enters the low-temperature curing zone 23 is pushed out and enters the first cooling zone 24 for cooling.

[0037] When the impregnation plate 1 in the first cooling zone 24 is transported to the corresponding corner by the electric roller 32, the corresponding sensor 4 senses the impregnation plate 1 and sends a position signal to the PLC control system. After receiving the position signal, the PLC control system controls the electric plate pusher 31 near the first cooling zone 24 to work and push the impregnation plate 1 into the second gas replacement zone 25. If the protective gas used in the second preheating transition zone 26 and the high-temperature cracking zone 27 is inconsistent with the protective gas used in the first preheating transition zone 22 and the low-temperature solidification zone 23, the second gas replacement zone 25 is used to complete the ventilation. If they are consistent, the gas replacement chamber of the second gas replacement zone 25 does not need to be ventilated, and then the impregnation plate 1 is pushed to the second preheating transition zone 26. The second preheating transition zone 26 does not have an independent heating device and relies on the waste heat of the high-temperature cracking zone 27 to preheat the impregnated body. After preheating, the sensor 4 located near the second preheating transition zone 26 senses the impregnation plate 1 and sends a position signal. The signal is sent to the PLC control system. After the PLC control system receives the position signal, it controls the electric pusher 31 near the second preheating transition zone 26 to work, push the impregnation plate 1 into the high-temperature cracking zone 27, and realize the high-temperature cracking of the impregnated body through the heating device 9. During the high-temperature cracking process, the protective gas is continuously introduced through the air inlet pipe to avoid oxidation. Similarly, the conveying member in the high-temperature cracking zone 27 is a non-electric roller 33. The impregnation plate 1 that enters the high-temperature cracking zone 27 later needs to slowly push out the impregnation plate 1 that enters first, and then enter the second cooling zone 28 for circulating cooling under the protection of the protective gas. When the sensor 4 located near the second cooling zone 28 senses the impregnation plate 1, it sends a position signal to the PLC control system. After the PLC control system receives the position signal, it controls the electric pusher 31 near the second cooling zone 28 to work, and at the same time, the electric isolation door 5 of the second cooling zone 28 is opened to push the impregnation plate 1 into the unloading zone 29, and finally it is taken away by the robot. In the continuous solidification-cracking production line, the positions of the rotary conveyor belt 2 corresponding to the loading zone 20 and the unloading zone 29 are exposed to the air environment, and the positions of the rotary conveyor belt 2 corresponding to the first gas replacement zone 21 to the second cooling zone 28 are all in a closed environment to prevent oxidation of the impregnated body during the production process.

[0038] Therefore, it can be seen that the utility model is a continuous curing-cracking production line, which concentrates the curing-cracking process of the impregnated material on one production line, and can realize the automated process of curing-cracking of the polymer material with a high degree of automation.

[0039] Furthermore, a branch conveyor belt 201 is provided between the second preheating transition zone 26, the high temperature cracking zone 27 and the second cooling zone 28. The two ends of the branch conveyor belt 201 are connected to the corresponding positions of the rotary conveyor belt 2. The branch conveyor belt 201 is provided with a plurality of conveying members for pushing the impregnation plate 1 to rotate thereon. The arrangement of the conveying members on the branch conveyor belt 201 is consistent with the arrangement of the conveying members on the rotary conveyor belt 2, that is, the conveying member arranged at the position of the branch conveyor belt 201 corresponding to the second preheating transition zone 26 is an electric pusher 31, the conveying member arranged at the position of the branch conveyor belt 201 corresponding to the high temperature cracking zone 27 is a non-electric roller 33, and the conveying member arranged at the position of the branch conveyor belt 201 corresponding to the second cooling zone 28 includes an electric roller 33 and an electric pusher 31. The rotary conveyor belt 2 is provided with sensors 4 for sensing the impregnation plate 1 at positions near the two ends of the branch conveyor belt 201. The conveying members on the branch conveyor belt 201 and the corresponding sensors 4 on the rotary conveyor belt 2 are also connected to the PLC control system.

[0040] Since the high-temperature cracking time is relatively long, when the number of impregnated plates 1 on the second preheating transition zone 26, the high-temperature cracking zone 27 and the second cooling zone 28 corresponding to the rotary conveyor belt 2 exceeds the load of the rotary conveyor belt 2, the conveying parts and the corresponding sensors 4 on the branch conveyor belt 201 can be opened, so that the impregnated plates 1 output from the second gas replacement zone 25 are pushed to the branch conveyor belt 201 via the electric pusher 31 on the second preheating transition zone 26, and are synchronously processed with the impregnated plates 1 on the rotary conveyor belt 2 to improve efficiency.

[0041] Furthermore, a third gas replacement zone (not shown in the figure) is provided between the second cooling zone 28 and the unloading zone 29. A gas replacement chamber is provided on the third gas replacement zone. The structure of the gas replacement chamber is the same as that of the gas replacement chamber of the first gas replacement zone 21, which can prevent air from entering the second cooling zone 28 during discharge, causing the impregnated body to be oxidized during cooling.

[0042] In the utility model, the electric push plate 31, the electric roller 32, the non-electric roller 33, the sensor 4, the electric isolation door 5, the vacuum pump 6, the ventilation system 7, the electric insulation door 8, the heating device 9 and the PLC control system are all well-known components in the art.

[0043] The above embodiments and drawings do not limit the product form and style of the present utility model. Any appropriate changes or modifications made by ordinary technicians in the relevant technical field should be deemed to be within the patent scope of the present utility model.

Claims

1. A continuous solidification-cracking production line, Features: The invention comprises an impregnation plate for placing impregnation materials, a rotary conveyor belt for conveying the impregnation plate, and a loading area, a first gas replacement area, a first preheating transition area, a low-temperature solidification area, a first cooling area, a second gas replacement area, a second preheating transition area, a high-temperature cracking area, a second cooling area and a unloading area arranged in sequence along the rotary conveyor belt. The rotary conveyor belt is provided with a plurality of conveying members for pushing the impregnation plate to rotate thereon, a gas replacement chamber is respectively provided on the first gas replacement area and the second gas replacement area, a vacuum pump and a ventilation system are respectively provided in each of the gas replacement chambers, a ventilation system is respectively provided in the first preheating transition area and the second preheating transition area, a heating device and a ventilation system are provided in the low-temperature solidification area and the high-temperature cracking area, a ventilation system is respectively provided in the first cooling area and the second cooling area, and a cooling circulation waterway is provided in the second cooling area; the first gas replacement area to the second cooling area is a closed space, and a PLC control system is also included, and each of the vacuum pumps, ventilation systems, heating devices and conveying members are also control-connected to the PLC control system.

2. A continuous solidification-cracking production line according to claim 1, Features: The loading zone, the first cooling zone, the second preheating transition zone and the second cooling zone are respectively arranged at the corners of the rotary conveyor belt.

3. A continuous solidification-cracking production line according to claim 1, Features: It also includes a sensing device, which includes a sensor for sensing the impregnation plate. The sensor is arranged at the corner of the rotary conveyor belt, and the sensor is connected to the PLC control system.

4. A continuous solidification-cracking production line according to claim 1, Features: The conveying member is one of an electric push plate device, an electric roller or a non-electric roller, or a combination of the two.

5. A continuous solidification-cracking production line according to claim 4, Features: The conveying member arranged on the rotary conveyor belt corresponding to the position between the loading zone and the low-temperature solidification zone includes an electric pusher, the conveying member arranged on the rotary conveyor belt corresponding to the position of the low-temperature solidification zone is a non-electric roller, the conveying member arranged on the rotary conveyor belt corresponding to the first cooling zone includes an electric roller, the conveying member arranged on the rotary conveyor belt corresponding to the position between the first cooling zone and the second gas replacement zone is an electric pusher, the conveying member arranged on the rotary conveyor belt corresponding to the position of the second preheating transition zone includes an electric roller and an electric pusher, the conveying member arranged on the rotary conveyor belt corresponding to the position of the high-temperature cracking zone is a non-electric roller, the conveying member arranged on the rotary conveyor belt corresponding to the position of the second cooling zone includes an electric roller and an electric pusher, and the conveying member arranged on the rotary conveyor belt corresponding to the position between the unloading zone and the loading zone is an electric roller.

6. A continuous solidification-cracking production line according to claim 1, Features: The ventilation system comprises an air inlet pipe and an air outlet pipe, and the heating device is a graphene heating device.

7. A continuous solidification-cracking production line according to claim 1, Features: A branch conveyor belt is also arranged between the second preheating transition zone, the high-temperature cracking zone and the second cooling zone. Both ends of the branch conveyor belt are respectively connected to corresponding positions of the rotary conveyor belt. The branch conveyor belt is provided with a plurality of conveying parts for pushing the impregnation plate to rotate thereon.

8. A continuous solidification-cracking production line according to claim 1, Features: The feed inlet and the discharge outlet of the gas replacement chamber are respectively installed with electric isolation doors, the feed inlet and the discharge outlet of the low-temperature solidification zone and the high-temperature cracking zone are respectively installed with electric insulation doors, and the discharge outlet of the second cooling zone is also installed with an electric isolation door, and each of the electric isolation doors and the electric insulation door is also controlled and connected to the PLC control system.

9. A continuous solidification-cracking production line according to claim 1, Features: A third gas replacement zone is further arranged between the second cooling zone and the material unloading zone, and a gas replacement chamber is arranged on the third gas replacement zone.